- CN209387715U CN209387715U CN201920103831.XU CN201920103831U CN209387715U CN 209387715 U CN209387715 U CN 209387715U CN 201920103831 U CN201920103831 U CN 201920103831U CN 209387715 U CN209387715 U CN 209387715U
- Authority
- CN
- China
- Prior art keywords
- power data
- electric power
- intelligent electric
- early warning
- electricity consumption
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Abstract
The utility model discloses remote user's intelligent electric meters to take control and abnormal electricity consumption early warning system, including intelligent electric meter, custom power data management end, server and mobile terminal;Custom power data management end includes the first electric power data processor, the second electric power data processor, electric power data comparing unit, timer, memory, expense computing controller, wireless communication module, breaker;The utility model can not only realize that power fluctuation monitors, while can monitor electric energy service condition;Abnormal power condition can be more precisely judged according to local electric power data library;Power supply can be quickly disconnected in unstable power, protect electrical equipment;It is able to carry out electricity expense calculating, and electricity usage situation and cost information are pushed to mobile terminal, is convenient for user monitoring and operation, when electricity consumption exceeds early warning value, excess warning message is uploaded and is sent to mobile terminal, be convenient for user query.
Description
Technical field
The utility model relates to intelligent electric meter systems more particularly to remote user's intelligent electric meter to take control and abnormal electricity consumption early warning
System.
Background technique
With the universalness of intelligent electric meter, for the good application of intelligent electric meter, there are still very large space, electrical managements
It is related to electricity charge calculating, power monitoring, so that electrical management is complex, existing power monitoring room uses collector by ammeter number
It according to management end is transferred to, not only has a single function, does not have the function of power fluctuation monitoring, the utilization of intelligent electric meter is not enough filled
Point;Data are acquired and are transmitted by collector, need complicated route;Furthermore also few can be accurate according to local data base
Monitoring electric power data is able to achieve the product of remaining sum early warning again.
Utility model content
The purpose of this utility model be that solve the above-mentioned problems and provide remote user's intelligent electric meter expense control and it is different
Common electricity early warning system, including intelligent electric meter, custom power data management end, server and mobile terminal;The intelligent electric meter
It is detected for electric power data;Custom power data management end includes the first electric power data processor, at the second electric power data
Manage device, electric power data comparing unit, timer, memory, expense computing controller, wireless communication module, breaker;The intelligence
Energy ammeter output end is connected with the first electric power data processor input terminal, the second electric power data processor input terminal respectively;It is described
First electric power data processor is connected with timer, memory, calculates for the storage of intelligent electric meter data, electric power data;It is described
First electric power data processor output end, the second electric power data processor output end connect the input of electric power data comparing unit respectively
End;The electric power data comparing unit output first electric power data processor input terminal of termination;The first electric power data processing
Device exports termination expense computing controller input terminal;The expense computing controller output end and breaker, wireless communication module
Connection;Custom power data management end is connected by server with mobile terminal, and remote power data monitoring, price are used for
Setting is transmitted with warning information.
Further, the wireless communication module is ZigBee module.
Further, the electric power data comparing unit includes comparator circuit.
It further, further include outage detection module;The outage detection module includes voltage collection circuit, charge and discharge electricity
Appearance, booster circuit, comparator circuit;The discharge capacity is for providing reference voltage;The voltage collection circuit passes through charge and discharge
Capacitor is connected with booster circuit input terminal;The booster circuit output terminates the comparator circuit;The voltage acquisition electricity
Road is connected with the comparator circuit;The comparator circuit output end is connected with the expense computing controller.
Further, custom power data management end further includes display;The display and expense, which calculate, to be controlled
Device output end is connected.
Further, custom power data management end further includes camera and face recognition module;The camera
It is connected by face recognition module with expense computing controller.
Further, custom power data management end further includes bank's card reader;Bank's card reader with
The expense computing controller is connected.
The utility model has the beneficial effects that: the utility model can not only realize that power fluctuation monitors, while can
Monitor electric energy service condition;Abnormal power condition can be more precisely judged according to local electric power data library;It can be in electric power
When unstable, power supply is quickly disconnected, protects electrical equipment;It is able to carry out electricity expense calculating, and by electricity usage situation and is taken
It is pushed to mobile terminal with information, is convenient for user monitoring and operation, when electricity consumption exceeds early warning value, uploads excess warning message simultaneously
It is sent to mobile terminal, is convenient for user query.
Detailed description of the invention
Fig. 1 is the system diagram of the control of remote user's intelligent electric meter expense and abnormal electricity consumption early warning system;
Fig. 2 is powered off the schematic diagram of detection module.
Specific embodiment
The utility model is described in further detail with reference to the accompanying drawing:
As shown in Fig. 1, the utility model remote user intelligent electric meter takes control and abnormal electricity consumption early warning system, including intelligence
Ammeter, custom power data management end, server and mobile terminal;The intelligent electric meter is detected for electric power data;The use
Family electric power data management end includes the first electric power data processor, the second electric power data processor, electric power data comparing unit, meter
When device, memory, expense computing controller, wireless communication module, breaker;The intelligent electric meter output end is electric with first respectively
Force data processor input terminal, the second electric power data processor input terminal are connected;The first electric power data processor and timing
Device, memory are connected, and calculate for the storage of intelligent electric meter data, electric power data;The first electric power data processor output end,
Second electric power data processor output end connects electric power data comparing unit input terminal respectively;The electric power data comparing unit output
Terminate the first electric power data processor input terminal;The first electric power data processor output termination expense computing controller input
End;The expense computing controller output end is connect with breaker, wireless communication module;Custom power data management end is logical
It crosses server to be connected with mobile terminal, be transmitted for remote power data monitoring, price fixing and warning information.
Intelligent electric meter output voltage current analog signal to the first electric power data processor and the second electric power data processor,
Electric power data comparing unit is comparator, for compare the output of the first electric power data processor based on normal electricity database
Threshold value, the storage of electric power data library and memory, memory also store having time data, when electric power data is the second electric power number extremely
When being greater than the first electric power data processor output valve according to processor output data, when comparator exports high level, the first electric power number
Expense computing controller is output control signals to according to processor, control breaker disconnects power delivery circuit.
Further, the wireless communication module is ZigBee module.
Further, the electric power data comparing unit includes comparator circuit.
It further, further include outage detection module;As shown in Fig. 2, the outage detection module includes voltage acquisition
Circuit, charge and discharge capacitance, booster circuit, comparator circuit;The discharge capacity is for providing reference voltage;The voltage acquisition
Circuit is connected by charge and discharge capacitance with booster circuit input terminal;The booster circuit output terminates the comparator circuit;Institute
Voltage collection circuit is stated to be connected with the comparator circuit;The comparator circuit output end and the expense computing controller phase
Even.Because when Sorry, your ticket has not enough value or voltage fluctuation is excessive or curent change is abnormal, expense computing controller is defeated after power system calculation
High level signal triggers circuit breaker trip out, disconnects power delivery circuit.Whether outage detection module detection circuit powers off;Charge and discharge electricity
Hold and pass through booster circuit output reference voltage, exports low and high level signal to expense computing controller by comparator circuit and carry out
Outage detection.
Further, custom power data management end further includes display;The display and expense, which calculate, to be controlled
Device output end is connected.
Further, custom power data management end further includes camera and face recognition module;The camera
It is connected by face recognition module with expense computing controller, realizes recognition of face landing charge control system.
Further, custom power data management end further includes bank's card reader;Bank's card reader with
The expense computing controller is connected.
The utility model can not only realize that power fluctuation monitors, while can monitor electric energy service condition;It being capable of foundation
Local electric power data library, more precisely judges abnormal power condition;Power supply can be quickly disconnected in unstable power, protected
Protect electrical equipment;It is able to carry out electricity expense calculating, and electricity usage situation and cost information are pushed to mobile terminal, is convenient for
User monitoring and operation.When electricity consumption exceeds early warning value, uploads excess warning message and be sent to mobile terminal, looked into convenient for user
It askes.
The limitation that the technical solution of the utility model is not limited to the above specific embodiments, all skills according to the present utility model
The technology deformation that art scheme is made, each falls within the protection scope of the utility model.
Claims (7)
1. remote user's intelligent electric meter takes control and abnormal electricity consumption early warning system, which is characterized in that including intelligent electric meter, custom power
Data management end, server and mobile terminal;The intelligent electric meter is detected for electric power data;The custom power data management
End includes the first electric power data processor, the second electric power data processor, electric power data comparing unit, timer, memory, takes
With computing controller, wireless communication module, breaker;The intelligent electric meter output end is defeated with the first electric power data processor respectively
Enter end, the second electric power data processor input terminal is connected;The first electric power data processor is connected with timer, memory,
It is calculated for the storage of intelligent electric meter data, electric power data;At the first electric power data processor output end, the second electric power data
Reason device output end connects electric power data comparing unit input terminal respectively;The electric power data comparing unit output first electric power number of termination
According to processor input terminal;The first electric power data processor exports termination expense computing controller input terminal;The expense meter
Controller output end is calculated to connect with breaker, wireless communication module;Custom power data management end is by server and moves
Dynamic terminal is connected, and transmits for remote power data monitoring, price fixing and warning information.
2. remote user's intelligent electric meter takes control and abnormal electricity consumption early warning system according to claim 1, which is characterized in that described
Wireless communication module is ZigBee module.
3. remote user's intelligent electric meter takes control and abnormal electricity consumption early warning system according to claim 1, which is characterized in that described
Electric power data comparing unit includes comparator circuit.
4. remote user's intelligent electric meter takes control and abnormal electricity consumption early warning system according to claim 1, which is characterized in that also wrap
Include outage detection module;The outage detection module includes voltage collection circuit, charge and discharge capacitance, booster circuit, comparator electricity
Road;The discharge capacity is for providing reference voltage;The voltage collection circuit is inputted by charge and discharge capacitance and booster circuit
End is connected;The booster circuit output terminates the comparator circuit;The voltage collection circuit and the comparator circuit phase
Even;The comparator circuit output end is connected with the expense computing controller.
5. remote user's intelligent electric meter takes control and abnormal electricity consumption early warning system according to claim 1, which is characterized in that described
Custom power data management end further includes display;The display is connected with expense computing controller output end.
6. remote user's intelligent electric meter takes control and abnormal electricity consumption early warning system according to claim 1, which is characterized in that described
Custom power data management end further includes camera and face recognition module;The camera passes through face recognition module and expense
Computing controller is connected.
7. remote user's intelligent electric meter takes control and abnormal electricity consumption early warning system according to claim 1, which is characterized in that described
Custom power data management end further includes bank's card reader;Bank's card reader and the expense computing controller phase
Even.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201920103831.XU CN209387715U (en) | 2019-01-22 | 2019-01-22 | Remote user's intelligent electric meter takes control and abnormal electricity consumption early warning system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201920103831.XU CN209387715U (en) | 2019-01-22 | 2019-01-22 | Remote user's intelligent electric meter takes control and abnormal electricity consumption early warning system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209387715U true CN209387715U (en) | 2019-09-13 |
Family
ID=67853758
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201920103831.XU Expired - Fee Related CN209387715U (en) | 2019-01-22 | 2019-01-22 | Remote user's intelligent electric meter takes control and abnormal electricity consumption early warning system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209387715U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113110173A (en) * | 2021-04-14 | 2021-07-13 | 北京正能远传节能技术研究院有限公司 | Control system for remote transmitting meter |
-
2019
- 2019-01-22 CN CN201920103831.XU patent/CN209387715U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113110173A (en) * | 2021-04-14 | 2021-07-13 | 北京正能远传节能技术研究院有限公司 | Control system for remote transmitting meter |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN204559175U (en) | A kind of electric automobile charging pile intelligent monitoring and controlling device | |
US20160197478A1 (en) | Power management device and system | |
CN204993616U (en) | Surveillance camera machine and wireless camera system with long -range function of awakeing up | |
US8699191B2 (en) | Power management arrangement and method in a utility meter | |
AU2007356889A1 (en) | System and method for transferring electrical power between grid and vehicle | |
CN108767892B (en) | Charging station system of electric automobile | |
CN105539177A (en) | Internet of things-based intelligent charging pile for electric automobile | |
CN103208845A (en) | Intelligent charging management terminal and implementation method for same | |
CN107404149A (en) | A kind of storage battery parallel power supply system based on straight-flow system | |
CN206031102U (en) | Intelligence direct current fills electric pile | |
CN209387715U (en) | Remote user's intelligent electric meter takes control and abnormal electricity consumption early warning system | |
CN201765272U (en) | Three-fee-controlled wireless intelligent electric energy meter | |
CN203377625U (en) | Communication lithium iron phosphate battery intelligent management device | |
CN106208363A (en) | Electrical network DC power-supply system | |
CN111398746A (en) | High-voltage cable partial discharge detection device | |
CN207426715U (en) | Energy storage managing device and energy storage monitor system | |
CN213457149U (en) | Embedded non-invasive load identification system | |
CN207442461U (en) | A kind of power consuming administrative system | |
CN208316410U (en) | A kind of CAN bus based vehicle-mounted distributing monitoring system | |
CN204992155U (en) | Storage battery car charging control socket | |
CN112953001A (en) | Distributed transformer area substation device based on 4G | |
CN206650495U (en) | A kind of intelligent charging spot electric cabinet | |
CN207082121U (en) | A kind of electronic equipment energy storage monitor system | |
CN207000196U (en) | The charging pile access device and charging pile of the shared charging of multidiameter delay charge shared system parallel | |
CN109444629A (en) | A kind of ground line on-line monitoring system based on electric power wireless telecommunications |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |