CN209338035U - A kind of building engineering construction is with can lifting bracket - Google Patents
A kind of building engineering construction is with can lifting bracket Download PDFInfo
- Publication number
- CN209338035U CN209338035U CN201920063832.6U CN201920063832U CN209338035U CN 209338035 U CN209338035 U CN 209338035U CN 201920063832 U CN201920063832 U CN 201920063832U CN 209338035 U CN209338035 U CN 209338035U
- Authority
- CN
- China
- Prior art keywords
- plate
- building engineering
- engineering construction
- lifting
- lifting bracket
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Types And Forms Of Lifts (AREA)
Abstract
The utility model discloses a kind of building engineering constructions with can lifting bracket, the top of pillar is equipped with top plate, rear side at the top of top plate is equipped with protective frame, rear side inside protective frame is equipped with Y355 motor, one end of Y355 motor is fixedly connected with rotation axis, one end of rotation axis is installed and driving gear, the two sides engagement of driving gear is connected with driven gear, shaft is installed in the middle part of driven gear, reel is installed on the outside of shaft, the surface of reel is arranged with drawstring, the bottom end of drawstring is equipped with connector, the two sides of connector are fixedly connected with connecting rope, the bottom end of connecting rope is equipped with lifting plate, outside at the top of lifting plate is equipped with charge slot, the winding direction of drawstring on two reels of the utility model is opposite, it can be realized the different liftings of lifting plate, and then realize the charge slot of left and right two One rise and one drop flexibly and fast reduces gyration time, ensure that the continuity of construction, improves construction efficiency, enhances the practicability of rack body.
Description
Technical field
The utility model relates to building engineering construction equipment technical fields, and in particular to a kind of building engineering construction is with can mention
Ascending branch frame.
Background technique
In the work progress of construction wall, in order to facilitate operation, it is often necessary to by material lifts such as building brick, sandstones
To eminence, traditional method is mainly completed by manually, and not only working efficiency is low, large labor intensity, and there is also certain
Risk, although had already appeared now it is some replace artificial lifting device, most structures are simple, only can be carried out single
Transport, gyration time is long, not can guarantee the continuity of construction, and practicability is poor, in addition, most of lifting device can not be to building
Material to be built to be fixed, construction material easily shakes during transportation, it is not only easy to cause the generation of drop event,
The abrasion to lifting device is also increased, its service life is reduced.
Utility model content
(1) technical problems to be solved
In order to overcome the shortage of prior art, it is proposed that a kind of building engineering construction with can lifting bracket, to solve above-mentioned back
The existing lifting device majority structure proposed in scape technology is simple, only can be carried out single transport, gyration time is long, not can guarantee
The continuity of construction, practicability is poor, in addition, construction material can not be fixed in most of lifting device, construction material
It easily shakes during transportation, is not only easy to cause the generation of drop event, also increase the mill to lifting device
The problem of damaging, reducing its service life.
(2) technical solution
The utility model is achieved through the following technical solutions: the utility model proposes a kind of building engineering constructions with can mention
Ascending branch frame, including rack body, pedestal, pillar, top plate, protective frame, shock-absorbing caster wheel, control panel, sliding slot, reinforcing rod, guiding
Pulley, Y355 motor, driving gear, driven gear, reel, drawstring, connector, connecting rope, lifting plate, the first idler wheel,
Charge slot, support rod, the second idler wheel, transmission shaft, shaft, pod door, pressing plate, spring and rubber pad, the bottom of the rack body
It is provided with the pedestal, the front of the pedestal is equipped with the control panel, and the quadrangle of the base top is equipped with described
Pillar offers the sliding slot on the outside of the pillar, and the top of the pillar is equipped with the top plate, the two sides of the top plate
The leading block is installed, the rear side at the top of the top plate is equipped with the protective frame, the rear side peace inside the protective frame
Equipped with the Y355 motor, one end of the Y355 motor is fixedly connected with the rotation axis, one end of the rotation axis
Installation and the driving gear, the two sides of the driving gear, which are engaged, is connected with the driven gear, in the driven gear
Portion is equipped with the shaft, and the reel is equipped on the outside of the shaft, and the surface of the reel is arranged with the drawing
Rope, the bottom end of the drawstring are equipped with the connector, and the two sides of the connector are fixedly connected with the connecting rope, the company
The bottom end of splicing is equipped with the lifting plate, and the both ends on the inside of the lifting plate are equipped with first idler wheel, the lifting plate
The charge slot is installed, the both ends inside the charge slot are equipped with the spring, one end of the spring on the outside of top
The pressing plate is installed, the both ends of the lifting plate bottom are equipped with the support rod, and the bottom end installation of the support rod is
The second idler wheel is stated, the bottom of the pedestal is equipped with the shock-absorbing caster wheel.
Further, the control panel and the Y355 motor are electrically connected.
Further, reinforcing rod is installed between the two neighboring pillar.
Further, the winding direction of the drawstring on two reels is opposite.
Further, it is used cooperatively between the sliding slot and first idler wheel and second idler wheel.
Further, pod door is hinged on the outside of the charge slot.
Further, the charge slot is connect with the pressing plate by the spring.
Further, the inside of the charge slot and the pressing plate is pasted with rubber pad.
(3) beneficial effect
The utility model compared with the existing technology, has the advantages that
1), the winding direction of the drawstring on two reels is on the contrary, can be realized the different liftings of lifting plate, and then realize
One rise and one drop of the two charge slots in left and right flexibly and fast reduces gyration time, ensure that the continuity of construction, improves and apply
Work efficiency rate enhances the practicability of rack body.
2) pod door, is hinged on the outside of charge slot, rotation flexibly, is opened fast, is conveniently carried out to residue fragment in slot clear
It is clean, reduce the later period clean-up intensity of rack body.
3), charge slot is connect with pressing plate by spring, is stretched flexibly, can be fixed to construction material, avoid its hair
It is raw to shake, the probability of drop event generation is reduced, the safety that rack body uses is improved.
Detailed description of the invention
Fig. 1 is the schematic view of the front view of the utility model.
Fig. 2 is the left view structural representation of the utility model.
Fig. 3 is side structure schematic view inside the containing tank of the utility model.
1- rack body;2- pedestal;3- pillar;4- top plate;5- protective frame;6- shock-absorbing caster wheel;7- control panel;8- is sliding
Slot;9- reinforcing rod;10- leading block;11-Y355 motor;12- driving gear;13- driven gear;14- reel;15- is drawn
Rope;16- connector;17- connecting rope;18- lifting plate;The first idler wheel of 19-;20- charge slot;21- support rod;The second idler wheel of 22-;
23- transmission shaft;24- shaft;25- pod door;26- pressing plate;27- spring;28- rubber pad.
Specific embodiment
In order to make the purpose of the utility model, technical solutions and advantages more clearly understood, below in conjunction with attached drawing and implementation
Example, the present invention will be further described in detail.It should be appreciated that specific embodiment described herein is only used to explain
The utility model is not used to limit the utility model.
A kind of building engineering construction as shown in Figs. 1-3 with can lifting bracket, including rack body 1, pedestal 2, pillar 3,
Top plate 4, protective frame 5, shock-absorbing caster wheel 6, control panel 7, sliding slot 8, reinforcing rod 9, leading block 10, Y355 motor 11, active
Gear 12, driven gear 13, reel 14, drawstring 15, connector 16, connecting rope 17, lifting plate 18, the first idler wheel 19, charge
Slot 20, support rod 21, the second idler wheel 22, transmission shaft 23, shaft 24, pod door 25, pressing plate 26, spring 27 and rubber pad 28, it is described
The bottom of rack body 1 is provided with the pedestal 2, and the front of the pedestal 2 is equipped with the control panel 7, and the pedestal 2 pushes up
The quadrangle in portion is equipped with the pillar 3, and the outside of the pillar 3 offers the sliding slot 8, and the top of the pillar 3 is equipped with
The top plate 4, the two sides of the top plate 4 are equipped with the leading block 10, and the rear side at 4 top of top plate is equipped with described anti-
Frame 5 is protected, the rear side inside the protective frame 5 is equipped with the Y355 motor 11, and one end of the Y355 motor 11 is fixed
It is connected with the rotation axis 23, one end of the rotation axis 23 is installed and the driving gear 12, and the two of the driving gear 12
Side engagement is connected with the driven gear 13, and the middle part of the driven gear 13 is equipped with the shaft 24, the shaft 24
Outside is equipped with the reel 14, and the surface of the reel 14 is arranged with the drawstring 15, the bottom end peace of the drawstring 15
Equipped with the connector 16, the two sides of the connector 16 are fixedly connected with the connecting rope 17, the bottom end of the connecting rope 17
The lifting plate 18 is installed, the both ends of 18 inside of lifting plate are equipped with first idler wheel 19, and the lifting plate 18 pushes up
The charge slot 20 is installed, the both ends inside the charge slot 20 are equipped with the spring 27, the spring 27 on the outside of portion
One end the pressing plate 26 is installed, the both ends of 18 bottom of lifting plate are equipped with the support rod 21, the support rod 21
Bottom end second idler wheel 22 is installed, the bottom of the pedestal 2 is equipped with the shock-absorbing caster wheel 6.
Wherein, the control panel 7 is electrically connected with the Y355 motor 11, and the control panel 7 controls described
The work of Y355 motor 11.
Wherein, reinforcing rod 9 is installed between the two neighboring pillar 3, structure is simple, improves the rack body 1
Integral strength, extend its service life.
Wherein, the winding direction of the drawstring 15 on two reels 14 is on the contrary, can be realized the lifting plate
18 different liftings, and then realize that one rise and one drop of the two charge slots 20 in left and right flexibly and fast reduces gyration time,
The continuity that ensure that construction, improves construction efficiency, enhances the practicability of the rack body 1.
Wherein, it being used cooperatively between the sliding slot 8 and first idler wheel 19 and second idler wheel 22, sliding is flexible,
While playing certain guiding and firm effect, the promotion speed of construction material is also accelerated, the rack body 1 is improved
Working efficiency.
Wherein, the outside of the charge slot 20 is hinged with pod door 25, and rotation flexibly, is opened fast, convenient to residue in slot
Fragment is cleaned, and the later period clean-up intensity of the rack body 1 is reduced.
Wherein, the charge slot 20 is connect with the pressing plate 26 by the spring 27, is stretched flexibly, can be to Building wood
Material is fixed, it is avoided to shake, and reduces the probability of drop event generation, improves what the rack body 1 used
Safety.
Wherein, the inside of the charge slot 20 and the pressing plate 26 is pasted with rubber pad 28, is provided on rubber pad 28
Anti-skid chequer, it is soft flexible, the fixed effect to construction material is further enhanced, while also reducing to the charge slot 20
Abrasion, extend its service life, save the job costs of the rack body 1.
A kind of building engineering construction that the utility model is mentioned with can lifting bracket, the bottom of rack body 1 is provided with bottom
Seat 2, the front of pedestal 2 are equipped with control panel 7, and the quadrangle at 2 top of pedestal is equipped with pillar 3, pacifies between two neighboring pillar 3
Equipped with reinforcing rod 9, structure is simple, improves the integral strength of rack body 1, extends its service life, and the outside of pillar 3 is opened
Equipped with sliding slot 8, the top of pillar 3 is equipped with top plate 4, and the two sides of top plate 4 are equipped with leading block 10, can play certain lead
To and supporting role, ensure that the up rightness of drawstring 15, the rear side at 4 top of top plate is equipped with protective frame 5, inside protective frame 5
Rear side is equipped with Y355 motor 11, and one end of Y355 motor 11 is fixedly connected with rotation axis 23, one end peace of rotation axis 23
Dress and driving gear 12, the two sides engagement of driving gear 12 are connected with driven gear 13, and the middle part of driven gear 13, which is equipped with, to be turned
Axis 24, the outside of shaft 24 are equipped with reel 14, and the surface of reel 14 is arranged with drawstring 15, the drawing on two reels 14
The winding direction of rope 15 is on the contrary, can be realized the different liftings of lifting plate 18, and then realize one liter of the two charge slots 20 in left and right
One drop, flexibly and fast, reduces gyration time, ensure that the continuity of construction, improve construction efficiency, enhance rack body
1 practicability, the bottom end of drawstring 15 are equipped with connector 16, and the two sides of connector 16 are fixedly connected with connecting rope 17, connecting rope
17 bottom end is equipped with lifting plate 18, and the both ends of 18 inside of lifting plate are equipped with the first idler wheel 19, the outside at 18 top of lifting plate
Charge slot 20 is installed, the outside of charge slot 20 is hinged with pod door 25, and rotation flexibly, is opened fast, convenient broken to residue in slot
Block is cleaned, and the later period clean-up intensity of rack body 1 is reduced, and the both ends inside charge slot 20 are equipped with spring 27, spring
27 one end is equipped with pressing plate 26, and charge slot 20 is connect with pressing plate 26 by spring 27, stretches flexibly, can to construction material into
Row is fixed, it is avoided to shake, and is reduced the probability of drop event generation, is improved the safety that rack body 1 uses, and is contained
The inside of hopper 20 and pressing plate 26 is pasted with rubber pad 28, and anti-skid chequer is provided on rubber pad 28, soft flexible, further
The fixed effect to construction material is enhanced, while also reducing the abrasion to charge slot 20, extends its service life, is saved
The job costs of rack body 1, the both ends of 18 bottom of lifting plate are equipped with support rod 21, and the bottom end of support rod 21 is equipped with
Second wheel 22 is used cooperatively between sliding slot 8 and the first idler wheel 19 and the second idler wheel 22, sliding flexibly, play certain guiding and
While firm effect, the promotion speed of construction material is also accelerated, improves the working efficiency of rack body 1, the bottom of pedestal 2
Portion is equipped with shock-absorbing caster wheel 6, has both facilitated the movement of rack body 1, can also play certain damping effect, ensure that its work
The stability of work when in use first leads to the construction material for needing to be promoted into being in the charge slot 20 of bottom after fixation
It crosses control panel 7 and starts the work of Y355 motor 11, driving gear 12 passes through driven gear under the action of transmission shaft 23 immediately
13 drive shaft 24 to rotate, and reel 14 rotates immediately, and the charge slot 20 in bottom rises with it, simultaneously, in top
The charge slot 20 in portion is begun to decline, and when the two position complete exchange, continues to charge into the charge slot 20 in bottom, with this
Meanwhile the material in top charge slot 20 is also picked and finishes, and is then again started up Y355 motor 11 and carries out feeding, such as
This repeatedly, until complete all construction workings, this building engineering construction with can lifting bracket, not only easy to operate, user
Just, and flexibly and fast, reliable and stable, safe and practical, damping noise reduction, work efficiency is high, and promotion effect is good, and maintenance cost is low,
Labor intensity is small, long service life.
Embodiment described above is only that preferred embodiments of the present invention are described, not practical to this
Novel conception and scope is defined.Without departing from the design concept of the present utility model, ordinary people in the field couple
The all variations and modifications that the technical solution of the utility model is made, should fall within the protection scope of the present utility model, this reality
With novel claimed technology contents, it is all described in the claims.
Claims (8)
1. a kind of building engineering construction with can lifting bracket, including it is rack body (1), pedestal (2), pillar (3), top plate (4), anti-
Protect frame (5), shock-absorbing caster wheel (6), control panel (7), sliding slot (8), reinforcing rod (9), leading block (10), Y355 motor
(11), driving gear (12), driven gear (13), reel (14), drawstring (15), connector (16), connecting rope (17), promotion
Plate (18), the first idler wheel (19), charge slot (20), support rod (21), the second idler wheel (22), transmission shaft (23), shaft (24), slot
Door (25), pressing plate (26), spring (27) and rubber pad (28), it is characterised in that: the bottom setting of the rack body (1) is
It states pedestal (2), the front of the pedestal (2) is equipped with the control panel (7), and the quadrangle at the top of the pedestal (2) is equipped with
The pillar (3) offers the sliding slot (8) on the outside of the pillar (3), and the top of the pillar (3) is equipped with the top
The two sides of plate (4), the top plate (4) are equipped with the leading block (10), and the rear side at the top of the top plate (4) is equipped with described
Protective frame (5), the internal rear side of the protective frame (5) are equipped with the Y355 motor (11), the Y355 motor (11)
One end be fixedly connected with the transmission shaft (23), the installation of one end of the transmission shaft (23) and the driving gear (12), institute
The two sides engagement for stating driving gear (12) is connected with the driven gear (13), and the middle part installation of the driven gear (13) is
It states shaft (24), is equipped with the reel (14) on the outside of the shaft (24), the surface of the reel (14) is arranged with
The bottom end of the drawstring (15), the drawstring (15) is equipped with the connector (16), and the two sides of the connector (16) are fixed
It is connected with the connecting rope (17), the bottom end of the connecting rope (17) is equipped with the lifting plate (18), the lifting plate (18)
The both ends of inside are equipped with first idler wheel (19), and the outside at the top of the lifting plate (18) is equipped with the charge slot
(20), the internal both ends of the charge slot (20) are equipped with the spring (27), and one end of the spring (27) is equipped with described
The both ends of pressing plate (26), lifting plate (18) bottom are equipped with the support rod (21), the bottom end peace of the support rod (21)
Equipped with second idler wheel (22), the bottom of the pedestal (2) is equipped with the shock-absorbing caster wheel (6).
2. a kind of building engineering construction according to claim 1 is with can lifting bracket, it is characterised in that: the control panel
(7) it is electrically connected with the Y355 motor (11).
3. a kind of building engineering construction according to claim 1 is with can lifting bracket, it is characterised in that: two neighboring described
Reinforcing rod (9) are installed between pillar (3).
4. a kind of building engineering construction according to claim 1 is with can lifting bracket, it is characterised in that: two spirals
The winding direction for taking turns the drawstring (15) on (14) is opposite.
5. a kind of building engineering construction according to claim 1 is with can lifting bracket, it is characterised in that: the sliding slot (8)
It is used cooperatively between first idler wheel (19) and second idler wheel (22).
6. a kind of building engineering construction according to claim 1 is with can lifting bracket, it is characterised in that: the charge slot
(20) pod door (25) are hinged on the outside of.
7. a kind of building engineering construction according to claim 1 is with can lifting bracket, it is characterised in that: the charge slot
(20) it is connect with the pressing plate (26) by the spring (27).
8. a kind of building engineering construction according to claim 1 is with can lifting bracket, it is characterised in that: the charge slot
(20) rubber pad (28) are pasted with the inside of the pressing plate (26).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201920063832.6U CN209338035U (en) | 2019-01-15 | 2019-01-15 | A kind of building engineering construction is with can lifting bracket |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201920063832.6U CN209338035U (en) | 2019-01-15 | 2019-01-15 | A kind of building engineering construction is with can lifting bracket |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209338035U true CN209338035U (en) | 2019-09-03 |
Family
ID=67761677
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201920063832.6U Expired - Fee Related CN209338035U (en) | 2019-01-15 | 2019-01-15 | A kind of building engineering construction is with can lifting bracket |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209338035U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111480487A (en) * | 2020-05-29 | 2020-08-04 | 晋江市豪泰农业发展有限公司 | Dragon fruit planting frame |
-
2019
- 2019-01-15 CN CN201920063832.6U patent/CN209338035U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111480487A (en) * | 2020-05-29 | 2020-08-04 | 晋江市豪泰农业发展有限公司 | Dragon fruit planting frame |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN212075107U (en) | Slag powder elevator hopper | |
CN209338035U (en) | A kind of building engineering construction is with can lifting bracket | |
CN209427750U (en) | A kind of automatic charging device of shot-blasting machine | |
CN209338049U (en) | It is a kind of it is for building can automatic lifting and inclination unloading elevator | |
CN110479792A (en) | A kind of pull-type pay off rack | |
CN207404533U (en) | A kind of construct for handling of cement bag | |
CN218778691U (en) | Building engineering material lifting machine | |
CN110668348A (en) | Lifting support convenient to move for building engineering construction | |
CN205873175U (en) | Over -and -under type powder conveyor | |
CN208531225U (en) | A kind of logistics cargo turnover rack | |
CN213894929U (en) | Lifting device for chemical equipment | |
CN211664631U (en) | Liftable support for constructional engineering | |
CN209352056U (en) | A kind of miberal powder bucket elevator | |
CN210680865U (en) | Feeding equipment for nylon production | |
CN219751856U (en) | Wall building equipment | |
CN207683403U (en) | A kind of mechanism of vehicle-mounted handling bicycle | |
CN206955299U (en) | It is surface-treated band collecting equipment | |
CN215208241U (en) | Energy-concerving and environment-protective type is hanger for construction | |
CN209226494U (en) | A kind of elevator applied in low mercury catalyst production | |
CN208655199U (en) | A kind of lift car media device easy to repair | |
CN218453789U (en) | Reducible extravagant loading funnel wireless control reforms transform device | |
CN219205895U (en) | Preserved egg soaking device | |
CN221319074U (en) | Mining bucket rotary crane lifting device for mining | |
CN215756138U (en) | Vertical type feeding device | |
CN215743805U (en) | Potassium-sodium feldspar ore production ore crushing device convenient for circular processing |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20190903 Termination date: 20210115 |