CN209165858U - A kind of plant area's chilled water water supply network hydraulic equilibrium system - Google Patents
A kind of plant area's chilled water water supply network hydraulic equilibrium system Download PDFInfo
- Publication number
- CN209165858U CN209165858U CN201821988903.5U CN201821988903U CN209165858U CN 209165858 U CN209165858 U CN 209165858U CN 201821988903 U CN201821988903 U CN 201821988903U CN 209165858 U CN209165858 U CN 209165858U
- Authority
- CN
- China
- Prior art keywords
- water
- branch pipe
- chilled water
- chilled
- water supply
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Abstract
The utility model relates to a kind of plant area's chilled water water supply network hydraulic equilibrium systems, the system includes chilled water water supplying unit, multiple chilled water water use sectors being set side by side and the water main, the return main that are arranged between chilled water water supplying unit and chilled water water use sector, branch pipe temperature sensor is electrically connected with branch pipe flow control valve, branch pipe differential pressure pickup is electrically connected with water pump group, and total flow sensor tube is electrically connected with freezing unit.Compared with prior art, the utility model controls the branch pipe flow control valve aperture in each chilled water water use sector return branch by branch pipe temperature sensor, adjust pipe network flow, and pressure difference comparison is carried out for pressure of return water sensor by each branch pipe differential pressure pickup and chilled water water supplying unit, adjust the unlatching quantity and frequency of water pump, reach the hydraulic equilibrium of the whole network, adjusts easy, high degree of automation.
Description
Technical field
The utility model belongs to plant area's chilled water hydrotechny field, and it is flat to be related to a kind of plant area's chilled water water supply network waterpower
Balance system.
Background technique
Hydraulic equilibrium is a kind of adjusting method for being directed to hydraulic misadjustment problem and generating, it is therefore an objective to eliminate hydraulic misadjustment, reach
To energy-saving.In plant area's chilled water water supply network, the unbalanced phenomenon of waterpower is relatively conventional, and waterpower imbalance is to cause
One of the main reason for energy consumption wastes.Meanwhile hydraulic equilibrium is the premise that guarantees other energy conservation measures and can reliably implement again, because
This should accomplish hydraulic equilibrium and it is necessary to which mandatory requirement system reaches for plant area's chilled water water supply network energy conservation first
Hydraulic equilibrium.
Existing plant area's chilled water water supply network hydraulic equilibrium system mainly includes variable-flow water system, parallel water pump group
Water system etc. is closed, although these types of hydraulic equilibrium system can improve hydraulic unbalance phenomenon to a certain extent, exists and adjusts
Section is inconvenient, the more low drawback of the degree of automation.
Utility model content
The purpose of this utility model is exactly to provide a kind of plant area's freezing to overcome the problems of the above-mentioned prior art
Water water supply network hydraulic equilibrium system.
The purpose of this utility model can be achieved through the following technical solutions:
A kind of plant area's chilled water water supply network hydraulic equilibrium system, the system include chilled water water supplying unit, it is multiple side by side
The chilled water water use sector of setting and the water main being arranged between chilled water water supplying unit and chilled water water use sector return
Supply mains, the chilled water water supplying unit include the water pump group being arranged in series and freezing unit, chilled water water list
Member is equipped with branch pipe temperature sensor, branch pipe differential pressure pickup and branch pipe flow control valve, and the return main is equipped with general pipeline
Flow sensor, the branch pipe temperature sensor are electrically connected with branch pipe flow control valve, the branch pipe differential pressure pickup with
The electrical connection of water pump group, total flow sensor tube are electrically connected with freezing unit.Branch pipe temperature sensor is according to the setting temperature difference
Automatically adjust the aperture of branch pipe flow control valve;Branch pipe differential pressure pickup automatically adjusts water pump group according to for the pressure difference between return water
In water pump open quantity and open frequency;Total flow sensor tube is according in freezing water demand automatic adjustment freezing unit
Refrigerator opens quantity and open frequency.
Further, the water pump group includes multiple water pump pipes being disposed in parallel between freezing unit and return main
Road, the pump tube are equipped with water pump, and the water pump is electrically connected with branch pipe differential pressure pickup.Branch pipe differential pressure pickup will
Pressure difference data feeds back to water pump, to adjust the working condition of water pump.
Further, pump tube butterfly valve is additionally provided on the pump tube.Pump tube butterfly valve is adjusted for flow.
Further, the freezing unit includes multiple refrigerators being disposed in parallel between water main and water pump group
Pipeline, the freezer pipe road are equipped with refrigerator, and the refrigerator is electrically connected with total flow sensor tube.General pipeline flow
Data on flows is fed back to refrigerator by sensor, to adjust the working condition of refrigerator.
Further, freezer pipe road is additionally provided with refrigerator pipeline regulating valve.Refrigerator pipeline regulating valve is used
It is adjusted in flow.
Further, it is additionally provided with bypass pipe between the water main and return main, which is equipped with difference
With the bypass pipe butterfly valve of total flow sensor tube, freezing mechatronics.According to refrigerator flow and general pipeline flow, pass through bypass pipe
Butterfly valve automatically adjusts bypass pipe flow.
Further, the chilled water water use sector includes the water supply branch being arranged between water main and return main
Pipe, return branch and multiple ends being disposed in parallel between water supply branch pipe and return branch energy pipeline, the branch pipe
The both ends of temperature sensor are connected with water supply branch pipe, return branch respectively, the both ends of the branch pipe differential pressure pickup respectively with
Water supply branch pipe, return branch are connected, and the branch pipe flow control valve is arranged in return branch.Branch pipe temperature sensor, branch
Pipe differential pressure pickup monitors the temperature difference between water supply branch pipe, return branch, pressure difference respectively.
Further, end energy pipeline is equipped with end-equipment and end energy piping flow regulating valve.End
End equipment can be air-conditioning box or other chilled water watering equipments.
Further, the end is with can be additionally provided with the end being electrically connected with end with energy piping flow regulating valve on pipeline
End energy pipeline temperature sensor.
Further, the end with can be additionally provided on pipeline end can pipeline differential pressure pickup and with end use
The alarm of energy pipeline differential pressure pickup electrical connection.Pressure difference alarm limitation is set, end-equipment is monitored in real time by Pressure difference feedback
Water supply condition.
The system further includes moisturizing unit as a preferred technical solution, which includes being connected with return main
Logical water pipe, the water pipe are equipped with constant pressure water compensation apparatus.Because system needs often to carry out blowdown, as overhaul of the equipments is arranged
The reasons such as dirty, section of tubing leakage, preset water return pipeline pressure upper lower limit value, will be passed through by constant pressure water compensation apparatus pressurization
With systems stabilisation pressure in the municipal tap water injection return main of water process.
The utility model is in practical application, the relatively high chilled water of terminal temperature is back to chilled water water supplying unit
In, refrigerator group is entered after being pressurized by water pump, is set by the end being supplied in each chilled water water use sector after freezing mechanism cold
In standby.
Wherein, the supply backwater temperature difference and pressure difference measured according to branch pipe temperature sensor and branch pipe differential pressure pickup adjusts water
Unlatching quantity, the open frequency of pump carry out the supply of chilled water, and adjust the aperture of branch pipe flow control valve;Water supply branch pipe passes through
End is distributed chilled water to each end-equipment with energy pipeline, and measuring end use by end energy pipeline temperature sensor can manage
The supply backwater temperature difference on road, and according to the set temperature adjust automatically end aperture of energy piping flow regulating valve, control chilled water
Flow, to realize that the water conservancy of each end-equipment and total water supply network balances.
Compared with prior art, the utility model has the following characteristics that
1) the branch pipe flow control valve in each chilled water water use sector return branch is controlled by branch pipe temperature sensor to open
Degree adjusts pipe network flow, and passes through each branch pipe differential pressure pickup with chilled water water supplying unit for the progress of pressure of return water sensor
Pressure difference comparison, adjusts the unlatching quantity and frequency of water pump, reaches the hydraulic equilibrium of the whole network, adjusts easy, high degree of automation;
2) feedback control is carried out by flow, the water pump operation state etc. to chilled water water use sector, realizes economic security
Operation under conditions of guaranteeing that the whole network end-equipment operates normally, improves water supply network hydraulic equilibrium, energy-saving.
Detailed description of the invention
Fig. 1 is the overall structure diagram of the utility model;
Description of symbols in figure:
1-water main, 2-return mains, 3-branch pipe temperature sensors, 4-branch pipe differential pressure pickups, 5-branch pipe streams
Adjustable valve, 6-total flow sensor tubes, 7-water pumps, 8-refrigerators, 9-bypass pipes, 10-bypass pipe butterfly valves, 11-water
Pump conduit butterfly valve, 12-refrigerator pipeline regulating valves, 13-water supply branch pipes, 14-return branch, 15-ends with can pipeline,
16-end-equipments, 17-ends energy piping flow regulating valve.
Specific embodiment
The utility model is described in detail in the following with reference to the drawings and specific embodiments.The present embodiment is with the utility model
Implemented premised on technical solution, the detailed implementation method and specific operation process are given, but the guarantor of the utility model
Shield range is not limited to the following embodiments.
Embodiment:
A kind of plant area's chilled water water supply network hydraulic equilibrium system as shown in Figure 1, including it is chilled water water supplying unit, multiple
The chilled water water use sector being set side by side and the water supply being arranged between chilled water water supplying unit and chilled water water use sector are total
Pipe 1, return main 2, chilled water water supplying unit include that the water pump group being arranged in series and freezing unit, chilled water water use sector are equipped with
Branch pipe temperature sensor 3, branch pipe differential pressure pickup 4 and branch pipe flow control valve 5, return main 2 are equipped with general pipeline flow sensing
Device 6, branch pipe temperature sensor 3 are electrically connected with branch pipe flow control valve 5, and branch pipe differential pressure pickup 4 is electrically connected with water pump group, general pipeline
Flow sensor 6 is electrically connected with freezing unit.
Wherein, water pump group includes multiple pump tubes being disposed in parallel between freezing unit and return main 2, water pump pipe
Road is equipped with water pump 7, and water pump 7 is electrically connected with branch pipe differential pressure pickup 4.Pump tube butterfly valve 11 is additionally provided on pump tube.
Freezing unit includes multiple refrigerator pipelines being disposed in parallel between water main 1 and water pump group, freezer pipe
Road is equipped with refrigerator 8, and refrigerator 8 is electrically connected with total flow sensor tube 6.Freezer pipe road is additionally provided with refrigerator pipeline tune
Save valve 12.Bypass pipe 9 is additionally provided between water main 1 and return main 2, which is equipped with passes with general pipeline flow respectively
The bypass pipe butterfly valve 10 that sensor 6, refrigerator 8 are electrically connected.
Chilled water water use sector includes the water supply branch pipe 13 being arranged between water main 1 and return main 2, return branch
14 and multiple ends for being disposed in parallel between water supply branch pipe 13 and return branch 14 with can pipeline 15, branch pipe temperature sensor
3 both ends are connected with water supply branch pipe 13, return branch 14 respectively, the both ends of branch pipe differential pressure pickup 4 respectively with water supply branch pipe 13,
Return branch 14 is connected, and branch pipe flow control valve 5 is arranged in return branch 14.End is equipped with end-equipment with energy pipeline 15
16 and end with can piping flow regulating valve 17.End is with can be additionally provided on pipeline 15 and end energy piping flow regulating valve 17
The end of electrical connection energy pipeline temperature sensor.End with can be additionally provided on pipeline 15 end energy pipeline differential pressure pickup with
And the alarm being electrically connected with end with energy pipeline differential pressure pickup.
In practical application, the relatively high chilled water of terminal temperature is back in chilled water water supplying unit, pass through water pump 7
Enter refrigerator group after pressurization, is supplied to after being freezed by refrigerator 8 in the end-equipment 16 in each chilled water water use sector.
Wherein, the supply backwater temperature difference and pressure difference measured according to branch pipe temperature sensor 3 and branch pipe differential pressure pickup 4 is adjusted
Unlatching quantity, the open frequency of water pump 7 carry out the supply of chilled water, and adjust the aperture of branch pipe flow control valve 5;Water supply branch pipe
13 are distributed chilled water to each end-equipment 16 with energy pipeline 15 by end, are passed through end and are measured with energy pipeline temperature sensor
The supply backwater temperature difference of end energy pipeline 15, and opening according to set temperature adjust automatically end energy piping flow regulating valve 17
Degree controls chilled-water flow, to realize that each end-equipment 16 and the water conservancy of total water supply network balance.
It can understand the above description of the embodiments is intended to facilitate those skilled in the art and use practical
It is novel.Person skilled in the art obviously easily can make various modifications to these embodiments, and illustrating herein
General Principle be applied in other embodiments without having to go through creative labor.Therefore, the utility model is not limited to above-mentioned
Embodiment, those skilled in the art's announcement according to the present utility model, do not depart from improvement that the utility model scope is made and
Modification should be all within the protection scope of the utility model.
Claims (10)
1. a kind of plant area's chilled water water supply network hydraulic equilibrium system, which is characterized in that the system include chilled water water supplying unit,
Multiple chilled water water use sectors being set side by side and the confession being arranged between chilled water water supplying unit and chilled water water use sector
Supply mains (1), return main (2), the chilled water water supplying unit includes the water pump group being arranged in series and freezes unit, described
Chilled water water use sector be equipped with branch pipe temperature sensor (3), branch pipe differential pressure pickup (4) and branch pipe flow control valve (5), institute
The return main (2) stated is equipped with total flow sensor tube (6), and the branch pipe temperature sensor (3) and branch pipe flow are adjusted
Valve (5) electrical connection, the branch pipe differential pressure pickup (4) is electrically connected with water pump group, total flow sensor tube (6) with it is cold
Freeze unit electrical connection.
2. a kind of plant area's chilled water water supply network hydraulic equilibrium system according to claim 1, which is characterized in that described
Water pump group includes multiple pump tubes being disposed in parallel between freezing unit and return main (2), on the pump tube
Equipped with water pump (7), the water pump (7) is electrically connected with branch pipe differential pressure pickup (4).
3. a kind of plant area's chilled water water supply network hydraulic equilibrium system according to claim 2, which is characterized in that described
Pump tube butterfly valve (11) are additionally provided on pump tube.
4. a kind of plant area's chilled water water supply network hydraulic equilibrium system according to claim 1, which is characterized in that described
Freezing unit includes multiple refrigerator pipelines being disposed in parallel between water main (1) and water pump group, the freezer pipe
Road is equipped with refrigerator (8), and the refrigerator (8) is electrically connected with total flow sensor tube (6).
5. a kind of plant area's chilled water water supply network hydraulic equilibrium system according to claim 4, which is characterized in that described
Freezer pipe road is additionally provided with refrigerator pipeline regulating valve (12).
6. a kind of plant area's chilled water water supply network hydraulic equilibrium system according to claim 4, which is characterized in that described
Bypass pipe (9) are additionally provided between water main (1) and return main (2), which is equipped with passes with general pipeline flow respectively
The bypass pipe butterfly valve (10) that sensor (6), refrigerator (8) are electrically connected.
7. a kind of plant area's chilled water water supply network hydraulic equilibrium system according to claim 1, which is characterized in that described
Chilled water water use sector includes the water supply branch pipe (13) being arranged between water main (1) and return main (2), return branch
(14) and multiple ends for being disposed in parallel between water supply branch pipe (13) and return branch (14) with can pipeline (15), it is described
The both ends of branch pipe temperature sensor (3) are connected with water supply branch pipe (13), return branch (14) respectively, the branch pipe pressure difference sensing
The both ends of device (4) are connected with water supply branch pipe (13), return branch (14) respectively, and branch pipe flow control valve (5) setting exists
In return branch (14).
8. a kind of plant area's chilled water water supply network hydraulic equilibrium system according to claim 7, which is characterized in that described
End energy pipeline (15) is equipped with end-equipment (16) and end energy piping flow regulating valve (17).
9. a kind of plant area's chilled water water supply network hydraulic equilibrium system according to claim 8, which is characterized in that described
End is used with the end that be additionally provided on energy pipeline (15) with end is electrically connected with energy piping flow regulating valve (17) can the pipeline temperature difference
Sensor.
10. a kind of plant area's chilled water water supply network hydraulic equilibrium system according to claim 8, which is characterized in that described
End with can be additionally provided on pipeline (15) end can pipeline differential pressure pickup and with end energy pipeline differential pressure pickup
The alarm of electrical connection.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821988903.5U CN209165858U (en) | 2018-11-29 | 2018-11-29 | A kind of plant area's chilled water water supply network hydraulic equilibrium system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821988903.5U CN209165858U (en) | 2018-11-29 | 2018-11-29 | A kind of plant area's chilled water water supply network hydraulic equilibrium system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209165858U true CN209165858U (en) | 2019-07-26 |
Family
ID=67340951
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201821988903.5U Active CN209165858U (en) | 2018-11-29 | 2018-11-29 | A kind of plant area's chilled water water supply network hydraulic equilibrium system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209165858U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109442817A (en) * | 2018-11-29 | 2019-03-08 | 宁波杭州湾新区祥源动力供应有限公司 | A kind of plant area's chilled water water supply network hydraulic equilibrium system |
-
2018
- 2018-11-29 CN CN201821988903.5U patent/CN209165858U/en active Active
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109442817A (en) * | 2018-11-29 | 2019-03-08 | 宁波杭州湾新区祥源动力供应有限公司 | A kind of plant area's chilled water water supply network hydraulic equilibrium system |
CN109442817B (en) * | 2018-11-29 | 2024-04-09 | 宁波杭州湾新区祥源动力供应有限公司 | Water power balance system of plant chilled water supply network |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109442817A (en) | A kind of plant area's chilled water water supply network hydraulic equilibrium system | |
CN102863074A (en) | Intelligent control method of blast aeration system of municipal sewage plant | |
US20100071787A1 (en) | System, including a variable orifice assembly, for hydraulically managing pressure in a fluid distribution system between pressure set points | |
CN110821457B (en) | Water mixing control method, controller and control system based on wellhead back pressure | |
CN215053447U (en) | Pipe network pressure-superposed matched high-level regulation and storage water supply device | |
CN209165858U (en) | A kind of plant area's chilled water water supply network hydraulic equilibrium system | |
WO2009039685A1 (en) | High precision automatic flow balancing device | |
CN111322447B (en) | Valve control method and valve integrating dynamic flow balance and energy control | |
CN2916447Y (en) | Divisional, timing, and temperature-based hot water supply control system | |
CN208794440U (en) | A kind of air preheater temperature control shunting device | |
CN115059782A (en) | Automatic control device for uniformly distributing flow of branch pipelines of multi-branch parallel pipe group | |
CN205259265U (en) | Running water advance water control device | |
CN110185930A (en) | A kind of LNG receiving station gasification installation combines the system utilized with electric power plant circulating water | |
CN215336603U (en) | Variable frequency pump and electric regulating valve temperature control device of heat exchange station heat supply system | |
CN207280009U (en) | A kind of new Regional Energy secondary pumping system | |
CN219411050U (en) | Two-way water supply and drainage system suitable for large-scale water supply pump station | |
CN209763215U (en) | Grading balancing device special for cold and hot supply | |
CN208983001U (en) | Air cooling tubes condenser draining system | |
CN203502856U (en) | Constant-temperature and energy-saving automatic control device of oil storage tank | |
CN208222623U (en) | Intelligent building thermal power plant unit | |
CN208475457U (en) | Self-operated type balances heating system | |
CN206488336U (en) | Adjustable injection apparatus and heating system | |
CN111430048A (en) | Loop for solving large leakage temperature fluctuation problem of nuclear power station chemical capacitance system | |
CN218544026U (en) | Water supply pipeline simulation system | |
CN211285523U (en) | Anti-freezing device for flap gate |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |