CN209350533U - A kind of concreting mold assembly overturning platform - Google Patents

A kind of concreting mold assembly overturning platform Download PDF

Info

Publication number
CN209350533U
CN209350533U CN201821239204.0U CN201821239204U CN209350533U CN 209350533 U CN209350533 U CN 209350533U CN 201821239204 U CN201821239204 U CN 201821239204U CN 209350533 U CN209350533 U CN 209350533U
Authority
CN
China
Prior art keywords
buffer
platform
pedestal
sliding block
sliding rail
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821239204.0U
Other languages
Chinese (zh)
Inventor
闫兴非
文小东
姚嘉轶
宗霏
张彦
张凯龙
丛旭
陈沣
陈锋
方科
眭书剑
黄逸飞
杨益帆
陈星霖
于沛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chengdu Investment And Investment Building Industrialization Co Ltd
Original Assignee
Chengdu Investment And Investment Building Industrialization Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chengdu Investment And Investment Building Industrialization Co Ltd filed Critical Chengdu Investment And Investment Building Industrialization Co Ltd
Priority to CN201821239204.0U priority Critical patent/CN209350533U/en
Application granted granted Critical
Publication of CN209350533U publication Critical patent/CN209350533U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The utility model discloses a kind of concreting mold assembly to overturn platform.Including assembly mounting platform, platform one end is arranged turnover mechanism, turnover mechanism include assembly be integrally connected be articulated with level ground pedestal, ground level arranges two sliding rails, every sliding rail one end is provided with buffer, has sliding block buffer front end in sliding rail mobile;Pedestal and sliding block are hinged with slide arm both ends respectively;For buffer in base turning, sliding block is mobile and contacts buffer realization buffering.Displacement of the utility model using damp type overturning platform for assembly is erect, platform by with steel reinforcement cage and pour pedestal that mold assemblies are connected as one ground be fixed on by articulated structure, complete to tie up and combine install after can directly carry out overturning setting;The overturning sliding block that front end is arranged when standing upright is contacted with buffer, buffers impulse force when standing upright, is made whole more stable safety, is realized the slow setting of mold entirety, improve operation stability and safety.

Description

A kind of concreting mold assembly overturning platform
Technical field
The utility model belongs to Architectural Equipment design field, especially belongs to concrete placing installation design and manufacturing technology Field, in particular to it is a kind of to overturn platform for concreting mold assembly used in concreting process.
Background technique
It is usually to pour construction in construction ground scene progress bridge pier that existing highway bridge, which is built, then carries out box girder webs Or will be completed after the synthesis construction of prefabricated profiled box beam, building technology is required to carry out large-scale cast in situs construction.With Being constantly progressive for bridge construction technology, bridge construction scale is increasing, pours and builds for carrying out bridge pier at construction ground scene It makes and is usually limited by conditions such as environment, construction organization is sufficiently complex, and construction cost is high, and the construction period is long.
Have at present and carry out the prefabricated construction technology poured of bridge pier in scale pre-fabricated factory, batch production is prefabricated, and pour can be with It significantly saves the time, guarantees construction duration, while can more guarantee quality, save the cost and reduction security risk.Usually exist It includes: the tying up of steel reinforcement cage, the combination installation and concreting of bridge pier mold that prefabricated pour of bridge pier is carried out under the conditions of batch production Etc. techniques;Wherein, since bridge pier usually height is higher, steel reinforcement cage and mold are completed using the method laterally tied up and installed Tie up with mold installation after overturn casting concrete again of attentioning, since steel reinforcement cage and mold weight are larger, and with bridge pier bottom Seat combines as a whole, and overturns in attentioning and usually occurs swinging and controlling the insecurity factors such as difficulty.
Summary of the invention
Deficiency discloses a kind of concreting mold assembly overturning platform to the utility model according to prior art.This reality It to solve the problems, such as to be to provide a kind of concreting mold assembly overturning platform with cushion performance with novel, it is flat using this When the assembly of platform progress steel reinforcement cage and mold overturns operation, steel reinforcement cage and bridge pier mold assemblies are attentioned by laterally horizontally-arranged overturning Be not in vertical preceding unexpected swing into vertical placement process, can be realized the slow setting of mold entirety, improve work Industry stability and safety.
The utility model is achieved through the following technical solutions:
Concreting mold assembly overturn platform, including for concreting steel reinforcement cage and mold assemblies installation Platform, it is characterised in that:
Turnover mechanism is arranged in platform one end, and the turnover mechanism with flowering structure by being constituted:
Can with steel reinforcement cage and pour the pedestal that mold assemblies are integrally connected, the hinge that pedestal is articulated with level ground connects It is can be achieved on lug from vertically to horizontal overturning;
Ground level arranges two sliding rails, and every sliding rail one end is provided with buffer, has sliding block in sliding rail before buffer End movement;
Pedestal and sliding block are hinged with slide arm both ends respectively;
For buffer in free state forward terminal location arrangements when base turning inclination 30-45 is spent, slide arm drives sliding block to move The dynamic position that can contact buffer.
Buffer described further is buffer spring, and spring one end is arranged in sliding rail outer end.
Further sliding rail is groove structure, and buffer front end arranges that sliding block is in the groove of buffer front end in a groove It is mobile.
The sliding rail has bumper end to be provided with backstop, sliding block endpoint location when backstop is set to pedestal horizontality.
The utility model is used to tie up the steel reinforcement cage and pour that completion and combination are installed using damp type overturning platform The displacements of mold assemblies is erect, platform by with steel reinforcement cage and pour the pedestal that mold assemblies are connected as one and pass through and hingedly tie Structure is fixed on ground, and completion can directly carry out overturning setting after tying up and combining installation;Due to steel reinforcement cage and mold assemblies For metal component, weight is larger, is overturning when standing upright, when center of gravity changes, due to gravity, and steel reinforcement cage and set of molds Zoarium can be accelerated across equalization point, and Integral swinging, suspender and assembly often occurs in excessive impact force, and there are huge safety is hidden Suffer from;The utility model uses Damping sliding rail structure, when center of gravity is displaced on integrated pedestal, the sliding block and buffering of front end setting Device contact, buffers impulse force when standing upright, makes whole more stable safety, realizes the slow setting of mold entirety, it is steady to improve operation Qualitative and safety.
Detailed description of the invention
Fig. 1 is the utility model prefabricated platform turnover mechanism structural schematic diagram;
Fig. 2 is the utility model prefabricated platform turnover mechanism rollover states schematic diagram;
Fig. 3 is that the utility model prefabricated platform turnover mechanism is totally turned over status diagram;
Fig. 4 is the prefabricated platform structural schematic diagram for including turnover mechanism.
In figure, A is pedestal, and B is buffer, and C is pedestal hinge position, and D is sliding block hinge position, and E is sliding block, and F is sliding rail, H It is slide arm, I is backstop.
Specific embodiment
The present invention will be further described With reference to embodiment, and specific embodiment is to the utility model The further explanation of principle, does not limit the utility model in any way, and technology same or like with the utility model does not have Range beyond the utility model protection.
In conjunction with attached drawing.
Concreting mold assembly overturns platform, the assembly peace including steel reinforcement cage and mold for concreting Assembling platform.
Turnover mechanism is arranged in platform one end, and turnover mechanism with flowering structure by being constituted:
Can with steel reinforcement cage and pour the pedestal A that mold is integrally connected, pedestal A is articulated with the hinge engaging lug of level ground It is upper to can be achieved from vertically to horizontal overturning;
Ground level arranges two sliding rail F, and every one end sliding rail F is provided with buffer B, has sliding block E to buffer in sliding rail F The front end device B is mobile;
Pedestal A and sliding block E is hinged with the both ends slide arm H respectively;
For buffer B in free state forward terminal location arrangements when pedestal A tip tilt 30-45 is spent, slide arm H drives sliding block The mobile position that can contact buffer B E.
This example buffer B is buffer spring, and spring one end is arranged in the outer end sliding rail F.Sliding rail F is groove structure, buffering The front end device B arranges that sliding block E is moved in the groove of the front end buffer B in a groove.
The utility model sliding rail F has the end buffer B to be provided with backstop I, sliding block E when backstop I is set to pedestal A horizontality Endpoint location.
As shown in Figure 1, Figure 2, Figure 3 shows, Fig. 1 is the utility model prefabricated platform turnover mechanism structural schematic diagram, and Fig. 2 is this reality With novel prefabricated platform turnover mechanism rollover states schematic diagram, Fig. 3 is that the utility model prefabricated platform turnover mechanism is totally turned over Status diagram;The platform that mold assemblies installation was tied up and poured to steel reinforcement cage is not represented in above-mentioned figure, is merely representative of Turnover mechanism, Fig. 1 are pedestal A upright state, the state steel reinforcement cage and to pour mold be accumbency state;Fig. 2 is pedestal A inclination State, the state steel reinforcement cage and pours mold and also tilts, and pedestal A drives sliding block E mobile and comes into contact with buffering by slide arm H The front end of device B, buffer B compress and buffer steel reinforcement cage and pour the impact of mold assemblies setting;Fig. 3 is complete compression shape State, steel reinforcement cage and pours mold and has erect completion.
The utility model buffer B preferably uses spring buffer, and spring may be mounted in sliding rail F groove, can also portion Divide and be mounted in sliding rail F groove, is partially installed in the limitation cylinder of the outer end sliding rail F, however, which kind of structure, has slow in sliding rail F It rushes the end device B and is provided with backstop I, sliding block E endpoint location, backstop I can be limited further when backstop I is set to pedestal A horizontality The movement of position sliding block E, guarantees the safety of overturning.
Fig. 4 is the prefabricated platform structural schematic diagram for including turnover mechanism, is tied up including the steel reinforcement cage for concreting With pour mold assemblies mounting platform, turnover mechanism is set to platform one end.

Claims (4)

1. a kind of concreting mold assembly overturns platform, including the steel reinforcement cage and mold assemblies for concreting Mounting platform, it is characterised in that:
Platform one end is provided with turnover mechanism, and the turnover mechanism with flowering structure by being constituted:
The pedestal (A) that can be integrally connected with steel reinforcement cage and mold assemblies, pedestal (A) are articulated with the hinge connection of level ground It is can be achieved on ear from vertically to horizontal overturning;
Ground level arranges two sliding rails (F), and every sliding rail (F) one end is provided with buffer (B), has sliding block (E) at sliding rail (F) The middle buffer front end (B) is mobile;
Pedestal (A) and sliding block (E) are hinged with the both ends slide arm (H) respectively;
Buffer (B) in free state forward terminal location arrangements when pedestal (A) tip tilt 30-45 is spent, slide by slide arm (H) driving The mobile position that can contact buffer (B) of block (E).
2. concreting mold assembly according to claim 1 overturns platform, it is characterised in that: the buffer (B) It is buffer spring, spring one end is arranged in the outer end sliding rail (F).
3. concreting mold assembly according to claim 1 overturns platform, it is characterised in that: the sliding rail (F) is Groove structure, the buffer front end (B) arrange that sliding block (E) moves in the groove of the front end buffer (B) in a groove.
4. concreting mold assembly according to claim 1 or 2 or 3 overturns platform, it is characterised in that: the sliding rail (F) end buffer (B) is provided with backstop (I), sliding block (E) endpoint location when backstop (I) is set to pedestal (A) horizontality.
CN201821239204.0U 2018-08-02 2018-08-02 A kind of concreting mold assembly overturning platform Active CN209350533U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821239204.0U CN209350533U (en) 2018-08-02 2018-08-02 A kind of concreting mold assembly overturning platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821239204.0U CN209350533U (en) 2018-08-02 2018-08-02 A kind of concreting mold assembly overturning platform

Publications (1)

Publication Number Publication Date
CN209350533U true CN209350533U (en) 2019-09-06

Family

ID=67778215

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821239204.0U Active CN209350533U (en) 2018-08-02 2018-08-02 A kind of concreting mold assembly overturning platform

Country Status (1)

Country Link
CN (1) CN209350533U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112281674A (en) * 2020-11-09 2021-01-29 成都交投建筑工业化有限公司 Construction method for horizontal turning and straightening of pier stud
CN114619416A (en) * 2022-05-16 2022-06-14 立臻精密智造(昆山)有限公司 Damping type turnover device

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112281674A (en) * 2020-11-09 2021-01-29 成都交投建筑工业化有限公司 Construction method for horizontal turning and straightening of pier stud
CN114619416A (en) * 2022-05-16 2022-06-14 立臻精密智造(昆山)有限公司 Damping type turnover device
CN114619416B (en) * 2022-05-16 2022-08-02 立臻精密智造(昆山)有限公司 Damping type turnover device

Similar Documents

Publication Publication Date Title
CN209350533U (en) A kind of concreting mold assembly overturning platform
CN103255726B (en) A kind of construction method of continuous beam arch combination bridge
CN206553961U (en) The short light-duty expanded letter combined type Hanging Basket of tower cable-stayed bridge
KR101239621B1 (en) Beam launching method using beam launcher with end strut having roller guide
CN211689943U (en) Assembled pier stud template upset buffer
CN102390783B (en) The method of mobile goliath and the system of enforcement the method in installation system
CN201648971U (en) Curved box girder sliding die frame
CN202787093U (en) Hydraulic climbing formwork device universally used by skew pier and straight pier
CN113136803B (en) River-crossing steel truss bridge closure method
CN211278936U (en) Prefabricated pier stud template roll-over stand with buffer function
CN103835238B (en) A kind of high pier cable stayed bridge No. 0 block non-stand construction method and the structure in constructing
CN212358363U (en) Suspended tower crane foundation
CN116377888A (en) Adjustable flange template device of cast-in-situ beam of cable-stayed bridge and construction process
CN106401606A (en) Framework trestle trolley
JP3238751U (en) Bridge girder erection machine
CN211523118U (en) Plane shutoff gate prevents putting reinforcing apparatus
CN212245935U (en) High mound girder steel top pushes away equipment hoist device
CN108842633B (en) Bridge deck elevation adjusting method
CN210887994U (en) Multi-use architecture construction platform of adjustable height
CN114016415A (en) Big cantilever bent cap mounting structure based on permanent template of UHPC
CN111749138A (en) Three-girder moving die frame structure
CN108678464B (en) Lifting and transverse moving type stereo garage stable in operation
CN111704090A (en) Prefabricated part overturning method
CN212404872U (en) Three-girder moving die frame structure
CN114922078B (en) Synchronous rapid construction method for PC (polycarbonate) combined Liang Yi sections of corrugated steel webs

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant