CN209128935U CN201821895665.3U CN201821895665U CN209128935U CN 209128935 U CN209128935 U CN 209128935U CN 201821895665 U CN201821895665 U CN 201821895665U CN 209128935 U CN209128935 U CN 209128935U
Authority
CN
China
Prior art keywords
snow
water
snow melt
water inlet
fixed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821895665.3U
Other languages
Chinese (zh)
Inventor
马志毅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201821895665.3U priority Critical patent/CN209128935U/en
Application granted granted Critical
Publication of CN209128935U publication Critical patent/CN209128935U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of gas heating type snow-melting systems comprising snow melt case, air accumulator are connect by appendix with gas-cooker;Heat-exchanger pump is fixed with outside boiler, the inside of boiler is fixed with the hot water inlet pipe that water outlet is connected to the water inlet of heat-exchanger pump, and the water outlet of heat-exchanger pump is taken over by hot water to be connected to snow melt case;It is offered on snow melt case into thrush.Advantage: the water in boiler is heated by gas-cooker, and during the accumulated snow on road is collected into snow melt case by snow sweeper, the hot water pumped out out of boiler by heat-exchanger pump is passed through in snow melt case by hot water adapter tube, carries out thawing processing to the accumulated snow being collected in snow melt case;As a result, during snow sweeper cleaning road snow mantle, accumulated snow is directly collected into snow melt case and is carried out snow melt processing, achievees the purpose that quickly to handle accumulated snow, avoided accumulated snow from being stacked on both sides of the road and continue accumulated snow processing, reduce intensity of workers.

Description

Gas heating type snow-melting system
Technical field:
The utility model relates to the automobile-used snow melting equipment technical fields of road snow removing, in particular to gas heating type snow melt system System.
Background technique:
The accumulated snow in winter, road will lead to traffic jam, influence the normal pass of vehicle and pedestrian, at present frequently with remove Snow measure is that the accumulated snow on road surface is cleared up to and is stacked into the both sides of road using snow removing vehicle, then by forklift and truck or rickshaw Equal means of transports are transported, but this processing mode is time-consuming and laborious, and the accumulated snow being deposited on both sides of the road can freeze, and makes It is difficult at cleaning, improve the labor intensity of staff.
Utility model content:
The purpose of this utility model is to provide a kind of accumulated snow fast melts for collecting snow sweeper to reach quick snow removing Purpose, avoid the gas heating type snow-melting system of accumulated snow on both sides of the road.
The utility model is implemented by following technical solution: gas heating type snow-melting system comprising snow melt case, air accumulator, Heat-exchanger pump and boiler;The bottom of the boiler is fixed with gas-cooker, and the air accumulator passes through appendix and the gas-cooker Connection;Temperature transmitter is equipped in the boiler, the temperature transmitter is electrically connected with the input terminal of controller, the control The output end of device is electrically connected with the igniter of the gas-cooker;The inside of the boiler is fixed with water outlet and the hot water The water outlet of the hot water inlet pipe of the water inlet connection of pump, the heat-exchanger pump are connected by hot water adapter tube and the inside of the snow melt case It is logical.
Further, the interior side-lower into thrush of the snow melt case is fixed with snow melt slot, and one end of the snow melt slot is set The other end in the lower section into thrush, the snow melt slot tilts down setting;The top of the snow melt slot is along its length It is fixed with hot water jet pipe, the water inlet of the hot water jet pipe is connected to the water outlet that the hot water is taken over.
Further, the water outlet of the spray head of the hot water jet pipe is obliquely installed to the low side of the snow melt slot.
It further, further include water supply pump, the inside of the snow melt case is fixed with the water inlet of water outlet Yu the water supply pump The cold water inlet of mouth connection setting, is respectively fixed with cold water jet pipe in the two sides of the snow melt slot along its length, described cold The water inlet of water spray pipe is connected to the water outlet of the water supply pump;The spray head of the cold water jet pipe is placed in the interior of the snow melt slot Portion.
Further, the water outlet of the spray head of the cold water jet pipe is obliquely installed to the low side of the snow melt slot.
Further, the first filter screen is fixed in the water inlet of the cold water inlet.
Further, the outside of the snow melt case is fixed with water injecting pump, the inside of the snow melt case be fixed with water outlet with The water filling water inlet pipe of the water inlet connection setting of the water injecting pump, the inside of the boiler is fixed with water inlet and the water filling The water filling outlet pipe of the water outlet connection setting of pump.
Further, the second filter screen is fixed in the water inlet of the water filling water inlet pipe.
Further, high-low-position liquidometer, the high-low-position liquidometer and the control are equipped in the inside of the boiler The input terminal of device processed is electrically connected, and the output end of the controller is electrically connected with the water injecting pump.
The advantages of the utility model: the water in boiler is heated by gas-cooker, and when snow sweeper will be on road During accumulated snow is collected into snow melt case, the hot water pumped out out of boiler by heat-exchanger pump is passed through snow melt case by hot water adapter tube It is interior, thawing processing is carried out to the accumulated snow being collected in snow melt case;It is as a result, during snow sweeper cleaning road snow mantle, accumulated snow is straight It connects and is collected into snow melt case and carries out snow melt processing, achieve the purpose that quickly to handle accumulated snow, accumulated snow is avoided to be stacked on both sides of the road And continue accumulated snow processing, reduce intensity of workers.
Detailed description of the invention:
Fig. 1 is the structural schematic diagram of the utility model.
Fig. 2 is the A direction view of Fig. 1.
The components in the drawings are labeled as follows: boiler 1, heat-exchanger pump 2, hot water inlet pipe 3, snow melt case 4, into thrush 5, melt Avenge slot 6, hot water jet pipe 7, appendix 8, gas-cooker 9, temperature transmitter 10, controller 11, igniter 12, water injecting pump 13, note It is water water inlet pipe 14, water filling outlet pipe 15, the first filter screen 16, high-low-position liquidometer 17, water supply pump 18, cold water inlet 19, cold Water spray pipe 20, hot water adapter tube 21, the second filter screen 22, air accumulator 23.
Specific embodiment:
As depicted in figs. 1 and 2, gas heating type snow-melting system comprising snow melt case 4, air accumulator 23, heat-exchanger pump 2 and heat Water tank 1;The bottom of boiler 1 is fixed with gas-cooker 9, and air accumulator 23 is connect by appendix 8 with gas-cooker 9;It is set in boiler 1 There is temperature transmitter 10, temperature transmitter 10 is electrically connected with the input terminal of controller 11, the output end and gas-cooker 9 of controller 11 Igniter 12 be electrically connected;The inside of boiler 1 is fixed with the hot water inlet pipe that water outlet is connected to the water inlet of heat-exchanger pump 2 3, the water outlet of heat-exchanger pump 2 is connected to by hot water adapter tube 21 with the inside of snow melt case 4;It, can be to boiler by the way that gas-cooker 9 is arranged The cold water injected in 1 is heated, and makes the igniter of 11 real-time control gas-cooker 9 of controller by temperature transmitter 10 12 opening and closing, and then hot water is made to remain at certain temperature range, that is, it can reach snow melt effect, the use of combustion gas can also be saved Amount;During the accumulated snow on road is collected into snow melt case 4 by snow sweeper, the heat that is pumped out out of boiler 1 by heat-exchanger pump 2 Water is passed through in snow melt case 4, carries out thawing processing to accumulated snow;Achieve the purpose that quickly to handle accumulated snow as a result, accumulated snow is avoided to accumulate Continue accumulated snow processing on both sides of the road to road, reduces intensity of workers.
The interior side-lower into thrush 5 of snow melt case 4 is fixed with snow melt slot 6, and one end of snow melt slot 6 is placed in under thrush 5 Side, the other end of snow melt slot 6 tilt down setting;The top of snow melt slot 6 is fixed with hot water jet pipe 7, hot water spray along its length The water inlet of pipe 7 is connected to the water outlet of hot water adapter tube 21;By snow melt slot 6 by from the accumulated snow centralized collection entered into thrush 5, And along snow melt slot 6 into snow melt case 4 in flow process, the hot water pumped out by heat-exchanger pump 2 is sprayed accumulated snow by hot water jet pipe 7, With this by the snow fast melt in snow melt slot 6, the water after melting is flowed into snow melt case 4.
The water outlet of the spray head of hot water jet pipe 7 is obliquely installed to the low side of snow melt slot 6;Convenient for the product in snow melt slot 6 It avenges and is impacted to the water outlet of snow melt slot 6, the accumulated snow facilitated in snow melt slot 6 is quickly pushed ahead, and snow melt efficiency is improved.
It further include water supply pump 18, the inside of snow melt case 4 is fixed with water outlet and is connected to setting with the water inlet of water supply pump 18 Cold water inlet 19 is respectively fixed with cold water jet pipe 20, the water inlet of cold water jet pipe 20 in the two sides of snow melt slot 6 along its length It is connected to the water outlet of water supply pump 18;The spray head of cold water jet pipe 20 is placed in the inside of snow melt slot 6;It is sprayed by cold water jet pipe 20 Cold water impacts the snow in snow melt slot 6, and reaches certain snow melt effect, while it being made to focus on the spray of hot water jet pipe 7 Head lower section, more rapidly carries out thawing processing to it convenient for the hot water of ejection.
The water outlet of the spray head of cold water jet pipe 20 is obliquely installed to the low side of snow melt slot 6;Convenient for the product in snow melt slot 6 It avenges and is impacted to the water outlet of snow melt slot 6, the accumulated snow facilitated in snow melt slot 6 is quickly pushed ahead, and snow melt efficiency is improved.
The first filter screen 16 is fixed in the water inlet of cold water pipe water inlet pipe;Enter cold water water inlet to by snow melt case 4 with this Cold water in pipe 19 is filtered, and the impurity being mixed in the cold water being melted into is avoided to damage water supply pump 18.
The outside of snow melt case 4 is fixed with water injecting pump 13, and the inside of snow melt case 4 is fixed with the water inlet of water outlet Yu water injecting pump 13 The water filling water inlet pipe 14 of mouth connection setting, the inside of boiler 1 is fixed with water inlet and is connected to setting with the water outlet of water injecting pump 13 Water filling outlet pipe 15;The cold water in snow melt case 4 is recovered in boiler 1 by water injecting pump 13, with this to snow melting after Cold water recycled.
The second filter screen 22 is fixed in the water inlet of water filling water inlet pipe 14;By the second filter screen 22 to by snow melt case 4 It is filtered into the cold water in water filling water inlet pipe 14, the impurity being mixed in the cold water being melted into is avoided to damage water injecting pump 13.
High-low-position liquidometer 17, the input terminal electricity of high-low-position liquidometer 17 and controller 11 are equipped in the inside of boiler 1 Connection, the output end of controller 11 are electrically connected with water injecting pump 13;It can be automatically controled water injecting pump 13 by high-low-position liquidometer 17 Start and stop, and then guarantee that the water level of injection boiler 1 is maintained in reasonable range.
Operation instruction: snow sweeper is treated in journey the accumulated snow on road, and the accumulated snow on road is received from into thrush 5 Collect in snow melt slot 6, meanwhile, the hot water pumped out out of boiler 1 by heat-exchanger pump 2 sprays into snow melt by the spray head of hot water jet pipe 7 In slot 6, thawing processing is carried out to the accumulated snow being collected in snow melt slot 6, and is pumped out out of snow melt case 4 by water supply pump 18 cold Water is sprayed into snow melt slot 6 by the spray head of cold water jet pipe 20, is impacted to accumulated snow;When the temperature transmitter 10 in boiler 1 When the water temperature value detected is lower than the lower limit value set, Real-time Feedback controls the igniter of gas-cooker 9 in controller 11 12 startings, start to heat the water in boiler 1, and when reaching the water temperature upper limit value of setting, controller 11 controls gas-cooker 9 Igniter 12 close, stopping boiler 1 is heated;When high-low-position liquidometer 17 detects the water level in boiler 1 Lower than setting lower limit value when, Real-time Feedback controls water injecting pump 13 by controller 11 and starts in controller 11, will be in snow melt case 4 Cold water injection boiler 1 in, when high-low-position liquidometer 17 detects that the water level of injection reaches the upper limit value of setting, pass through control Device 11 processed controls water injecting pump 13 and stops working.
The above is only the preferred embodiment of the utility model only, is not intended to limit the utility model, all at this Within the spirit and principle of utility model, any modification, equivalent replacement, improvement and so on should be included in the utility model Protection scope within.

Claims (9)

1. gas heating type snow-melting system, which is characterized in that it includes snow melt case, air accumulator, heat-exchanger pump and boiler;The heat The bottom of water tank is fixed with gas-cooker, and the air accumulator is connect by appendix with the gas-cooker;It is equipped in the boiler Temperature transmitter, the temperature transmitter are electrically connected with the input terminal of controller, the output end of the controller and the combustion gas The igniter of stove is electrically connected;The inside of the boiler is fixed with the hot water that water outlet is connected to the water inlet of the heat-exchanger pump Water inlet pipe, the water outlet of the heat-exchanger pump is taken over by hot water to be connected to the inside of the snow melt case.
2. gas heating type snow-melting system according to claim 1, which is characterized in that the snow melt case into thrush Side-lower is fixed with snow melt slot, one end of the snow melt slot be placed in it is described into the lower section of thrush, the other end of the snow melt slot to Under be obliquely installed;The top of the snow melt slot is fixed with hot water jet pipe, the water inlet of the hot water jet pipe and institute along its length State the water outlet connection of hot water adapter tube.
3. gas heating type snow-melting system according to claim 2, which is characterized in that the spray head of the hot water jet pipe goes out The mouth of a river is obliquely installed to the low side of the snow melt slot.
4. according to any gas heating type snow-melting system of Claims 2 or 3, which is characterized in that it further include water supply pump, institute The inside for stating snow melt case is fixed with the cold water inlet that water outlet is connected to setting with the water inlet of the water supply pump, in the snow melt The two sides of slot are respectively fixed with cold water jet pipe, the water inlet of the cold water jet pipe and the water outlet of the water supply pump along its length Connection;The spray head of the cold water jet pipe is placed in the inside of the snow melt slot.
5. gas heating type snow-melting system according to claim 4, which is characterized in that the spray head of the cold water jet pipe goes out The mouth of a river is obliquely installed to the low side of the snow melt slot.
6. gas heating type snow-melting system according to claim 4, which is characterized in that in the water inlet of the cold water inlet Mouth is fixed with the first filter screen.
7. according to claim 1, any gas heating type snow-melting system in 2,3,5 or 6, which is characterized in that the snow melt The outside of case is fixed with water injecting pump, and the inside of the snow melt case is fixed with water outlet and is connected to setting with the water inlet of the water injecting pump Water filling water inlet pipe, the inside of the boiler be fixed with water inlet be connected to the water outlet of the water injecting pump setting water filling go out Water pipe.
8. gas heating type snow-melting system according to claim 7, which is characterized in that in the water inlet of the water filling water inlet pipe Mouth is fixed with the second filter screen.
9. gas heating type snow-melting system according to claim 7, which is characterized in that be equipped in the inside of the boiler High-low-position liquidometer, the high-low-position liquidometer are electrically connected with the input terminal of the controller, the output end of the controller with The water injecting pump electrical connection.
CN201821895665.3U 2018-11-15 2018-11-15 Gas heating type snow-melting system Active CN209128935U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821895665.3U CN209128935U (en) 2018-11-15 2018-11-15 Gas heating type snow-melting system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821895665.3U CN209128935U (en) 2018-11-15 2018-11-15 Gas heating type snow-melting system

Publications (1)

Publication Number Publication Date
CN209128935U true CN209128935U (en) 2019-07-19

Family

ID=67245558

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821895665.3U Active CN209128935U (en) 2018-11-15 2018-11-15 Gas heating type snow-melting system

Country Status (1)

Country Link
CN (1) CN209128935U (en)

Similar Documents

Publication Publication Date Title
CN102277848B (en) Thermal mechanical snow removal vehicle
CN207176607U (en) Snow sweeper
KR101758767B1 (en) Snow-removing apparatus foe roof of assembly panel type building
CN107804286A (en) A kind of cleaning device of shield glass and guiding gutter
CN107476242B (en) A kind of multi-functional highway repairing spray wind devices
CN209128935U (en) Gas heating type snow-melting system
CN206428648U (en) A kind of bridge deicer
US9725861B2 (en) Snow-to-slurry conversion apparatus
CN203475374U (en) Road surface snow removal system and snow removal vehicle
CN203515644U (en) Warming and humidifying device in mine
CN206844040U (en) Ice and snow road snow-clearing car
CN206529733U (en) Multi-functional deicing, cleaning road surface sanitation cart
CN206305101U (en) A kind of high temperature and high pressure steam cleaning machine
CN205875068U (en) Multipurpose street cleaning device
CN210737447U (en) Quick snow melting vehicle
CN209854643U (en) Road snow removing vehicle
CN213267708U (en) Sanitation car deicing system and sanitation car
CN109083077B (en) Snow shoveling vehicle with steam deicing function
CN208633042U (en) A kind of dedicated accumulated snow processing equipment of town road
CN209211380U (en) A kind of Highway Maintenance emergency high temperature snow sweeper
CN112681208A (en) Multifunctional efficient environment-friendly snow melting and breaking absorption device
CN214737738U (en) Intelligent water resistance quick snow melting vehicle
SE533491C2 (en) snowplow
CN202055217U (en) Road snow clearing device
CN218263395U (en) Pavement crack repairing device

Legal Events