CN209215508U - AFGF finished-product testing machine - Google Patents

AFGF finished-product testing machine Download PDF

Info

Publication number
CN209215508U
CN209215508U CN201821608894.2U CN201821608894U CN209215508U CN 209215508 U CN209215508 U CN 209215508U CN 201821608894 U CN201821608894 U CN 201821608894U CN 209215508 U CN209215508 U CN 209215508U
Authority
CN
China
Prior art keywords
isolating transformer
current
switch
winding
module
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821608894.2U
Other languages
Chinese (zh)
Inventor
朱振中
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Intelligent Automation Equipment Co Ltd
Original Assignee
Shenzhen Intelligent Automation Equipment Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Intelligent Automation Equipment Co Ltd filed Critical Shenzhen Intelligent Automation Equipment Co Ltd
Priority to CN201821608894.2U priority Critical patent/CN209215508U/en
Application granted granted Critical
Publication of CN209215508U publication Critical patent/CN209215508U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Emergency Protection Circuit Devices (AREA)

Abstract

The utility model discloses and provides a kind of AFGF finished-product testing machine, it includes power supply, power switch, current-limiting resistance, change-over switch, AF/GF module, load switch and load, it further includes isolating transformer, the first winding and secondary winding turn ratio of the isolating transformer are 1:1, the current-limiting resistance is that a fixed resistance and an adjustable resistance are composed in series, the AF/GF module includes single-chip microcontroller, voltage and current measurement, relay board, peripheral components, it is to test in practical work process automatically, personnel's intervention is not needed, entire product is enclosed in test fixture, operator can not touch product, guarantee that operation safety is reliable.Leakage current is simulated with isolating transformer, is easy setting, electric current is stablized, and precision is high;Test equipment efficient quick will not cause really to leak electricity to the earth, guarantee the safety of the entire electricity consumption of factory.

Description

AFGF finished-product testing machine
Technical field
The utility model relates to electronic and electrical equipment test industry, teaching experiment platform, more particularly to production in batch at Product detection field.
Background technique
Safe and intelligent is all pursued in present life, household, factory electrical equipment be also required to safe and intelligent, smart grid Other than over-voltage over-current protection, also there are anti-lightning strike protection, earth leakage protective etc..The electric appliances such as breaker, switch, plug, socket member Part will do anti-lightning strike anti-leakage function, these electric elements have anti-lightning strike anti-leakage function, just must be tight in production and assembly Lattice test anti-lightning strike anti-leakage function index, our AFGF finished-product testing machine tests this function, certainly we Equipment there is basic over-voltage to test, cross the functions such as current test, also offer lightning stroke simulation test function, simulate leakage tests, electric leakage Test this part we provide simulation leakage current electrostatic can achieve 0.01mA.AF is anti-lightning strike function, and GF is leakproof electric work Energy.In electrical equipment use process, the principle of lightning stroke and drain conditions occurs it is well known that lightning stroke situation occurs for AF, GF occurs Drain conditions, such schematic circuit cannot be used for carrying out functional test in product line certainly in practice, because of production line More test equipments work at the same time, while leaking electricity to the earth, then the total leakage switch of factory is once testing tripping, entire workshop does not have Method production.The test circuit of other simulation leakage functions is so had, the test circuit of existing traditional simulation leakage current is Electric current asymmetry by limiting the firewire and zero curve that flow through device simulates leaky without to circuit test.It is such The circuit of simulation leakage function is the leakage current value that needs are formed with resistance current limliting, circuit directly by access network voltage and Builtin voltage fluctuation, the interference of the factors such as ripple, the leakage current value stability and low precision of simulation.It is leaked based on simulation above The shortcomings that current circuit, it is proposed that using the method for isolating transformer, the voltage fluctuation of shielding wire road and ripple in this way Interference.The Method And Principle and advantage of leakage current: front end input regulated power supply, active line are simulated with isolating transformer method The fluctuation of road voltage and ripple, so that it may be isolated transformer isolation, because isolating transformer can store energy, play buffering Effect, isolating transformer itself have reactance, are distributed capacitive reactance, impedance, can inhibit voltage fluctuation and the interference of ripple in this way, guarantee The precision of the leakage current value of simulation, electric leakage flow control precision can achieve 0.01mA.
Utility model content
Technical problem to be solved in the utility model is overcome the deficiencies in the prior art, provides a kind of addition isolation transformation Device, can be with the AFGF finished-product testing machine of batch detection product.
The technical scheme adopted by the utility model is a kind of AFGF finished-product testing machine, it include power supply, power switch, Current-limiting resistance, change-over switch, AF/GF module 5, load switch and load, it further includes isolating transformer, the isolating transformer The hot end of first winding connect the firewire of the power supply by a pole of the power switch, the isolating transformer it is primary The cold end of winding connects the zero curve of the power supply, the first winding of the isolating transformer by another pole of the power switch Cold end and secondary winding cold end connect and connect with the input N-terminal of the AF/GF module, the isolating transformer it is primary The hot end of winding is connect with the end input H of the AF/GF module, described in the hot end connection of the secondary winding of the isolating transformer One end of current-limiting resistance, the other end of the current-limiting resistance connect the input terminal of the change-over switch, and the two of the change-over switch A output end is separately connected the end output H and the N-terminal of the AF/GF module, and the end output H of the AF/GF module and N-terminal lead to respectively The two poles of the earth and the load for crossing the load switch connect.
The first winding and secondary winding turn ratio of the isolating transformer are 1:1.
The current-limiting resistance is that a fixed resistance and an adjustable resistance are composed in series.
The AF/GF module includes single-chip microcontroller, voltage and current measurement, relay board, peripheral components, in practical work process It is to test automatically, does not need personnel's intervention, entire product is enclosed in test fixture, and operator can not touch product, Any part for having electricity can not be touched, guarantees that operation safety is reliable.
The beneficial effects of the utility model are: it includes power supply, power switch, current-limiting resistance, turns due to the utility model Switch, AF/GF module, load switch 6 and load are changed, it further includes isolating transformer, the first winding of the isolating transformer It is 1:1 with secondary winding turn ratio, the current-limiting resistance is that a fixed resistance and an adjustable resistance are composed in series, described AF/GF module includes single-chip microcontroller, voltage and current measurement, relay board, peripheral components, is to test in practical work process automatically, Personnel's intervention is not needed, entire product is enclosed in test fixture, and operator can not touch product, it is also not possible to touch Any part for having electricity guarantees that operation safety is reliable.So the utility model has the following beneficial effects:
1. simulating leakage current with isolating transformer, it is easy setting, electric current is stablized, and current value precision can guarantee 0.01mA;
2. test equipment efficient quick, reliable in test product electric leakage parameter safety, speed is fast, and it is really right to cause The earth leaks electricity, and guarantees the safety of the entire electricity consumption of factory;
3. product is to test automatically during the test, does not need personnel and intervene, in test process, entire product closing In test fixture, operator can not touch product, it is also not possible to touch any part for having electricity;Guarantee operation in this way Securely and reliably;
4. compact-sized, light and handy, simple, maintenance is easy to operate;
5. complete machine long service life.
Detailed description of the invention
Fig. 1 is the utility model circuit principle structure schematic diagram.
Specific embodiment
As shown in Figure 1, the utility model it include power supply 1, power switch 2, current-limiting resistance 3, change-over switch 4, AF/GF mould Block 5, load switch 6 and load 7, it further includes isolating transformer 8, and the hot end of the first winding of the isolating transformer 8 passes through One pole of the power switch 2 connects the firewire of the power supply 1, and the cold end of the first winding of the isolating transformer 8 passes through institute Another pole for stating power switch 2 connects the zero curve of the power supply 1, the cold end of the first winding of the isolating transformer 8 and secondary The cold end of winding is connected and is connect with the input N-terminal of the AF/GF module 5, the hot end of the first winding of the isolating transformer 8 It is connect with the end input H of the AF/GF module 5, the hot end of the secondary winding of the isolating transformer 8 connects the current-limiting resistance 3 one end, the other end of the current-limiting resistance 3 connect the input terminal of the change-over switch 4, and two of the change-over switch 4 are defeated Outlet is separately connected the end output H and the N-terminal of the AF/GF module 5, and the end output H of the AF/GF module 5 and N-terminal pass through respectively The two poles of the earth of the load switch and the load connect.
The first winding and secondary winding turn ratio of the isolating transformer 8 are 1:1.
The current-limiting resistance 3 is that a fixed resistance and an adjustable resistance are composed in series.
The AF/GF module 5 includes single-chip microcontroller, voltage and current measurement, relay board, peripheral components, practical work process In be to test automatically, do not need personnel's intervention, entire product is enclosed in test fixture, and operator can not touch product, It is also impossible to touch any part for having electricity, guarantees that operation safety is reliable.
In the present embodiment, the power switch 2 controls power supply 1 and accesses, the load switch control load access, and described turn It changes switch 4 and controls working condition, 3 current limliting of current-limiting resistance is in 5.85mA, load current 20A, the input of front end power supply 1 pressure stabilizing electricity Source, the fluctuation of voltage and ripple on working line, so that it may the isolation of transformer 8 is isolated, because isolating transformer 8 can store energy Amount plays buffer function, and isolating transformer 8 has reactance in itself, is distributed capacitive reactance, impedance, can inhibit voltage fluctuation and line in this way The interference of wave guarantees that the precision of the leakage current value of simulation, electric leakage flow control precision can achieve 0.01mA.Fully meet batch The demand of production test.

Claims (3)

1.AFGF finished-product testing machine, it includes power supply (1), power switch (2), current-limiting resistance (3), change-over switch (4), AF/GF Module (5), load switch (6) and load (7), it is characterised in that: it further includes isolating transformer (8), the isolating transformer (8) hot end of first winding connects the firewire of the power supply (1) by a pole of the power switch (2), and the isolation becomes The cold end of the first winding of depressor (8) connects the zero curve of the power supply (1) by another pole of the power switch (2), described The connection of the cold end of the cold end of the first winding of isolating transformer (8) and secondary winding and the input N with the AF/GF module (5) End connection, the hot end of the first winding of the isolating transformer (8) is connect with the end input H of the AF/GF module (5), described The hot end of the secondary winding of isolating transformer (8) connects one end of the current-limiting resistance (3), the current-limiting resistance (3) it is another End connects the input terminal of the change-over switch (4), and two output ends of the change-over switch (4) are separately connected the AF/GF mould The end output H of block (5) and N-terminal, the end output H of the AF/GF module (5) and N-terminal pass through the load switch (6) respectively The two poles of the earth connect with the load (7).
2. AFGF finished-product testing machine according to claim 1, it is characterised in that: the isolating transformer (8) it is primary around Group is 1:1 with secondary winding turn ratio.
3. AFGF finished-product testing machine according to claim 1, it is characterised in that: the current-limiting resistance (3) is a fixation Resistance and an adjustable resistance are composed in series.
CN201821608894.2U 2018-09-30 2018-09-30 AFGF finished-product testing machine Active CN209215508U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821608894.2U CN209215508U (en) 2018-09-30 2018-09-30 AFGF finished-product testing machine

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821608894.2U CN209215508U (en) 2018-09-30 2018-09-30 AFGF finished-product testing machine

Publications (1)

Publication Number Publication Date
CN209215508U true CN209215508U (en) 2019-08-06

Family

ID=67455226

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821608894.2U Active CN209215508U (en) 2018-09-30 2018-09-30 AFGF finished-product testing machine

Country Status (1)

Country Link
CN (1) CN209215508U (en)

Similar Documents

Publication Publication Date Title
CN203798934U (en) Electric power DC insulation fault simulation and testing device
CN203037769U (en) Wind power and photovoltaic grid-connected testing platform
CN111551875A (en) Fault simulation system of multi-state transformer
CN202886592U (en) Virtual load device of single-phase electric energy meter
CN204361791U (en) A kind of circuit structure of intelligent low-pressure distribution terminal
CN106205306A (en) A kind of 35kV capacitance type potential transformer Simulation Model of Ferroresonance
CN209215508U (en) AFGF finished-product testing machine
CN103312188B (en) For power supply and the method for testing thereof of reactor performance test in power electronic equipment
CN110912102A (en) Low-voltage power supply network leakage fault protection method based on zero phase transfer
CN204179639U (en) Intelligent leakage circuit breaker
CN204423067U (en) A kind of impulse current generator control device
He et al. Study on the overvoltage and insulation coordination of flexible DC power distribution network
CN204044320U (en) The device of inspection arc-fault circuit interrupter
CN105353258B (en) A kind of test method of test transformer differential protection reactance transformer excitation surge current
CN203983953U (en) Two instrument transformer monitorings, control and the cancellation element of high-power transformer multipoint earthing
CN103560484A (en) Multipoint ground-connection current control device for three current transformers to monitor transformer clamping parts in online mode
CN209070051U (en) PT broken string and singlephase earth fault simulator
CN203466630U (en) Microcomputer protection measurement-control device
CN207882372U (en) Comprehensive protector of motor tester
CN201298812Y (en) An AC power supply controlling device with a controllable output period
CN201945650U (en) Performance test system for high-capacity reactive power dynamic compensating device
CN205210272U (en) Direct current contactor switch -on breaking capacity test device under ambient condition of plateau
CN205301463U (en) Photovoltaic inverter high voltage passes through test system based on chain SVG
CN205038275U (en) Brake unit testing device
Zhe et al. Study on reactive automatic compensation system design

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant