CN209339584U - A kind of scaffold mesh sheet mounting assembly and mesh sheet mounting structure - Google Patents

A kind of scaffold mesh sheet mounting assembly and mesh sheet mounting structure Download PDF

Info

Publication number
CN209339584U
CN209339584U CN201822222658.3U CN201822222658U CN209339584U CN 209339584 U CN209339584 U CN 209339584U CN 201822222658 U CN201822222658 U CN 201822222658U CN 209339584 U CN209339584 U CN 209339584U
Authority
CN
China
Prior art keywords
mesh sheet
hanging plate
fixed
scaffold
lower platen
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201822222658.3U
Other languages
Chinese (zh)
Inventor
施志峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xiamen Anke Technology Co Ltd
Original Assignee
Xiamen Anke Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xiamen Anke Technology Co Ltd filed Critical Xiamen Anke Technology Co Ltd
Priority to CN201822222658.3U priority Critical patent/CN209339584U/en
Application granted granted Critical
Publication of CN209339584U publication Critical patent/CN209339584U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Revetment (AREA)

Abstract

The utility model discloses a kind of scaffold mesh sheet mounting assembly, including preceding hanging plate, pedestal, top board and lower platen;Preceding hanging plate is in being vertically arranged, and the bottom and upper segment of preceding hanging plate respectively has a first from left right two for catching on the hook of mesh sheet frame, and there are four hooks altogether;Before the front end of pedestal is fixed on hanging plate, and the rear end of substrate is fixed with the cross bar bolt for installing scaffold cross bar;Top board is fixed on the base in a manner of capable of sliding back and forth, and there are the gaps of clamping mesh sheet between top board and the top of preceding hanging plate;Lower platen in a manner of capable of sliding back and forth it is fixed on the base, lower platen and preceding hanging plate it is following between there are the gaps of clamping mesh sheet.The invention also discloses corresponding mesh sheet mounting structures.The utility model can connect adjacent four mesh sheet up and down, and the installation for greatly facilitating mesh sheet is fixed, and Fast Installation mesh sheet is realized, and assembly and disassembly is quite convenient to, fast.

Description

A kind of scaffold mesh sheet mounting assembly and mesh sheet mounting structure
Technical field
The utility model relates to a kind of scaffold mesh sheet mounting assemblies, and its mesh sheet mounting structure of application.
Background technique
Scaffold refer to construction site vertically and horizontally transported for convenience of worker operation and solving and the various brackets set up. In order to make construction personnel's operation safety, safe mesh sheet, especially attachment type raise scaffold will be installed in scaffold periphery, it is The scaffold set up along building structure outer surface is the new type scaffold technology that beginning of this century fast development is got up, it is by eminence Operation becomes lower operation, and hanging operation is become frame body inside processing, has significant low-carbon, high-tech content and more passes through The features such as helping, is safer, more convenient, the installation of mesh sheet is also even more important.Elevating function based on attachment type raise scaffold, Construction and fitting-out work construction operation are greatly facilitated, and high altitude operation also improves requirement to the installation fixation of mesh sheet, Not requiring nothing more than installation securely, while also will require installation should be convenient, fast.For this purpose, the present inventor deeply conceives, actively grind Study carefully, tests, develop the design finally, thus this case generates.
Utility model content
The purpose of this utility model is to provide a kind of scaffold mesh sheet mounting assembly and its mesh sheet mounting structure of application, The installation of mesh sheet can be facilitated to fix, realize Fast Installation mesh sheet.
To achieve the goals above, the solution of the utility model is:
A kind of scaffold mesh sheet mounting assembly, including preceding hanging plate, pedestal, top board and lower platen;Preceding hanging plate is in set vertically It sets, the bottom and upper segment of preceding hanging plate respectively has a first from left right two for catching on the hook of mesh sheet frame, and there are four hooks altogether; Before the front end of pedestal is fixed on hanging plate, and the rear end of substrate is fixed with the cross bar bolt for installing scaffold cross bar;Upper pressure Plate is fixed on the base in a manner of capable of sliding back and forth, and there are the gaps of clamping mesh sheet between top board and the top of preceding hanging plate; Lower platen in a manner of capable of sliding back and forth it is fixed on the base, lower platen and preceding hanging plate it is following between there are between clamping mesh sheet Gap.
In I-shaped, respectively there is I-shaped bottom and upper segment the preceding hanging plate the right two hooks confession of a first from left to catch on mesh sheet Frame.
The pedestal has level board and the vertical plate positioned at level board rear end, and the front end of level board is fixed on preceding hanging plate On, vertical plate is fixed with the cross bar bolt for installing scaffold cross bar;Top board is fixed on water in a manner of capable of sliding back and forth On plate;The rear end of lower platen is bent into perpendicular mounting portion, the through-hole passed through for cross bar bolt is opened up on perpendicular mounting portion, by cross bar Bolt, which passes through through-hole, is assembled in lower platen on vertical plate in a manner of capable of sliding back and forth.
The front end of the pedestal level board is bent into weld part, before weld part is fixed by welding on hanging plate.
The top board has the arc splenium and horizontal mounting portion that are upturned, the top of arc splenium and preceding hanging plate it Between there are the gaps of clamping mesh sheet, open up sliding slot on horizontal mounting portion, then open up mounting hole on pedestal level board, for fixed The follower bolt of pressing plate is interspersed in sliding slot and mounting hole the level board for making top board mode capable of sliding back and forth be fixed on pedestal On.
The lower platen has perpendicular splenium, Z-type portion and perpendicular mounting portion, erect splenium and preceding hanging plate it is following between there are clampings The gap of mesh sheet, Z-type portion are connected between perpendicular splenium and perpendicular mounting portion.
A kind of scaffold mesh sheet mounting structure, four hooks of hanging plate are hooked on up and down respectively before above-mentioned mounting assembly On four adjacent mesh sheet frames, and the bottom and upper segment of preceding hanging plate is respectively cooperating with top board and lower platen grips up and down Four adjacent mesh sheet of left and right, the rear end of mounting assembly substrate is by the fixed scaffold cross bar of cross bar bolt.
The perpendicular splenium cooperation of the following and lower platen of the preceding hanging plate clamps the following mesh sheet of left and right two, and lower platen erects Mounting portion is mutually supported with the scaffold cross bar on cross bar bolt, fixes lower platen, and then grips following left and right two Mesh sheet.
After adopting the above scheme, the mounting assembly of the utility model has four hooks up and down, can be used for catching on phase Adjacent four mesh sheet up and down, then top board and lower platen is cooperated to grip, the installation for greatly facilitating mesh sheet is fixed, real Fast Installation mesh sheet is showed, assembly and disassembly is quite convenient to, fast.
The present invention will be further described with reference to the accompanying drawings and examples.
Detailed description of the invention
Fig. 1 is the stereoscopic schematic diagram of the utility model fastener;
Fig. 2 is the front perspective view of the utility model mesh sheet mounting structure;
Fig. 3 is the face upwarding stereogram of the utility model mesh sheet mounting structure;
Fig. 4 is the top perspective view of the utility model mesh sheet mounting structure.
Label declaration
Mounting assembly 100:
Preceding hanging plate 10, hook 11;
Pedestal 20, level board 21, vertical plate 22, weld part 23, cross bar bolt 25;
Top board 30, arc splenium 31, horizontal mounting portion 32, sliding slot 33, follower bolt 34;
Lower platen 40, erects mounting portion 41, and through-hole 42 erects splenium 43, Z-type portion 44;
Mesh sheet 200, frame 210;
Cross bar 300.
Specific embodiment
As shown in Figures 1 to 4, the utility model discloses a kind of scaffold mesh sheet mounting assembly 100, including preceding hanging plate 10, pedestal 20, top board 30 and lower platen 40.For preceding hanging plate 10 in being vertically arranged, the bottom and upper segment of preceding hanging plate 10 respectively has one The first from left right two are used to catch on the hook 11 of 200 frame 210 of mesh sheet, and there are four hooks 11 altogether.The front end of pedestal 20 is fixed on (it can be used and be welded and fixed) on preceding hanging plate 10, and the rear end of substrate 20 is fixed with cross bar bolt 25, and cross bar bolt 25 is then for solid Dingan County fills scaffold cross bar 300.Top board 30 is fixed on pedestal 20 in a manner of capable of sliding back and forth, top board 30 and preceding hanging plate There are the gaps of clamping mesh sheet 200 between 10 top.Lower platen 40 is fixed on pedestal 20 in a manner of capable of sliding back and forth, under Pressing plate 40 and preceding hanging plate 10 it is following between there are the gaps of clamping mesh sheet 200.
The specific form of above-mentioned each component can be such as the present embodiment, but shown in being not limited to the present embodiment.
The preceding hanging plate 10 is specifically in I-shaped, and I-shaped bottom and upper segment respectively has right two hooks 11 of a first from left For catching on the frame 210 of mesh sheet 200.
The pedestal 20 has level board 21 and the vertical plate 22 positioned at 21 rear end of level board.The front end of level board 21 is fixed On preceding hanging plate 10.Vertical plate 22 is fixed with cross bar bolt 25, and cross bar bolt 25 is then for installing scaffold cross bar 300.Upper pressure Plate 30 is fixed on level board 21 in a manner of capable of sliding back and forth.The rear end of lower platen 40 is bent into perpendicular mounting portion 41, erects installation Through-hole 42 is opened up in portion 41 to pass through for cross bar bolt 25, by cross bar bolt 25 pass through through-hole 42 make lower platen 40 with can front and back it is sliding Dynamic mode is assembled on vertical plate 22.In order to facilitate fixation, the front end of 20 level board 21 of pedestal is also bent into weld part 23, before weld part 23 is fixed by welding on hanging plate 10.
The top board 30 has the arc splenium 31 and horizontal mounting portion 32 being upturned.Arc splenium 31 and preceding hanging plate There are the gap of clamping mesh sheet 200 between 10 top, the elasticity of arc splenium 31 can make to clamp stronger.Horizontal mounting portion Sliding slot 33 is opened up on 32, mounting hole (not shown) is then opened up on 20 level board 21 of pedestal, for fixing the pressure of top board 30 Crab bolt 34 is interspersed in sliding slot 33 and mounting hole the level board for making the mode capable of sliding back and forth of top board 30 be fixed on pedestal 20 On 21.
The lower platen 40 has perpendicular splenium 43, Z-type portion 44 and perpendicular mounting portion 41.Perpendicular splenium 43 is following with preceding hanging plate 10 Between there are the gap of clamping mesh sheet 200, Z-type portion 44 is connected between perpendicular splenium 43 and perpendicular mounting portion 41, the elasticity in Z-type portion 44 It can make to clamp stronger.
The utility model further discloses a kind of scaffold mesh sheet mounting structure, i.e., above-mentioned mesh sheet mounting assembly 100 is in foot hand Application on frame, four hooks 11 of hanging plate 10 are hooked on four adjacent up and down nets respectively before above-mentioned mounting assembly 100 On 200 frame 210 of piece, and the bottom and upper segment of preceding hanging plate 11 is respectively cooperating with top board 30 and lower platen 40 grips up and down Scaffold cross bar 300 is fixed by cross bar bolt 25 in the rear end of four adjacent mesh sheet 200 of left and right, 100 substrate 20 of mounting assembly, To make mounting assembly 100 be fixed on scaffold.In this way, the utility model greatly facilitates mesh sheet 200 on scaffold Installation is fixed, and realizes Fast Installation mesh sheet 200, assembly and disassembly is quite convenient to, fast.
In the present embodiment, the cooperation of perpendicular splenium 43 of the following and lower platen 40 of the preceding hanging plate 10 clamps following left and right two A mesh sheet 200, the perpendicular mounting portion 41 of lower platen 40 are supported with 300 phase of scaffold cross bar on cross bar bolt 25, make lower platen 40 It is fixed, and then grip the mesh sheet 200 of following left and right two.
The foregoing is merely the implementation examples of the utility model, are not limitation of the utility model.It should be pointed out that ability The technical staff in domain can according to need the modification for making not creative contribution after reading this specification, but as long as at this All by the protection of Patent Law in the scope of the claims of utility model.

Claims (8)

1. a kind of scaffold mesh sheet mounting assembly, it is characterised in that: including preceding hanging plate, pedestal, top board and lower platen;Preceding hanging plate In being vertically arranged, the bottom and upper segment of preceding hanging plate respectively has a first from left right two for catching on the hook of mesh sheet frame, and one is shared Four hooks;Before the front end of pedestal is fixed on hanging plate, and the rear end of substrate is fixed with the cross bar for installing scaffold cross bar Bolt;Top board is fixed on the base in a manner of capable of sliding back and forth, and there are clamping nets between top board and the top of preceding hanging plate The gap of piece;Lower platen in a manner of capable of sliding back and forth it is fixed on the base, lower platen and preceding hanging plate it is following between there are folders Hold the gap of mesh sheet.
2. a kind of scaffold mesh sheet mounting assembly as described in claim 1, it is characterised in that: the preceding hanging plate in I-shaped, Respectively there is I-shaped bottom and upper segment right two hooks of a first from left to supply to catch on the frame of mesh sheet.
3. a kind of scaffold mesh sheet mounting assembly as described in claim 1, it is characterised in that: the pedestal have level board and Vertical plate positioned at level board rear end, before the front end of level board is fixed on hanging plate, vertical plate is fixed with for installing scaffold The cross bar bolt of cross bar;Top board is fixed on level board in a manner of capable of sliding back and forth;The rear end of lower platen is bent into perpendicular peace Dress portion opens up the through-hole passed through for cross bar bolt on perpendicular mounting portion, and passing through through-hole by cross bar bolt makes lower platen with can front and back The mode of sliding is assembled on vertical plate.
4. a kind of scaffold mesh sheet mounting assembly as claimed in claim 3, it is characterised in that: the top board, which has, tilts upward The arc splenium and horizontal mounting portion risen, there are the gap of clamping mesh sheet, level peaces between arc splenium and the top of preceding hanging plate Open up sliding slot in dress portion, then open up mounting hole on pedestal level board, the follower bolt for fixing top board be interspersed in sliding slot and It is fixed on top board mode capable of sliding back and forth on the level board of pedestal.
5. a kind of scaffold mesh sheet mounting assembly as claimed in claim 3, it is characterised in that: the lower platen has perpendicular pressure Portion, Z-type portion and perpendicular mounting portion, erect splenium and preceding hanging plate it is following between there are the gap of clamping mesh sheet, Z-type portion is connected to perpendicular pressure Between portion and perpendicular mounting portion.
6. a kind of scaffold mesh sheet mounting assembly as claimed in claim 3, it is characterised in that: the front end of the pedestal level board It is bent into weld part, before weld part is fixed by welding on hanging plate.
7. a kind of scaffold mesh sheet mounting structure, it is characterised in that: a kind of such as foot hand described in any one of claims 1 to 6 Four hooks of hanging plate are hooked on respectively on four adjacent up and down mesh sheet frames before frame mesh sheet mounting assembly, and preceding The bottom and upper segment of hanging plate is respectively cooperating with top board and lower platen grips four adjacent up and down mesh sheet, mounting assembly The rear end of substrate is by the fixed scaffold cross bar of cross bar bolt.
8. a kind of scaffold mesh sheet mounting structure as claimed in claim 7, it is characterised in that: the preceding hanging plate it is following under The perpendicular splenium cooperation of pressing plate clamps the following mesh sheet of left and right two, the perpendicular mounting portion of lower platen and the scaffold cross on cross bar bolt Bar is mutually supported, and lower platen is fixed, and then grips the mesh sheet of following left and right two.
CN201822222658.3U 2018-12-27 2018-12-27 A kind of scaffold mesh sheet mounting assembly and mesh sheet mounting structure Active CN209339584U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201822222658.3U CN209339584U (en) 2018-12-27 2018-12-27 A kind of scaffold mesh sheet mounting assembly and mesh sheet mounting structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201822222658.3U CN209339584U (en) 2018-12-27 2018-12-27 A kind of scaffold mesh sheet mounting assembly and mesh sheet mounting structure

Publications (1)

Publication Number Publication Date
CN209339584U true CN209339584U (en) 2019-09-03

Family

ID=67759629

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201822222658.3U Active CN209339584U (en) 2018-12-27 2018-12-27 A kind of scaffold mesh sheet mounting assembly and mesh sheet mounting structure

Country Status (1)

Country Link
CN (1) CN209339584U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110821195A (en) * 2019-11-07 2020-02-21 上海精硕建设发展有限公司 Mesh mounting method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110821195A (en) * 2019-11-07 2020-02-21 上海精硕建设发展有限公司 Mesh mounting method

Similar Documents

Publication Publication Date Title
CN209339584U (en) A kind of scaffold mesh sheet mounting assembly and mesh sheet mounting structure
CN109319040A (en) A kind of scaffold building method for hull turn of the bilge region
CN207420037U (en) A kind of building template securing device reinforces rod piece and securing device
CN206022916U (en) Combined type power cabinet
CN209429512U (en) A kind of scaffold mesh sheet Fast Installation fastener and mesh sheet mounting structure
CN207273086U (en) Frame assembly fixture
CN206448406U (en) A kind of connection component of curtain wall cross beam and column
CN202470597U (en) Center beam assembly structure and refrigerator adopting same
CN211114413U (en) Stainless steel support for factory building with roof rail mounted installation
CN206888811U (en) A kind of distribution cabinet door mounting structure of fast demountable
CN205783699U (en) A kind of idle call installing plate
CN206799781U (en) PCB board electroplating rack
CN205857671U (en) A kind of suspension bracket attachment platform
CN203847521U (en) Integrated metal connecting piece for sofa
CN210395813U (en) Algae well ceiling module
CN202764264U (en) Bag making machine wallboard
CN103438085A (en) Fixing device for racking device
CN207251487U (en) A kind of fixing device of inverter
CN208849087U (en) A kind of spinning frame terminal support
CN211548525U (en) Panel for outer wall with connection structure
CN208464008U (en) Internal cavity of bowl washer reinforcement structure
CN211681722U (en) External convenient installation auxiliary device
CN209925502U (en) Anti-seismic support base
CN208652094U (en) Inverter hanging structure
CN208971710U (en) A kind of wall hanging speaker

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of utility model: The utility model relates to a scaffold net piece installation component and a net piece installation structure

Effective date of registration: 20210608

Granted publication date: 20190903

Pledgee: Xiamen Branch of PICC

Pledgor: XIAMEN ANKE TECHNOLOGY Co.,Ltd.

Registration number: Y2021980004492

PE01 Entry into force of the registration of the contract for pledge of patent right
PC01 Cancellation of the registration of the contract for pledge of patent right

Date of cancellation: 20220725

Granted publication date: 20190903

Pledgee: Xiamen Branch of PICC

Pledgor: XIAMEN ANKE TECHNOLOGY Co.,Ltd.

Registration number: Y2021980004492

PC01 Cancellation of the registration of the contract for pledge of patent right
CP03 Change of name, title or address

Address after: 361000 702, Hengyi building, No.1-3, Zhongling Road, Huli District, Xiamen City, Fujian Province

Patentee after: Xiamen Anke Technology Co.,Ltd.

Country or region after: Zhong Guo

Address before: 361000 702, Hengyi building, No.1-3, Zhongling Road, Huli District, Xiamen City, Fujian Province

Patentee before: XIAMEN ANKE TECHNOLOGY Co.,Ltd.

Country or region before: Zhong Guo

CP03 Change of name, title or address