CN209082699U - One kind is for construction steel structure high-altitude construction Quick Connect Kit - Google Patents

One kind is for construction steel structure high-altitude construction Quick Connect Kit Download PDF

Info

Publication number
CN209082699U
CN209082699U CN201821612940.6U CN201821612940U CN209082699U CN 209082699 U CN209082699 U CN 209082699U CN 201821612940 U CN201821612940 U CN 201821612940U CN 209082699 U CN209082699 U CN 209082699U
Authority
CN
China
Prior art keywords
steel
steel plate
construction
threaded hole
girder steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201821612940.6U
Other languages
Chinese (zh)
Inventor
李开防
张�浩
李炳良
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tengzhou Construction And Installation Engineering Group Co
Original Assignee
Tengzhou Construction And Installation Engineering Group Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tengzhou Construction And Installation Engineering Group Co filed Critical Tengzhou Construction And Installation Engineering Group Co
Priority to CN201821612940.6U priority Critical patent/CN209082699U/en
Application granted granted Critical
Publication of CN209082699U publication Critical patent/CN209082699U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

The utility model discloses one kind for construction steel structure high-altitude construction Quick Connect Kit, is related to technical field of buildings.This is used for construction steel structure high-altitude construction Quick Connect Kit, including steel column, fixing sleeve, fixing bolt, the first girder steel, the first steel plate, the first threaded hole, the second girder steel, the second steel plate and bindiny mechanism, fixing sleeve is fixedly connected by the fixing bolt that outer surface thread connects with steel column, first girder steel is welded on the side of fixing sleeve, first steel plate is respectively welded at the top and bottom of the first girder steel, first steel plate is connect by bindiny mechanism with the second steel plate, second steel plate is respectively welded at the top and bottom of the second girder steel, and the first threaded hole is provided on the first girder steel.The utility model is aligned grafting by carrying out locating rod with locating slot, facilitates the quick located coincident to the first threaded hole and the second threaded hole, facilitates and increases the speed of installation and the precision of positioning to the quick positioning between the first girder steel and the second girder steel.

Description

One kind is for construction steel structure high-altitude construction Quick Connect Kit
Technical field
The utility model relates to technical field of buildings, specially a kind of quickly to connect dress for the construction of construction steel structure high-altitude It sets.
Background technique
With making rapid progress for new technology, new material, new process and new equipment, the representative steel construction as one of " "four news" (new ideas " Technology continues to develop, and the structural steelwork of large span, big height and large area has complied with low-carbon energy-saving and environmentally protective construction Theory, wherein the high-altitude installation of girder steel has become a great problem of Construction Technology of Steel Configuration, has low efficiency and installation accuracy low The problem of needing to take a long time to being aligned between two girder steels to be installed.
Utility model content
The utility model provides one kind for construction steel structure high-altitude construction Quick Connect Kit, this is used for building iron knot Structure high-altitude construction Quick Connect Kit, quickly positions two girder steels, increases the precision and efficiency of steel girder erection.
In order to achieve the above object, the utility model is achieved by the following technical programs: one kind being used for construction steel structure High-altitude construction Quick Connect Kit, including steel column, fixing sleeve, fixing bolt, the first girder steel, the first steel plate, the first threaded hole, second Girder steel, the second steel plate and bindiny mechanism, the fixing sleeve are socketed in the top of steel column outer surface, and the fixing sleeve passes through outer surface The fixing bolt of threaded connection is fixedly connected with steel column, and first girder steel is welded on the side of fixing sleeve, first steel plate Quantity is two, and two first steel plates are respectively welded at the top and bottom of the first girder steel, and first steel plate passes through company Connection mechanism is connect with the second steel plate, and the quantity of second steel plate is two, and two second steel plates are respectively welded at second The top and bottom of girder steel, first threaded hole are provided on the first girder steel.
The bindiny mechanism includes locating rod, locating slot, hinge, snap-gauge and the second threaded hole, one end of the locating rod It is welded with the first steel plate far from the side of fixing sleeve, the locating rod is plugged on far from one end of the first steel plate and is provided with the second steel The inside of the locating slot of plate side, one end of the hinge are welded on the second girder steel, and the other end of the hinge is welded on card The side of plate, second threaded hole are provided on snap-gauge.
Preferably, the shape of first girder steel and the second girder steel is identical, the shape of first steel plate and the second steel plate It is identical.
Preferably, the outer surface of the steel column is welded with limit plate, and the limit plate is located at the lower section of fixing sleeve.
Preferably, the quantity of the snap-gauge is two, and two snap-gauges are symmetrically distributed in the front and back of the second girder steel.
Preferably, the size of first threaded hole and the second threaded hole is identical, and the first threaded hole and the second threaded hole Quantity is equal.
Preferably, the quantity of the locating rod is two, and the shape of two locating rods is rectangle, and the shape of locating slot Shape mutually agrees with locating rod.
By above-mentioned technical proposal, the utility model provides a kind of for the quick connection dress of construction steel structure high-altitude construction It sets.At least have it is following the utility model has the advantages that
(1), this is used for construction steel structure high-altitude construction Quick Connect Kit, by the way that locating rod to be aligned with locating slot Grafting facilitates the quick located coincident to the first threaded hole and the second threaded hole, facilitates to the first girder steel and the second girder steel Between it is quick positioning increase the speed of installation and the precision of positioning.
(2), this is used for construction steel structure high-altitude construction Quick Connect Kit, passes through the grafting of locating rod and locating slot, increasing Added the stability and supportive connecting to the first steel plate with the second steel plate, be convenient to use bolt to snap-gauge and the first girder steel into Row location and installation facilitates the adjusting to snap-gauge angle by the folding of hinge, makes snap-gauge in the first girder steel and the second girder steel pair Expansible facilitates docking when connecing, and bolt is easy to use to sequentially pass through the first threaded hole and the second threaded hole of coincidence after the completion of docking Location and installation is carried out to the first girder steel and the second girder steel, is then fixed using nut and increases fixed stability.
Detailed description of the invention
Attached drawing described herein is used to provide a further understanding of the present invention, and is constituted part of this application:
Fig. 1 is the structural schematic diagram of the utility model;
Fig. 2 is the overlooking structure diagram of the second girder steel in the utility model Fig. 1.
In figure: 1 steel column, 2 fixing sleeves, 3 fixing bolts, 4 first girder steels, 5 first steel plates, 6 first threaded holes, 7 second girder steels, 8 second steel plates, 9 bindiny mechanisms, 901 locating rods, 902 locating slots, 903 hinges, 904 snap-gauges, 905 second threaded holes, 10 limits Plate.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment.
The utility model provides a kind of technical solution referring to FIG. 1-2: one kind is quick for the construction of construction steel structure high-altitude Attachment device, including steel column 1, fixing sleeve 2, fixing bolt 3, the first girder steel 4, the first steel plate 5, the first threaded hole 6, the second girder steel 7, Second steel plate 8 and bindiny mechanism 9, the first girder steel 4 is identical with the shape of the second girder steel 7, the shape of the first steel plate 5 and the second steel plate 8 Shape is identical, and fixing sleeve 2 is socketed in the top of 1 outer surface of steel column, and the outer surface of steel column 1 is welded with limit plate 10, and limit plate 10 In the lower section of fixing sleeve 2, the limit to fixing sleeve 2 is facilitated, facilitates the screw thread on the threaded hole and steel column 1 on fixing sleeve 2 Hole alignment installation, fixing sleeve 2 are fixedly connected by the fixing bolt 3 that outer surface thread connects with steel column 1, and the first girder steel 4 is welded on The side of fixing sleeve 2, the quantity of the first steel plate 5 are two, two the first steel plates 5 be respectively welded at the first girder steel 4 top and Bottom, the first steel plate 5 are connect by bindiny mechanism 9 with the second steel plate 8, and the quantity of the second steel plate 8 is two, two the second steel plates 8 are respectively welded at the top and bottom of the second girder steel 7, and the first threaded hole 6 is provided on the first girder steel 4.
By carrying out locating rod 901 with locating slot 902 to be aligned grafting, facilitate to the first threaded hole 6 and the second screw thread The quick located coincident in hole 905 facilitates the speed that installation is increased to the quick positioning between the first girder steel 4 and the second girder steel 7 The precision of degree and positioning.
Bindiny mechanism 9 includes locating rod 901, locating slot 902, hinge 903, snap-gauge 904 and the second threaded hole 905, positioning One end of bar 901 and the first steel plate 5 are welded far from the side of fixing sleeve 2, one end grafting of the locating rod 901 far from the first steel plate 5 In the inside for the locating slot 902 for being provided with 8 side of the second steel plate, the quantity of locating rod 901 is two, two locating rods 901 Shape is rectangle, and the shape of locating slot 902 is agreed with 901 phase of locating rod, and one end of hinge 903 is welded on the second girder steel On 7, the other end of hinge 903 is welded on the side of snap-gauge 904, and the second threaded hole 905 is provided on snap-gauge 904, the first screw thread Hole 6 is identical with the size of the second threaded hole 905, and the first threaded hole 6 and 905 quantity of the second threaded hole are equal, the number of snap-gauge 904 Amount is two, and two snap-gauges 904 are symmetrically distributed in the front and back of the second girder steel 7, increase the stability of installation.
It is socketed with lifting rope in the outer surface of the second girder steel 7 and the second steel plate 8, the top of lifting rope is fixedly connected with hoisting machine, Facilitate the movement to the second girder steel 7.
By the grafting of locating rod 901 and locating slot 902, the stabilization connecting to the first steel plate 5 with the second steel plate 8 is increased Property and supportive, being convenient to use bolt carries out location and installation to snap-gauge 904 and the first girder steel 4, by the folding of hinge 903, The adjusting to 904 angle of snap-gauge is facilitated, convenient pair of expansible when the first girder steel 4 and the second girder steel 7 dock of snap-gauge 904 is made It connects, the first threaded hole 6 and the second threaded hole 905 for being easy to use bolt to sequentially pass through coincidence after the completion of docking are to the first girder steel 4 Location and installation is carried out with the second girder steel 7, is then fixed using nut and increases fixed stability.
In summary: this is used for construction steel structure high-altitude construction Quick Connect Kit, by by locating rod 901 and locating slot 902 carry out alignment grafting, facilitate the quick located coincident to the first threaded hole 6 and the second threaded hole 905, facilitate to first Quick positioning between girder steel 4 and the second girder steel 7 increases the speed of installation and the precision of positioning.
By the grafting of locating rod 901 and locating slot 902, the stabilization connecting to the first steel plate 5 with the second steel plate 8 is increased Property and supportive, being convenient to use bolt carries out location and installation to snap-gauge 904 and the first girder steel 4, by the folding of hinge 903, The adjusting to 904 angle of snap-gauge is facilitated, convenient pair of expansible when the first girder steel 4 and the second girder steel 7 dock of snap-gauge 904 is made It connects, the first threaded hole 6 and the second threaded hole 905 for being easy to use bolt to sequentially pass through coincidence after the completion of docking are to the first girder steel 4 Location and installation is carried out with the second girder steel 7, is then fixed using nut and increases fixed stability.
It has been carried out in detail to provided by the utility model for construction steel structure high-altitude construction Quick Connect Kit above It introduces.The utility model applies specific case and is expounded to the principles of the present invention and embodiment, the above implementation The explanation of example is merely used to help understand the method and its core concept of the utility model.It should be pointed out that for the art Those of ordinary skill for, without departing from the principle of this utility model, can also to the utility model carry out it is several Improvement and modification, modifications and modifications also fall within the protection scope of the claims of the utility model.

Claims (6)

1. one kind for construction steel structure high-altitude construct Quick Connect Kit, including steel column (1), fixing sleeve (2), fixing bolt (3), First girder steel (4), the first steel plate (5), the first threaded hole (6), the second girder steel (7), the second steel plate (8) and bindiny mechanism (9), Be characterized in that: the fixing sleeve (2) is socketed in the top of steel column (1) outer surface, and the fixing sleeve (2) is connected by outer surface thread The fixing bolt (3) connect is fixedly connected with steel column (1), and first girder steel (4) is welded on the side of fixing sleeve (2), and described first The quantity of steel plate (5) is two, and two first steel plates (5) are respectively welded at the top and bottom of the first girder steel (4), described First steel plate (5) is connect by bindiny mechanism (9) with the second steel plate (8), and the quantity of second steel plate (8) is two, two Second steel plate (8) is respectively welded at the top and bottom of the second girder steel (7), and first threaded hole (6) is provided with first On girder steel (4);
The bindiny mechanism (9) includes locating rod (901), locating slot (902), hinge (903), snap-gauge (904) and the second screw thread Hole (905), one end and the first steel plate (5) of the locating rod (901) are welded far from the side of fixing sleeve (2), the locating rod (901) one end far from the first steel plate (5) is plugged on the inside for being provided with the locating slot (902) of the second steel plate (8) side, described One end of hinge (903) is welded on the second girder steel (7), and the other end of the hinge (903) is welded on the side of snap-gauge (904) Face, second threaded hole (905) are provided on snap-gauge (904).
2. according to claim 1 a kind of for construction steel structure high-altitude construction Quick Connect Kit, it is characterised in that: institute State that the first girder steel (4) is identical with the shape of the second girder steel (7), first steel plate (5) is identical with the shape of the second steel plate (8).
3. according to claim 1 a kind of for construction steel structure high-altitude construction Quick Connect Kit, it is characterised in that: institute The outer surface for stating steel column (1) is welded with limit plate (10), and the limit plate (10) is located at the lower section of fixing sleeve (2).
4. according to claim 1 a kind of for construction steel structure high-altitude construction Quick Connect Kit, it is characterised in that: institute The quantity for stating snap-gauge (904) is two, and two snap-gauges (904) are symmetrically distributed in the front and back of the second girder steel (7).
5. according to claim 1 a kind of for construction steel structure high-altitude construction Quick Connect Kit, it is characterised in that: institute It is identical with the size of the second threaded hole (905) to state the first threaded hole (6), and the first threaded hole (6) and the second threaded hole (905) number It measures equal.
6. according to claim 1 a kind of for construction steel structure high-altitude construction Quick Connect Kit, it is characterised in that: institute The quantity for stating locating rod (901) is two, and the shape of two locating rods (901) is rectangle, and the shape of locating slot (902) Mutually agree with locating rod (901).
CN201821612940.6U 2018-09-30 2018-09-30 One kind is for construction steel structure high-altitude construction Quick Connect Kit Expired - Fee Related CN209082699U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821612940.6U CN209082699U (en) 2018-09-30 2018-09-30 One kind is for construction steel structure high-altitude construction Quick Connect Kit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821612940.6U CN209082699U (en) 2018-09-30 2018-09-30 One kind is for construction steel structure high-altitude construction Quick Connect Kit

Publications (1)

Publication Number Publication Date
CN209082699U true CN209082699U (en) 2019-07-09

Family

ID=67118237

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821612940.6U Expired - Fee Related CN209082699U (en) 2018-09-30 2018-09-30 One kind is for construction steel structure high-altitude construction Quick Connect Kit

Country Status (1)

Country Link
CN (1) CN209082699U (en)

Similar Documents

Publication Publication Date Title
CN206053324U (en) A kind of curved adjustable securing member of building template list
CN106088360B (en) A kind of two-tube lower edge connecting node of large span list truss structure and truss structure
CN203223003U (en) Detachable triangular jig frame for steel truss assembling
CN203079594U (en) Balance arm of tower crane and tower crane
CN202007535U (en) Supporting reinforcing structure
CN205976596U (en) Assembly type building supporting frame
CN209082699U (en) One kind is for construction steel structure high-altitude construction Quick Connect Kit
CN203834688U (en) Enhancement steel reinforced concrete structure beam column joint structure
CN102174836B (en) Framework column bending hysteresis test specimen with reusable stiffening bar sections
CN208934254U (en) A kind of assembled Steel Reinforced Concrete Special-Shaped Columns connecting structure
CN207121993U (en) The hinged joint that a kind of reinforced concrete frame structure bracing members are reinforced
CN214995278U (en) Large-volume concrete combined raft support
CN206128294U (en) Shake interchangeable upper end in back suspension type steel frame power consumption beam column node
CN201605793U (en) Moving clamping piece of overhanging steel frame
CN208702127U (en) A kind of large-span steel construction scaffold integral slide device
CN103882941B (en) Modular many high-rise assembling type steel structure frame center support systems
CN103882944B (en) Modular many high-rise assembling type steel structure frame systems
CN207314524U (en) A kind of high performance concrete chain type combining structure
CN205348759U (en) Shear wall template system for construction
CN205998902U (en) A kind of combination type stock section being applied to large-scale tower crane fast assembling-disassembling
CN206898704U (en) A kind of complicated day font component
CN206370239U (en) A kind of bridge structural model device
CN110821135A (en) Attached lifting scaffold
CN212688706U (en) Scattered assembling type positioning support
CN103967116A (en) Self-resetting line-shaped herringbone supporting system for industrialized assembly type multistory and high-rise steel structures

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190709