CN209311607U CN201821533497.3U CN201821533497U CN209311607U CN 209311607 U CN209311607 U CN 209311607U CN 201821533497 U CN201821533497 U CN 201821533497U CN 209311607 U CN209311607 U CN 209311607U
Authority
CN
China
Prior art keywords
test
cabinet
converter
host
electrically connected
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201821533497.3U
Other languages
Chinese (zh)
Inventor
姜新
徐勤
熊奉超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang kaiyao Lighting Co Ltd
Original Assignee
Zhejiang kaiyao Lighting Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang kaiyao Lighting Co Ltd filed Critical Zhejiang kaiyao Lighting Co Ltd
Priority to CN201821533497.3U priority Critical patent/CN209311607U/en
Application granted granted Critical
Publication of CN209311607U publication Critical patent/CN209311607U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Testing Electric Properties And Detecting Electric Faults (AREA)

Abstract

The utility model discloses a kind of three-in-one test equipment for testing ballast, test host, the display in test cabinet and the test equipment component in test cabinet including test cabinet, in test cabinet;Test host is electrically connected with display, and test equipment component is electrically connected with test host.The test equipment component includes converter, the voltage resistant instrument in test cabinet, the power meter in test cabinet, the isolating transformer in test cabinet and the pressure regulating instrument in test cabinet in test cabinet;Voltage resistant instrument, power meter and converter are electrically connected with test host, and voltage resistant instrument, power meter, isolating transformer and pressure regulator are electrically connected with converter.Voltage resistant instrument, power meter and converter, which are attached the utility model by data line with test host, to be had the characteristics that can to effectively improve testing efficiency, test accuracy height, saves manpower, reduces cost.

Description

Test the three-in-one test equipment of ballast
Technical field
The utility model relates to conventional fluorescent ballast the field of test technology, can effectively improve test effect more particularly, to one kind The three-in-one test equipment for the test ballast that rate, test accuracy are high, save manpower, reduce cost.
Background technique
LED lamp comes into each corner of production and living, although the development of LED lamp is become better and better now, It is still to be lighted using conventional fluorescent fluorescent tube in the engineering of part, while part ballast can drive simultaneously now LED works, therefore conventional fluorescent ballast still remains the market space.
For conventional fluorescent ballast due to being limited by design bottom, product test can just be fully met by needing to carry out multiple tracks test Demand achievees the purpose that use, simultaneously because price is more cheap, the factory for producing ballast must improve day production capacity and be used to drop Low production cost, this also means that needing to put into more manpowers carries out relevant ballast test, this does not meet existing Trend.
Ballast test mainly includes packaging section voltage-withstand test, protection test and lights test, when manual operation is tested, is A kind of duplicate heavy labor, test result need artificial observation, test and miss caused by often occurring as the problems such as fatigue Sentence, results in the outflow of rejected product.Therefore it develops a can test multiple tracks to be synthesized together, be met with less manpower The production requirement just demand urgent at major power supply manufacturing enterprise.
Utility model content
The purpose of utility model of the utility model is that waste of human resource, test error are larger in the prior art in order to overcome Deficiency, providing a kind of can effectively improve the test ballast that testing efficiency, test accuracy are high, save manpower, reduce cost The three-in-one test equipment of device.
To achieve the goals above, the utility model uses following technical scheme:
A kind of three-in-one test equipment for testing ballast, test host including test cabinet, in test cabinet, Display in test cabinet and the test equipment component in test cabinet;Test host is electrically connected with display, Test equipment component is electrically connected with test host.
The utility model is a kind of three-in-one test equipment for testing ballast, and test cabinet is for placing in test process The various equipment to be used, test host are surveyed for controlling test process, display for showing the information such as test data Trying apparatus assembly is the specific instrument used during the test.
Preferably, the test equipment component includes the converter being set in test cabinet, is set to test machine Voltage resistant instrument in cabinet, the power meter in test cabinet, the isolating transformer in test cabinet and be set to test cabinet Interior pressure regulating instrument;Voltage resistant instrument, power meter and converter are electrically connected with test host, and voltage resistant instrument, power meter, isolation become Depressor and pressure regulator are electrically connected with converter.Voltage resistant instrument, power meter and converter are logical with test host Data line is crossed to be attached.
Converter mainly realizes conversion of the product from safety test conversion at performance test voltage, under regular situation It is converted into 198V exchange from 2000V exchange, to meet the voltage under different test requests.Voltage resistant instrument is to carry out ballast tolerance electricity The instrument of aptitude tests is pressed, power meter is mainly used for testing the power of ballast.
Preferably, the test equipment component further includes product and test load to be measured, product and test load to be measured It is electrically connected with converter.
Preferably, the test equipment component further includes external cabling port, product and test load to be measured are by connecing Line end mouth is electrically connected with converter.
Preferably, product to be measured is ballast, test load is fluorescent tube, and external cabling port is 20 spelling rectangles Socket.20 spell rectangular receptacle line using standardization connection, and itself has foolproof function, can effectively avoid because of employee's wiring Mistake and cause product accidentally survey the case where.
Preferably, the test cabinet is in rectangle, test cabinet includes top plate and bottom plate and 3 blocks of side plates, 3 fast side plates point It is not vertical with top plate and bottom plate to connect.
Preferably, the bottom plate lower part is equipped with several movable pulleies easy to carry, if being equipped in the test cabinet Dry partition, test host, display, converter, voltage resistant instrument, power meter, isolating transformer and pressure regulating instrument are respectively positioned on On corresponding partition.
Preferably, being equipped with the rubber layer for buffering colliding forces on 3 pieces of side plate interior sides faces.It is set in the whole series test In standby handling process, it may occur that in vibration or test process, if there is external collision, will lead to the collision of equipment room, influence Test effect.
Therefore, the utility model has the following beneficial effects:
The utility model is a kind of three-in-one test equipment for testing ballast, and collection voltage-withstand test, protection are tested and lighted Test function directly carries out the conversion of high-low pressure, is controlled by test host in one, high-low pressure converter, eliminates artificial progress The danger of pressurization.Ballast and fluorescent tube spell rectangular receptacles by 20 and are linked into high-low pressure converter, can directly carry out Pressure resistance lights test with load, and the present apparatus saves manpower, while saving testing cost and testing time.Power meter measurement Test result directly carries out experimental data comparison in test host, judges test result, and present apparatus test accuracy rate is high, avoids The erroneous judgement of manual testing.Therefore the utility model have can effectively improve testing efficiency, test accuracy are high, save manpower, The characteristics of reducing cost.
Detailed description of the invention
Fig. 1 is a kind of appearance diagram of the utility model;
Fig. 2 is a kind of circuit module connection diagram of the utility model.
In figure: test cabinet 1 tests host 2, display 3, high-low pressure converter 4, voltage resistant instrument 5, power meter 6, isolation change Depressor 7, pressure regulating instrument 8, product 9 to be measured, test load 10, external cabling port 11.
Specific embodiment
The utility model is further described with reference to the accompanying drawings and detailed description.
Embodiment as shown in Figure 1 is a kind of three-in-one test equipment for testing ballast, including test cabinet 1, is set to Test host 2, the display 3 in test cabinet and the test equipment component in test cabinet in test cabinet; Test host is electrically connected with display, and test equipment component is electrically connected with test host.Test equipment component includes being set to test Converter 4 in cabinet, the power meter 6 in test cabinet, is set to and surveys the voltage resistant instrument 5 in test cabinet Isolating transformer 7 in test-run a machine cabinet and the pressure regulating instrument in test cabinet 8;As shown in Fig. 2, voltage resistant instrument, power meter and height Pressure converter is electrically connected with test host, and voltage resistant instrument, power meter, isolating transformer and pressure regulator are electric with converter Connection.
Test equipment component further includes product 9 and test load 10 to be measured, and product and test load to be measured are and high-low pressure Converter electrical connection.It further include external cabling port 11, product and test load to be measured are converted by Wiring port and high-low pressure Device electrical connection.Product to be measured is ballast, and test load is fluorescent tube, and external cabling port is 20 spelling rectangular receptacles.
Test cabinet is in rectangle, and test cabinet includes top plate and bottom plate and 3 blocks of side plates, 3 fast side plates respectively with top plate and bottom plate Vertical connection.Bottom plate lower part is equipped with 4 movable pulleies easy to carry, several partitions, test master are equipped in test cabinet Machine, display, converter, voltage resistant instrument, power meter, isolating transformer and pressure regulating instrument are respectively positioned on corresponding partition.3 pieces The rubber layer for buffering colliding forces is coated on side plate interior sides face.
The course of work of the utility model is as follows:
When testing, test operation personnel start test equipment first, and ballast and fluorescent tube pass through two respectively Ten spelling rectangular receptacles connect the converter in three-in-one test equipment.After ballast access, test operation personnel control System test host is tested, and test host control converter is tested, and converter is transferred to high pressure access State, test host send test signal to voltage resistant instrument, and voltage resistant instrument starts to act, and test host collecting test data.
After the completion of voltage-withstand test, voltage resistant instrument is issued to converter completes signal, and converter cuts low pressure Test pattern.Test host enters protection test pattern, power meter read test data, test the specification value of host and setting into Row compares to determine, and after as a result passing through, test host continues to instruct converter, ballast into test pattern is lighted, and bears It carries fluorescent tube to be powered on, power meter read test data, the specification value of test data input test host and setting carries out Determine, is terminated by rear test program, device powers down.
It should be understood that the present embodiment is merely to illustrate the utility model rather than limitation the scope of the utility model.Furthermore It should be understood that after reading the content taught by the present invention, those skilled in the art can make the utility model various Change or modification, these equivalent forms also fall within the scope of the appended claims of the present application.

Claims (8)

1. a kind of three-in-one test equipment for testing ballast, characterized in that including test cabinet (1), be set in test cabinet Test host (2), the display (3) in test cabinet and the test equipment component in test cabinet;Test master Machine is electrically connected with display, and test equipment component is electrically connected with test host.
2. the three-in-one test equipment of test ballast according to claim 1, characterized in that the test equipment component Converter (4) including being set in test cabinet, is set in test cabinet the voltage resistant instrument (5) in test cabinet Power meter (6), the isolating transformer (7) in test cabinet and the pressure regulating instrument (8) in test cabinet;Voltage resistant instrument, Power meter and converter are electrically connected with test host, voltage resistant instrument, power meter, isolating transformer and pressure regulator with height Low voltage converter electrical connection.
3. the three-in-one test equipment of test ballast according to claim 2, characterized in that the test equipment component It further include product to be measured (9) and test load (10), product and test load to be measured are electrically connected with converter.
4. the three-in-one test equipment of test ballast according to claim 3, characterized in that further include external terminal Mouth (11), product and test load to be measured are electrically connected by Wiring port with converter.
5. the three-in-one test equipment of test ballast according to claim 1 or 2 or 3 or 4, characterized in that production to be measured Product are ballast, and test load is fluorescent tube, and external cabling port is 20 spelling rectangular receptacles.
6. the three-in-one test equipment of test ballast according to claim 1, characterized in that the test cabinet is in square Shape, test cabinet include top plate and bottom plate and 3 blocks of side plates, and 3 fast side plates are vertical with top plate and bottom plate respectively to be connect.
7. the three-in-one test equipment of test ballast according to claim 6, characterized in that the bottom plate lower part is equipped with Several movable pulleies easy to carry, the test cabinet is interior to be equipped with several partitions, and test host, display, high-low pressure turn Parallel operation, voltage resistant instrument, power meter, isolating transformer and pressure regulating instrument are respectively positioned on corresponding partition.
8. the three-in-one test equipment of test ballast according to claim 6, characterized in that on 3 pieces of side plate interior sides faces It is equipped with the rubber layer for buffering colliding forces.
CN201821533497.3U 2018-09-19 2018-09-19 Test the three-in-one test equipment of ballast Expired - Fee Related CN209311607U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821533497.3U CN209311607U (en) 2018-09-19 2018-09-19 Test the three-in-one test equipment of ballast

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821533497.3U CN209311607U (en) 2018-09-19 2018-09-19 Test the three-in-one test equipment of ballast

Publications (1)

Publication Number Publication Date
CN209311607U true CN209311607U (en) 2019-08-27

Family

ID=67669927

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821533497.3U Expired - Fee Related CN209311607U (en) 2018-09-19 2018-09-19 Test the three-in-one test equipment of ballast

Country Status (1)

Country Link
CN (1) CN209311607U (en)

Similar Documents

Publication Publication Date Title
CN102542888A (en) Comprehensive electrotechnical and electronic technique experiment platform
CN207851236U (en) A kind of chip testing plate and chip test system
CN202600108U (en) Testing system for printed circuit board
CN203981834U (en) The inverter board pick-up unit of railway DC600V power supply passenger vehicle
CN202454137U (en) Electrician technique and electronic technique comprehensive experiment box
CN206515435U (en) A kind of general jigsaw automatic testing equipment
CN108761328A (en) Electric tool switch test device and system
CN106324532A (en) Test machine for LED driving power sources
CN202995451U (en) A vehicle-mounted controller automatic testing device
CN202003226U (en) Electrical measurement and control system with signal conditioning function
CN106054059B (en) A kind of power automatic device chip card automatically testing platform
CN108776295A (en) A kind of efficient ETAP automatization test systems
CN208760921U (en) A kind of aircraft drop in beam electric attachments automatic test equipment
CN104049219A (en) Automatic test instrument for power source test
CN202003227U (en) Electrical measurement and control system with signal switching function
CN209311607U (en) Test the three-in-one test equipment of ballast
CN109470961A (en) A kind of omnipotent detection station of power equipment quality based on modularized design
CN206321732U (en) ICT comprehensive testers
CN204882853U (en) Electric energy meter pressure resistance test installation
CN207832960U (en) A kind of circuit board testing system
CN101354417A (en) Circuit board test device of electrical energy meter based on virtual instrument technique
CN203165313U (en) Electronic circuit fault setting device
CN202471932U (en) Simulation testing platform for comprehensive battery management system
CN204617470U (en) The sub-electrical practice training platform of a kind of intelligent embedded type electric
CN209248002U (en) A kind of LED light strip ageing tester

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190827