CN209393429U - Paint spraying system - Google Patents
Paint spraying system Download PDFInfo
- Publication number
- CN209393429U CN209393429U CN201821825055.6U CN201821825055U CN209393429U CN 209393429 U CN209393429 U CN 209393429U CN 201821825055 U CN201821825055 U CN 201821825055U CN 209393429 U CN209393429 U CN 209393429U
- Authority
- CN
- China
- Prior art keywords
- paint
- transparent
- spray booth
- spray
- spraying system
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Details Or Accessories Of Spraying Plant Or Apparatus (AREA)
Abstract
The utility model embodiment discloses a kind of paint spraying system, including paint spray booth, controlled observation room, spray-painting plant, spray painting control device, wherein: the spray-painting plant is set in the paint spray booth, and the spray painting control device with the spray-painting plant communication connection is provided in the controlled observation room;It is provided with partition between the paint spray booth and the controlled observation room, transparent viewing port at least one is set on the partition, the transparent viewing port is detachably equipped with transparent protective layer.The reduction of transparent viewing port cleaning cost may be implemented in the utility model embodiment, makes personnel that can obviously observe spray painting indoor situations, effective monitoring spraying process from controlled observation room.
Description
Technical field
The utility model relates to automobile processing technology, especially a kind of paint spraying system.
Background technique
Automotive lacquer is to show coast of paint on car surface to achieve the effect that protect automobile.Paint spray booth is to carry out spray painting work
Important place.Vehicle body spray painting is painted compared to components, and spray area is bigger, and paint consumption is bigger.During spraying,
Especially by hand spray operation in the case where, can inevitably generate a large amount of coating clouds, be attached to spray painting chamber interior walls on.Coating cloud
It is attached to compare in spray painting chamber interior walls and is difficult to clear up, need to expend a large amount of manpower and material resources, also to sacrifice the valuable production time.
A large amount of coating clouds not only cause spray painting indoor environmental quality decline, clean increased costs, the personnel of also causing can not be clearly viewed
In paint spray booth, it is unable to effective monitoring spraying process.
Utility model content
The utility model embodiment provides a kind of paint spraying system, and the indoor feelings of spray painting are clearly viewed in the personnel of may be implemented
Condition, effective monitoring spraying process.
The paint spraying system of the utility model embodiment, including paint spray booth, controlled observation room, spray-painting plant, spray painting control dress
It sets, in which:
The spray-painting plant is set in the paint spray booth, is provided in the controlled observation room logical with the spray-painting plant
Interrogate the spray painting control device of connection;
It is provided with partition between the paint spray booth and the controlled observation room, transparent sight at least one is set on the partition
Cha Kou, the transparent viewing port are detachably equipped with transparent protective layer.
Optionally, in any of the above-described paint spraying system embodiment of the utility model, the transparent protective layer includes flexible saturating
Bright film.
Optionally, in any of the above-described paint spraying system embodiment of the utility model, the flexible transparent film includes and institute
State the transparent plastic film that transparent viewing port size matches.
Optionally, in any of the above-described paint spraying system embodiment of the utility model, predeterminable area is arranged on the partition
Transparent glass partition window, the transparent viewing port are set on the transparent glass partition window, described in the transparent glass partition window
Remove the region coating coating cloud absorbent coating of the transparent viewing port in the side of paint spray booth.
Optionally, in any of the above-described paint spraying system embodiment of the utility model, the inside of the paint spray booth is except described
Remaining wall surface of bright glass partition window is equipped with stainless steel panel.
Optionally, in any of the above-described paint spraying system embodiment of the utility model, in the stainless steel panel described in coating
Coating cloud absorbent coating.
Optionally, in any of the above-described paint spraying system embodiment of the utility model, the coating cloud absorbent coating includes water-soluble
Property dust adhering agent coating.
Optionally, it in any of the above-described paint spraying system embodiment of the utility model, is provided on the floor of the paint spray booth
Sink, the sink are covered by grid, track are provided on the grid, is provided with vehicle location on the track
Slot.
Optionally, in any of the above-described paint spraying system embodiment of the utility model, it is additionally provided with fan in the paint spray booth,
Coating cloud drainage in part is entered sink by the fan.
Based on above-mentioned paint spraying system provided by the embodiment of the utility model, by between paint spray booth and controlled observation room
Transparent viewing port is set on partition, can make personnel that can be clearly apparent in paint spray booth in controlled observation room;By in transparent sight
The upper detachable installation transparent protective layer of Cha Kou, can enable operator when protective layer, which is painted indoor coating cloud, influences transparency
It is enough simply and easily to replace transparent protective layer, it ensures that transparent viewing port can make to obviously observe in paint spray booth, reduces transparent
Observation panel cleaning cost.
Below by drawings and examples, the technical solution of the utility model is described in further detail.
Detailed description of the invention
The attached drawing for constituting part of specification describes the embodiments of the present invention, and is used for together with description
Explain the principles of the present invention.
The utility model can be more clearly understood according to following detailed description referring to attached drawing, in which:
Fig. 1 is the structural schematic diagram of the paint spraying system of some embodiments of the utility model;
Fig. 2 is the structure side structure schematic view of paint spray booth in other embodiments of the utility model.
Specific embodiment
The various exemplary embodiments of the utility model are described in detail now with reference to attached drawing.It should also be noted that unless another
It illustrates outside, the component and the positioned opposite of step, numerical expression and numerical value otherwise illustrated in these embodiments is unlimited
The scope of the utility model processed.
Simultaneously, it should be appreciated that for ease of description, the size of various pieces shown in attached drawing is not according to reality
Proportionate relationship draw.
Be to the description only actually of at least one exemplary embodiment below it is illustrative, never as to this is practical
Novel and its application or any restrictions used.
Technology and equipment known to person of ordinary skill in the relevant may be not discussed in detail, but in appropriate situation
Under, the technology and equipment should be considered as part of specification.
It should also be noted that similar label and letter indicate similar terms in following attached drawing, therefore, once a certain Xiang Yi
It is defined in a attached drawing, then in subsequent attached drawing does not need that it is further discussed.
Fig. 1 is the structural schematic diagram of the paint spraying system of some embodiments of the utility model.As shown in Figure 1, the present embodiment
Paint spraying system includes: paint spray booth 1, controlled observation room 2, spray-painting plant 11, spray painting control device 21, wherein spray-painting plant 11 is set
It is placed in paint spray booth 1, the spray painting control device 21 with 11 communication connection of spray-painting plant is provided in controlled observation room 2;Paint spray booth 1
It is provided with partition 3 between controlled observation room 2, transparent viewing port 31 at least one is set on partition 3, transparent viewing port 31 is torn open
It unloads and transparent protective layer 32 is installed.
In the present embodiment, monitoring personnel is observed in paint spray booth 1 by transparent viewing port 31 in controlled observation room 2 and is sprayed
Paint the spray painting operation situation of device 11.Spray-painting plant 11 is controlled by the spray painting control device 21 being arranged in controlled observation room 2
Movement, for example, spray painting operation starts, spray painting operation terminates, the time interval in painting process between each movement, various originals
Whether the stirring ratio and spray-painting plant 11 of speed and spray painting paint vehicle that paint vehicle enters generate failure etc..In addition to this, exist
The staff to be painted manually in paint spray booth can also pass through monitoring personnel of the transparent viewing port 31 into controlled observation room 2
The situation in paint spray booth 1 is conveyed, such as after paint spraying personnel have found manual spray gun obstruction unexpected situation in paint spray booth 1, it can be with
It avoids leaving paint spray booth 1 and enters back into unexpected situation solution caused by controlled observation room 2 is reported and released to unexpected situation never
Timely problem directly carries out signal report by monitoring personnel of the transparent viewing port 31 into controlled observation room 2, saves failure
The time of exclusion has ensured the efficiency of spraying operation.
Due in paint spray booth 1 carry out spray area it is larger, to paint vehicle consumption biggish spraying operation when, especially by
In the case where hand spray operation, it can inevitably generate a large amount of coating clouds and be attached on the wall surface of 1 inside of paint spray booth, both cause
Environmental quality declines in paint spray booth 1, and causes the operator in controlled observation room 2 that can not observe and understand in paint spray booth 1, cannot
Reach effective monitoring spraying process.The coating cloud cleaning of attachment is relatively difficult, and the interval short period just needs large area to clear up, and needs
A large amount of manpower and material resources are expended, the valuable production time is especially sacrificed, influence production efficiency.
It is opened up on the partition 3 that paint spraying system provided in this embodiment is arranged between paint spray booth 1 and controlled observation room 2 transparent
The side of observation panel 31, the paint spray booth 1 at transparent viewing port 31 is detachably installed by transparent protective layer 32.Transparent protective layer 32
It can regularly replace, can both ensure that the monitoring personnel in controlled observation room 2 has enough visuals field and clarity to observe paint spray booth 1
Interior situation, it is thus also avoided that the case where often manpower and material resources caused by avoiding progress large area cleaning in paint spray booth 1 waste;It removes
Except this, periodically carrying out replacement to transparent protective layer 32 can be completed or stop the short period without stopping spraying operation
It completes, for example, can spend the short period that transparent protective layer can be completed by the operator in paint spray booth 1 after daily stop work
32 replacement, it is simple to operate, the efficiency of spraying operation in paint spray booth 1 is not influenced.
What transparent protective layer 32 was chosen is easily to be adhered to transparent viewing port 31, and conveniently dismantle from transparent viewing port 32
The transparent material to get off.The matter for the paint that material selected by transparent protective layer 32 can not spray spray-painting plant 11 in paint spray booth 1
Amount has an impact, such as certain transparent materials easily have an impact the gas of paint vehicle quality, and painting quality is caused to decline, and influence to spray
Apply the quality of effect and product.
Spray-painting plant 11 includes auto spray painting device and manual spray-painting plant, and wherein auto spray painting device can be automatic spray
Paint robot.So that auto spray painting machine people is completed auto spray painting work by program setting, the control device that paints can also be passed through
21 control auto spray painting machine people complete spray painting operation, such as control the proportion of auto spray painting machine people original paint and meet to blend
Spray desired paint vehicle;For manual spray-painting plant, monitoring personnel is needed before paint vehicle enters paint spray booth 1 by spraying operation institute
The paint vehicle needed is configured, which is completed by spray painting control device 21.
The present embodiment by the way that transparent viewing port 31 is arranged on the partition 3 that is arranged between paint spray booth 1 and controlled observation room 2,
And regular dismounting installs transparent protective layer 32 in transparent viewing port 31, has both ensured the monitoring personnel energy in controlled observation room 2
The operation observed to enough clear and definites the situation in paint spray booth, control spray-painting plant 11 in time, it is thus also avoided that interval short period
Need the case where cleaning to 1 interior sidewall surface of paint spray booth, reduce the manpower and material resources that clean painting room 1 is wasted, save at
This, improves the efficiency of spraying operation.
In some embodiments, transparent protective layer 32 includes flexible transparent film.Flexible transparent film needs in the present embodiment
There is a degree of adsorptivity, is also possible to that the side of flexible transparent film being bonded with transparent viewing port 31 is provided with one
Fixed binder, but the binder does not remain during flexible transparent film is dismantled in transparent viewing port.It can at one
In the example of choosing, transparent viewing port 31 be glass, flexible transparent film include match with 31 size of transparent viewing port it is transparent
Plastic film, such as preservative film used in production and living decide the size of transparent plastic film and the ruler of transparent viewing port 31
Size very little identical or slightly larger than transparent viewing port 31 ensures that transparent viewing port 31 does not contact i.e. with the coating cloud in paint spray booth 1
It can.By adhering to layer of transparent plastic film in transparent viewing port 31, neither influence monitoring personnel is supervised from transparent viewing port 31
Control paint spray booth 1 in situation clarity, and it is simple to operate, reduce the clean cost of watch window.
In some embodiments, as shown in Figure 1, transparent glass partition window, transparent viewing port is arranged in predeterminable area on partition 3
31 are set on transparent glass partition window, remove the region coating paint of transparent viewing port in the side of the paint spray booth of transparent glass partition window 1
Mist absorbent coating.Three block-shaped identical regions are labeled on partition 3 as shown in Figure 1, which is the present embodiment
Related transparent glass partition window.
The present embodiment by the way that transparent glass partition window is arranged on partition 3, can ensure paint spray booth 1 and controlled observation room 2 it
Between can improve the quality painted manually with light transmission;Is being carried out to paint spray booth 1, monitoring personnel is also large area coating cloud clean initial stage
More wide-field monitoring can be carried out to the situation in paint spray booth 1 by transparent glass partition window.The present embodiment passes through on partition 3
Transparent glass partition window is set, and monitoring personnel can also be by transparent glass observation window after coating cloud is attached on transparent glass observation window
It indistinctly observes the situation in paint spray booth 1, is confirmed after finding indeterminate fault by transparent viewing port 31.Improve spray painting
The timeliness of indoor 11 fault discovery of spray-painting plant and the quality painted manually.
In some embodiments, remaining wall surface that transparent glass partition window is removed in the inside of paint spray booth 1 is equipped with stainless steel panel.
Since its own characteristic advantage is not easily susceptible to chemical attack, the coating cloud that the paint vehicle for spraying operation generates is adhered to not stainless steel
It is not easy to generate corrosiveness to stainless steel panel after in rust steel panel, causes the structural damage of stainless steel panel.The present embodiment
It can keep wall surface completely not by the corrosion of coating cloud for a long time by installing stainless steel panel in 1 interior sidewall surface of paint spray booth, and
Stainless steel panel easy cleaning, reduces the maintenance cost of paint spray booth 1.
In further embodiments, coating cloud absorbent coating, the coating cloud absorbent coating can also be coated in stainless steel panel
It can be liquid and be attached to the coating cloud absorbent coating formed in stainless steel panel after brushing, be also possible to flexible plastic film
It is pasted onto the coating cloud absorbent coating formed in stainless steel panel by another side after brushing liquid coating cloud absorption coating on one side, may be used also
To be it may occur to persons skilled in the art that the coating cloud absorbent coating that is formed in stainless steel panel of other modes, the present embodiment
It does not limit this.
The present embodiment can make the spraying operation in paint spray booth 1 by coating coating cloud absorbent coating in stainless steel panel
When the coating cloud that generates absorbed by coating cloud absorbent coating, reduce the coating cloud concentration in paint spray booth 1, can extend coating cloud be attached to it is transparent
Protective layer 32 causes the time of transparent protective layer 32 translucency difference.
In an optional example, coating cloud absorbent coating can be water-soluble dust adhering agent coating.The present embodiment is by adopting
With water-soluble dust adhering agent coating, the coating cloud in paint spray booth 1 can be effectively adsorbed.It only needs to use after coating cloud absorption to a certain extent
Water cleans the cleaning operation for just completing wall surface, and then wall surface after the cleaning brushes water-soluble dust adhering agent coating again.
The coating cloud in paint spray booth 1 can be not only adsorbed, extension coating cloud is attached to transparent protective layer 32 and causes 32 translucency of transparent protective layer
The time of difference, and it is easy to clean.
In some embodiments, as shown in Fig. 2, Fig. 2 is the structure side of paint spray booth in other embodiments of the utility model
Depending on structural schematic diagram, the floor of paint spray booth 1 is provided with sink 13, sink 13 is covered by grid 14, is arranged on grid 14
There is track 15, vehicle location slot is provided on track 15.The floor of paint spray booth 1 is covered by grid 14 in the present embodiment, spray painting
The coating cloud part generated in operation process is fallen on floor, and sink 13 is arranged on floor and is covered by grid 14.Pass through grid 14
Avoiding vehicle from getting wet sink and vehicle insulation to be sprayed influences coating quality.Coating cloud can also enter sink by grid 14
13, absorbed by the water in sink 13, not only reduce the coating cloud concentration in paint spray booth 1, also extend coating cloud be attached to it is transparent anti-
Sheath 32 causes the time of transparent protective layer 32 translucency difference.
In one alternate embodiment, as shown in Fig. 2, being additionally provided with fan 12 in paint spray booth 1, fan 12 paints part
Mist drainage enters sink 13, can further decrease the coating cloud concentration in paint spray booth 1, and extension coating cloud is attached to transparent protective layer 32 and makes
At the time of transparent protective layer 32 translucency difference, also reduce to a certain extent to the clean investment of 1 inner wall of paint spray booth.
Description of the utility model is given for the purpose of illustration and description, and is not that exhaustively or incite somebody to action this
Utility model is limited to disclosed form.Many modifications and variations are obvious for the ordinary skill in the art.
Embodiment was chosen and described in order to better illustrate the principle and practical application of the utility model, and makes the common skill of this field
Art personnel it will be appreciated that the utility model to designing various embodiments suitable for specific applications with various modifications.
Claims (9)
1. a kind of paint spraying system, which is characterized in that including paint spray booth, controlled observation room, spray-painting plant, paint control device,
In:
The spray-painting plant is set in the paint spray booth, is provided in the controlled observation room and is communicated company with the spray-painting plant
The spray painting control device connect;
It is provided with partition between the paint spray booth and the controlled observation room, transparent observing at least one is set on the partition
Mouthful, the transparent viewing port is detachably equipped with transparent protective layer.
2. paint spraying system according to claim 1, which is characterized in that the transparent protective layer includes flexible transparent film.
3. paint spraying system according to claim 2, which is characterized in that the flexible transparent film includes and the transparent sight
Examine the transparent plastic film that mouthful size matches.
4. paint spraying system according to any one of claim 1-3, which is characterized in that predeterminable area is set on the partition
Transparent glass partition window is set, the transparent viewing port is set on the transparent glass partition window, in the institute of the transparent glass partition window
Remove the region coating coating cloud absorbent coating of the transparent viewing port in the side for stating paint spray booth.
5. paint spraying system according to claim 4, which is characterized in that the inside of the paint spray booth except the transparent glass every
Remaining wall surface of window is equipped with stainless steel panel.
6. paint spraying system according to claim 5, which is characterized in that coat the coating cloud absorption in the stainless steel panel
Coating.
7. paint spraying system according to claim 5 or 6, which is characterized in that the coating cloud absorbent coating includes water-soluble viscous
Dust agent coating.
8. paint spraying system according to claim 1, which is characterized in that the floor of the paint spray booth is provided with sink, institute
It states sink to cover by grid, track is provided on the grid, is provided with vehicle location slot on the track.
9. paint spraying system according to claim 8, which is characterized in that be additionally provided with fan, the wind in the paint spray booth
Coating cloud drainage in part is entered sink by fan.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821825055.6U CN209393429U (en) | 2018-11-07 | 2018-11-07 | Paint spraying system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821825055.6U CN209393429U (en) | 2018-11-07 | 2018-11-07 | Paint spraying system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209393429U true CN209393429U (en) | 2019-09-17 |
Family
ID=67879467
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201821825055.6U Active CN209393429U (en) | 2018-11-07 | 2018-11-07 | Paint spraying system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209393429U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110732446A (en) * | 2019-10-31 | 2020-01-31 | 重庆市佳禾家具制造有限公司 | board spraying process |
CN113663999A (en) * | 2021-08-18 | 2021-11-19 | 黑龙江华明管业有限公司 | Spout zinc case convenient to clearance is inside |
-
2018
- 2018-11-07 CN CN201821825055.6U patent/CN209393429U/en active Active
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110732446A (en) * | 2019-10-31 | 2020-01-31 | 重庆市佳禾家具制造有限公司 | board spraying process |
CN110732446B (en) * | 2019-10-31 | 2021-09-07 | 重庆市佳禾家具制造有限公司 | Door panel spraying process |
CN113663999A (en) * | 2021-08-18 | 2021-11-19 | 黑龙江华明管业有限公司 | Spout zinc case convenient to clearance is inside |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US6124044A (en) | Polymeric peel-off coating compositions and methods of use thereof | |
CN209393429U (en) | Paint spraying system | |
CN101450343B (en) | Coating method of building materials | |
CN101341304A (en) | Material for indoor decoration, coating method and material thereof | |
CN101861212A (en) | Have the robot of cleaning device and the method for work of attaching troops to a unit | |
NZ578514A (en) | Fluid filter system with filters of three different density materials and method | |
CN2821006Y (en) | Self cleaning building wall material | |
CN110152955A (en) | A kind of intelligent and high-efficiency no sag automobile grid spraying process | |
CN205392864U (en) | Paint spray booth | |
CN102167522A (en) | Method for producing uvioresistant nano self-cleaning automobile glass | |
CN208810405U (en) | A kind of environmental protection type moving paint spray booth | |
CN206965994U (en) | A kind of portable paint spray booth bassinet structure | |
CN214183726U (en) | Quick paint spraying apparatus of surface for hardware component processing | |
CN204842072U (en) | Oil spout workstation | |
CN207385018U (en) | UV coating clouds separate eliminating equipment | |
CN205833490U (en) | A kind of environmental protection paint spraying booth | |
CN105623450B (en) | A kind of environmentally friendly dust-binding membrane and its preparation method and application | |
EP1333938A1 (en) | Polymeric peel-off coating compositions and method of use thereof | |
JP2707931B2 (en) | Ducting equipment for painting | |
CN108395739A (en) | A kind of special self-cleaning protective agent of architecture indoor metope and preparation method and application method | |
CN109668196A (en) | A kind of electron ion purification of waste gas system and its production technology with Nano self-cleaning | |
CN202099962U (en) | Aluminum plate with self-cleaning function | |
CN207343121U (en) | A kind of spray robot | |
CN105665207A (en) | Process for shielding engine part label | |
CN116200062B (en) | Additive for preventing paint surface from being polluted, and preparation method and application thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |