CN209179005U CN201821693715.XU CN201821693715U CN209179005U CN 209179005 U CN209179005 U CN 209179005U CN 201821693715 U CN201821693715 U CN 201821693715U CN 209179005 U CN209179005 U CN 209179005U
Authority
CN
China
Prior art keywords
mud
concrete pile
bored concrete
casing
holing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821693715.XU
Other languages
Chinese (zh)
Inventor
续文昊
陈新喜
王俊佚
李赟
陈华
卢雄峰
鲍旺
张弘锦
樊晨强
谢正涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN201821693715.XU priority Critical patent/CN209179005U/en
Application granted granted Critical
Publication of CN209179005U publication Critical patent/CN209179005U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

Arranging device is fallen the utility model relates to a kind of mud of direct circulation holing with slurry wall protection bored concrete pile, comprising: set on ground and encloses casing structure set on bored concrete pile;It is connected to the structure for conveying of casing structure;It is connected to the sedimentation basin of structure for conveying;And the groove of the mortar of casing structure is overflowed for collecting, groove is enclosed set on casing structure, and is connected to sedimentation basin.The utility model is enclosed using casing structure set on bored concrete pile, is prevented mud spluttering and is influenced environment.The groove for enclosing set on casing structure and being connected to sedimentation basin is set, so that groove has certain storage capacity and mortar is transported in sedimentation basin if there is mud spluttering can be fallen into groove.Using multiple-protection, mud spluttering is prevented, there is good protection effect.Casing structure and sedimentation basin are connected to using structure for conveying, to carry out slurry transportation, realizes that mud discharges in a organized way and collects the transport saving duration.

Description

The mud of direct circulation holing with slurry wall protection bored concrete pile falls arranging device
Technical field
The utility model relates to the realm of building construction, espespecially a kind of mud of direct circulation holing with slurry wall protection bored concrete pile falls to arrange Device.
Background technique
In the infrastructure of cities and towns, usually uses mud off pore-forming technique and construct, after the completion of mud off pore-forming, filling It needs to carry out borehole cleaning deslagging to the slurry coat method in stake before note concrete, the density of slurry coat method, percent sand is made to reach perfusion The requirement of concrete.
The construction method of borehole cleaning deslagging is usually direct circulation method at present, and direct circulation method is with preparing in advance and satisfactory Mud is sent into the stake holes bottom of bored concrete pile with slush pump, and by the pressure of slush pump, original slurry coat method is extruded bored concrete pile Stake holes, while boring mud being swept along out, be flowed into sedimentation basin.
But in the prior art, mud is easy to leak out in the construction process, pollutes construction site, needs to require efforts Cleaning reduces construction efficiency.
Utility model content
The purpose of the utility model is to overcome the defects of the prior art, provide a kind of direct circulation holing with slurry wall protection perfusion The mud of stake falls arranging device, solves mud in the prior art and is easy to leak out, pollute construction site, needs to require efforts clear The problem of reason, reduction construction efficiency.
Realizing the technical solution of above-mentioned purpose is:
The mud that the utility model provides a kind of direct circulation holing with slurry wall protection bored concrete pile falls arranging device, comprising:
Set on ground and enclose casing structure set on bored concrete pile;
It is connected to the structure for conveying of the casing structure;
It is connected to the sedimentation basin of the structure for conveying;And
The groove of the mortar of the casing structure is overflowed for collecting, the groove is enclosed set on the casing structure, and is connected to In the sedimentation basin.
The mud of the utility model direct circulation holing with slurry wall protection bored concrete pile fall arranging device the utility model has the advantages that
The mud of the utility model direct circulation holing with slurry wall protection bored concrete pile fall arranging device using casing structure enclose be set to fill Stake is infused, the mud in bored concrete pile is protected in the construction process, mud spluttering is prevented and influences environment.Setting, which is enclosed, is set to shield Barrel structure and the groove for being connected to sedimentation basin, so that groove has certain storage if there is mud spluttering can be fallen into groove Mortar is simultaneously transported in sedimentation basin by ability.Multiple-protection prevents mud spluttering, has good protection effect.Using conveying Fabric connectivity is in casing structure and sedimentation basin, to carry out slurry transportation, realizes that mud is discharged in a organized way, collects, transported, saves Duration.
The mud of the utility model direct circulation holing with slurry wall protection bored concrete pile fall arranging device further improvement lies in that, it is described Casing structure includes:
Set on ground and enclose interior casing set on bored concrete pile;And
Set on ground and the outer casing set on the interior casing is enclosed, stays and is set centainly between the outer casing and the interior casing Spacing, the outer casing are connected with the structure for conveying.
The mud of the utility model direct circulation holing with slurry wall protection bored concrete pile fall arranging device further improvement lies in that, it is described The top of interior casing is lower than the top of the outer casing.
The mud of the utility model direct circulation holing with slurry wall protection bored concrete pile fall arranging device further improvement lies in that, it is described Interior casing is fixedly connected with the outer casing.
The mud of the utility model direct circulation holing with slurry wall protection bored concrete pile fall arranging device further improvement lies in that, it is described Interior casing is fixedly connected with the outer casing by reinforcing bar.
The mud of the utility model direct circulation holing with slurry wall protection bored concrete pile fall arranging device further improvement lies in that, it is described Groove is enclosed set on the outer casing.
The mud of the utility model direct circulation holing with slurry wall protection bored concrete pile fall arranging device further improvement lies in that, it is described Structure for conveying includes:
It is connected to the delivery pipe of the outer casing, the communicating position of the delivery pipe and the outer casing is lower than the interior shield The top of cylinder;And
The oblique mud ditch for being connected to the delivery pipe and the sedimentation basin.
The mud of the utility model direct circulation holing with slurry wall protection bored concrete pile fall arranging device further improvement lies in that, it is described The communicating position of sedimentation basin and the mud ditch is equipped with filtering grid.
The mud of the utility model direct circulation holing with slurry wall protection bored concrete pile fall arranging device further improvement lies in that, it is described Delivery pipe includes interconnected steel pipe and rubber tube, and the steel pipe is connected to the outer casing, and the rubber tube is connected to institute State mud ditch.
Detailed description of the invention
Fig. 1 is that the mud of the utility model direct circulation holing with slurry wall protection bored concrete pile falls the structural schematic diagram of arranging device.
Fig. 2 is that the mud of the utility model direct circulation holing with slurry wall protection bored concrete pile falls the cross-sectional view of arranging device.
Specific embodiment
The utility model is described in further detail in the following with reference to the drawings and specific embodiments.
Refering to fig. 1, it is shown that the mud of the utility model direct circulation holing with slurry wall protection bored concrete pile falls the structure of arranging device Schematic diagram.Referring to Fig.2, showing that the mud of the utility model direct circulation holing with slurry wall protection bored concrete pile falls the section view of arranging device Figure.Referring to figs. 1 and 2, it includes: to be set to that the mud of the utility model direct circulation holing with slurry wall protection bored concrete pile, which falls arranging device, Ground 10 and enclose casing structure 30 set on bored concrete pile 20;It is connected to the structure for conveying 50 of casing structure 30;It is connected to conveying knot The sedimentation basin 60 of structure 50;And the groove 40 of the mortar of casing structure 30 is overflowed for collecting, groove 40 is enclosed set on casing structure 30, And it is connected to sedimentation basin 60.
When mortar spilling casing structure 30, then falls into enclose and be assembled in the groove 40 of casing structure 30, groove 40 It is connected to sedimentation basin 60, so that the mortar in groove 40 will flow into sedimentation basin 60, prevents the mortar overflowed pollution environment.
Mud as the utility model direct circulation holing with slurry wall protection bored concrete pile falls a better embodiment of arranging device, Referring to figs. 1 and 2, casing structure 30 includes: set on ground 10 and to enclose interior casing 31 set on bored concrete pile 20;And it is set to Ground 10 and the outer casing 32 set on interior casing 31 is enclosed, is stayed between outer casing 32 and interior casing 31 and set a fixed spacing, outer casing 32 It is connected with structure for conveying 50, to realize that barrel structure 30 is connected with structure for conveying 50.
The top of interior casing 31 is lower than the top of outer casing 32.The height of outer casing 32 is greater than the height of interior casing 31, fills It infuses the mortar in stake 20 and overflows interior casing 31, then interior casing 31 and outer casing 32 enclose the aggregation in space set and progress on the ground Precipitating, when mortar gathers the communicating position of outer casing 32 and structure for conveying 50, it is heavy that mortar is delivered to by structure for conveying 50 60 further progress of shallow lake pond precipitating.Initially interior casing 31 and outer casing 32 enclose the aggregation in space set and progress to mortar on the ground It is excessive and block structure for conveying 50 to can be avoided slurry density for precipitating.
In the present embodiment, double protection is carried out using outer casing 32 and interior casing 31, prevents mud from splashing down in casing knot The outside of structure 30, influences construction environment.Outer casing 32 and interior casing 31 are all made of steel plate and bend.Outer casing 32 and interior casing 31 size is depending on the size of the bored concrete pile of practice of construction.
Mud as the utility model direct circulation holing with slurry wall protection bored concrete pile falls a better embodiment of arranging device, Referring to figs. 1 and 2, interior casing 31 is fixedly connected with outer casing 32, to prevent interior casing 31 and outer casing 32 from mutually moving It is dynamic, it ensure that the stability of structure.
Mud as the utility model direct circulation holing with slurry wall protection bored concrete pile falls a better embodiment of arranging device, Referring to figs. 1 and 2, interior casing 31 is fixedly connected with outer casing 32 by reinforcing bar 33.
In the present embodiment, interior casing 31 and outer casing 32 are fixedly connected with using the perforation plug welding of reinforcing bar 33.
Mud as the utility model direct circulation holing with slurry wall protection bored concrete pile falls a better embodiment of arranging device, Referring to figs. 1 and 2, groove 40 is enclosed set on outer casing 32.Groove 40 can store certain mud, prevent mud from oozing out. In the construction process, if there is mud, spluttering, the mud splashed down can be fallen into groove 40 out of casing structure 30, prevent mud Any flowing, pollutes environment.
Mud as the utility model direct circulation holing with slurry wall protection bored concrete pile falls a better embodiment of arranging device, Referring to figs. 1 and 2, structure for conveying 50 includes: the delivery pipe 51 for being connected to outer casing 31, delivery pipe 51 and outer casing 32 Communicating position is lower than the top of interior casing 31;And the oblique mud ditch 52 for being connected to delivery pipe 51 and sedimentation basin 60.Mud ditch 52 can temporarily store the mud that delivery pipe 51 transfers out.
Referring to figs. 1 and 2, delivery pipe 51 and the communicating position of outer casing 32 are lower than the top of interior casing 31, thus Convenient for interior casing 31 and outer casing 32 enclose the aggregation in space set on the ground and the mortar precipitated is highly reaching conveying When the communicating position of pipe 51 and outer casing 32, delivery pipe 51 is automatically flowed into, and prevents mortar from passing back into interior casing 31, and reduces effect Rate.
In the present embodiment, the length of one end of the close sedimentation basin 60 of mud ditch 52 is less than the opposite another of mud ditch 52 The length of one end precipitates slurry transportation into sedimentation basin 60 to facilitate aggregation mud.Mud ditch 52 is iron sheet slot. The height 500mm of mud ditch 52, mud ditch 52 is angularly disposed, and the height of one end of the close sedimentation basin 60 of mud ditch 52 is lower than mud The height of the opposite other end of stock tank 52.
Mud as the utility model direct circulation holing with slurry wall protection bored concrete pile falls a better embodiment of arranging device, Referring to figs. 1 and 2, the communicating position of sedimentation basin 60 and mud ditch 52 is equipped with filtering grid 53, prevents the stone that diameter is excessive Son etc. falls into sedimentation basin 60 and damages slush pump.
Mud as the utility model direct circulation holing with slurry wall protection bored concrete pile falls a better embodiment of arranging device, Referring to figs. 1 and 2, delivery pipe 51 includes interconnected steel pipe 510 and rubber tube 511, and steel pipe 510 is connected to outer casing 32, steel pipe 510 has certain hardness, is easy to be connected to fixation with outer casing 32.Rubber tube 511 is connected to mud ditch 52.Rubber Pipe 511 has certain flexibility, can be bent, easy for installation.
The mud of the utility model direct circulation holing with slurry wall protection bored concrete pile falls the having the beneficial effect that of arranging device
The mud of the utility model direct circulation holing with slurry wall protection bored concrete pile fall arranging device using casing structure enclose be set to fill Stake is infused, the mud in bored concrete pile is protected in the construction process, mud spluttering is prevented and influences environment.Setting, which is enclosed, is set to shield Barrel structure and the groove for being connected to sedimentation basin, so that groove has certain storage if there is mud spluttering can be fallen into groove Mortar is simultaneously transported in sedimentation basin by ability.Multiple-protection prevents mud spluttering, has good protection effect.Using conveying Fabric connectivity is in casing structure and sedimentation basin, to carry out slurry transportation, realizes that mud is discharged in a organized way, collects, transported, saves Duration.
Combine figure embodiment that the utility model is described in detail above, those skilled in the art can root Many variations example is made to the utility model according to above description.Thus, certain details in embodiment should not constitute practical to this Novel restriction, the utility model will be using the ranges that the appended claims define as the protection scope of the utility model.

Claims (9)

1. a kind of mud of direct circulation holing with slurry wall protection bored concrete pile falls arranging device characterized by comprising
Set on ground and enclose casing structure set on bored concrete pile;
It is connected to the structure for conveying of the casing structure;
It is connected to the sedimentation basin of the structure for conveying;And
The groove of the mortar of the casing structure is overflowed for collecting, the groove is enclosed set on the casing structure, and is connected to institute State sedimentation basin.
2. the mud of direct circulation holing with slurry wall protection bored concrete pile as described in claim 1 falls arranging device, which is characterized in that described Casing structure includes:
Set on ground and enclose interior casing set on bored concrete pile;And
Set on ground and the outer casing set on the interior casing is enclosed, is stayed between the outer casing and the interior casing between setting centainly Away from the outer casing is connected with the structure for conveying.
3. the mud of direct circulation holing with slurry wall protection bored concrete pile as claimed in claim 2 falls arranging device, which is characterized in that described The top of interior casing is lower than the top of the outer casing.
4. the mud of direct circulation holing with slurry wall protection bored concrete pile as claimed in claim 2 falls arranging device, which is characterized in that described Interior casing is fixedly connected with the outer casing.
5. the mud of direct circulation holing with slurry wall protection bored concrete pile as claimed in claim 4 falls arranging device, which is characterized in that described Interior casing is fixedly connected with the outer casing by reinforcing bar.
6. the mud of direct circulation holing with slurry wall protection bored concrete pile as claimed in claim 2 falls arranging device, which is characterized in that described Groove is enclosed set on the outer casing.
7. the mud of direct circulation holing with slurry wall protection bored concrete pile as claimed in claim 2 falls arranging device, which is characterized in that described Structure for conveying includes:
It is connected to the delivery pipe of the outer casing, the communicating position of the delivery pipe and the outer casing is lower than the interior casing Top;And
The oblique mud ditch for being connected to the delivery pipe and the sedimentation basin.
8. the mud of direct circulation holing with slurry wall protection bored concrete pile as claimed in claim 7 falls arranging device, which is characterized in that described The communicating position of sedimentation basin and the mud ditch is equipped with filtering grid.
9. the mud of direct circulation holing with slurry wall protection bored concrete pile as claimed in claim 7 falls arranging device, which is characterized in that described Delivery pipe includes interconnected steel pipe and rubber tube, and the steel pipe is connected to the outer casing, and the rubber tube is connected to institute State mud ditch.
CN201821693715.XU 2018-10-18 2018-10-18 The mud of direct circulation holing with slurry wall protection bored concrete pile falls arranging device Active CN209179005U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821693715.XU CN209179005U (en) 2018-10-18 2018-10-18 The mud of direct circulation holing with slurry wall protection bored concrete pile falls arranging device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821693715.XU CN209179005U (en) 2018-10-18 2018-10-18 The mud of direct circulation holing with slurry wall protection bored concrete pile falls arranging device

Publications (1)

Publication Number Publication Date
CN209179005U true CN209179005U (en) 2019-07-30

Family

ID=67361723

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821693715.XU Active CN209179005U (en) 2018-10-18 2018-10-18 The mud of direct circulation holing with slurry wall protection bored concrete pile falls arranging device

Country Status (1)

Country Link
CN (1) CN209179005U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113550309A (en) * 2021-08-26 2021-10-26 上海城建市政工程(集团)有限公司 Construction method of multi-pile-hole combined steel platform capable of preventing slurry from overflowing
CN113716833A (en) * 2021-08-31 2021-11-30 杭州国泰环保科技股份有限公司 Dewatering equipment and dewatering method for building slurry treatment
CN113738275A (en) * 2021-09-02 2021-12-03 中铁二十三局集团第四工程有限公司 Anti-pollution construction method for cast-in-situ bored pile in pile foundation engineering

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113550309A (en) * 2021-08-26 2021-10-26 上海城建市政工程(集团)有限公司 Construction method of multi-pile-hole combined steel platform capable of preventing slurry from overflowing
CN113716833A (en) * 2021-08-31 2021-11-30 杭州国泰环保科技股份有限公司 Dewatering equipment and dewatering method for building slurry treatment
CN113738275A (en) * 2021-09-02 2021-12-03 中铁二十三局集团第四工程有限公司 Anti-pollution construction method for cast-in-situ bored pile in pile foundation engineering
CN113738275B (en) * 2021-09-02 2024-02-27 中铁二十三局集团第四工程有限公司 Anti-pollution construction method for bored pile of pile foundation engineering

Similar Documents

Publication Publication Date Title
CN209179005U (en) The mud of direct circulation holing with slurry wall protection bored concrete pile falls arranging device
CN103233693B (en) Drilled pile pile foundation secondary pile hole cleaning device and clear hole method
CN110629777A (en) Well point dewatering device and system and construction method thereof
CN212656251U (en) Positive circulation slurry hole cleaning system for underwater pile foundation percussion drill construction
CN206647046U (en) A kind of PHC pipe piles core device native clearly
CN209066518U (en) A kind of constructing structure of section of stake forced-landing tilt correcting structure and miniature steel pipe pile
CN207452926U (en) A kind of instrument for improving Application of light well point precipitation efficiency
CN207846131U (en) A kind of highway engineering drain tank
CN104675349A (en) Sand screening and punching construction method of churn drill
CN203475593U (en) Pump station base and pump station
CN203429781U (en) Pump station base and pump station
CN207701096U (en) Pile foundation construction secondary pile hole cleaning sand filter under a kind of bridge water
CN210857183U (en) Porous grouting device
CN210025773U (en) Sinking type slurry storage and treatment system
CN209368830U (en) A kind of full-sleeve underwater gliders slurry collecting device
CN207878508U (en) A kind of backward flowing preventing device in cable shaft
CN208167743U (en) A kind of concrete sealing bottom magazine attachment
CN203514501U (en) Prefabricated pump station
CN207144030U (en) A kind of power station desilting equipment
CN204662621U (en) A kind of concrete pump pipe cleaning tapping equipment
CN215290209U (en) Foundation pit drainage structure
CN210382115U (en) Irrigation equipment that possesses environmental protection
CN204875796U (en) Check type steel sheet piling cofferdam water spray formula cloth magazine attachment
CN104074178B (en) Cell-type surge-chamber in a kind of impedance
CN204626450U (en) Concrete filled steel tube buttress type retaining wall for high fill area