CN209114732U - A kind of building iron connection structure - Google Patents
A kind of building iron connection structure Download PDFInfo
- Publication number
- CN209114732U CN209114732U CN201821792422.7U CN201821792422U CN209114732U CN 209114732 U CN209114732 U CN 209114732U CN 201821792422 U CN201821792422 U CN 201821792422U CN 209114732 U CN209114732 U CN 209114732U
- Authority
- CN
- China
- Prior art keywords
- link slot
- connector
- main connector
- auxiliary
- bolt
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 title claims abstract description 28
- 229910052742 iron Inorganic materials 0.000 title claims abstract description 14
- 238000009434 installation Methods 0.000 claims abstract description 12
- NJPPVKZQTLUDBO-UHFFFAOYSA-N novaluron Chemical compound C1=C(Cl)C(OC(F)(F)C(OC(F)(F)F)F)=CC=C1NC(=O)NC(=O)C1=C(F)C=CC=C1F NJPPVKZQTLUDBO-UHFFFAOYSA-N 0.000 claims description 13
- 229910000831 Steel Inorganic materials 0.000 abstract description 6
- 239000010959 steel Substances 0.000 abstract description 6
- 230000003014 reinforcing effect Effects 0.000 description 31
- 238000010276 construction Methods 0.000 description 6
- 238000003466 welding Methods 0.000 description 4
- 238000009435 building construction Methods 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 238000011900 installation process Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 230000006641 stabilisation Effects 0.000 description 1
- 238000011105 stabilization Methods 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
Landscapes
- Joining Of Building Structures In Genera (AREA)
Abstract
The utility model discloses a kind of building iron connection structures, including main connector, the main connector is cross, the upside of the main connector, downside, left and right side is respectively arranged with link slot, left link slot, lower link slot and right link slot, and the main connector is close to upper link slot, left link slot, the part of lower link slot and right link slot is mounted on screw, there are two auxiliary connectors close to the installation symmetrical above and below of the part of lower link slot and right link slot for the main connector, each auxiliary connector is equipped with link slot far from the side of main connector, connection bolt is mounted on each auxiliary connector.The utility model solves the problems, such as that existing steel bar connecting structure connection number of steel bars is fixed, adaptable, can be adjusted according to the actual situation, and mounting means can also be selected as needed, practical, structure is simple.
Description
Technical field
The utility model relates to build connection structure technical field more particularly to a kind of building iron connection structure.
Background technique
It often will use reinforcing bar in building construction, necessarily involve the connection to reinforcing bar at this time, it is therefore desirable to connect using reinforcing bar
Binding structure realizes the connection between multiple reinforcing bars.
The number of steel bars of existing steel bar connecting structure connection is mostly fixed, cannot be adjusted according to actually required, because
This leads to the problem of installation process inconvenience, brings larger puzzlement to construction personnel, therefore needs to design a kind of building iron connection
Structure.
Utility model content
Purpose of the utility model is to solve disadvantages existing in the prior art, such as: existing steel bar connecting structure
The number of steel bars of connection is mostly fixed, cannot be adjusted, therefore lead to the problem of installation process inconvenience, be given according to actually required
Construction personnel brings larger puzzlement.
To achieve the goals above, the utility model adopts the technical scheme that
A kind of building iron connection structure, including main connector, the main connector are cross, the main connector
Upside, downside, left and right side are respectively arranged with link slot, left link slot, lower link slot and right link slot, and the main company
Fitting is mounted on screw close to the part of upper link slot, left link slot, lower link slot and right link slot, and the main connector leans on
There are two auxiliary connectors for the part installation symmetrical above and below of nearly lower link slot and right link slot, and each auxiliary connector is far from main
The side of connector is equipped with link slot, is mounted on connection bolt on each auxiliary connector.
Preferably, the auxiliary connector is welded with pedestal close to the side of main connector, right on each pedestal
Claim installation there are two fixing bolt, the first tapped blind hole for cooperating fixing bolt is provided on the main connector.
Preferably, each fixing bolt is symmetrically opened up in the vertical direction there are two tapped through hole, each described
It is mounted on reinforcing bolt in tapped through hole, it is blind that the second screw thread that bolt is reinforced in multiple cooperations is provided with above the pedestal
Hole.
Preferably, each connection bolt is made of screw rod and nut, and it is fixed to be equipped between the screw rod and nut
Position pin.
Preferably, the upper link slot, left link slot, lower link slot, right link slot and each link slot are circle
Cylindrical groove.
Preferably, each auxiliary connector is welded with main connector.
Compared with prior art, the utility model has the beneficial effects that
1, main connector, upper link slot, left link slot, lower link slot and right link slot can realize four in the utility model
Connection between reinforcing bar, by the way that reinforcing bar is inserted into link slot, left link slot, lower link slot and right link slot respectively and passes through spiral shell
Nail is fixed, and completes connection, by the way that reinforcing bar combination is connected the stability for being conducive to promote reinforcing bar connection.
2, the utility model realizes peace of the auxiliary connector on main connector by pedestal, fixing bolt and reinforcing bolt
Dress, and the installation of auxiliary connector have selectivity, can the installation number according to actual needs to auxiliary connector be adjusted,
With very strong adaptability, is conducive to facilitate construction personnel that the connection of reinforcing bar to be installed, facilitates the work of construction personnel.
3, the utility model can be according to the connection type of construction Object Selection auxiliary connector and main connector, to temporarily building
It builds when being constructed, by pedestal, fixing bolt and bolt can be reinforced auxiliary connector is installed, used in temporary building
It after the completion, can be by removing and very easily dismantling to reinforcing bar fixing bolt and reinforcing bolt, to realize the secondary of reinforcing bar
It utilizes, when constructing to non-provisional building, auxiliary connector and main connector can be welded by welding,
Welding manner is conducive to promote the compactness that main connector is connect with auxiliary connector, can further promote the stabilization of reinforcing bar connection
Property, to guarantee the service life of building.
Detailed description of the invention
Fig. 1 be the utility model proposes a kind of positive apparent direction of building iron connection structure cross section structure schematic diagram;
Fig. 2 is structural schematic diagram at the A of Fig. 1.
In figure: 1 main connector, link slot, 3 left link slots, 4 lower link slots, 5 right link slots, 6 screws, 7 auxiliary connections on 2
Part, 8 pedestals, 9 connection bolts, 10 link slots, 11 fixing bolts, 12 reinforce bolt.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model
Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole
Embodiment.
In the description of the present invention, it should be understood that term " on ", "lower", "front", "rear", "left", "right",
The orientation or positional relationship of the instructions such as "top", "bottom", "inner", "outside" is to be based on the orientation or positional relationship shown in the drawings, and is only
For ease of description the utility model and simplify description, rather than the device or element of indication or suggestion meaning must have it is specific
Orientation, be constructed and operated in a specific orientation, therefore should not be understood as limiting the present invention.
Referring to Fig.1-2, a kind of building iron connection structure, including main connector 1, main connector 1 are cross, main connection
The upside of part 1, downside, left and right side are respectively arranged with link slot 2, left link slot 3, lower link slot 4 and right link slot 5,
And main connector 1 is mounted on screw 6 close to the part of upper link slot 2, left link slot 3, lower link slot 4 and right link slot 5, it is main
There are two auxiliary connector 7, each auxiliary connections close to the installation symmetrical above and below of the part of lower link slot 4 and right link slot 5 for connector 1
Part 7 is equipped with link slot 10 far from the side of main connector 1, and connection bolt 9 is mounted on each auxiliary connector 7;
It should be noted that by the way that the reinforcing bar on upside, left side, downside and right side to be inserted into link slot 2, left connection respectively
In slot 3, lower link slot 4 and right link slot 5, and realize reinforcing bar in upper link slot 2, left link slot 3, lower link slot by screw 6
4 and right link slot 5 in fixation, with realize four reinforcing bars connection, the company between multiple reinforcing bars is realized by auxiliary connector 7
It connects, and auxiliary connector 7 is detachable connection, therefore can be adjusted according to the reinforcing bar number and location actually connected,
Adaptable strong feature;
In the above-described embodiments, auxiliary connector 7 is welded with pedestal 8 close to the side of main connector 1, on each pedestal 8
It is symmetrically installed there are two fixing bolt 11, the first tapped blind hole for cooperating fixing bolt 11 is provided on main connector 1;
It should be noted that blind by the first screw thread that two fixing bolts 11 are screwed in corresponding position on main connector 1
Hole to realize detachable installation of the auxiliary connector 7 on main connector 1, have the characteristics that it is easy to install and quick detachable, suitable for facing
The construction of Shi Jianzhu can be by removing very easily fixing bolt 11 and reinforcing bolt 12 after the completion of temporary building use
Reinforcing bar is dismantled, to realize the secondary use of reinforcing bar;
Wherein, each fixing bolt 11 is symmetrically opened up in the vertical direction there are two tapped through hole, each tapped through hole
It is inside mounted on and reinforces bolt 12, the top of pedestal 8 is provided with the second tapped blind hole that bolt 12 is reinforced in multiple cooperations;
By the way that two reinforcing bolts 12 are screwed in tapped through hole and the second tapped blind hole, positioning is played to fixing bolt 11 and is made
With connection for reinforcing between pedestal 8 and main connector 1, to reinforce the connection between auxiliary connector 7 and main connector 1;
Wherein, each connection bolt 9 is made of screw rod and nut, by positioning pin connection between screw rod and nut, is led to
It crosses positioning pin screw rod and nut is fixed, avoids the relative rotation between screw rod and nut, to advantageously ensure that reinforcing bar
The stability installed in auxiliary connector 7, the positioning pin are preferably that split pin should be noted that reinforcing bar between installation, needs
It reserves tapped through hole and is used for connecting screw, and installation of the position of the tapped through hole according to connection bolt 9 on auxiliary connector 7
Position is selected;
Wherein, upper link slot 2, left link slot 3, lower link slot 4, right link slot 5 and each link slot 10 are cylinder
Slot;
It should be noted that cylindrical groove is more bonded the reinforcing bar of cylindrical body, be conducive to be promoted reinforcing bar in link slot 10
The compactness of installation, stablizing to the installation of reinforcing bar has certain booster action;
In another preferred embodiment, each auxiliary connector 7 is welded with main connector 1, suitable for non-provisional building
Construction, by welding welds auxiliary connector 7 and main connector 1, welding manner is conducive to promote main connector
1 compactness connecting with auxiliary connector 7, can further promote the stability of reinforcing bar connection, to guarantee the service life of building.
The preferable specific embodiment of the above, only the utility model, but the protection scope of the utility model is not
It is confined to this, anyone skilled in the art is within the technical scope disclosed by the utility model, practical according to this
Novel technical solution and its utility model design are subject to equivalent substitution or change, should all cover the protection model in the utility model
Within enclosing.
Claims (6)
1. a kind of building iron connection structure, including main connector (1), which is characterized in that the main connector (1) is cross
Shape, the upside of the main connector (1), downside, left and right side be respectively arranged with link slot (2), left link slot (3), under
Link slot (4) and right link slot (5), and the main connector (1) is close to upper link slot (2), left link slot (3), lower link slot
(4) it is mounted on screw (6) with the part of right link slot (5), the main connector (1) is close to lower link slot (4) and right connection
There are two auxiliary connector (7) for the installation symmetrical above and below of the part of slot (5), and each auxiliary connector (7) is far from main connector (1)
Side be equipped with link slot (10), be mounted on each auxiliary connector (7) connection bolt (9).
2. a kind of building iron connection structure according to claim 1, which is characterized in that the auxiliary connector (7) is close
The side of main connector (1) is welded with pedestal (8), is symmetrically installed on each pedestal (8) there are two fixing bolt
(11), the first tapped blind hole for cooperating fixing bolt (11) is provided on the main connector (1).
3. a kind of building iron connection structure according to claim 2, which is characterized in that each fixing bolt (11)
It is symmetrically opened up in the vertical direction there are two tapped through hole, is mounted in each tapped through hole and reinforces bolt (12),
The second tapped blind hole that bolt (12) are reinforced in multiple cooperations is provided with above the pedestal (8).
4. a kind of building iron connection structure according to claim 1, which is characterized in that each connection bolt (9)
It is made of screw rod and nut, positioning pin is installed between the screw rod and nut.
5. a kind of building iron connection structure according to claim 1, which is characterized in that the upper link slot (2), Zuo Lian
Access slot (3), lower link slot (4), right link slot (5) and each link slot (10) are cylindrical groove.
6. a kind of building iron connection structure according to claim 1, which is characterized in that each auxiliary connector (7)
Welded with main connector (1).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821792422.7U CN209114732U (en) | 2018-11-01 | 2018-11-01 | A kind of building iron connection structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821792422.7U CN209114732U (en) | 2018-11-01 | 2018-11-01 | A kind of building iron connection structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209114732U true CN209114732U (en) | 2019-07-16 |
Family
ID=67203345
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201821792422.7U Expired - Fee Related CN209114732U (en) | 2018-11-01 | 2018-11-01 | A kind of building iron connection structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209114732U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111749488A (en) * | 2020-06-30 | 2020-10-09 | 福建省永富建设集团有限公司 | Novel reinforcing and connecting structure for reinforcing steel bar for house building |
-
2018
- 2018-11-01 CN CN201821792422.7U patent/CN209114732U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111749488A (en) * | 2020-06-30 | 2020-10-09 | 福建省永富建设集团有限公司 | Novel reinforcing and connecting structure for reinforcing steel bar for house building |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN209114732U (en) | A kind of building iron connection structure | |
CN210441349U (en) | Folding and be convenient for air conditioner support of installation | |
CN209100780U (en) | Electromechanical antidetonation suspension and support is built with high-intensitive stand column device | |
CN208236003U (en) | A kind of tool for replacing grid node | |
CN207406179U (en) | It is a kind of without lock hatch door rocking arm torsion resistant device | |
CN207518084U (en) | A kind of steady type cabinet | |
CN205426995U (en) | Novel electric energy meter of terminal box supports fixedly device | |
CN215055325U (en) | Steel construction truss plate is short to be chosen board outward and is exempted from formwork device | |
CN209607547U (en) | A kind of impact-proof structure and transformer applied to amorphous transformer | |
CN209078637U (en) | A kind of novel grounded downlead M16 bolt disassembly tool | |
CN208849282U (en) | A kind of ammeter protective plate convenient for adjusting installation | |
CN208445156U (en) | Pole-mounted switch case | |
CN209729760U (en) | Double power supply automatic transfer switch | |
CN209194731U (en) | It is a kind of for assembling type steel structure building module module hoisting and the device of connection | |
CN209350483U (en) | Beam column mold | |
CN209169810U (en) | For replacing the auxiliary device of insulator and/or cross-arm | |
CN208470065U (en) | Siding is built in one kind reinforces tooling | |
CN205677071U (en) | A kind of rise long-span overhanging steel structure | |
CN112575962A (en) | Prefabricated reinforced concrete structural beam for prefabricated house building | |
CN212053012U (en) | Frame structure of pool box | |
CN214146327U (en) | Transmission connecting mechanism for automatic equipment | |
CN205024890U (en) | Aluminum single plate | |
CN209455989U (en) | Removable derrick crane stock | |
CN209066609U (en) | A kind of connection structure of box plainly-packed room peripheral board | |
CN211637756U (en) | Stable reinforcing part for stainless steel wire drawing processing |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20190716 |
|
CF01 | Termination of patent right due to non-payment of annual fee |