CN209227378U - Central hard shoulder formwork jumbo - Google Patents

Central hard shoulder formwork jumbo Download PDF

Info

Publication number
CN209227378U
CN209227378U CN201821986086.XU CN201821986086U CN209227378U CN 209227378 U CN209227378 U CN 209227378U CN 201821986086 U CN201821986086 U CN 201821986086U CN 209227378 U CN209227378 U CN 209227378U
Authority
CN
China
Prior art keywords
template
door frame
drop
hard shoulder
demoulding
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821986086.XU
Other languages
Chinese (zh)
Inventor
余波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chengdu Colitt Machinery Manufacturing Co Ltd
Original Assignee
Chengdu Colitt Machinery Manufacturing Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chengdu Colitt Machinery Manufacturing Co Ltd filed Critical Chengdu Colitt Machinery Manufacturing Co Ltd
Priority to CN201821986086.XU priority Critical patent/CN209227378U/en
Application granted granted Critical
Publication of CN209227378U publication Critical patent/CN209227378U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of central hard shoulder formwork jumbos; including drop in beam, door frame, template, translation mechanism, walking mechanism, lifting body and demoulding mechanism; drop in beam is slidably arranged on door frame crossbeam; translation mechanism, which is located on door frame crossbeam, drives drop in beam to move on door frame crossbeam; template is hinged with drop in beam; demoulding mechanism one end is hinged with template, and the other end is hinged with door frame, and door frame is slid vertically with walking mechanism by lifting body and connect.The utility model realizes in-situ continuous pouring center hard shoulder, and the central hard shoulder seam poured is few, and seam is small, and surface quality is high, and template disconnects that labor intensity is low, and operator is greatly decreased, high production efficiency.

Description

Central hard shoulder formwork jumbo
Technical field
The utility model relates to a kind of central hard shoulder formwork jumbos, belong to construction equipment field.
Background technique
There are the central hard shoulder for preventing isolation from vehicle being prevented to be flushed to reverse track, mesh in bridge structure in bridge medium design Before be all made of hand fit's lifting machine on-site assembly fritter template when applying central hard shoulder, and dowel installation is played on bridge floor Pull rod, very heavy fixed after-pouring concrete, the demoulding again after concrete reaches demoulding strength, so circulation construction complete it is all every From pier.
This construction method has the disadvantage that 1, frequently dismounting shuttering work intensity is big, and construction efficiency is low;2, using fritter Template assemblies seam is big, and seam is more, and surface quality is poor, unsightly.
Summary of the invention
The purpose of the utility model is to overcome the above problems of the existing technology, provide a kind of central hard shoulder template Trolley.The utility model realizes in-situ continuous pouring center hard shoulder, and the central hard shoulder seam poured is few, and seam is small, Surface quality is high, and template disconnects that labor intensity is low, and operator is greatly decreased, high production efficiency.
To achieve the above object, the technical solution adopted in the utility model is as follows:
A kind of center hard shoulder formwork jumbo, it is characterised in that: including drop in beam, door frame, template, translation mechanism, vehicle with walking machine Structure, lifting body and demoulding mechanism, drop in beam are slidably arranged on door frame crossbeam, and translation mechanism, which is located on door frame crossbeam, drives drop in beam It is moved on door frame crossbeam, template is hinged with drop in beam, and demoulding mechanism one end is hinged with template, and the other end is hinged with door frame, door frame It is slid vertically and is connect with walking mechanism by lifting body.
The translation mechanism is 4 translation oil cylinders, and walking mechanism is 4 groups of traveling wheels, and lifting body is 4 jacking cylinders, Demoulding mechanism is 4 demoulding oil jars.
The drop in beam is 2, and every drop in beam both ends are provided with sliding sleeve, and drop in beam passes through the door frame crossbeam of sliding sleeve and door frame both ends Slide laterally connection.
Oil cylinder hinge ear and template hinge ear are provided on the sliding sleeve, oil cylinder cuts with scissors ear and translation oil cylinder one end is hinged, translation oil The hinge ear being arranged on the cylinder other end and door frame crossbeam is hinged.
The template is 2 groups, and template cuts with scissors ear by template and drop in beam is hinged, cuts with scissors ear by the oil cylinder being arranged in template and takes off Mould oil cylinder one end is hinged.
The template hinge ear being arranged on the demoulding oil jar other end and door frame is hinged.
The template is monolithic construction, and 2 groups of templates cooperatively form central hard shoulder shape.
The door frame, which is slid vertically by jacking cylinder with traveling wheel, to be connect.
Using utility model has the advantages that
1, the utility model realizes in-situ continuous pouring center hard shoulder, and uses integral mold plate, the center poured every Few from pier seam, seam is small, and surface quality is high, and appearance is more beautiful.
2, using whole formwork erection, by the translation mechanism of setting, walking mechanism, lifting body and demoulding mechanism, template is torn open It is low to connect labor intensity, operator is greatly decreased, high production efficiency.
Detailed description of the invention
Fig. 1 is the utility model trolley lining cutting state front view;
Fig. 2 is that the utility model trolley demoulds state front view;
Fig. 3 is the utility model trolley side view;
In the figure, it is marked as 1, drop in beam, 2, door frame, 3, template, 4, walking mechanism, 5, door frame crossbeam, 6, translation oil cylinder, 7, top Oil-lifting jar, 8, demoulding oil jar, 9, rail.
Specific embodiment
Embodiment 1
A kind of center hard shoulder formwork jumbo, including drop in beam 1, door frame 2, template 3, translation mechanism, walking mechanism 4, jacking Mechanism and demoulding mechanism, drop in beam 1 are slidably arranged on door frame crossbeam 5, and translation mechanism, which is located on door frame crossbeam 5, drives drop in beam 1 to exist It is moved on door frame crossbeam 5, template 3 and drop in beam 1 are hinged, and demoulding mechanism one end and template 3 are hinged, and the other end and door frame 2 are hinged, door Frame 2, which is slid vertically by lifting body with walking mechanism, to be connect.
The translation mechanism is 4 translation oil cylinders 6, and walking mechanism 4 is 4 groups of traveling wheels, and lifting body is 4 jacking cylinders 7, demoulding mechanism is 4 demoulding oil jars 8.
The drop in beam 1 is 2, and every 1 both ends of drop in beam are provided with sliding sleeve, and drop in beam 1 passes through the door frame of sliding sleeve and 2 both ends of door frame Crossbeam 5 slides laterally connection.
Oil cylinder hinge ear and template hinge ear are provided on the sliding sleeve, oil cylinder cuts with scissors ear and 6 one end of translation oil cylinder is hinged, translation oil The hinge ear being arranged on 6 other end of cylinder and door frame crossbeam 5 is hinged.
The template 3 is 2 groups, and template 3 cuts with scissors ear by template and drop in beam 1 is hinged, cuts with scissors ear by the oil cylinder being arranged in template 3 It is hinged with 8 one end of demoulding oil jar.
The template hinge ear being arranged on 8 other end of demoulding oil jar and door frame 2 is hinged.
The template 3 is monolithic construction, and 2 groups of templates 3 cooperatively form central hard shoulder shape.
The door frame 2, which is slid vertically by jacking cylinder 7 with traveling wheel, to be connect.
Embodiment 2
The present embodiment combination attached drawing is described further the utility model structure and working principle.
As shown, central hard shoulder formwork jumbo by 21,2 group of drop in beam, 3,1 groups of template door frames, 2,4 translation oil cylinders 6, 4 groups of 4,4, the walking mechanism demoulding oil jar 8 of jacking cylinder 7,4 compositions.
Every 1 both ends of drop in beam are provided with the sliding sleeve of 1 group oil cylinder of band hinge ear, are additionally provided at least 2 groups of template hinge ears;2 extensions Beam 1 is slid laterally with the door frame crossbeam 5 at 2 both ends of door frame by sliding sleeve and is connect;Be arranged on sliding sleeve oil cylinder hinge ear respectively with translation 6 one end of oil cylinder is hinged, and the hinge ear being arranged on 6 other end of translation oil cylinder and door frame crossbeam 5 is hinged;2 groups of 3 one end of template are respectively with 2 Template hinge ear on root drop in beam 1 hingedly cuts with scissors ear by the oil cylinder being arranged in template 3 simultaneously and 8 one end of demoulding oil jar is hinged, demoulding The template hinge ear being arranged on 8 other end of oil cylinder and door frame 2 is hinged;Door frame 2 is perpendicular by 4 jacking cylinder 7 and 4 group walking mechanisms 4 To being slidably connected.
The working principle of the utility model is as follows:
First in predetermined position steel rail laying 9, trolley is passed through along the position that rail running extremely needs by walking mechanism 4 Translation oil cylinder 6 adjusts template 3 to position is needed, and rises jacking cylinder 7 to needing position, by 8 adjusting template 3 of demoulding oil jar to The position needed, casting concrete withdraw demoulding oil jar 8 after concrete reaches demoulding strength, withdraw translation oil cylinder 6 and are detached from Template 3 is to clear up template and to smear release agent, by 4 walking carriage of walking mechanism to next mould position, aforesaid operations again It completes until central hard shoulder concrete pouring construction.

Claims (8)

1. a kind of center hard shoulder formwork jumbo, it is characterised in that: including drop in beam (1), door frame (2), template (3), translation mechanism, Walking mechanism (4), lifting body and demoulding mechanism, drop in beam (1) are slidably arranged on door frame crossbeam (5), and translation mechanism is located at door Drive drop in beam (1) to move on door frame crossbeam (5) on frame crossbeam (5), template (3) and drop in beam (1) hingedly, demoulding mechanism one end with Hingedly, hingedly, door frame (2) is slid vertically by lifting body with walking mechanism (4) and is connect template (3) for the other end and door frame (2).
2. center hard shoulder formwork jumbo according to claim 1, it is characterised in that: the translation mechanism is 4 translations Oil cylinder (6), walking mechanism (4) are 4 groups of traveling wheels, and lifting body is 4 jacking cylinders (7), and demoulding mechanism is 4 demoulding oil jars (8).
3. center hard shoulder formwork jumbo according to claim 2, it is characterised in that: the drop in beam (1) is 2, every Drop in beam (1) both ends are provided with sliding sleeve, and drop in beam (1) is slid laterally with the door frame crossbeam (5) at door frame (2) both ends by sliding sleeve and connect.
4. center hard shoulder formwork jumbo according to claim 3, it is characterised in that: be provided with oil cylinder hinge on the sliding sleeve Ear and template cut with scissors ear, and oil cylinder cuts with scissors ear and translation oil cylinder (6) one end is hinged, set on translation oil cylinder (6) other end and door frame crossbeam (5) The hinge ear set is hinged.
5. center hard shoulder formwork jumbo according to claim 4, it is characterised in that: the template (3) is 2 groups, template (3) ear and drop in beam (1) are cut with scissors hingedly by template, ear is cut with scissors by the oil cylinder being arranged on template (3) and demoulding oil jar (8) one end is cut with scissors It connects.
6. center hard shoulder formwork jumbo according to claim 5, it is characterised in that: demoulding oil jar (8) other end It is hinged that ear is cut with scissors with the template being arranged on door frame (2).
7. center hard shoulder formwork jumbo according to claim 6, it is characterised in that: the template is monolithic construction, 2 Group template (3) cooperatively forms central hard shoulder shape.
8. center hard shoulder formwork jumbo according to claim 7, it is characterised in that: the door frame (2) passes through jacking oil Cylinder (7) slides vertically with traveling wheel to be connect.
CN201821986086.XU 2018-11-29 2018-11-29 Central hard shoulder formwork jumbo Active CN209227378U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821986086.XU CN209227378U (en) 2018-11-29 2018-11-29 Central hard shoulder formwork jumbo

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821986086.XU CN209227378U (en) 2018-11-29 2018-11-29 Central hard shoulder formwork jumbo

Publications (1)

Publication Number Publication Date
CN209227378U true CN209227378U (en) 2019-08-09

Family

ID=67505277

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821986086.XU Active CN209227378U (en) 2018-11-29 2018-11-29 Central hard shoulder formwork jumbo

Country Status (1)

Country Link
CN (1) CN209227378U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111926711A (en) * 2020-08-12 2020-11-13 宁波交通工程建设集团有限公司 Quick assembly disassembly's T type roof beam template
CN114603695A (en) * 2022-02-14 2022-06-10 中铁上海工程局集团有限公司 Self-walking opening and closing template system for assembled railway bridge pier stud and construction method thereof

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111926711A (en) * 2020-08-12 2020-11-13 宁波交通工程建设集团有限公司 Quick assembly disassembly's T type roof beam template
CN111926711B (en) * 2020-08-12 2021-07-27 宁波交通工程建设集团有限公司 Quick assembly disassembly's T type roof beam template
CN114603695A (en) * 2022-02-14 2022-06-10 中铁上海工程局集团有限公司 Self-walking opening and closing template system for assembled railway bridge pier stud and construction method thereof

Similar Documents

Publication Publication Date Title
CN209227378U (en) Central hard shoulder formwork jumbo
CN102022123B (en) Integral lining method for tunnel with altered diameter by model board trolley
CN205370586U (en) Multibreak face reducing tunnel lining platform truck of large -span
CN103982200B (en) Slide rail Mobile steel mould trolley in tunneling boring
CN207944955U (en) Tunnel widened section two serves as a contrast trolley
CN106593469A (en) Trolley for construction of inverted arch
CN204041080U (en) General formula needle beam lining trolley in a kind of
CN103352710A (en) Suspension overturn type tunnel inverted arch formwork trolley and construction method thereof
CN109281689A (en) Integral construction method based on tunnel trestle full width inverted arch template
CN110145341A (en) A kind of gang form system for circular tunnel concreting
CN211314235U (en) Tunnel inverted arch and filling concrete paver
CN110468715A (en) Mobile formwork passing method and excessively aperture apparatus
CN110173281A (en) A kind of sliding mode system for circular tunnel concreting
CN211221232U (en) Highway steel and concrete composite beam structure template based on assembly
CN210712938U (en) Pipe gallery trolley
CN202164548U (en) Deck type mobile formwork bridge-building machine dedicated to double T type bridge construction
CN203515607U (en) Adjustable steel mould trolley of tunnel widening section
CN216586211U (en) Bottom die integrated hanging basket
CN206015534U (en) The self-propelled running gear of cantilever box beam Hanging Basket
CN205591932U (en) Full -automatic highway, railway ditch cable duct lining cutting platform truck
CN110714785A (en) Pipe gallery top plate construction trolley, trolley set and construction method
CN208310801U (en) A kind of working portable shifting formwork trolley of channel wall
CN210975880U (en) Adjustable open cut tunnel is hydraulic pressure platform truck by oneself
CN210105880U (en) Alternate hydraulic lifting template ditch cable trough trolley device