CN209263986U - Marking pile is used in a kind of positioning of Electric Power Survey - Google Patents

Marking pile is used in a kind of positioning of Electric Power Survey Download PDF

Info

Publication number
CN209263986U
CN209263986U CN201822220838.8U CN201822220838U CN209263986U CN 209263986 U CN209263986 U CN 209263986U CN 201822220838 U CN201822220838 U CN 201822220838U CN 209263986 U CN209263986 U CN 209263986U
Authority
CN
China
Prior art keywords
intercommunicating pore
mark
drive shaft
pile body
auger spindle
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201822220838.8U
Other languages
Chinese (zh)
Inventor
王宜强
唐琳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HUNAN JUYUAN ELECTRIC POWER SURVEY DESIGN CO Ltd
Original Assignee
HUNAN JUYUAN ELECTRIC POWER SURVEY DESIGN CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HUNAN JUYUAN ELECTRIC POWER SURVEY DESIGN CO Ltd filed Critical HUNAN JUYUAN ELECTRIC POWER SURVEY DESIGN CO Ltd
Priority to CN201822220838.8U priority Critical patent/CN209263986U/en
Application granted granted Critical
Publication of CN209263986U publication Critical patent/CN209263986U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Earth Drilling (AREA)

Abstract

The utility model relates to a kind of Electric Power Survey positioning marking piles, including mark pile body and for driving the driving mechanism in mark bar body insertion soil layer, the bottom of the mark pile body is provided with round table-like drill bit, corresponding first intercommunicating pore is equipped at the center of the mark pile body, corresponding second intercommunicating pore, the diameter of the diameter of second intercommunicating pore less than the first intercommunicating pore are equipped at the center of the round table-like drill bit;The driving mechanism includes drive shaft, the bottom of the drive shaft is connected with downwards corresponding auger spindle into a ladder, the auger spindle bottom is arranged to coniform, after the drive shaft and auger spindle are installed on corresponding first intercommunicating pore and the second intercommunicating pore respectively, the auger spindle bottom stretching second intercommunicating pore cooperatively forms coniform with the round table-like drill bit.The utility model can be effectively reduced mark pile body and squeeze into the difficulty of soil layer, and it is fast to squeeze into soil layer speed, squeeze into soil layer rear stability foot.

Description

Marking pile is used in a kind of positioning of Electric Power Survey
Technical field
The utility model relates to a kind of positioning marking pile, in particular to a kind of Electric Power Survey positioning marking piles.
Background technique
Currently, needing to carry out to pinpoint on-site land survey accordingly when carrying out the planning process of power circuit in power industry. Due in route fixed position it is more, distance farther out, it is therefore desirable to using corresponding marking pile to the position pinpointed in route into Line flag is assessed route, improved and is finally determined so as to more convenient.Marking pile is used in existing Electric Power Survey positioning Have the defects that one very it is big be exactly directly squeeze into soil layer difficulty it is big, and use and dig that cave is pre-buried that working hour is caused to increase, and mark The stability deficiency of will bar is easy to topple over.Therefore, design is a can be effectively reduced the difficulty for squeezing into soil layer, and squeeze into soil layer speed Degree is fast, squeezes into the research purpose that the Electric Power Survey positioning of soil layer rear stability foot is the utility model with marking pile.
Utility model content
For above-mentioned technical problem of the existing technology, the utility model lies in that providing a kind of Electric Power Survey positioning mark Remember that stake, the Electric Power Survey positioning can effectively solve the problem that above-mentioned technical problem of the existing technology with marking pile.
The technical solution of the utility model is:
A kind of Electric Power Survey positioning marking pile, including indicate pile body and be used to drive in mark bar body insertion soil layer Driving mechanism, the bottom of the mark pile body is provided with round table-like drill bit, and the round table-like drill bit is with pile body is indicated Integral structure is equipped with corresponding first intercommunicating pore at the center of the mark pile body, at the center of the round table-like drill bit Equipped with corresponding second intercommunicating pore, the diameter of the diameter of second intercommunicating pore less than the first intercommunicating pore;The driving mechanism packet Containing drive shaft, the bottom of the drive shaft is connected with downwards corresponding auger spindle into a ladder, the diameter of the auger spindle and described the Two connection bore dias are consistent, and the diameter of the drive shaft is consistent with the first connection bore dia, the auger spindle bottom setting At coniform, after the drive shaft and auger spindle are installed on corresponding first intercommunicating pore and the second intercommunicating pore respectively, the auger spindle bottom Portion's stretching second intercommunicating pore cooperatively forms coniform with the round table-like drill bit.
The top side detachable of the mark pile body is socketed with corresponding capping, is equipped at the center of the capping corresponding Mounting hole, the mounting hole and marker peg body fits that capping is equipped with by it are mounted on marker peg bodies top, the capping Side wall and marker peg bodies top between by it is corresponding to lock bolt lock.
Corresponding hammer plate is connected at the top of the drive shaft, the hammer plate and drive shaft and auger spindle are by metal material system It is standby to form.
The mark pile body and round table-like drill bit are fabricated by enhancing composite material.
Corresponding power industry warning mark is printed in the mark pile body.
The advantages of the utility model:
When the utility model is installed, the drive shaft of the utility model and auger spindle are installed on corresponding first respectively and connected In through-hole and the second intercommunicating pore, cooperatively form auger spindle bottom the second intercommunicating pore of stretching with the round table-like drill bit coniform.So The hammer plate at the top of hammer directly impact drive shaft is held afterwards, drive shaft and auger spindle is squeezed into soil layer, in the effect of drive shaft and auger spindle Under, drive driving mark bar body smoothly quickly to squeeze into soil layer.After mark bar body is squeezed into soil layer, it can will drive Mechanism integrally takes out, then by seal cap positioning device at the top of mark pile body.It can effectively be dropped by driving mechanism Low mark pile body squeezes into the difficulty of soil layer, effectively promotes mark pile body and squeezes into the speed of soil layer, and can effectively ensure to mark Will pile body squeezes into the stability after soil layer.The utility model can be by driving mechanism after mark pile body smoothly squeezes into soil layer It takes out, driving mechanism can constantly repeat to apply to squeezing into for unlike signal pile body.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the utility model.
Fig. 2 is the structural schematic diagram that marker peg bodies top is socketed with capping.
Specific embodiment
In order to facilitate the understanding of those skilled in the art, existing make structure of the embodiment combination attached drawing to the utility model into one Step detailed description:
With reference to Fig. 1-2, a kind of Electric Power Survey positioning marking pile, including mark pile body 1 and for driving marker post sheet Body 1 is inserted into the driving mechanism 2 in soil layer, and the bottom of the mark pile body 1 is provided with round table-like drill bit 3, the round table-like brill First 2 are integrated with mark pile body 1, are equipped with corresponding first intercommunicating pore 101 at the center of the mark pile body 1, It is equipped with corresponding second intercommunicating pore 301 at the center of the round table-like drill bit 3, the diameter of second intercommunicating pore 301 is less than the The diameter of one intercommunicating pore 101;The driving mechanism 2 includes drive shaft 201, and the bottom of the drive shaft 201 is downward into a ladder It is connected with corresponding auger spindle 202, the diameter of the auger spindle 202 drive shaft consistent, described with 301 diameter of the second intercommunicating pore 201 diameter is consistent with 101 diameter of the first intercommunicating pore, and 202 bottom of auger spindle is arranged to coniform, the drive shaft 201 and after auger spindle 202 is installed on corresponding first intercommunicating pore 101 and the second intercommunicating pore 301 respectively, 202 bottom of auger spindle is stretched Second intercommunicating pore 301 cooperatively forms coniform with the round table-like drill bit 3 out.
The top side detachable of the mark pile body 1 is socketed with corresponding capping 5, is equipped with phase at the center of the capping 5 The mounting hole answered, the mounting hole and mark pile body 1 that capping 5 is equipped with by it are fitted to 1 top of mark pile body, institute It states and lock bolt 6 is locked by corresponding between the side wall of capping 5 and 1 top of mark pile body.
The top of the drive shaft 201 is connected with corresponding hammer plate 4, and the hammer plate 4 is with drive shaft 201 and auger spindle 203 It is prepared by metal material.The mark pile body 1 and round table-like drill bit 3 are fabricated by enhancing composite material.It is described Corresponding power industry warning mark (not identifying) is printed in mark pile body 1.
When the utility model is installed, the drive shaft 201 of the utility model and auger spindle 202 are installed on accordingly respectively In first intercommunicating pore 101 and the second intercommunicating pore 301,202 bottom of auger spindle is made to stretch out the second intercommunicating pore 301 and the round table-like drill bit 3 cooperatively form it is coniform.Then the hammer plate 6 for holding hammer directly 201 top of impact drive shaft, drive shaft 201 and auger spindle 202 are squeezed into In soil layer, under the action of drive shaft 201 and auger spindle 202, driving mark bar body 1 is driven smoothly quickly to squeeze into soil layer.? It, can be by the whole taking-up of driving mechanism 2, then by 4 positioning devices of capping in marker peg after mark bar body 1 is squeezed into soil layer The top of ontology 1.
The above is only the preferred embodiment of the present invention, it is all done according to present utility model application the scope of the patents it is equal Deng variation and modification, the covering scope of the utility model all should belong to.

Claims (5)

1. a kind of Electric Power Survey positioning marking pile, including mark pile body and for driving in mark bar body insertion soil layer Driving mechanism, it is characterised in that: the bottom of the mark pile body is provided with round table-like drill bit, the round table-like drill bit and mark Pile body is integrated, and is equipped with corresponding first intercommunicating pore, the round table-like drill bit at the center of the mark pile body Center at be equipped with corresponding second intercommunicating pore, the diameter of the diameter of second intercommunicating pore less than the first intercommunicating pore;The drive Motivation structure includes drive shaft, and the bottom of the drive shaft is connected with downwards corresponding auger spindle, the diameter of the auger spindle into a ladder Consistent with the second connection bore dia, the diameter of the drive shaft is consistent with the first connection bore dia, the auger spindle Bottom be arranged to it is coniform, after the drive shaft and auger spindle are installed on corresponding first intercommunicating pore and the second intercommunicating pore respectively, institute State auger spindle bottom stretch out second intercommunicating pore cooperatively formed with the round table-like drill bit it is coniform.
2. a kind of Electric Power Survey positioning marking pile according to claim 1, it is characterised in that: the mark pile body Top side detachable is socketed with corresponding capping, and corresponding mounting hole is equipped at the center of the capping, and capping is equipped with by it Mounting hole and marker peg body fits be mounted on marker peg bodies top, the side wall and marker peg bodies top of the capping it Between by accordingly to lock bolt lock.
3. a kind of Electric Power Survey positioning marking pile according to claim 1, it is characterised in that: the top of the drive shaft It is connected with corresponding hammer plate, the hammer plate and drive shaft and auger spindle are prepared by metal material.
4. a kind of Electric Power Survey positioning marking pile according to claim 1, it is characterised in that: the mark pile body with Round table-like drill bit is fabricated by enhancing composite material.
5. a kind of Electric Power Survey positioning marking pile according to claim 1, it is characterised in that: in the mark pile body It is printed with corresponding power industry warning mark.
CN201822220838.8U 2018-12-27 2018-12-27 Marking pile is used in a kind of positioning of Electric Power Survey Active CN209263986U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201822220838.8U CN209263986U (en) 2018-12-27 2018-12-27 Marking pile is used in a kind of positioning of Electric Power Survey

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201822220838.8U CN209263986U (en) 2018-12-27 2018-12-27 Marking pile is used in a kind of positioning of Electric Power Survey

Publications (1)

Publication Number Publication Date
CN209263986U true CN209263986U (en) 2019-08-16

Family

ID=67565746

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201822220838.8U Active CN209263986U (en) 2018-12-27 2018-12-27 Marking pile is used in a kind of positioning of Electric Power Survey

Country Status (1)

Country Link
CN (1) CN209263986U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115655246A (en) * 2022-12-09 2023-01-31 国网甘肃省电力公司兰州供电公司 Digital three-dimensional electric power survey mark pile and installation method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115655246A (en) * 2022-12-09 2023-01-31 国网甘肃省电力公司兰州供电公司 Digital three-dimensional electric power survey mark pile and installation method thereof

Similar Documents

Publication Publication Date Title
CN209263986U (en) Marking pile is used in a kind of positioning of Electric Power Survey
CN110887607A (en) Building outer wall infiltration detection device
CN210979200U (en) Stable placing rack for environment detection equipment
CN212808333U (en) Environmental protection monitoring facilities
CN203241265U (en) Novel base course core drilling machine
CN212300915U (en) Soil pollution sample is with boring getting device
CN209432005U (en) A kind of water conservancy project ring geology crack measuring device
CN214459810U (en) Guideboard for tunnel entrance
CN209039984U (en) A kind of bridge construction drilling equipment
CN211076260U (en) Buoy device for hydrology and water utilization
CN204203462U (en) A kind of mono-base station of GPS
CN204570512U (en) Novel portable road construction warning board
CN211522971U (en) Luminous signboard
CN206298843U (en) Traffic sign fixed mount
CN210036735U (en) Marking rod for remote sensing surveying and mapping
CN218241141U (en) Teaching device for training rescue at sea
CN218035227U (en) Water level measuring device for environmental monitoring
CN216238235U (en) Town road sign convenient to installation
CN218646300U (en) Anti-interference ground collapse monitoring device
CN206856947U (en) A kind of cylindrical offshore anemometer tower
CN213061767U (en) A indicate way frame for wisdom tourism
CN217055290U (en) Monitoring alarm equipment for detecting coal mine geological disasters
CN101323223A (en) Teaching demonstration and board writing teaching aid
CN210616442U (en) Large-scale traffic sign tilting mechanism
CN205171402U (en) Highway sign

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant