CN209104729U - A kind of movable cable testing bridge for carrying out arc splicing and using - Google Patents

A kind of movable cable testing bridge for carrying out arc splicing and using Download PDF

Info

Publication number
CN209104729U
CN209104729U CN201822222323.1U CN201822222323U CN209104729U CN 209104729 U CN209104729 U CN 209104729U CN 201822222323 U CN201822222323 U CN 201822222323U CN 209104729 U CN209104729 U CN 209104729U
Authority
CN
China
Prior art keywords
gantry ontology
plate
bolt
elastic connection
cable testing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201822222323.1U
Other languages
Chinese (zh)
Inventor
陆凯
李晓芹
梅卫东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Kay Shun Electric Co Ltd
Original Assignee
Jiangsu Kay Shun Electric Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Kay Shun Electric Co Ltd filed Critical Jiangsu Kay Shun Electric Co Ltd
Priority to CN201822222323.1U priority Critical patent/CN209104729U/en
Application granted granted Critical
Publication of CN209104729U publication Critical patent/CN209104729U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

Arc, which can be carried out, the utility model discloses one kind splices the movable cable testing bridge used, including gantry ontology and cover board, placing groove is provided on the inside of the gantry ontology, the cover board is located at the top of gantry ontology, connecting hole is offered on the outside of the left and right ends of the gantry ontology, and connection bolt is connected on the inside of connecting hole, elastic connection plate is connected on the inside of the connection bolt, installation bolt is connected on the inside of the installation convex block, and the lower end for installing bolt is connected with active plate, the two sides up and down of the gantry ontology are provided with fixed link, and fixation hole is offered on the outside of fixed link.This can carry out the movable cable testing bridge that arc splicing uses and be provided with elastic connection plate, it can be in order to being attached by mobilizable elastic connection plate to adjacent gantry ontology in the use process of device, the elastic connection plate of spring steel plate material can improve the using flexible of device in order to be bent various suitable angles simultaneously.

Description

A kind of movable cable testing bridge for carrying out arc splicing and using
Technical field
The utility model relates to cable testing bridge correlative technology field, specially a kind of arc that can carry out splices the activity used Formula cable testing bridge.
Background technique
Cable testing bridge can support in order to the laying of cable, all be applied in many buildings, cable testing bridge is most It depends on and is arranged on various buildings and piping lane bracket, but the internal structure of building is not frank and outspoken, and existing Building much also a large amount of building structure for using arc, and existing cable testing bridge is also being used when carrying out and being laid with and turn to The fixed steering linkage member of fixed-direction is brought so that the laying flexibility of cable testing bridge is poor to the laying of cable testing bridge It is inconvenient.
In view of the above-mentioned problems, innovated on the basis of arc splices the movable cable testing bridge used original Design.
Utility model content
Arc can be carried out the purpose of this utility model is to provide one kind and splices the movable cable testing bridge used, to solve It is proposed that cable testing bridge structure is fixed in above-mentioned background technique, laying is inflexible for use, is not easy to the problem of multi-angle turns to.
To achieve the above object, the utility model provides the following technical solutions: one kind can carry out arc and splice the work used Dynamic formula cable testing bridge, including gantry ontology and cover board are provided with placing groove on the inside of the gantry ontology, and before gantry ontology Two upper sides are provided with flanging afterwards, and the cover board is located at the top of gantry ontology, and is respectively provided with below the front and rear sides of cover board There is convex edge, offer connecting hole on the outside of the left and right ends of the gantry ontology, and be connected with connection bolt on the inside of connecting hole, It is connected with elastic connection plate on the inside of the connection bolt, and is provided with installation convex block below the middle part of elastic connection plate, it is described Installation bolt is connected on the inside of installation convex block, and the lower end for installing bolt is connected with active plate, and active plate Top be provided with support plate, the two sides up and down of the gantry ontology are provided with fixed link, and offer on the outside of fixed link Fixation hole, and fixing bolt is connected on the inside of fixation hole.
Preferably, the flanging and gantry ontology are integrated, and the positional structure of flanging and convex edge is mutually coincide, And convex edge and cover board are integrated.
Preferably, the connecting hole is evenly distributed on the left and right sides of gantry ontology and elastic connection plate, and gantry ontology It is connected with each other between elastic connection plate by connection bolt.
Preferably, the elastic connection plate is provided with 2, and mutual by active plate between adjacent spring connecting plate Connection, and the width of active plate is equal to the width of gantry ontology.
Preferably, the active plate and support plate are weldedization structure, and active plate and installation convex block Between be connected with each other by installation bolt, and convex block is installed and elastic connection plate is integrated.
Preferably, fixation hole, and the left and right ends of fixed link and adjacent gantry are evenly distributed on the outside of the fixed link It is connected with each other between ontology by fixing bolt.
Compared with prior art, the utility model has the beneficial effects that this, which can carry out arc, splices the movable electricity used Cable gantry;
1, the elastic connection plate that can carry out bending connection, mating connection hole and connection in the use process of device are provided with Bolt uses, can be in order to be attached by mobilizable elastic connection plate to adjacent gantry ontology, while spring steel plate The elastic connection plate of material can be in order to be bent various suitable angles, so that the splicing steering of gantry ontology is no longer limited to volume Fixed angle improves the using flexible of device;
2, the fixed link being connected and fixed can be adjusted by being provided with, and fixation hole and fixation are cooperated in the use process of device Bolt uses, and fixation, holding pair can be supported in order to the connection structure to gantry ontology after bending and elastic connection plate The overall structure of device supports, while the adjustable connection length of fixed link and multiple fixation holes is convenient for adaptation elastic connection plate Differently curved radian uses convenient for the flexible bending of device.
Detailed description of the invention
Fig. 1 is the utility model side structure schematic diagram;
Fig. 2 is the utility model positive structure schematic;
Fig. 3 is overlooking structure diagram after the splicing of the utility model elastic connection plate benging;
Fig. 4 is the utility model active plate structural schematic diagram.
In figure: 1, gantry ontology;2, placing groove;3, flanging;4, cover board;5, convex edge;6, connecting hole;7, bolt is connected;8, Elastic connection plate;9, convex block is installed;10, bolt is installed;11, active plate;12, support plate;13, fixed link;14, fixed Hole;15, fixing bolt.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work Every other embodiment obtained, fall within the protection scope of the utility model.
Please refer to Fig. 1-4, the utility model provides a kind of technical solution: one kind can carry out arc splicing use it is movable Cable testing bridge, including gantry ontology 1, placing groove 2, flanging 3, cover board 4, convex edge 5, connecting hole 6, connection bolt 7, elastic connection plate 8, convex block 9, installation bolt 10, active plate 11, support plate 12, fixed link 13, fixation hole 14 and fixing bolt 15, bridge are installed The inside of frame ontology 1 is provided with placing groove 2, and is provided with flanging 3 above the front and rear sides of gantry ontology 1, and cover board 4 is located at bridge The top of frame ontology 1, and convex edge 5 is provided with below the front and rear sides of cover board 4, it is opened on the outside of the left and right ends of gantry ontology 1 Inside equipped with connecting hole 6, and connecting hole 6 is connected with connection bolt 7, and the inside of connection bolt 7 is connected with elastic connection plate 8, And installation convex block 9 is provided with below the middle part of elastic connection plate 8, the inside of installation convex block 9 is connected with installation bolt 10, and installs The lower end of bolt 10 is connected with active plate 11, and the top of active plate 11 is provided with support plate 12, gantry ontology 1 Two sides up and down be provided with fixed link 13, and the outside of fixed link 13 offers fixation hole 14, and the inside of fixation hole 14 It is connected with fixing bolt 15.
The flanging 3 and gantry ontology 1 of this example are integrated, and the positional structure of flanging 3 and convex edge 5 is mutually coincide, And convex edge 5 and cover board 4 are integrated, and toilet cover plate 4 is covered above gantry ontology 1 and protected, while flanging 3 and convex edge 5 can effectively reinforce the lateral edge structural strength of gantry ontology 1 and cover board 4.
Connecting hole 6 is evenly distributed on the left and right sides of gantry ontology 1 and elastic connection plate 8, and gantry ontology 1 and elasticity are even It is connected with each other between fishplate bar 8 by connection bolt 7, it is adjustable convenient for being carried out by elastic connection plate 8 to adjacent gantry ontology 1 Arc connection.
Elastic connection plate 8 is provided with 2, and is connected with each other between adjacent spring connecting plate 8 by active plate 11, and And the width of active plate 11 is equal to the width of gantry ontology 1, and convenient for being attached fixation to adjacent spring connecting plate 8, side Just elastic connection plate 8 keeps curved arc to connect.
Active plate 11 and support plate 12 are weldedization structure, and between active plate 11 and installation convex block 9 It is connected with each other by installation bolt 10, and convex block 9 is installed and elastic connection plate 8 is integrated, be convenient for active plate 11 and support plate 12 Auxiliary support is attached to elastic connection plate 8.
The outside of fixed link 13 is evenly distributed with fixation hole 14, and the left and right ends of fixed link 13 and adjacent gantry ontology 1 Between be connected with each other by fixing bolt 15, convenient for consolidating when elastic connection plate 8 is bent between adjacent gantry ontology 1 It is fixed, convenient for keeping the bending state of elastic connection plate 8.
Working principle: when the movable cable testing bridge that arc splicing uses can be carried out using this, according to Fig. 1-2, Gantry ontology 1 can be set up first with normal cable testing bridge, cover board 4 is then closed on gantry ontology 1, makes convex edge 5 Fitting is kept to place with the flanging 3 of placing groove 2;
The splicing of device is being carried out in use, connection bolt 7 can be used and pass through connecting hole 6 for bullet according to Fig. 1-4 Property connecting plate 8 and one end of gantry ontology 1 be connected with each other, then by the other end of elastic connection plate 8 and gantry ontology 1 to be spliced It is attached by connecting bolt 7, after the elastic connection plate 8 for installing two sides, it is convex installation can be passed through by installation bolt 10 Block 9, the lower section after active plate 11 and support plate 12 to be mounted on to two-side elastic connecting plate 8 carry out Auxiliary support, while can Then suitable fixation hole can be selected when installing side elastic connection plate 8 when laying direction carries out bending adjusting 14, it exerts a force to elastic connection plate 8, so that elastic connection plate 8 is carried out bending adjusting, while can be by selection fixed link 13 The fixation hole 14 of suitable position is attached support using the two sides gantry ontology 1 after 15 pairs of fixing bolt bending connections, so that The laying of gantry ontology 1 can keep curved laying direction, consequently facilitating the laying to gantry ontology 1 carries out flexible modulation, The content being not described in detail in this specification belongs to the prior art well known to professional and technical personnel in the field.
While there has been shown and described that the embodiments of the present invention, for the ordinary skill in the art, It is understood that these embodiments can be carried out with a variety of variations in the case where not departing from the principles of the present invention and spirit, repaired Change, replacement and variant, the scope of the utility model is defined by the appended claims and the equivalents thereof.

Claims (6)

1. one kind, which can carry out arc, splices the movable cable testing bridge used, including gantry ontology (1) and cover board (4), feature It is: is provided with placing groove (2) on the inside of the gantry ontology (1), and is provided with above the front and rear sides of gantry ontology (1) Flanging (3), the cover board (4) is located at the top of gantry ontology (1), and is provided with convex edge below the front and rear sides of cover board (4) (5), it is offered connecting hole (6) on the outside of the left and right ends of the gantry ontology (1), and the company of being connected on the inside of connecting hole (6) Connecting bolt (7) is connected with elastic connection plate (8) on the inside of the connection bolt (7), and below the middle part of elastic connection plate (8) It is provided with installation convex block (9), installation bolt (10) is connected on the inside of the installation convex block (9), and install under bolt (10) End is connected with active plate (11), and support plate (12) are provided with above active plate (11), the gantry ontology (1) two sides up and down are provided with fixed link (13), and fixation hole (14) are offered on the outside of fixed link (13), and fixation hole (14) fixing bolt (15) are connected on the inside of.
2. one kind according to claim 1, which can carry out arc, splices the movable cable testing bridge used, it is characterised in that: institute It states flanging (3) and gantry ontology (1) is integrated, and the positional structure of flanging (3) and convex edge (5) is mutually coincide, and Convex edge (5) and cover board (4) are integrated.
3. one kind according to claim 1, which can carry out arc, splices the movable cable testing bridge used, it is characterised in that: institute State the left and right sides that connecting hole (6) is evenly distributed on gantry ontology (1) and elastic connection plate (8), and gantry ontology (1) and elasticity It is connected with each other between connecting plate (8) by connection bolt (7).
4. one kind according to claim 1, which can carry out arc, splices the movable cable testing bridge used, it is characterised in that: institute It states elastic connection plate (8) and is provided with 2, and be connected with each other between adjacent spring connecting plate (8) by active plate (11), and And the width of active plate (11) is equal to the width of gantry ontology (1).
5. one kind according to claim 1, which can carry out arc, splices the movable cable testing bridge used, it is characterised in that: institute Stating active plate (11) and support plate (12) is weldedization structure, and active plate (11) and install convex block (9) it Between be connected with each other by installation bolt (10), and convex block (9) is installed and elastic connection plate (8) is integrated.
6. one kind according to claim 1, which can carry out arc, splices the movable cable testing bridge used, it is characterised in that: institute It states and is evenly distributed on the outside of fixed link (13) fixation hole (14), and the left and right ends of fixed link (13) and adjacent gantry ontology (1) it is connected with each other between by fixing bolt (15).
CN201822222323.1U 2018-12-28 2018-12-28 A kind of movable cable testing bridge for carrying out arc splicing and using Active CN209104729U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201822222323.1U CN209104729U (en) 2018-12-28 2018-12-28 A kind of movable cable testing bridge for carrying out arc splicing and using

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201822222323.1U CN209104729U (en) 2018-12-28 2018-12-28 A kind of movable cable testing bridge for carrying out arc splicing and using

Publications (1)

Publication Number Publication Date
CN209104729U true CN209104729U (en) 2019-07-12

Family

ID=67163579

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201822222323.1U Active CN209104729U (en) 2018-12-28 2018-12-28 A kind of movable cable testing bridge for carrying out arc splicing and using

Country Status (1)

Country Link
CN (1) CN209104729U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113451953A (en) * 2021-07-01 2021-09-28 江苏精通电气工程设备有限公司 Cable bridge convenient to install and installation method thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113451953A (en) * 2021-07-01 2021-09-28 江苏精通电气工程设备有限公司 Cable bridge convenient to install and installation method thereof
CN113451953B (en) * 2021-07-01 2022-06-21 江苏精通电气工程设备有限公司 Cable bridge convenient to install and installation method thereof

Similar Documents

Publication Publication Date Title
CN209104729U (en) A kind of movable cable testing bridge for carrying out arc splicing and using
CN207363376U (en) A kind of transmission line of electricity on-line monitoring case special stand mechanism
CN111864670A (en) Fire-resistant cable bridge
CN205509402U (en) Pallet type cable bridge stand
CN205140403U (en) Center of display, casing of display and display
CN113451953B (en) Cable bridge convenient to install and installation method thereof
CN209786686U (en) Groove type vertical upward bending bridge frame
CN210867046U (en) High-availability cable bridge
CN208316217U (en) A kind of Novel bridge frame using simple connection type
CN213989987U (en) Multifunctional cable bridge
CN212028756U (en) A gallows is laid to corridor pipeline multilayer
CN208861009U (en) A kind of box of passing by one's way for optical fiber wiring
CN209308325U (en) A kind of quartz plate convenient for splicing
CN208334736U (en) Dilatation combined insertion piece formula optical splitter
CN208352898U (en) Single button bracket can be filled with the pipe of Rapid Combination
CN208352891U (en) A kind of high-strength energy-saving cable testing bridge
CN207719425U (en) A kind of broadcasting engineering cable connecting arrangement
CN207759881U (en) A kind of adjustable lift car cableway
CN215906694U (en) Protector of hydraulic and hydroelectric engineering side slope
CN205857520U (en) Plank connecting structure and sheet material
CN216672459U (en) Knob type fixed hot galvanizing cable bridge
CN214069429U (en) Universal three-way bridge connecting piece
CN213243488U (en) Novel cable suspension bracket
CN217815390U (en) Pump line reinforcing apparatus
CN213793917U (en) Mineral insulated cable instrument of buckling

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant