CN209028013U - A kind of chemical plant installations pipe-line system purging detection device - Google Patents
A kind of chemical plant installations pipe-line system purging detection device Download PDFInfo
- Publication number
- CN209028013U CN209028013U CN201821495386.8U CN201821495386U CN209028013U CN 209028013 U CN209028013 U CN 209028013U CN 201821495386 U CN201821495386 U CN 201821495386U CN 209028013 U CN209028013 U CN 209028013U
- Authority
- CN
- China
- Prior art keywords
- frame
- wall
- detection
- block
- chemical plant
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Supports For Pipes And Cables (AREA)
Abstract
The utility model discloses a kind of chemical plant installations pipe-line systems to purge detection device, it is related to pipe detection field, whether clean it is intended to detect chemical plant installations blowing pipeline, its drip irrigation device includes the detection components that the blowning installation for being placed on pipe head, the support holder assembly for being placed on pipe outlet, the rack component that support holder assembly top is arranged in and sliding are mounted in rack component, achievees the purpose that simply to detect chemical plant installations pipe-line system purging situation.
Description
Technical field
The utility model relates to pipe detection fields, more specifically, it relates to which a kind of chemical plant installations pipe-line system purges
Detection device.
Background technique
Before chemical plant installations goes into operation, the whole process pipes and equipment that need to be installed to it after the assay was approved are purged and are cleaned
(hereinafter referred to as purge), its purpose be by using air, steam, water and purging in relation to fluid media (medium)s such as chemical solutions,
The means such as flushing, physics remove the dust debris etc. that construction and installation remained therebetween and invested in the process its inner wall, prevent from going into operation
When test run, the problems such as causing the blocking Pipeline damage equipment occurred therefrom, be to guarantee the smooth test run of device and long period safety
One important test program of production.
But the length and bending angle of chemical plant installations pipeline are different, when being detected to the dust in pipeline very not
Easily.
Summary of the invention
In view of the deficienciess of the prior art, the purpose of this utility model is to provide a kind of chemical plant installations pipe-line systems to blow
Detection device is swept, there is the advantage of simple detection chemical plant installations pipe-line system purging situation.
To achieve the above object, the utility model provides following technical solution:
A kind of chemical plant installations pipe-line system purging detection device, including being placed on the blowning installation of pipe head, placing
Pipe outlet support holder assembly, be arranged in support holder assembly top rack component and sliding be mounted on rack
Detection components in component.
By taking above-mentioned technical proposal, blowning installation is blown into pipeline, if containing dust in pipeline, dust is flowing
It takes offence under the drive of body, blows out, fallen in detection components from pipe outlet, feelings are sticked by the dust in observation detection components
Condition, and then whether achieve the purpose that judge in pipeline containing dust.
The utility model is further arranged to: the support holder assembly includes support base, is rotatably connected on support bottom
The fold pedestal of seat surrounding and the telescopic mast being arranged at the center of support base upper surface.
By taking above-mentioned technical proposal, placement can be allowed according to the height of the height adjustment telescopic rod of pipe outlet
Frame component and pipeline opening are opposite, recycle rotation fold pedestal, change the contact area of support holder assembly and ground, prevent from stretching
In the telescopic process of bar, the mass centre changing of device, device is toppled over.
The utility model is further arranged to: the rack component includes the placement for being vertically arranged in flexible top end
Frame and the steady rest being arranged between placement frame opposed apexes, the placement frame top are provided through placement mouth vertically,
Sliding rail is provided on the inside of two upright side walls of placement frame.
By taking above-mentioned technical proposal, sliding rail detection components and rack component are flexibly connected, and steady rest increases
Place the intensity of frame.
The utility model is further arranged to: the detection components include that slip is placed on the detection placed in frame
Deckle board, the clamping piece that detection deckle board top and bottom end is arranged in and clamped part are fixed on the detection display part on detection deckle board,
The detection deckle board two sides are provided with T-type sliding block.
It is aobvious by the replaceable new detection of clamping piece before detecting blowing pipeline situation by taking above-mentioned technical proposal
Show part, guarantees the accuracy of detection.
The utility model is further arranged to: at least horizontal pane wall and at least one vertical frame wall for placing frame
On be provided with telescopic component, the steady rest includes cross trestle and can be in the cabinet frame column in cross trestle, the telescopic mast
Top is provided with loading plate, and the horizontal bottom wall sliding for placing frame is connected on loading plate.
By taking above-mentioned technical proposal, the size for placing frame, reselection can be adjusted according to the size of pipeline opening
The detection components of suitable size, it is ensured that the dust in pipeline is all blown in detection components, is observed by people.
The utility model is further arranged to: the frame wall for placing frame includes fixed frame wall and activity box wall, institute
State the conduit and the fastener being arranged in activity box wall that telescopic component includes the horse tooth trough shape being provided in fixed frame wall.
By taking above-mentioned technical proposal, is slided in conduit by fastener and realizes the size adjustment for placing frame,
And conduit and fastener also increase the bonding strength between activity box wall and fixed frame wall.
The utility model is further arranged to: cavity is provided in the activity box wall, the cavity is close to conduit
Through setting, the fastener includes the fixed link that cavity closed end is arranged, protrudes to be arranged and stretch out cavity one end in fixed link for one end
Cylindrical bar, be connected with cylindrical bar fixed block, be rotatably connected on fixed block side wall movable block, be connected to fixed block and work
Reset spring between motion block and along the sliding of fixed link circumference rotation annulated column, cover cylindrical bar and with synchronous turn of rotation annulated column
Dynamic limited block, the similar length of the limited block and fixed block, the width of the limited block is less than the length of fixed block, described
It is equipped with arcwall face between the roof and lateral wall of movable block, inclined surface, institute are equipped between the bottom wall and inner sidewall of the movable block
It states reset spring to be arranged between inclined surface and fixed block, guide ring is arranged far from one end of fixed frame wall in the activity box wall
Item, the guide ring item are provided with the looping pit being connected to cavity, and the rotation annulated column is provided with behaviour far from one end of limited block
Make bar, the operating stick is pierced by looping pit.
By taking above-mentioned technical proposal, when stretch frame wall, movable block can be rotated down, and be stuck in conduit
When T-type horizontal ends, movable block will not be rotated up by the position-limiting action of limited block, while when needing activity compression frame wall, be turned
Rotating ring column drives limited block rotation, so that limited block is lost position-limiting action to movable block, movable block is rotated up, then activity box wall
It moves downward.
The utility model is further arranged to: one end that the operating stick is pierced by looping pit is provided with operating block, described
The cross-sectional area of operating block is greater than the cross-sectional area of operating stick.
By taking above-mentioned technical proposal, rotation annulated column rotation is operated convenient for operator, reaches laborsaving convenient purpose.
The utility model is further arranged to: being provided with several exhaust outlets on the placement frame and detection deckle board.
By using above-mentioned technical proposal, because the monsoon intensity of blowing device is very big, exhaust outlet can anti-locking apparatus blown down,
Influence detection effect.
In conclusion the utility model has the following beneficial effects:
1, using support holder assembly, rack component and detection components, achieve the purpose that simply to detect blowing pipeline situation;
2, using telescopic component and telescopic mast, rack component can be adjusted according to the height and pipe diameter size of pipeline
Height and size are suitable for various pipelines.
Detailed description of the invention
Fig. 1 is the schematic perspective view of embodiment;
Fig. 2 is to embody the structure chart for supporting holder assembly, rack component and detection components in embodiment;
Fig. 3 is the cross-sectional view to embody support base modular construction in embodiment;
Fig. 4 is the partial enlarged view to embody telescopic component structure in embodiment;
Fig. 5 is the schematic diagram for being in stationary state to embody fastener in embodiment.
Fig. 6 is the schematic diagram being in active state to embody fastener in embodiment.
Appended drawing reference: 1, pipeline;2, blowning installation;3, holder assembly is supported;4, rack component;5, detection components;6, it turns over
Roll over pedestal;7, support base;8, telescopic mast;9, steady rest;10, frame is placed;11, display part is detected;12, clamping piece;13, it examines
Survey deckle board;14, telescopic component;15, conduit;16, fastener;17, fixed frame wall;18, activity box wall;19, a cabinet frame column;20, ten
Cabinet frame column;21, reset spring;22, limited block;23, fixed block;24, movable block;25, cylindrical bar;26, annulated column is rotated;27, it grasps
Make bar;28, looping pit;29, operating block;30, loading plate;31, exhaust outlet;32, handle;33, mouth is placed;34, T-type sliding block;35,
Sliding rail;36, arcwall face;37, inclined surface;38, cavity;39, fixed link;40, it is oriented to draw runner.
Specific embodiment
The utility model is described in further detail below in conjunction with attached drawing.
Embodiment:
A kind of chemical plant installations pipe-line system purging detection device, as shown in Figure 1, including being placed on blowing for 1 input end of pipeline
Device of air 2, the support holder assembly 3 for being placed on 1 outlet end of pipeline, be arranged in support 3 top of holder assembly rack component 4 and
The detection components 5 being mounted in rack component 4 are slid, 5 top of detection components is provided with handle 32.
As shown in Fig. 2, support holder assembly 3 includes support base 7, it is rotatably connected on the fold pedestal 6 of 7 surrounding of support base
With the telescopic mast 8 being arranged at 7 upper surface center of support base, rack component 4 includes being vertically arranged in 8 top of telescopic mast
It places frame 10 and the steady rest 9 placed in frame 10 is set, place 10 top of frame and be provided through placement mouth 33 vertically,
It places and is provided with sliding rail 35 on the inside of 10 liang of upright side walls of frame.
As shown in Fig. 2, detection components 5 include that slip is placed on the detection deckle board 13 placed in frame 10, setting is being examined
The clamping piece 12 and clamped part 12 for surveying 13 top of deckle board and bottom end are fixed on the detection display part 11 detected on deckle board 13, this reality
It can be aluminium foil, wet calico and double-sided adhesive etc. with novel detection display part 11, detection 13 two sides of deckle board are provided with T-type sliding block
34, it detects and is provided with several exhaust outlets 31 on deckle board 13.
As shown in figure 3, being provided with telescopic component 14 in the horizontal bottom wall of placement frame 10 and a vertical frame wall, frame is placed
10 another horizontal pane wall and vertical frame wall with free extension, can place the horizontal bottom wall of frame 10 and vertical frame wall includes solid
Determine frame wall 17 and activity box wall 18, steady rest 9 includes cross trestle 20 and can stretch in the cabinet frame column 19 in cross trestle 20
8 top of column is provided with loading plate 30, and the horizontal bottom wall sliding for placing frame 10 is connected on loading plate 30;It is set in activity box wall 18
It is equipped with cavity 38, telescopic component 14 includes the conduit 15 for the horse tooth trough shape being arranged in fixed frame wall 17 and is arranged in cavity 38
Fastener 16, cavity 38 close to one end of conduit 15 through setting;According to the pipe of the height of the outlet end of pipeline 1 and pipe outlet
Diameter adjusts the height of telescopic mast 8 and places the length and width of frame 10, then installs the detection components 5 of suitable size, makes to detect
Component 5 is sufficiently opposite with the outlet of pipeline 1.
As shown in Figure 4, Figure 5 and Figure 6, fastener 16 includes the fixed link 39 that 38 closed end of cavity is arranged in, is arranged in fixation
Bar 39 stretches out the cylindrical bar 25 of 38 one end of cavity (Fig. 3), fixed block 23 of the cylindrical bar 25 far from 39 one end of fixed link is arranged in, turns
The dynamic movable block 24 being connected in 23 two opposite side walls of fixed block, the reset spring being connected between fixed block 23 and movable block 24
21 and along 39 circumferencial direction of fixed link sliding rotation annulated column 26, cover on cylindrical bar 25 with rotation annulated column 26 synchronous rotation
Limited block 22, the similar length of limited block 22 and fixed block 23, the width of limited block 22 are less than the length of fixed block 23, movable block
It is equipped with arcwall face 36 between 24 roof and lateral wall, inclined surface 37 is equipped between the bottom wall and inner sidewall of movable block 24, resets
Spring 21 is arranged between inclined surface 37 and fixed block 23, and guiding draw runner 40(Fig. 3 is provided on activity box wall 18);It is oriented to draw runner
40 are provided with the looping pit 28 being connected to cavity 38, rotate annulated column 26 far from one end of limited block 22 and are provided with operating stick 27, grasp
Make bar 27 and be pierced by looping pit 28, one end that operating stick 27 is pierced by looping pit 28 is provided with operating block 29, the cross section of operating block 29
Product is greater than the cross-sectional area of operating stick 27.
The course of work:
Staff places blowning installation 2 in the input end of pipe under test 1, places support in the outlet end of pipeline 1
Holder assembly 3 adjusts the height of telescopic mast 8 according to the height of pipeline 1, is then adjusted according to the caliber of pipeline 1 and places frame 10
Size.
Activity box wall 18 is pulled first, and the fastener 16 in fixed link 39 slides in the conduit 15 of fixed frame wall 17, slides
When, by conduit 15 T-type vertical section when movable block 24 by conduit 15 extruding so that rotate down, reset spring 21 is squeezed
Pressure, when movable block 24 slides into the T-type horizontal segment of sliding slot 15, reset spring 21 resets, and movable block 24 restores horizontal, and by
The position-limiting action of limited block 22, movable block 24 will not be rotated up (Fig. 5), therefore movable block 24 is stuck in conduit 15, while
, can be with free extension without the frame wall of telescopic component 14 during fastener 16 slides, while a cabinet frame column 19 of steady rest 9 exists
Sliding in cross trestle 20, the horizontal bottom wall for placing frame 10 are slided on loading plate 30, complete the big ditty for placing frame 10
It is whole.
Then the detection display part 11 of suitable size clamping piece 12 is clipped on detection deckle board 13, then will test component 5
It is placed in placement frame 10 by placing mouth 33, finally further according to the height of rack component 4, rotation fold pedestal 6
The contact area of adjustment support holder assembly 3 and ground, and then adjust rack component 4, support holder assembly 3 and detection components 5
Center of gravity, keeps the stability of three, then opens blowning installation 2.
After detection, detection components 5 are taken out, along 28 moving operation block 29 of looping pit, and then drive 26 turns of annulated column of rotation
Dynamic, the limited block 22 for making and rotating the connection of annulated column 26 rotates 90 °, and limited block 22 is made to lose the position-limiting action to movable block 24, under
Sliding activity box wall 18, movable block 24 are rotated up, and then are packed up and placed frame 10(Fig. 6).
This specific embodiment is only the explanation to the utility model, is not limitations of the present invention, ability
Field technique personnel can according to need the modification that not creative contribution is made to the present embodiment after reading this specification, but
As long as all by the protection of Patent Law in the scope of the claims of the utility model.
Claims (9)
1. a kind of chemical plant installations pipe-line system purges detection device, it is characterised in that: including being placed on blowing for pipeline (1) input end
Device of air (2), the support holder assembly (3) for being placed on pipeline (1) outlet end, setting are in the rack for supporting holder assembly (3) top
The detection components (5) that component (4) and sliding are mounted in rack component (4).
2. a kind of chemical plant installations pipe-line system according to claim 1 purges detection device, it is characterised in that: the support
Holder assembly (3) includes support base (7), and the fold pedestal (6) for being rotatably connected on support base (7) surrounding and setting are at support bottom
Telescopic mast (8) at seat (7) upper surface center.
3. a kind of chemical plant installations pipe-line system according to claim 2 purges detection device, it is characterised in that: the placement
Frame component (4) includes being vertically arranged in the placement frame (10) on telescopic mast (8) top and being arranged steady in placement frame (10)
Determine frame (9), placement frame (10) top is provided through vertically places mouth (33), the vertical side of the placement frame (10) two
Sliding rail (35) are provided on the inside of wall.
4. a kind of chemical plant installations pipe-line system according to claim 3 purges detection device, it is characterised in that: the detection
Component (5) includes that sliding is placed on the detection deckle board (13) placed in frame (10), setting at detection deckle board (13) top and bottom
The clamping piece (12) and clamped part (12) at end are fixed on the detection display part (11) in detection deckle board (13), the detection deckle board
(13) two sides are provided with T-type sliding block (34).
5. a kind of chemical plant installations pipe-line system according to claim 3 purges detection device, it is characterised in that: the placement
It is provided with telescopic component (14) in at least horizontal pane wall and at least one vertical frame wall of frame (10), steady rest (9) packet
The cabinet frame column (19) that includes cross trestle (20) and can stretch in cross trestle (20), telescopic mast (8) top are provided with
Loading plate (30), the horizontal bottom wall sliding for placing frame (10) are connected on loading plate (30).
6. a kind of chemical plant installations pipe-line system according to claim 5 purges detection device, it is characterised in that: the placement
The horizontal pane wall of frame (10) and vertical frame wall include fixed frame wall (17) and activity box wall (18), the telescopic component (14)
The fastener (16) of conduit (15) and setting including the horse tooth trough shape being provided in fixed frame wall (17) in activity box wall (18).
7. a kind of chemical plant installations pipe-line system according to claim 6 purges detection device, it is characterised in that: the activity
It is provided with cavity (38) in frame wall (18), the cavity (38) runs through setting, the fastener (16) close to the one end of conduit (15)
The circle of cavity (38) one end is stretched out in fixed link (39) including being arranged to be arranged in the fixed link (39) of cavity (38) closed end, protrusion
Mast (25), the fixed block (23) being connected with cylindrical bar (25), the activity being rotatably connected in fixed block (23) two opposite side walls
Block (24), the reset spring (21) being connected between fixed block (23) and movable block (24) and along fixed link (39) circumference slide
Rotation annulated column (26), cover cylindrical bar (25) and with rotation annulated column (26) rotate synchronously limited block (22), the limited block
(22) and the similar length of fixed block (23), the width of the limited block (22) are less than the length of fixed block (23), the activity
Arcwall face (36) are equipped between the roof and lateral wall of block (24), is equipped with and inclines between the bottom wall and inner sidewall of the movable block (24)
Inclined-plane (37), the reset spring (21) are arranged between inclined surface (37) and fixed block (23), and the activity box wall (18) is remote
Guide ring item (40) are arranged in one end from fixed frame wall (17), are provided in the guide ring item (40) and to be connected to cavity (38)
Looping pit (28), rotation annulated column (26) are provided with operating stick (27), the operating stick far from the one end of limited block (22)
(27) looping pit (28) are pierced by.
8. a kind of chemical plant installations pipe-line system according to claim 7 purges detection device, it is characterised in that: the operation
One end that bar (27) is pierced by looping pit (28) is provided with operating block (29), and the cross-sectional area of the operating block (29) is greater than operating stick
(27) cross-sectional area.
9. a kind of chemical plant installations pipe-line system according to claim 4 purges detection device, it is characterised in that: the detection
Several exhaust outlets (31) are provided on deckle board (13).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821495386.8U CN209028013U (en) | 2018-09-12 | 2018-09-12 | A kind of chemical plant installations pipe-line system purging detection device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821495386.8U CN209028013U (en) | 2018-09-12 | 2018-09-12 | A kind of chemical plant installations pipe-line system purging detection device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209028013U true CN209028013U (en) | 2019-06-25 |
Family
ID=66877248
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201821495386.8U Active CN209028013U (en) | 2018-09-12 | 2018-09-12 | A kind of chemical plant installations pipe-line system purging detection device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209028013U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113567406A (en) * | 2021-07-21 | 2021-10-29 | 南通联翔机械有限公司 | Simple inner hole cleanliness inspection instrument |
-
2018
- 2018-09-12 CN CN201821495386.8U patent/CN209028013U/en active Active
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113567406A (en) * | 2021-07-21 | 2021-10-29 | 南通联翔机械有限公司 | Simple inner hole cleanliness inspection instrument |
CN113567406B (en) * | 2021-07-21 | 2022-05-31 | 南通联翔机械有限公司 | Simple inner hole cleanliness inspection instrument |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN209028013U (en) | A kind of chemical plant installations pipe-line system purging detection device | |
CN210882806U (en) | Glass film production line | |
CN111649687A (en) | Three-dimensional optical scanner | |
CN210935542U (en) | Fixing device for spraying paint on instrument shell | |
CN209014514U (en) | Wall defect detection equipment | |
CN208334145U (en) | A kind of programmable constant temperature and moisture test machine | |
CN214368576U (en) | Intelligent inspection robot for underwater pipeline | |
CN214297545U (en) | Device for monitoring oil gas concentration on oil tank | |
CN221050804U (en) | Automatic needle machine of checking of dust protected | |
CN209525812U (en) | A kind of physics experiments of high school apparatus for demonstrating | |
CN209829059U (en) | Storage rack for cleaned test tubes | |
CN107976126B (en) | Shell recovery device for shell speed measurement and recovery method thereof | |
CN108162618B (en) | A kind of physics steel ball labelling apparatus | |
CN215678365U (en) | Multi-index rapid water quality detection device | |
CN219715530U (en) | Lightning protection detection box convenient to height-adjusting | |
CN220851263U (en) | Flaw detector for pipeline flaw detection | |
CN114278806B (en) | CCTV pipeline endoscopic detector for urban pipeline network layout | |
CN212391477U (en) | Gas monitoring device for tunnel construction | |
CN216410829U (en) | Rotary evaporator for laboratory detection | |
CN215768225U (en) | Oil content detection alarm device for medical compressed air system | |
CN110216591B (en) | Vertical pipeline sand blaster with retracting device | |
JPH07185487A (en) | Device for removing residual matter in container bag | |
CN220794540U (en) | Rotary multifunctional detection device | |
CN219495578U (en) | Pipeline tightness detection device | |
CN216433056U (en) | High-efficient plastics bottleneck detection device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |