CN209339936U - Controllable penetration rate combined type sand-filling apparatus - Google Patents
Controllable penetration rate combined type sand-filling apparatus Download PDFInfo
- Publication number
- CN209339936U CN209339936U CN201821787534.3U CN201821787534U CN209339936U CN 209339936 U CN209339936 U CN 209339936U CN 201821787534 U CN201821787534 U CN 201821787534U CN 209339936 U CN209339936 U CN 209339936U
- Authority
- CN
- China
- Prior art keywords
- sand
- jar block
- fill out
- pressure head
- tube
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Abstract
The utility model discloses controllable penetration rate combined type sand-filling apparatus, device includes fill out sand tube, pressure head, sand core is filled in the fill out sand tube, it further includes slide bar, scale bar, jar block that the pressure head, which is placed in fill out sand tube and is pressed on sand core, the jar block slides on slide bar, the lower end of the slider connects baffle ring, and the baffle ring is located at below jar block, to jar block axial limiting, the baffle ring lower end connects scale bar, and scale bar lower end connects pressure head.The utility model realizes stratum loose sand (or quartz sand of certain mesh number) progress jarring using quality, jar block freely falling body height and the jarring number of control jar block controllable to the permeability of sand core.
Description
Technical field
The utility model relates to indoor logistics organizations technical field, specifically controllable penetration rate combined type back-up sand is filled
It sets.
Background technique
It, need to be to different length in many indoor logistics organizations when without molding rock core or without enough actual reservoir rock cores
Sand core is filled and presented to simulate actual reservoir in the fill out sand tube of degree or different inner diameters.At present in experimental implementation, one is often used
The T-type stainless steel steel column that root and back-up sand length of tube, diameter are adapted, then stainless steel steel column top is hit with hammer to realize, but
This method exists as following drawbacks: 1, with the mode back-up sand hit is pounded, it is random to pound the dynamics of hitting, and on the one hand be easy to cause compacting uneven
Even, sand core permeability made of another aspect is also random, is unable to control the permeability for making core.And practical logistics organizations are often
The actual conditions for needing to simulate reservoir, the sand core permeability for needing to fill and present out it is controllable (such as permeability within the scope of some, Huo Zheyi
Need to fill and present the rock core of several sections of different permeabilities in root fill out sand tube), or for comparative experiments effect, logistics organizations need to carry out
Parallel laboratory test, this just needs to fill and present multiple sand cores similar in permeability.Current back-up sand method is unable to reach.2, for difference
Length (7cm~10cm~20cm~30cm~50cm~100cm or even longer), different inner diameters (usually have 2.5cm and
Fill out sand tube 3.8cm), when back-up sand, just need to be equipped with more T-type stainless steel steel columns of different length, different inner diameters, cause material
Waste.3, when needing to simulate in-layer heterogeneity in a fill out sand tube, the sand of different permeability sections can not be accurately controlled
Core length.
Application number: 201520019902.X discloses a kind of mechanical three-dimensional sandpack column compaction apparatus, mainly by handle,
Lead screw, connector, connecting rod first, crossbeam, otic placode, bracket, support plate, connecting plate first, expansion screw, connecting plate second, connects fixture nut
Bar second, squeeze board, short axle, pressure head and pressure sand mo(u)ld type composition, the handle are inserted into lead screw base apertures, swing handle, lead screw
Rotate and move upwards, lead screw lifts one end of the beam by connecting rod first, the crossbeam other end by connecting rod second push squeeze board to
The compacting work of pressure sand mo(u)ld type is realized in lower movement under pressure head effect.The beneficial effects of the utility model are as follows: three-dimensional can be achieved
The uniform compaction of sandpack column, structure is simple, time saving, laborsaving, practical, the sand mold that can be used in all kinds of stratum simulation processes
It is compacted work.
Application number: 201820369131.0 disclose a kind of vertical fill out sand tube sand-filling apparatus.It is by Universal hydraulic device, cube
Steel framework, loading pipe, hinge, fixation steel plate, fill out sand tube and vertical vibrating pump group at.The utility model makes quartz sand filling uniformly,
It can prevent Experimental Flowing Object from channelling occurs along back-up sand inside pipe wall.The device can uniform compaction fill out sand tube, work efficiency is high, is easy to push away
Extensively, strong applicability.
Application number: 201720764437.1 are related to technical field of petroleum extraction, and in particular to a kind of novel fill out sand tube combination
Device is equipped with external screw thread on the outside of fill out sand tube including the hollow tubular fill out sand tube fixed on the ground;It further include compaction apparatus, pressure
Actual load is set including being compacted cap;The compacting cap is tubular, and upper end is solid section, and solid section is connected with external vibration device;
Lower end is hollow parts, and fill out sand tube protrudes into the hollow parts, and hollow parts inner wall is equipped with matched with fill out sand tube external screw thread
Internal screw thread;It further include compaction rod, compaction rod one end is protruded into fill out sand tube, and one end is located at fill out sand tube and is compacted the hole of cap solid section
In gap.The utility model is compacted back-up sand by the internal and external threads coupling of fill out sand tube and compacting cap, so that fill out sand tube stress
More uniformly, the deformation for a long time using rear fill out sand tube is not will cause.
Application number: 201721603591.7 disclose a kind of pressure-resistant fill out sand tube, including fastener tube, the fastener tube are multiple
The stainless steel fastener tube used, the fastener tube is interior to be equipped with tube body, and the tube body is disposable fill out sand tube, the import of the tube body
End and the equal sealed set in outlet end, the tube body is interior to be equipped with husky body, and the input end of the tube body is fixedly connected with water inlet pipe, described
The one end of water inlet pipe far from tube body is through tube body and extends outwardly, and limitting casing, the limit are threaded in the fastener tube
Frame is equipped with opening corresponding with water inlet pipe.The utility model facilitates the placement of tube body by the way that tube body to be put into fastener tube,
So that it is compressed limited block by tightening limitting casing again, and then tube body is stablized, in addition fastener tube is nonexpondable in the present apparatus
Stainless steel fastener tube, tube body is disposable fill out sand tube, then at low cost, and disposable fill out sand tube is easily cut, and then facilitates scientific research people
Member is tested, to obtain accurate physical parameter.
Application number: 201420292866.X discloses a kind of automatic cycle back-up sand system, including storage sand device, back-up sand leakage
Head, oil pipe and casing, the storage sand device and back-up sand leakage head cooperation are fed, and the feed end of oil pipe, oil pipe is arranged in back-up sand leakage head
It is arranged in casing, feed end is located at outside casing, and discharge end is located in casing, and casing annulus is formed between oil pipe and casing, covers
The circulation mechanism for the liquid in casing annulus to be injected to oil pipe by oil pipe feed end is provided on pipe.It is practical new using this
After type, the control of sand face is accurate, while eliminating pump truck, reduces costs, since operation liquid forms interior circulation, decreases simultaneously
The usage amount of operation liquid.
To solve the above problems, can realize using combined type sand-filling apparatus controllable to the permeability for filling and presenting sand core, institute is filled and presented
The sand core for needing permeability meets the needs of simulation actual reservoir permeability;The high sand core of permeability repeatability is filled and presented, is met parallel
The demand of experiment;The different permeabilities combination sand core that random length can be filled and presented in a fill out sand tube, it is non-to meet simulation reservoir
The demand of matter.
Utility model content
The purpose of this utility model is to provide controllable penetration rate combined type sand-filling apparatus, utilize the matter of control jar block
Amount, jar block freely falling body height and jarring number carry out jarring, Ke Yibao to stratum loose sand (or quartz sand of certain mesh number)
The sand core permeability that card repeatedly loads is identical or substantially close to the realization purpose controllable to the permeability of sand core.
In order to achieve the above objectives, the utility model uses following technical solution, controllable penetration rate combined type back-up sand dress
It sets, including fill out sand tube, pressure head, sand core is filled in the fill out sand tube, the pressure head is placed in fill out sand tube and is pressed on sand core, also wraps
Slide bar, scale bar, jar block are included, the jar block slides on slide bar, and the lower end of the slider connects baffle ring, and the baffle ring is located at
Below jar block, to jar block axial limiting, the baffle ring lower end connects scale bar, and scale bar lower end connects pressure head.
The slide bar upper end connecting T-shaped handle, T-type handle is also to jar block axial limiting.
The jar block center opens up slide opening, and slide bar is threaded through in the slide opening of jar block, jar block sliding opposite with slide bar.
The pressure head outer diameter is consistent with back-up sand bore, and the scale bar outer diameter is less than back-up sand bore.
The slide bar upper end screw thread type connecting T-shaped handle, the slide bar screw thread type connect baffle ring, and baffle ring lower end screw thread type connects
Scale bar is connect, scale bar lower end screw thread type connects pressure head.
The utility model has the advantages that compared with prior art
1, can only with a set of combined type sand-filling apparatus can be completed different length, different inner diameters fill out sand tube back-up sand,
Tool material is greatly saved;
2, can be achieved it is controllable to the permeability of back-up sand sand core, meet more sand cores similar in indoor filling permeability and
The needs for needing the sand core of multistage difference permeability of length are loaded in a piece fill out sand tube;
3, easy to operate, can be according to different experiments demand, a people screws flexible combination can be completed manually, to meet
To the back-up sand of different length, different inner diameters and different permeability sand cores in laboratory.
Detailed description of the invention
Fig. 1 is the controllable penetration rate combined type sand-filling apparatus structural schematic diagram of the utility model.
In figure: 1-T-type handle;2-jar blocks;3-slide bars;4-baffle rings;5-scale bars;6-pressure heads;7-back-up sands
Pipe;8-sand cores.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model
Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole
Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work
Every other embodiment obtained, fall within the protection scope of the utility model.
Referring to Fig. 1, the utility model provides a kind of technical solution: controllable penetration rate combined type sand-filling apparatus, including fill out
Sandpipe 7, pressure head 6, the fill out sand tube is interior to fill sand core 8, and it further includes slide bar that the pressure head, which is placed in fill out sand tube and is pressed on sand core,
3, scale bar 5, jar block 2, the jar block slide on slide bar, and the lower end of the slider connects baffle ring 4, and the baffle ring is located at shake
Below hammer, to jar block axial limiting, the baffle ring lower end connects scale bar, and scale bar lower end connects pressure head.
The slide bar upper end connecting T-shaped handle 1, T-type handle is also to jar block axial limiting.
The jar block center opens up slide opening, and slide bar is threaded through in the slide opening of jar block, jar block sliding opposite with slide bar.
It is all the utility model that certain jar block, which slides this unlimited one kind of the mode on slide bar as long as the two opposite can be slided,
The guiding mechanisms such as protection scope, such as sliding block slide way mechanism.
The pressure head outer diameter is consistent with back-up sand bore, and the scale bar outer diameter is less than back-up sand bore.
The slide bar upper end screw thread type connecting T-shaped handle, the slide bar screw thread type connect baffle ring, and baffle ring lower end screw thread type connects
Scale bar is connect, scale bar lower end screw thread type connects pressure head.Above-mentioned various connection types are also not necessarily limited to screw thread type connection, other connections
Mode belongs to the modes such as the protection scope of the utility model, such as welding.
The T-type handle is made of the pedestal of integral type and cylinder, and internal screw thread is arranged at cylinder lower part, can be connected with slide bar;Institute
The slide bar of different length is stated, there is external screw thread at both ends;The jar block is hollow elongated cylinder, and internal diameter is slightly larger than cunning
Bar outer diameter can cover free to slide on slide bar;There is internal screw thread at the baffle ring, both ends, and outer diameter is slightly larger than in jar block
Diameter can stop when jar block slides to baffle ring jar block to continue to slide;Uniform quarter is uniformly carved on the scale bar
Degree, there is external screw thread at both ends.Scale pole length can have 10cm, 20cm more;The pressure head outer diameter is true according to back-up sand bore
It is fixed, there are commonly 2.5 centimetres and 3.8 centimetres two kinds in indoor logistics organizations, processing and fabricating can also be required according to specific experiments.
When experiment, with reference first to the assembling for shown in Fig. 1, being combined formula sand-filling apparatus.Pass through the internal and external threads of each component
Successively by T-type handle 1, slide bar 3, jar block 2, baffle ring 4, the scale bar 5 of appropriate length and outer diameter and back-up sand bore match
Pressure head 6 connect.
Then fill out sand tube back-up sand is carried out.It is measured with measuring device (devices such as graduated cylinder or measuring cup of measurable volume or quality) certain
Amount or the stratum loose sand (or quartz sand) of certain volume are poured into fill out sand tube, and combined type sand-filling apparatus pressure head end is placed in fill out sand tube
On interior sand face, T-type handle base is held on the other hand, jar block is mentioned to top end of sliding rod and then loosed one's grip on the other hand, makes jar block natural
It slides, when jar block slides to not continuing to slide at baffle ring, then repeatedly landing process n times (the jar block cunning of jar block
Process number is fallen to need to set according to experiment) complete first time back-up sand;Then pressure head is taken out, repeats first time back-up sand process,
Until fill out sand tube back-up sand is completed, due to the quality of jar block, jar block freely falling body height, jarring number, stratum loose sand quartz
The amount of sand is all constant, it is possible to guarantee that the sand core permeability repeatedly loaded is identical, realize controllable to the permeability of sand core
Purpose.Then Logistics automatic system can be carried out.
Embodiment 1:
For the requirement for meeting parallel test, load that length similar in two permeabilities is 7 centimetres, internal diameter is 2.5 centimetres
Fill out sand tube.
Choose the scale bar that length is 10 centimetres, the pressure head that outer diameter is 2.5 centimetres, referring to Fig.1 by T-type handle, slide bar, shake
Hammer, baffle ring, scale bar (length is 10 centimetres) and pressure head (outer diameter is 2.5 centimetres) connect.Dosage tolerance takes fixed body
Long-pending or fixed mass reservoir sand (or quartz sand) is fitted into fill out sand tube, and combined type sand-filling apparatus pressure head end is placed in fill out sand tube
Sand face on, jar block is mentioned to top end of sliding rod, it is then allowed to slide naturally to baffle ring, repeat jar block slide process 5 times,
Complete first time back-up sand pressure compacting;Then first time back-up sand compacting process is repeated, until fill out sand tube is filled up.
An other fill out sand tube is changed, repeats the back-up sand process of first fill out sand tube completely.Since the quality of jar block is certain,
The landing height of jar block is fixed, and the jarring number of jar block is certain, and every time plus the amount of sand is fixed, therefore jar block is to sand core
Compaction is constant, it is possible to guarantee that the sand core permeability that loads twice is identical or substantially close to can satisfy parallel test
Demand.
Embodiment 2:
Loading a root long degree is 35 centimetres, the fill out sand tube that internal diameter is 3.8 centimetres.
Choose two scale bars that length is 20 centimetres, the pressure head that outer diameter is 3.8 centimetres, referring to Fig.1 by T-type handle, cunning
Bar, jar block, (outer diameter is for baffle ring, scale bar (length is that 20 centimetres of two scale bars are also connected with baffle ring) and pressure head
3.8 centimetres) it connects.Back-up sand and debulking methods are with embodiment 1, until fill out sand tube is filled up.
Embodiment 3:
Loading a root long degree is 15 centimetres, the fill out sand tube that internal diameter is 2.5 centimetres, and sand core requires to be divided into have obvious permeability poor
Different three sections, three segment length are respectively 3 centimetres, 5 centimetres, 7 centimetres.
Choosing length is 20 centimetres of scale bar, the pressure head that outer diameter is 2.5 centimetres, referring to Fig.1 will by T-type handle, slide bar,
Jar block, baffle ring, scale bar (length is 200 centimetres) and pressure head (outer diameter is 2.5 centimetres) connect.
When back-up sand, the combined type sand-filling apparatus connected is put into empty fill out sand tube first, from the upper surface of fill out sand tube
The reading L1 on scale bar is read in place's head-up, then in fill out sand tube plus mesh number be M1 (mesh number M1 is a range value, such as 20
Mesh~40 mesh) sand, back-up sand and debulking methods all notice that head-up reads scale bar in back-up sand with embodiment 1, every time after compacting
The reading L2 of pipe upper end surface, until | L2-L1 |=3 centimetres, complete first segment back-up sand;Then, changing another mesh number is M2
The sand of (mesh number M2 is a range value, such as 80 mesh~100 mesh) continues back-up sand, is compacted with sand-filling apparatus, and look squarely reading
Scale bar fill out sand tube upper end surface reading L3, until | L3-L2 |=5 centimetres, complete second segment back-up sand;Then changing mesh number is
The sand of M3 (mesh number M3 is a range value, such as 180 mesh~200 mesh) continues the back-up sand of third section, and looks squarely reading scale
Bar fill out sand tube upper end surface reading L4, until | L4-L3 |=7 centimetres, complete the back-up sand of third section.So far entire fill out sand tube
Back-up sand is completed.
Its internal cores of the fill out sand tube loaded in this way are just divided into three sections that permeability has notable difference, can be used to simulation layer
Between heterogeneity.
In the description of the present invention, it should be understood that temporald eixis or positional relationship are based on the figure
Orientation or positional relationship is merely for convenience of description the utility model, rather than the device or element of indication or suggestion meaning must
There must be specific orientation, be constructed and operated in a specific orientation, therefore should not be understood as limiting the present invention.
While there has been shown and described that the embodiments of the present invention, for the ordinary skill in the art,
It is understood that these embodiments can be carried out with a variety of variations in the case where not departing from the principles of the present invention and spirit, repaired
Change, replacement and variant, the scope of the utility model is defined by the appended claims and the equivalents thereof.
Claims (5)
1. controllable penetration rate combined type sand-filling apparatus, including fill out sand tube, pressure head, the fill out sand tube is interior to fill sand core, the pressure head
It is placed in fill out sand tube and is pressed on sand core, which is characterized in that further include slide bar, scale bar, jar block, the jar block slides
On slide bar, the lower end of the slider connects baffle ring, and the baffle ring is located at below jar block, to jar block axial limiting, the baffle ring
Lower end connects scale bar, and scale bar lower end connects pressure head.
2. controllable penetration rate combined type sand-filling apparatus according to claim 1, which is characterized in that the slide bar upper end connection
T-type handle, T-type handle is also to jar block axial limiting.
3. controllable penetration rate combined type sand-filling apparatus according to claim 1 or 2, which is characterized in that in the jar block
The heart opens up slide opening, and slide bar is threaded through in the slide opening of jar block, jar block sliding opposite with slide bar.
4. controllable penetration rate combined type sand-filling apparatus according to claim 1 or 2, which is characterized in that the pressure head outer diameter
Consistent with back-up sand bore, the scale bar outer diameter is less than back-up sand bore.
5. controllable penetration rate combined type sand-filling apparatus according to claim 2, which is characterized in that slide bar upper end screw thread
Formula connecting T-shaped handle, the slide bar screw thread type connect baffle ring, and baffle ring lower end screw thread type connects scale bar, scale bar lower end screw thread
Formula connects pressure head.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821787534.3U CN209339936U (en) | 2018-10-31 | 2018-10-31 | Controllable penetration rate combined type sand-filling apparatus |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821787534.3U CN209339936U (en) | 2018-10-31 | 2018-10-31 | Controllable penetration rate combined type sand-filling apparatus |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209339936U true CN209339936U (en) | 2019-09-03 |
Family
ID=67747018
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201821787534.3U Expired - Fee Related CN209339936U (en) | 2018-10-31 | 2018-10-31 | Controllable penetration rate combined type sand-filling apparatus |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209339936U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111119874A (en) * | 2018-10-31 | 2020-05-08 | 中国石油化工股份有限公司 | Combined type sand filling device with controllable permeability and sand filling method |
-
2018
- 2018-10-31 CN CN201821787534.3U patent/CN209339936U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111119874A (en) * | 2018-10-31 | 2020-05-08 | 中国石油化工股份有限公司 | Combined type sand filling device with controllable permeability and sand filling method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106769341B (en) | A kind of rocks sample preparation device and preparation method containing blind joint | |
CN208206964U (en) | Simulate high-pressure slip-casting device under buried stratum river channels | |
CN205786019U (en) | Sample sample preparation and demoulding equipment are cut in a kind of pressure-controlled loess hollow cylinder circulation torsion | |
CN201525076U (en) | Artificial cement core preparing device | |
CN103926122B (en) | To shake out rock core and making apparatus thereof and method for making | |
CN209339936U (en) | Controllable penetration rate combined type sand-filling apparatus | |
CN106596223A (en) | Production method of rock core for compact gravel rock oil displacement | |
CN212985193U (en) | Visual large-diameter sand filling model device for physical simulation experiment | |
CN107831052B (en) | Special large-diameter sand filling model device and method for physical simulation experiment | |
CN109372476A (en) | A kind of production method of multi-functional fracture hole oil reservoir injecting physical model | |
CN103383378B (en) | Oil gas adsorption-desorption displacement experiment device | |
CN101393188A (en) | Method for characterization research of depth fluid flowing diverting agent in oil field | |
CN210741971U (en) | Standard remolding soil sample bidirectional sample pressing device | |
CN107387069A (en) | A kind of sandpack column pipe automatic compact device | |
CN116556937A (en) | Coal-bed gas well exploitation evaluation system and evaluation method | |
CN106988703B (en) | A kind of consolidation device and consolidation method of chemical sand control agent | |
CN107976369B (en) | Simulation system and experimental method for synchronous grouting by shield method | |
CN114397432B (en) | Concrete structure surface crack detection device | |
CN207964411U (en) | A kind of liquid soil compacting sampling device | |
CN111119874B (en) | Combined sand filling device with controllable permeability and sand filling method | |
CN206926054U (en) | A kind of making mould of adjustable analog material standard specimen | |
CN113107459A (en) | Oil displacement sand pipe model sand filling-discharging integrated device and experimental method | |
CN109113733A (en) | Simple fill out sand tube compaction apparatus | |
CN201429536Y (en) | Gravel soil large-scale triaxial accelerated drainage sample pore-forming sample preparation device | |
CN209579945U (en) | Multifunctional fabricated concrete mold |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20190903 Termination date: 20201031 |
|