CN209028013U - A kind of chemical plant installations pipe-line system purging detection device - Google Patents

A kind of chemical plant installations pipe-line system purging detection device Download PDF

Info

Publication number
CN209028013U
CN209028013U CN201821495386.8U CN201821495386U CN209028013U CN 209028013 U CN209028013 U CN 209028013U CN 201821495386 U CN201821495386 U CN 201821495386U CN 209028013 U CN209028013 U CN 209028013U
Authority
CN
China
Prior art keywords
frame
wall
detection
block
chemical plant
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821495386.8U
Other languages
Chinese (zh)
Inventor
奚治政
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanjing Huayuan Engineering Management Co Ltd
Original Assignee
Nanjing Huayuan Engineering Management Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanjing Huayuan Engineering Management Co Ltd filed Critical Nanjing Huayuan Engineering Management Co Ltd
Priority to CN201821495386.8U priority Critical patent/CN209028013U/en
Application granted granted Critical
Publication of CN209028013U publication Critical patent/CN209028013U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Supports For Pipes And Cables (AREA)

Abstract

The utility model discloses a kind of chemical plant installations pipe-line systems to purge detection device, it is related to pipe detection field, whether clean it is intended to detect chemical plant installations blowing pipeline, its drip irrigation device includes the detection components that the blowning installation for being placed on pipe head, the support holder assembly for being placed on pipe outlet, the rack component that support holder assembly top is arranged in and sliding are mounted in rack component, achievees the purpose that simply to detect chemical plant installations pipe-line system purging situation.

Description

A kind of chemical plant installations pipe-line system purging detection device
Technical field
The utility model relates to pipe detection fields, more specifically, it relates to which a kind of chemical plant installations pipe-line system purges Detection device.
Background technique
Before chemical plant installations goes into operation, the whole process pipes and equipment that need to be installed to it after the assay was approved are purged and are cleaned (hereinafter referred to as purge), its purpose be by using air, steam, water and purging in relation to fluid media (medium)s such as chemical solutions, The means such as flushing, physics remove the dust debris etc. that construction and installation remained therebetween and invested in the process its inner wall, prevent from going into operation When test run, the problems such as causing the blocking Pipeline damage equipment occurred therefrom, be to guarantee the smooth test run of device and long period safety One important test program of production.
But the length and bending angle of chemical plant installations pipeline are different, when being detected to the dust in pipeline very not Easily.
Summary of the invention
In view of the deficienciess of the prior art, the purpose of this utility model is to provide a kind of chemical plant installations pipe-line systems to blow Detection device is swept, there is the advantage of simple detection chemical plant installations pipe-line system purging situation.
To achieve the above object, the utility model provides following technical solution:
A kind of chemical plant installations pipe-line system purging detection device, including being placed on the blowning installation of pipe head, placing Pipe outlet support holder assembly, be arranged in support holder assembly top rack component and sliding be mounted on rack Detection components in component.
By taking above-mentioned technical proposal, blowning installation is blown into pipeline, if containing dust in pipeline, dust is flowing It takes offence under the drive of body, blows out, fallen in detection components from pipe outlet, feelings are sticked by the dust in observation detection components Condition, and then whether achieve the purpose that judge in pipeline containing dust.
The utility model is further arranged to: the support holder assembly includes support base, is rotatably connected on support bottom The fold pedestal of seat surrounding and the telescopic mast being arranged at the center of support base upper surface.
By taking above-mentioned technical proposal, placement can be allowed according to the height of the height adjustment telescopic rod of pipe outlet Frame component and pipeline opening are opposite, recycle rotation fold pedestal, change the contact area of support holder assembly and ground, prevent from stretching In the telescopic process of bar, the mass centre changing of device, device is toppled over.
The utility model is further arranged to: the rack component includes the placement for being vertically arranged in flexible top end Frame and the steady rest being arranged between placement frame opposed apexes, the placement frame top are provided through placement mouth vertically, Sliding rail is provided on the inside of two upright side walls of placement frame.
By taking above-mentioned technical proposal, sliding rail detection components and rack component are flexibly connected, and steady rest increases Place the intensity of frame.
The utility model is further arranged to: the detection components include that slip is placed on the detection placed in frame Deckle board, the clamping piece that detection deckle board top and bottom end is arranged in and clamped part are fixed on the detection display part on detection deckle board, The detection deckle board two sides are provided with T-type sliding block.
It is aobvious by the replaceable new detection of clamping piece before detecting blowing pipeline situation by taking above-mentioned technical proposal Show part, guarantees the accuracy of detection.
The utility model is further arranged to: at least horizontal pane wall and at least one vertical frame wall for placing frame On be provided with telescopic component, the steady rest includes cross trestle and can be in the cabinet frame column in cross trestle, the telescopic mast Top is provided with loading plate, and the horizontal bottom wall sliding for placing frame is connected on loading plate.
By taking above-mentioned technical proposal, the size for placing frame, reselection can be adjusted according to the size of pipeline opening The detection components of suitable size, it is ensured that the dust in pipeline is all blown in detection components, is observed by people.
The utility model is further arranged to: the frame wall for placing frame includes fixed frame wall and activity box wall, institute State the conduit and the fastener being arranged in activity box wall that telescopic component includes the horse tooth trough shape being provided in fixed frame wall.
By taking above-mentioned technical proposal, is slided in conduit by fastener and realizes the size adjustment for placing frame, And conduit and fastener also increase the bonding strength between activity box wall and fixed frame wall.
The utility model is further arranged to: cavity is provided in the activity box wall, the cavity is close to conduit Through setting, the fastener includes the fixed link that cavity closed end is arranged, protrudes to be arranged and stretch out cavity one end in fixed link for one end Cylindrical bar, be connected with cylindrical bar fixed block, be rotatably connected on fixed block side wall movable block, be connected to fixed block and work Reset spring between motion block and along the sliding of fixed link circumference rotation annulated column, cover cylindrical bar and with synchronous turn of rotation annulated column Dynamic limited block, the similar length of the limited block and fixed block, the width of the limited block is less than the length of fixed block, described It is equipped with arcwall face between the roof and lateral wall of movable block, inclined surface, institute are equipped between the bottom wall and inner sidewall of the movable block It states reset spring to be arranged between inclined surface and fixed block, guide ring is arranged far from one end of fixed frame wall in the activity box wall Item, the guide ring item are provided with the looping pit being connected to cavity, and the rotation annulated column is provided with behaviour far from one end of limited block Make bar, the operating stick is pierced by looping pit.
By taking above-mentioned technical proposal, when stretch frame wall, movable block can be rotated down, and be stuck in conduit When T-type horizontal ends, movable block will not be rotated up by the position-limiting action of limited block, while when needing activity compression frame wall, be turned Rotating ring column drives limited block rotation, so that limited block is lost position-limiting action to movable block, movable block is rotated up, then activity box wall It moves downward.
The utility model is further arranged to: one end that the operating stick is pierced by looping pit is provided with operating block, described The cross-sectional area of operating block is greater than the cross-sectional area of operating stick.
By taking above-mentioned technical proposal, rotation annulated column rotation is operated convenient for operator, reaches laborsaving convenient purpose.
The utility model is further arranged to: being provided with several exhaust outlets on the placement frame and detection deckle board.
By using above-mentioned technical proposal, because the monsoon intensity of blowing device is very big, exhaust outlet can anti-locking apparatus blown down, Influence detection effect.
In conclusion the utility model has the following beneficial effects:
1, using support holder assembly, rack component and detection components, achieve the purpose that simply to detect blowing pipeline situation;
2, using telescopic component and telescopic mast, rack component can be adjusted according to the height and pipe diameter size of pipeline Height and size are suitable for various pipelines.
Detailed description of the invention
Fig. 1 is the schematic perspective view of embodiment;
Fig. 2 is to embody the structure chart for supporting holder assembly, rack component and detection components in embodiment;
Fig. 3 is the cross-sectional view to embody support base modular construction in embodiment;
Fig. 4 is the partial enlarged view to embody telescopic component structure in embodiment;
Fig. 5 is the schematic diagram for being in stationary state to embody fastener in embodiment.
Fig. 6 is the schematic diagram being in active state to embody fastener in embodiment.
Appended drawing reference: 1, pipeline;2, blowning installation;3, holder assembly is supported;4, rack component;5, detection components;6, it turns over Roll over pedestal;7, support base;8, telescopic mast;9, steady rest;10, frame is placed;11, display part is detected;12, clamping piece;13, it examines Survey deckle board;14, telescopic component;15, conduit;16, fastener;17, fixed frame wall;18, activity box wall;19, a cabinet frame column;20, ten Cabinet frame column;21, reset spring;22, limited block;23, fixed block;24, movable block;25, cylindrical bar;26, annulated column is rotated;27, it grasps Make bar;28, looping pit;29, operating block;30, loading plate;31, exhaust outlet;32, handle;33, mouth is placed;34, T-type sliding block;35, Sliding rail;36, arcwall face;37, inclined surface;38, cavity;39, fixed link;40, it is oriented to draw runner.
Specific embodiment
The utility model is described in further detail below in conjunction with attached drawing.
Embodiment:
A kind of chemical plant installations pipe-line system purging detection device, as shown in Figure 1, including being placed on blowing for 1 input end of pipeline Device of air 2, the support holder assembly 3 for being placed on 1 outlet end of pipeline, be arranged in support 3 top of holder assembly rack component 4 and The detection components 5 being mounted in rack component 4 are slid, 5 top of detection components is provided with handle 32.
As shown in Fig. 2, support holder assembly 3 includes support base 7, it is rotatably connected on the fold pedestal 6 of 7 surrounding of support base With the telescopic mast 8 being arranged at 7 upper surface center of support base, rack component 4 includes being vertically arranged in 8 top of telescopic mast It places frame 10 and the steady rest 9 placed in frame 10 is set, place 10 top of frame and be provided through placement mouth 33 vertically, It places and is provided with sliding rail 35 on the inside of 10 liang of upright side walls of frame.
As shown in Fig. 2, detection components 5 include that slip is placed on the detection deckle board 13 placed in frame 10, setting is being examined The clamping piece 12 and clamped part 12 for surveying 13 top of deckle board and bottom end are fixed on the detection display part 11 detected on deckle board 13, this reality It can be aluminium foil, wet calico and double-sided adhesive etc. with novel detection display part 11, detection 13 two sides of deckle board are provided with T-type sliding block 34, it detects and is provided with several exhaust outlets 31 on deckle board 13.
As shown in figure 3, being provided with telescopic component 14 in the horizontal bottom wall of placement frame 10 and a vertical frame wall, frame is placed 10 another horizontal pane wall and vertical frame wall with free extension, can place the horizontal bottom wall of frame 10 and vertical frame wall includes solid Determine frame wall 17 and activity box wall 18, steady rest 9 includes cross trestle 20 and can stretch in the cabinet frame column 19 in cross trestle 20 8 top of column is provided with loading plate 30, and the horizontal bottom wall sliding for placing frame 10 is connected on loading plate 30;It is set in activity box wall 18 It is equipped with cavity 38, telescopic component 14 includes the conduit 15 for the horse tooth trough shape being arranged in fixed frame wall 17 and is arranged in cavity 38 Fastener 16, cavity 38 close to one end of conduit 15 through setting;According to the pipe of the height of the outlet end of pipeline 1 and pipe outlet Diameter adjusts the height of telescopic mast 8 and places the length and width of frame 10, then installs the detection components 5 of suitable size, makes to detect Component 5 is sufficiently opposite with the outlet of pipeline 1.
As shown in Figure 4, Figure 5 and Figure 6, fastener 16 includes the fixed link 39 that 38 closed end of cavity is arranged in, is arranged in fixation Bar 39 stretches out the cylindrical bar 25 of 38 one end of cavity (Fig. 3), fixed block 23 of the cylindrical bar 25 far from 39 one end of fixed link is arranged in, turns The dynamic movable block 24 being connected in 23 two opposite side walls of fixed block, the reset spring being connected between fixed block 23 and movable block 24 21 and along 39 circumferencial direction of fixed link sliding rotation annulated column 26, cover on cylindrical bar 25 with rotation annulated column 26 synchronous rotation Limited block 22, the similar length of limited block 22 and fixed block 23, the width of limited block 22 are less than the length of fixed block 23, movable block It is equipped with arcwall face 36 between 24 roof and lateral wall, inclined surface 37 is equipped between the bottom wall and inner sidewall of movable block 24, resets Spring 21 is arranged between inclined surface 37 and fixed block 23, and guiding draw runner 40(Fig. 3 is provided on activity box wall 18);It is oriented to draw runner 40 are provided with the looping pit 28 being connected to cavity 38, rotate annulated column 26 far from one end of limited block 22 and are provided with operating stick 27, grasp Make bar 27 and be pierced by looping pit 28, one end that operating stick 27 is pierced by looping pit 28 is provided with operating block 29, the cross section of operating block 29 Product is greater than the cross-sectional area of operating stick 27.
The course of work:
Staff places blowning installation 2 in the input end of pipe under test 1, places support in the outlet end of pipeline 1 Holder assembly 3 adjusts the height of telescopic mast 8 according to the height of pipeline 1, is then adjusted according to the caliber of pipeline 1 and places frame 10 Size.
Activity box wall 18 is pulled first, and the fastener 16 in fixed link 39 slides in the conduit 15 of fixed frame wall 17, slides When, by conduit 15 T-type vertical section when movable block 24 by conduit 15 extruding so that rotate down, reset spring 21 is squeezed Pressure, when movable block 24 slides into the T-type horizontal segment of sliding slot 15, reset spring 21 resets, and movable block 24 restores horizontal, and by The position-limiting action of limited block 22, movable block 24 will not be rotated up (Fig. 5), therefore movable block 24 is stuck in conduit 15, while , can be with free extension without the frame wall of telescopic component 14 during fastener 16 slides, while a cabinet frame column 19 of steady rest 9 exists Sliding in cross trestle 20, the horizontal bottom wall for placing frame 10 are slided on loading plate 30, complete the big ditty for placing frame 10 It is whole.
Then the detection display part 11 of suitable size clamping piece 12 is clipped on detection deckle board 13, then will test component 5 It is placed in placement frame 10 by placing mouth 33, finally further according to the height of rack component 4, rotation fold pedestal 6 The contact area of adjustment support holder assembly 3 and ground, and then adjust rack component 4, support holder assembly 3 and detection components 5 Center of gravity, keeps the stability of three, then opens blowning installation 2.
After detection, detection components 5 are taken out, along 28 moving operation block 29 of looping pit, and then drive 26 turns of annulated column of rotation Dynamic, the limited block 22 for making and rotating the connection of annulated column 26 rotates 90 °, and limited block 22 is made to lose the position-limiting action to movable block 24, under Sliding activity box wall 18, movable block 24 are rotated up, and then are packed up and placed frame 10(Fig. 6).
This specific embodiment is only the explanation to the utility model, is not limitations of the present invention, ability Field technique personnel can according to need the modification that not creative contribution is made to the present embodiment after reading this specification, but As long as all by the protection of Patent Law in the scope of the claims of the utility model.

Claims (9)

1. a kind of chemical plant installations pipe-line system purges detection device, it is characterised in that: including being placed on blowing for pipeline (1) input end Device of air (2), the support holder assembly (3) for being placed on pipeline (1) outlet end, setting are in the rack for supporting holder assembly (3) top The detection components (5) that component (4) and sliding are mounted in rack component (4).
2. a kind of chemical plant installations pipe-line system according to claim 1 purges detection device, it is characterised in that: the support Holder assembly (3) includes support base (7), and the fold pedestal (6) for being rotatably connected on support base (7) surrounding and setting are at support bottom Telescopic mast (8) at seat (7) upper surface center.
3. a kind of chemical plant installations pipe-line system according to claim 2 purges detection device, it is characterised in that: the placement Frame component (4) includes being vertically arranged in the placement frame (10) on telescopic mast (8) top and being arranged steady in placement frame (10) Determine frame (9), placement frame (10) top is provided through vertically places mouth (33), the vertical side of the placement frame (10) two Sliding rail (35) are provided on the inside of wall.
4. a kind of chemical plant installations pipe-line system according to claim 3 purges detection device, it is characterised in that: the detection Component (5) includes that sliding is placed on the detection deckle board (13) placed in frame (10), setting at detection deckle board (13) top and bottom The clamping piece (12) and clamped part (12) at end are fixed on the detection display part (11) in detection deckle board (13), the detection deckle board (13) two sides are provided with T-type sliding block (34).
5. a kind of chemical plant installations pipe-line system according to claim 3 purges detection device, it is characterised in that: the placement It is provided with telescopic component (14) in at least horizontal pane wall and at least one vertical frame wall of frame (10), steady rest (9) packet The cabinet frame column (19) that includes cross trestle (20) and can stretch in cross trestle (20), telescopic mast (8) top are provided with Loading plate (30), the horizontal bottom wall sliding for placing frame (10) are connected on loading plate (30).
6. a kind of chemical plant installations pipe-line system according to claim 5 purges detection device, it is characterised in that: the placement The horizontal pane wall of frame (10) and vertical frame wall include fixed frame wall (17) and activity box wall (18), the telescopic component (14) The fastener (16) of conduit (15) and setting including the horse tooth trough shape being provided in fixed frame wall (17) in activity box wall (18).
7. a kind of chemical plant installations pipe-line system according to claim 6 purges detection device, it is characterised in that: the activity It is provided with cavity (38) in frame wall (18), the cavity (38) runs through setting, the fastener (16) close to the one end of conduit (15) The circle of cavity (38) one end is stretched out in fixed link (39) including being arranged to be arranged in the fixed link (39) of cavity (38) closed end, protrusion Mast (25), the fixed block (23) being connected with cylindrical bar (25), the activity being rotatably connected in fixed block (23) two opposite side walls Block (24), the reset spring (21) being connected between fixed block (23) and movable block (24) and along fixed link (39) circumference slide Rotation annulated column (26), cover cylindrical bar (25) and with rotation annulated column (26) rotate synchronously limited block (22), the limited block (22) and the similar length of fixed block (23), the width of the limited block (22) are less than the length of fixed block (23), the activity Arcwall face (36) are equipped between the roof and lateral wall of block (24), is equipped with and inclines between the bottom wall and inner sidewall of the movable block (24) Inclined-plane (37), the reset spring (21) are arranged between inclined surface (37) and fixed block (23), and the activity box wall (18) is remote Guide ring item (40) are arranged in one end from fixed frame wall (17), are provided in the guide ring item (40) and to be connected to cavity (38) Looping pit (28), rotation annulated column (26) are provided with operating stick (27), the operating stick far from the one end of limited block (22) (27) looping pit (28) are pierced by.
8. a kind of chemical plant installations pipe-line system according to claim 7 purges detection device, it is characterised in that: the operation One end that bar (27) is pierced by looping pit (28) is provided with operating block (29), and the cross-sectional area of the operating block (29) is greater than operating stick (27) cross-sectional area.
9. a kind of chemical plant installations pipe-line system according to claim 4 purges detection device, it is characterised in that: the detection Several exhaust outlets (31) are provided on deckle board (13).
CN201821495386.8U 2018-09-12 2018-09-12 A kind of chemical plant installations pipe-line system purging detection device Active CN209028013U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821495386.8U CN209028013U (en) 2018-09-12 2018-09-12 A kind of chemical plant installations pipe-line system purging detection device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821495386.8U CN209028013U (en) 2018-09-12 2018-09-12 A kind of chemical plant installations pipe-line system purging detection device

Publications (1)

Publication Number Publication Date
CN209028013U true CN209028013U (en) 2019-06-25

Family

ID=66877248

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821495386.8U Active CN209028013U (en) 2018-09-12 2018-09-12 A kind of chemical plant installations pipe-line system purging detection device

Country Status (1)

Country Link
CN (1) CN209028013U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113567406A (en) * 2021-07-21 2021-10-29 南通联翔机械有限公司 Simple inner hole cleanliness inspection instrument

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113567406A (en) * 2021-07-21 2021-10-29 南通联翔机械有限公司 Simple inner hole cleanliness inspection instrument
CN113567406B (en) * 2021-07-21 2022-05-31 南通联翔机械有限公司 Simple inner hole cleanliness inspection instrument

Similar Documents

Publication Publication Date Title
CN209028013U (en) A kind of chemical plant installations pipe-line system purging detection device
CN210882806U (en) Glass film production line
CN111649687A (en) Three-dimensional optical scanner
CN210935542U (en) Fixing device for spraying paint on instrument shell
CN209014514U (en) Wall defect detection equipment
CN208334145U (en) A kind of programmable constant temperature and moisture test machine
CN214368576U (en) Intelligent inspection robot for underwater pipeline
CN214297545U (en) Device for monitoring oil gas concentration on oil tank
CN221050804U (en) Automatic needle machine of checking of dust protected
CN209525812U (en) A kind of physics experiments of high school apparatus for demonstrating
CN209829059U (en) Storage rack for cleaned test tubes
CN107976126B (en) Shell recovery device for shell speed measurement and recovery method thereof
CN108162618B (en) A kind of physics steel ball labelling apparatus
CN215678365U (en) Multi-index rapid water quality detection device
CN219715530U (en) Lightning protection detection box convenient to height-adjusting
CN220851263U (en) Flaw detector for pipeline flaw detection
CN114278806B (en) CCTV pipeline endoscopic detector for urban pipeline network layout
CN212391477U (en) Gas monitoring device for tunnel construction
CN216410829U (en) Rotary evaporator for laboratory detection
CN215768225U (en) Oil content detection alarm device for medical compressed air system
CN110216591B (en) Vertical pipeline sand blaster with retracting device
JPH07185487A (en) Device for removing residual matter in container bag
CN220794540U (en) Rotary multifunctional detection device
CN219495578U (en) Pipeline tightness detection device
CN216433056U (en) High-efficient plastics bottleneck detection device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant