CN209380716U - A kind of head rolling machine material frame - Google Patents

A kind of head rolling machine material frame Download PDF

Info

Publication number
CN209380716U
CN209380716U CN201822179640.XU CN201822179640U CN209380716U CN 209380716 U CN209380716 U CN 209380716U CN 201822179640 U CN201822179640 U CN 201822179640U CN 209380716 U CN209380716 U CN 209380716U
Authority
CN
China
Prior art keywords
platform
expected
steel
bracket
backplate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201822179640.XU
Other languages
Chinese (zh)
Inventor
王富国
杨奇
胡俊杰
刘燕
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuxi Tianchen Cold-drawing Steel Co Ltd
Original Assignee
Wuxi Tianchen Cold-drawing Steel Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuxi Tianchen Cold-drawing Steel Co Ltd filed Critical Wuxi Tianchen Cold-drawing Steel Co Ltd
Priority to CN201822179640.XU priority Critical patent/CN209380716U/en
Application granted granted Critical
Publication of CN209380716U publication Critical patent/CN209380716U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Metal Rolling (AREA)

Abstract

The utility model provides a kind of head rolling machine material frame, including pedestal, the pedestal is the square plate of setting on the ground, there are two brackets for the both ends installation of the pedestal, the lower end of the bracket is fixedly connected with bottom plate at triangle, material rack backplate is installed among two brackets being mounted on the base, the middle section of the material frame backplate is re-entrant cavity, expect that the re-entrant cavity of frame backplate forms storage space, for placing the steel for having carried out rolling head operation, it is equipped on one of bracket of two brackets and rolls material platform, platform to be expected is installed on another bracket, it is described roll material platform and platform to be expected be long column construction, the platform to be expected and the material stage+module that rolls are above the re-entrant cavity of material frame backplate, and it is high that material platform is rolled described in the platform ratio to be expected.By the utility model, to solve traditional head rolling machine feeding style low efficiency of the existing technology, steel stack unordered problem.

Description

A kind of head rolling machine material frame
Technical field
The utility model relates to a kind of feed devices, and in particular to a kind of head rolling machine material frame.
Background technique
In field of machining, cold-drawn structural steel requires to carry out rolling head operation before carrying out cold drawing operation.And for bar The steel of shape, strip, such as big round steel, square band steel, traditional method is to carry steel manually by operating personnel to rolling head Machine carries out pricking head operation.But since the usual volume of steel to rolling head is larger, quantity is more, for operating personnel, removes Industry large labor intensity is operated, low efficiency, steel are often stacked unordered.
Utility model content
The utility model provides a kind of head rolling machine material frame, to solve traditional head rolling machine feeding style of the existing technology Low efficiency, steel stack unordered problem.
In order to solve the above technical problems, the utility model provides a kind of head rolling machine material frame, including pedestal, the pedestal is to set Square plate on the ground is set, there are two brackets for the both ends installation of the pedestal, and the lower end of the bracket and bottom plate are at triangle Shape is fixedly connected, and material rack backplate is installed among two be mounted on the base bracket, the middle section of the material frame backplate is The re-entrant cavity of re-entrant cavity, material frame backplate forms storage space, for placing the steel for having carried out rolling head operation, two brackets One of bracket on be equipped with and roll material platform, platform to be expected is installed on another bracket, it is described to roll material platform and wait expect Platform is long column construction, the platform to be expected and it is described roll material stage+module material frame backplate re-entrant cavity above, and It is high that material platform is rolled described in the platform ratio to be expected.
Described roll expects that platform and platform to be expected are separately mounted on two brackets by rotational pin.
The utility model bring the utility model has the advantages that the utility model head rolling machine material frame, setting material rack backplate, to roll material flat Platform and platform to be expected, the re-entrant cavity of material frame backplate form storage space and roll material for placing the steel for having carried out rolling head operation Platform is used to place the steel for carrying out rolling head operation, and platform to be expected is used to place the steel that preparation carries out rolling head operation, is rolled When head operation, cold-drawn structural steel is pushed into head rolling machine on material platform and carries out rolling head operation from rolling by operating personnel, roll it is good after cold drawing type Steel is put in the re-entrant cavity of entering bin backplate, and entire operation process is continuously smooth, the steel point finished to rolling head steel and rolling head Area is placed, and it is orderly reasonable that steel are stacked, and greatly reduces labor intensity, improves working efficiency.
Detailed description of the invention
Fig. 1 is the main view of the head rolling machine material frame of the utility model embodiment.
Fig. 2 is the side view of the head rolling machine material frame of the utility model embodiment.
Fig. 3 is the operation schematic diagram of the head rolling machine material frame of the utility model embodiment.
Wherein, 1- pedestal, 2- bracket, 3- expect that frame backplate, 4- roll material platform, 5- platform to be expected, 6- rotational pin, 7- steel.
Specific embodiment
To keep the purpose of this utility model, technical solution and advantage clearer, below in conjunction with drawings and the specific embodiments, The utility model is described in further detail.
As shown in Figs. 1-2, the utility model provides a kind of head rolling machine material frame, including pedestal 1, and the pedestal 1 is that setting exists Square plate on ground, there are two brackets 2 for the both ends installation of the pedestal 1, and the lower end of the bracket 2 and bottom plate are at triangle It is fixedly connected, material rack backplate 3 is installed, the middle section of the material frame backplate 3 is among two be mounted on the base bracket 2 The re-entrant cavity of re-entrant cavity, material frame backplate 3 forms storage space, for placing the steel for having carried out rolling head operation, two branch It is equipped on one of bracket 2 of frame and rolls material platform, for placing the steel for carrying out rolling head operation, installed on another bracket Need to be expected platform, (for place preparation carry out rolling head operation steel, it is described roll material platform 4 and platform to be expected 5 be long cylindricality Structure, the platform 5 to be expected and the material platform 4 that rolls are mounted on above the re-entrant cavity of material frame backplate, and the platform to be expected 5 Expect that platform 4 is high than described roll.
Material platform 4 and the platform to be expected 5 of rolling is separately mounted on two brackets 2 by rotational pin 6.So that rolling material platform 4 and platform to be expected 5 can with rotational pin 6 be axis be overturn, has carried out prick head operation after, will roll expect platform and platform to be expected it is past Upper overturning, so that not blocking above the re-entrant cavity of material frame backplate, convenient lifting steel upwards, transfer has carried out pricking head operation Steel 7.
The head rolling machine material frame of the utility model, is cold-drawn structural steel before cold drawing, provides the feeding of steel for rolling head process Device is particularly suitable for the rolling head operation of rod-shaped, strip or the biggish steel of area.
The course of work of the utility model: as shown in figure 3, when operation, usually by the head rolling machine material of two playscript with stage directions utility models Frame is placed side by side, by preparation carry out rolling head operation steel lie in a horizontal plane in two bench dog machine material framves wait expect on platform, carry out When rolling head operation, worker from wait expect on platform take out a steel be placed on roll material platform on, operating personnel from roll material platform on will Cold-drawn structural steel is pushed into head rolling machine and carries out rolling head operation, and the cold-drawn structural steel after rolling well is put in the re-entrant cavity of entering bin backplate, owns Steel have carried out after pricking head operation, will roll material platform and platform to be expected up is overturn, above the re-entrant cavity for expecting frame backplate at this time It does not block, lifts by crane steel upwards, transfer prick the steel of head operation.In this way, make entire operation process continuously smooth, The steel subregion finished to rolling head steel and rolling head is placed, and without any confusion, can be substantially reduced labor intensity, be improved working efficiency, And security risk is not present.
In conclusion the head rolling machine material frame of the utility model, setting material rack backplate roll material platform and platform to be expected, material The re-entrant cavity of frame backplate forms storage space, for placing the steel for having carried out rolling head operation, rolls material platform for being placed into The steel of row rolling head operation, platform to be expected are used to place the steel that preparation carries out rolling head operation, when carrying out rolling head operation, operation people Cold-drawn structural steel is pushed into head rolling machine on material platform and carries out rolling head operation from rolling by member, roll it is good after cold-drawn structural steel put entering bin backplate In re-entrant cavity, entire operation process is continuously smooth, and the steel subregion finished to rolling head steel and rolling head is placed, and steel are stacked with Sequence is reasonable, greatly reduces labor intensity, improves working efficiency.
The above description is only the embodiments of the present invention, is not intended to limit the utility model, for this field Technical staff for, various modifications and changes may be made to the present invention.Within the spirit and principle of the utility model, Any modification, equivalent replacement, improvement and so on should be included within the scope of the claims of the utility model.

Claims (2)

1. a kind of head rolling machine material frame, including pedestal (1), the pedestal (1) is the square plate of setting on the ground, the pedestal (1) both ends installation is there are two bracket (2), and the lower end of the bracket (2) is fixedly connected with bottom plate at triangle, and feature exists In installation material rack backplate (3) among two brackets (2) being mounted on the base, the middle section of the material frame backplate (3) is The re-entrant cavity of re-entrant cavity, material frame backplate (3) forms storage space, for placing the steel for having carried out rolling head operation, two It is equipped on one of bracket (2) of bracket and rolls material platform, platform to be expected is installed on another bracket, it is described to roll material platform (4) and platform to be expected (5) is long column construction, and the platform (5) to be expected and material platform (4) that rolls are mounted on material frame backplate Re-entrant cavity above, and it is high described in the platform to be expected (5) ratio to roll material platform (4).
2. head rolling machine material frame as described in claim 1, which is characterized in that described roll expects that platform (4) and platform to be expected (5) pass through Rotational pin (6) is separately mounted on two brackets (2).
CN201822179640.XU 2018-12-24 2018-12-24 A kind of head rolling machine material frame Active CN209380716U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201822179640.XU CN209380716U (en) 2018-12-24 2018-12-24 A kind of head rolling machine material frame

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201822179640.XU CN209380716U (en) 2018-12-24 2018-12-24 A kind of head rolling machine material frame

Publications (1)

Publication Number Publication Date
CN209380716U true CN209380716U (en) 2019-09-13

Family

ID=67873559

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201822179640.XU Active CN209380716U (en) 2018-12-24 2018-12-24 A kind of head rolling machine material frame

Country Status (1)

Country Link
CN (1) CN209380716U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111014313A (en) * 2019-12-10 2020-04-17 江苏鑫乾冷拉型钢有限公司 Auxiliary processing equipment for heading machine

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111014313A (en) * 2019-12-10 2020-04-17 江苏鑫乾冷拉型钢有限公司 Auxiliary processing equipment for heading machine

Similar Documents

Publication Publication Date Title
CN103213113A (en) Material rack provided with automatic overturning structure
CN209380716U (en) A kind of head rolling machine material frame
CN206050928U (en) A kind of carrying implement for panel in battenboard
CN203781754U (en) Movable weight hoister
CN201501739U (en) Self-clamping type horizontal cross coil steel hanging tong
CN201544217U (en) Improved roller placing rack
CN201472693U (en) Vertical steel coil packaging machine
CN203141478U (en) Material rack with automatic turnover mechanism
CN212884206U (en) Disc steel bar unwinding frame
CN210175547U (en) Cable drum transportation frame
CN208855683U (en) A kind of working roll cart
CN203141641U (en) Pipe drawing device of mold enabling multiple building blocks to be formed at one time
CN216038166U (en) Multifunctional hanging device for mounting building construction formwork
CN210098548U (en) Automatic feeding device of diameter reducing machine
CN205120757U (en) A auxiliary stand that is used for charge / discharge cabinet battery to put on shelf
CN202807193U (en) Flat steel collecting device
CN108115030A (en) A kind of punching die frame of automatic charging discharging
CN102795370B (en) Flat steel collecting device
CN211565841U (en) Fabric storage rack convenient to move
CN211520997U (en) Wire rod take-up device
CN211027829U (en) Clamping mechanism of plate bending machine
CN210365845U (en) Multi-stage lifting device for long steel bar
CN204842476U (en) Automatic cold pilger mill who packs
CN216233910U (en) Novel steel band coiled material storage rack
CN209773115U (en) Adjustable take-up and pay-off device for coal mine

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant