Prior art keywords
support
pivoting part
flexible traction
traction component
lift actuator
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821038979.1U
Other languages
Chinese (zh)
Inventor
陶声荣
李晓刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Jiete Intelligent Furniture Co ltd
Original Assignee
Jiangsu Jelt Lifting System Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Jelt Lifting System Co ltd filed Critical Jiangsu Jelt Lifting System Co ltd
Priority to CN201821038979.1U priority Critical patent/CN209017982U/en
Application granted granted Critical
Publication of CN209017982U publication Critical patent/CN209017982U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Invalid Beds And Related Equipment (AREA)

Abstract

The utility model discloses a kind of synchronization lifting mechanisms, and including the first support connecting with the lift side of the first lift actuator, first support is gone up and down with the lifting of the first lift actuator;The second support connecting with the lift side of the second lift actuator, second support are gone up and down with the lifting of the second lift actuator;One end of first flexible traction component is fixedly connected with fixing pipe in second, first flexible traction component is flexibly and after the cooperation of the other end of one end of second support, one end of first support, first support, and fixing pipe is fixed in the other end and first of the first flexible traction component;Fixing pipe is fixed in one end and first of second flexible traction component, flexibly and after the cooperation of the other end of one end of first support, one end of second support, second support, the other end of the second flexible traction component is fixedly connected second flexible traction component with fixing pipe in second.The utility model can ensure that the component being supported on synchronization lifting mechanism is not in inclined state.

Description

Synchronization lifting mechanism and desk
Technical field
The utility model relates to a kind of synchronization lifting mechanism and desks.
Background technique
Desk is commonly in life, work and Learning in School as a kind of daily necessities, general desk usually by Desktop is formed by fixedly connecting with table leg, and the length of table leg is also fixed, so that the height of entire desktop is to fix not It is adjustable.And with the difference of application environment and the application demand of different crowd, to the high diversity of desk, automatic Degree, the requirement of level of comfort are also higher and higher.
It there is now the table leg support using gas spring as desk and make face, control gas spring is installed in the lower surface of desktop The control assembly opened or closed, the control assembly (are connect by components such as drag-lines with the tieback connection on a connection component Rope connector is hinged on connection component) connection, the other end of the tieback connection and the switch of gas spring support, when needing table When son rises or drops, power rotates tieback connection by drag-line by user by control control assembly, to make gas spring Switch open, so that gas spring rises or drops according to the intention of user.
Since the table leg at desk both ends is supported by gas spring, when manipulating desk lifting, need to keep gas spring same Step operation, is otherwise raised and lowered on one side, and another side is tilted also in not dynamic state so as to cause desktop, such as when When needing to decline desktop, it is big that manipulator applies the lower pressure received to one end of desk, and the lower pressure that the other end applies is small, this Kind situation is to be easiest to cause desktop inclined.
Summary of the invention
The purpose of this utility model is to provide a kind of synchronization lifting mechanism and desk, the utility model, which can ensure that, to be supported Component on synchronization lifting mechanism is not in inclined state.
The technical solution for solving above-mentioned technical problem is as follows:
Synchronization lifting mechanism, including it is the first lift actuator, the second lift actuator, fixing pipe in first, solid in second Fixed pipe, further includes that the first lift actuator and the second lift actuator is made to synchronize the synchronization mechanism of lifting, synchronization mechanism packet It includes:
The first support being connect with the lift side of the first lift actuator, first support with the first lift actuator lifting And it goes up and down;
The second support being connect with the lift side of the second lift actuator, second support with the second lift actuator lifting And it goes up and down;
One end of first flexible traction component, the first flexible traction component is fixedly connected with fixing pipe in second, and first Flexible traction component is flexibly and after the cooperation of the other end of one end of second support, one end of first support, first support, and first The other end of flexible traction component is fixedly connected with fixing pipe in first;
One end of second flexible traction component, the second flexible traction component is fixedly connected with fixing pipe in first, and second Flexible traction component is flexibly and after the cooperation of the other end of one end of first support, one end of second support, second support, and second The other end of flexible traction component is fixedly connected with fixing pipe in second.
A kind of desk, including desktop further include synchronization lifting mechanism, the desktop with it is same in the synchronization lifting mechanism Walk mechanism connection.
The advantages of the utility model are as follows: synchronous when the first lift actuator and the second lift actuator make elevating movement Mechanism is formed simultaneously restraining function power to the first lift actuator and the second lift actuator, to avoid the occurrence of the first lifting drive The lifting of the dynamic device situation too fast relative to the lifting of the second lift actuator, so that the first lift actuator and the second lifting are driven The lifting of dynamic device is synchronous, it is ensured that the component (such as desktop) being supported on synchronization lifting mechanism will not run-off the straight.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the desk of the utility model;
Fig. 2 is that the schematic diagram after desktop is concealed on the basis of Fig. 1;
Fig. 3 is the schematic diagram concealed after crossbeam, the first movable outer tube and the second movable outer tube on the basis of Fig. 2;
Fig. 4 is that the schematic diagram after the first inner tube and the second inner tube is concealed on the basis of Fig. 3;
Fig. 5 is the installation diagram of first support and the first pivoting part, the second pivoting part and third pivoting part;
Fig. 6 is the installation diagram of second support and the 4th pivoting part, the 5th pivoting part and the 6th pivoting part;
Fig. 7 is the schematic diagram of the first connector;
Fig. 8 is the schematic diagram of the second connector;
Appended drawing reference of the Fig. 1 into Fig. 8:
10 be desktop;
20 be the first support member, 21 be the second support member;
30 be the first lift actuator, 301 be first axle, 31 be the second lift actuator, 311 be the second axis;
40 it is first support, 401 be the first hole, 411 be first support ontology, 412 be the first pivoting part, 413 is Two-revolution component, 414 are third pivoting part;
41 it is second support, 410 is the second hole, 421 is second support ontology, 422 is the 4th pivoting part, 423 is Five pivoting parts, 424 are the 6th pivoting part;
42 be the first flexible traction component;
43 be the second flexible traction component;
50 be the first inner tube, and 51 be the first connector, and 510 be the first U-shaped interconnecting piece, and 511 be the first bending interconnecting piece;
60 be the second inner tube, and 61 be the second connector, and 610 be the second U-shaped interconnecting piece, and 611 be the second bending interconnecting piece;
70 it is crossbeam, 71 be the first movable outer tube, 72 is the second movable outer tube;
80 be the first friction component.
Specific embodiment
First embodiment
As shown in Figure 1, the desk of the utility model includes desktop 10, the first support member 20, the second support member 21, Fixing pipe in one lift actuator 30, the second lift actuator 31, first fixing pipe and makes the first lift actuator in second The synchronization mechanism of lifting is synchronized with the second lift actuator, the relationship to each section and between them carries out detailed below Illustrate:
As illustrated in fig. 1 and 2, in one or more embodiments, the first support member 20 and the second support member 21 are divided Not Wei Yu the lower section of desktop 10, the first lift actuator 30 is installed in the first support member 20, in the second support member 21 Second lift actuator 31 is installed, the first lift actuator 30 and the second lift actuator 31 preferentially use gas spring, and first liter The structure of driver 30 and the second lift actuator 31 and the assembly with the first support member 20 and the second support member 21 are dropped Structure preferentially uses the structure disclosed in Publication No. CN106308039A, and details are not described herein.First lift actuator, 30 He Second lift actuator 31 can also be using components such as cylinder or hydraulic cylinders.
As shown in Figures 2 to 6, synchronization mechanism include: first support 40, second support 41, the first flexible traction component 42, Second flexible traction component 43, is below described in detail the structure of synchronization mechanism:
As shown in Figures 2 to 6, one end of first support 40 is connect with the lift side of the first lift actuator 30, and first Frame 40 is gone up and down, first support 40 and the preferred connection type of the first lift actuator 30 with the lifting of the first lift actuator 30 It is that one end of first support 40 is equipped with the first hole 401, the lift side of the first lift actuator 30 is equipped with the first mounting hole, and one First axle 301 passes through the first hole 401 and the first mounting hole, so that the first lift actuator 30 and first support 40 connect into one Body;Preferably, a part of first support 40 is located in first in fixing pipe, and a part of the first lift actuator 30 also is located at In first in fixing pipe.Fixing pipe one end is fixedly connected with the first support member 20 in first, therefore, when the first lift actuator When 30 lift side lifting drives first support 40 to go up and down, fixing pipe will not be moved in first.
As shown in Figures 2 to 6, first support 41 includes: first support ontology 411, the first pivoting part 412, second times Rotation member 413, third pivoting part 414, the first pivoting part 412 are installed in rotation on one end of first support ontology 411, Second pivoting part 413 is installed in rotation on one end of first support ontology 411;Third pivoting part 414 is rotationally pacified Mounted in the other end of first support ontology 411.
As shown in Figures 2 to 6, the section of first support ontology 411 is U-shaped, it is preferable that first support ontology 411 is slot Steel, the first pivoting part 412 and the second pivoting part 413 are respectively positioned in the slot of 411 one end of first support ontology, the first axle 301 pass through the first pivoting part 412 and the second pivoting part 413, so that the first pivoting part 412 and the second pivoting part 413 It is supported by first axle 301, so that the first pivoting part 412 and the second pivoting part 413 can turn round.And third pivoting part 414 be located at 411 other end of first support ontology slot in, third pivoting part 414 by the first mandrel (not shown) into Row support, so that third pivoting part 414 can turn round.First pivoting part 412, the second pivoting part 413, third rotating part Part 414 is bearing or one of idler wheel or sprocket wheel.
As shown in Figures 2 to 6, one end of second support 41 is connect with the lift side of the second lift actuator 31, and second Frame 41 is gone up and down, second support 41 and the preferred connection type of the second lift actuator 31 with the lifting of the second lift actuator 31 It is that one end of second support 41 is equipped with the second hole 410, the lift side of the second lift actuator 31 is equipped with the second mounting hole, and one Second axis 311 passes through the second hole 410 and the second mounting hole, so that the second lift actuator 31 and second support 41 connect into one Body.Preferably, a part of second support 41 is located in second in fixing pipe, and a part of the second lift actuator 31 also is located at In second in fixing pipe.Fixing pipe one end is fixedly connected with the second support member 21 in second, therefore, when the second lift actuator When 31 lift side lifting drives second support 41 to go up and down, fixing pipe will not be moved in second.
As shown in Figures 2 to 6, second support 42 includes: second support ontology 421, the 4th pivoting part 422, the 5th time Rotation member 423, the 6th pivoting part 424, the 4th pivoting part 422 are installed in rotation on one end of second support ontology 421, 5th pivoting part 423 is installed in rotation on one end of second support ontology 421;6th pivoting part 424 is rotationally pacified Mounted in the other end of second support ontology 421.
As shown in Figures 2 to 6, the section of second support ontology 421 is U-shaped, it is preferable that second support ontology 421 is slot Steel, the 4th pivoting part 422 and the 5th pivoting part 423 are respectively positioned in the slot of 421 one end of second support ontology, second axis 311 pass through the 4th pivoting part 422 and the 5th pivoting part 423, so that the 4th pivoting part 422 and the 5th pivoting part 423 It is supported by the second axis 311, so that the 4th pivoting part 422 and the 5th pivoting part 423 can turn round.And the 6th pivoting part 424 are located in the slot of 421 other end of second support ontology, and the 6th pivoting part 424 is supported by the second mandrel, thus the Six pivoting parts 424 can turn round.4th pivoting part 422, the 5th pivoting part 423, the 6th pivoting part 424 be bearing or One of idler wheel or sprocket wheel.
As shown in Figures 2 to 6, one end of the first flexible traction component 42 is fixedly connected with fixing pipe in second, and first scratches Property traction element 42 flexibly with the other end of one end of second support 41, one end of first support 40, first support 41 cooperate Afterwards, the other end of the first flexible traction component 42 is fixedly connected with fixing pipe in first.Preferably, first flexible traction portion Part 42 and the 5th pivoting part 423, the first pivoting part 412 and the flexible cooperation of third pivoting part 414, the flexibility cooperate class It is similar to the fit system of belt and belt pulley, i.e., the first flexible traction component 42 is by the 5th pivoting part 423, the first pivoting part 412 and third pivoting part 414 be tensioned.
As shown in Figures 2 to 6, one end of the second flexible traction component 43 is fixedly connected with fixing pipe in first, and second scratches Property traction element 42 flexibly with the other end of one end of first support 40, one end of second support 41, second support 41 cooperate Afterwards, the other end of the second flexible traction component 43 is fixedly connected with fixing pipe in second.The second flexible traction component and Two-revolution component 413, the 4th pivoting part 422 and the 6th pivoting part flexibility cooperation, flexibility cooperation be similar to belt with The fit system of belt pulley, i.e. the second flexible traction component 43 are by the 6th pivoting part 424, the second pivoting part 413 and The tensioning of four pivoting parts 422.
As shown in Figures 2 to 6, fixing pipe includes the first inner tube 50 and the first connector 51 in described first, in first One end of pipe 50 and the first support member 20 are fixed, and at least part of the first connector 51 is located in the first inner tube 50 and with the One inner tube 50 is fixed, and the first connector 51 is by the both ends of the first U-shaped interconnecting piece 510 and the first U-shaped interconnecting piece 510 through bent At the first bending interconnecting piece 511 form, offer first through hole, the first U-shaped interconnecting piece on the tube wall of first inner tube 50 510, which pass through first through hole, is located in the first inner tube 50, and first, which bends interconnecting piece 511, is located at the outside of the first inner tube 50 and with first Inner tube 50 is fixedly connected.
As shown in Figures 2 to 6, fixing pipe includes the second inner tube 60 and the second connector 61 in described second, and second connects At least part of fitting 61 is located in the second inner tube 60 and fixes with the second inner tube 60, and the second connector 61 is by the second U-shaped company Second bending interconnecting piece 611 of the both ends of socket part 610 and the second U-shaped interconnecting piece 610 through being bent to form forms, in described second The second through-hole is offered on the tube wall of pipe 60, the second U-shaped interconnecting piece 610 is located in the second inner tube 60 by the second through-hole, and second Bending interconnecting piece 611 is located at the outside of the second inner tube 60 and is fixedly connected with the second inner tube 60.
As shown in Fig. 2 to Fig. 8, one end of the first flexible traction component 42 is fixedly connected with the second connector 61, and first scratches The other end of property traction element 42 is fixedly connected with the first connector 51, and one end of the second flexible traction component 43 is connect with first Part 51 is fixedly connected, and the other end of the second flexible traction component 43 is fixedly connected with the second connector 61.Preferably, first is flexible One end of traction element 42 is fixedly connected with the second U-shaped interconnecting piece 610 of the second connector 61 by screw or pin, and first scratches The other end of property traction element 42 is fixedly connected with the first U-shaped interconnecting piece 510 of the first connector 51 by screw or pin, and One end of two flexible traction components 43 is fixedly connected with the first U-shaped interconnecting piece 510 of the first connector 51 by screw or pin, The other end of second flexible traction component 43 and the second U-shaped interconnecting piece 610 of the second connector 61 are fixed by screw or pin Connection.
As shown in Figures 2 to 6, the first flexible traction component 42 and the second flexible traction component 43 are respectively rope form portion Part or strip-shaped members or one of steel wire or chain.When the first flexible traction component 42 and the second flexible traction component 43 use When cord-like component or strip-shaped members or steel wire, the first pivoting part 412, the second pivoting part 413, third pivoting part 414, Four pivoting parts 422, the 5th pivoting part 423, the 6th pivoting part 424 use bearing or idler wheel, these bearings or idler wheel Outer circumference surface is equipped with groove, for being adapted to the first flexible traction component 42 and the second flexible traction component 43.
As shown in Figures 2 to 6, when the first flexible traction component 42 and the second flexible traction component 43 are using chain, the Single-revolution component 412, the second pivoting part 413, third pivoting part 414, the 4th pivoting part 422, the 5th pivoting part 423, the 6th pivoting part 424 uses sprocket wheel.
As shown in Figures 2 to 6, the desk of the utility model further includes that movable the 71, second activity of outer tube of crossbeam 70, first is outer Pipe 72, one end of crossbeam 70 and the lift side of the first lift actuator 30 are fixed, and the other end of crossbeam 70 and the second lifting drive The lift side of device 31 is fixed;Crossbeam 70 is connect with first axle 301, in this way, when the first lift actuator 30 and the second lifting driving When the lift side lifting of device 31, crossbeam 70 is gone up and down in company with the first lift actuator 30 and the second lift actuator 31.
As shown in Figures 2 to 6, one end of the first movable outer tube 71 and one end of crossbeam 70 are fixed, the first movable outer tube 71 It is gone up and down in company with the lifting of crossbeam 70.First movable 71 sets of the outer tube is in first in fixing pipe, i.e., the first movable 71 sets of outer tube In the first inner tube 50, the first friction component 80 is installed in the first inner tube 50, it is preferable that the first friction component 80 is fixed on On the outer peripheral surface of the other end of first inner tube 50, the inner wall of the first friction component 80 and the first movable outer tube 71 cooperates, and is the The lifting of one movable outer tube 71 is oriented to.Second friction group is installed on the inner peripheral surface of the other end of the first movable outer tube 71 The outer peripheral surface of part, the second friction component and the first inner tube 50 cooperates, and the lifting for the first movable outer tube 71 is oriented to, and first rubs Brush assembly 80 and the second friction component are also possible to sliding friction component, the first friction component either rolling friction component 80 and second friction component structure and the patent of Publication No. CN106308039A in the structure that discloses it is identical, it is no longer superfluous herein It states.
As shown in Figures 2 to 6, one end of the second movable outer tube 72 and the other end of crossbeam 70 are fixed, the second movable outer tube 72 go up and down in company with the lifting of crossbeam 70.Second movable 72 sets of outer tube is in second in fixing pipe.I.e. second movable 72 sets of outer tube In the second inner tube 60, third friction component is installed in the second inner tube 60, it is preferable that third friction component is fixed on second On the outer peripheral surface of the other end of inner tube 60, the inner wall of third friction component and the second movable outer tube 72 cooperates, and is the second activity The lifting of outer tube 72 is oriented to.The 4th friction component is installed on the inner peripheral surface of the other end of the second movable outer tube 72, the Four friction components and the outer peripheral surface of the second inner tube 60 cooperate, and the lifting for the second movable outer tube 72 is oriented to, third friction group Part and the 4th friction component are also possible to sliding friction component, third friction component and the 4th either rolling friction component The structure disclosed in the structure of friction component and the patent of Publication No. CN106308039A is identical, and details are not described herein.
The desktop 10 is fixed with the synchronization mechanism in the synchronization lifting mechanism.Crossbeam in desktop 10 and synchronization mechanism 70 is fixed.
The working process of the utility model is as follows: when needing to make the desktop of desk to rise, the first lifting is opened by switch Power is transferred to first axle 301, the second lifting driving by driver 30 and the second lift actuator 31, the first lift actuator 30 Power is transferred to the second axis 311 by device 31, and first axle 301 and the second axis drive crossbeam 70, desktop 10, first support ontology 411 Rise with second support ontology 421, since the first pivoting part 412 and the second pivoting part 413 pass through first axle 301 and first Rack body 411, the first pivoting part 412 and the second pivoting part 413 pass through first axle 301 and first support ontology 411, the Three pivoting parts 414 are connect by the first mandrel with first support ontology 411, the 4th pivoting part 422 and the 5th pivoting part 423 pass through the second mandrel and first support ontology by the second axis 311 and second support ontology 421, the 6th pivoting part 424 421 connections, therefore when first support ontology 411 and second support ontology 421 rise, the revolution of the first pivoting part 412, second Component 413, third pivoting part 414 rise in company with first support ontology 411, third pivoting part 422, the 4th pivoting part 423, the 4th pivoting part 424 rises in company with first support ontology 421, and the first connector 51 and the second connector 61 cannot move Dynamic, at this moment, the spacing between the first connector 51 and third pivoting part 414 becomes smaller, the second connector 61 and the 6th rotating part Spacing between part 424 becomes smaller, and the first pivoting part 412 and the 5th pivoting part 423 form the first flexible traction component 42 Upward pulling force effect forces the first flexible traction component 42 mobile, and mobile direction is the first pivoting part 412 to the 5th time 423 direction of rotation member is mobile, and the second pivoting part 413 and the 4th pivoting part 422 are to 43 shape of the second flexible traction component At upward pulling force effect, force the second flexible traction component 43 mobile, mobile direction is the 4th pivoting part 422 to second 413 direction of pivoting part is mobile, in this way, when the first lift actuator 30 and the second lift actuator 31 rise, first Flexible traction component 42 and the second flexible traction component 43 lead the first lift actuator 30 and the formation of the second lift actuator 31 Production is used, so that the first lift actuator 30 is synchronous with the rising of the second lift actuator 31.Conversely, when the first lifting is driven When dynamic device 30 and the second lift actuator 31 decline, similarly, the first flexible traction component 42 and the second flexible traction component 43 Restraining function is formed to the first lift actuator 30 and the second lift actuator 31, so that the first lift actuator 30 and second liter It is synchronous for dropping the decline of driver 31.
Second embodiment
The present invention is not limited to the above embodiments, for example, the both ends of the first support 40 and second support 41 are equal Be respectively equipped with the slot being arc-shaped, the first flexible traction component 42 and the second flexible traction component 43 respectively with first support With the slot cooperation in second support.Such mode does not need to install the first pivoting part in first support 40 412, second times Rotation member 413, third pivoting part 414 do not need to install the revolution of the 4th pivoting part the 422, the 5th in second support 41 yet Component 423, the 6th pivoting part 424.In this manner, when the first flexible traction component 42 and the second flexible traction component When 43 use strip-shaped members or cord-like component, formed between the first flexible traction component 42 and first support 40 and second support 41 Face contact, when the first flexible traction component 42 is mobile, the first flexible traction component 42 and the second flexible traction component 43 with The frictional force of forming face and face between first support 40 and second support 41.When the first flexible traction component 42 and the second flexibility are led Line face is formed when drawing component 43 using steel wire, between the first flexible traction component 42 and first support 40 and second support 41 to connect Touching, when the first flexible traction component 42 is mobile, in the first flexible traction component 42 and the second flexible traction component 43 and first The frictional force of line and face is formed between bracket 40 and second support 41.In such mode, no matter the first flexible traction component 42 With the second flexible traction component 43 using strip-shaped members or cord-like component or steel wire, the first flexible traction component 42 and second is flexible When traction element 43 is mobile and the frictional force between first support 40 and second support 41 is all larger than rubbing in first embodiment Power is wiped, therefore, preferentially uses the structure of first embodiment in actual use.
The case where synchronous lifting device of the utility model is suitable for desk is illustrated above by embodiment, however, this The synchronous lifting device of utility model is not limited to use on desk, can also be on chair or other need the occasion that goes up and down Carry out using.

Claims (10)

1. synchronization lifting mechanism, including it is the first lift actuator, the second lift actuator, fixing pipe in first, fixed in second Pipe, which is characterized in that further include that the first lift actuator and the second lift actuator is made to synchronize the synchronization mechanism of lifting, together Walking mechanism includes:
The first support connecting with the lift side of the first lift actuator, first support rise with the lifting of the first lift actuator Drop;
The second support connecting with the lift side of the second lift actuator, second support rise with the lifting of the second lift actuator Drop;
One end of first flexible traction component, the first flexible traction component is fixedly connected with fixing pipe in second, and first is flexible For traction element flexibly and after the cooperation of the other end of one end of second support, one end of first support, first support, first is flexible The other end of traction element is fixedly connected with fixing pipe in first;
One end of second flexible traction component, the second flexible traction component is fixedly connected with fixing pipe in first, and second is flexible For traction element flexibly and after the cooperation of the other end of one end of first support, one end of second support, second support, second is flexible The other end of traction element is fixedly connected with fixing pipe in second.
2. synchronization lifting mechanism according to claim 1, which is characterized in that fixing pipe includes the first inner tube in described first And first connector, the first connector are located in the first inner tube and fix with the first inner tube, the first flexible traction component it is another One end is fixedly connected with the first connector, and one end of the second flexible traction component is fixedly connected with the first connector;
Fixing pipe includes the second inner tube and the second connector in described second, and the second connector is located in the second inner tube and with the Two inner tubes are fixed, and one end of the first flexible traction component is fixedly connected with the second connector, the second flexible traction component it is another End is fixedly connected with the second connector.
3. synchronization lifting mechanism according to claim 1, which is characterized in that a part of first support is located at solid in first Determine in pipe, a part of second support is located in second in fixing pipe.
4. according to claim 1 to synchronization lifting mechanism described in one of 3, which is characterized in that first support includes:
First support ontology;
It is installed in rotation on first pivoting part of first support ontology one end;
It is installed in rotation on second pivoting part of first support ontology one end;
It is installed in rotation on the third pivoting part of the first support ontology other end;
Second support includes: second support ontology;
It is installed in rotation on the 4th pivoting part of second support ontology one end;
It is installed in rotation on the 5th pivoting part of second support ontology one end;
It is installed in rotation on the 6th pivoting part of the second support ontology other end;
The first flexible traction component and the 5th pivoting part, the first pivoting part and third pivoting part flexibility cooperate;
The second flexible traction component and the second pivoting part, the 4th pivoting part and the 6th pivoting part cooperate.
5. synchronization lifting mechanism according to claim 4, which is characterized in that the first pivoting part, the second pivoting part, Three pivoting parts, the 4th pivoting part, the 5th pivoting part, the 6th pivoting part are bearing or one of idler wheel or sprocket wheel.
6. synchronization lifting mechanism according to claim 5, which is characterized in that the first pivoting part, the second pivoting part, When three pivoting parts, the 4th pivoting part, the 5th pivoting part, the 6th pivoting part are bearing or idler wheel, bearing or idler wheel Outer circumference surface is equipped with groove.
7. according to claim 1 to synchronization lifting mechanism described in one of 3, which is characterized in that the first flexible traction component It is respectively cord-like component or strip-shaped members or one of steel wire or chain with the second flexible traction component.
8. according to claim 1 to synchronization lifting mechanism described in one of 3, which is characterized in that the first support and second The both ends of frame are respectively equipped with the slot being arc-shaped, and the first flexible traction component and the second flexible traction component are respectively with Slot cooperation on one bracket and second support.
9. according to claim 1 to synchronization lifting mechanism described in one of 3, which is characterized in that further include:
Crossbeam, one end of crossbeam and the lift side of the first lift actuator are fixed, the other end of crossbeam and the second lift actuator Lift side fix;
The first fixed movable outer tube of one end and one end of crossbeam, the first activity outer tube sleeve is in first in fixing pipe;
The second fixed movable outer tube of the other end of one end and crossbeam, the second activity outer tube sleeve is in second in fixing pipe.
10. a kind of desk, including desktop, which is characterized in that further include synchronous liter as claimed in any one of claims 1 to 9 Descending mechanism, the desktop are fixed with the synchronization mechanism in the synchronization lifting mechanism.
CN201821038979.1U 2018-07-02 2018-07-02 Synchronization lifting mechanism and desk Active CN209017982U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821038979.1U CN209017982U (en) 2018-07-02 2018-07-02 Synchronization lifting mechanism and desk

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821038979.1U CN209017982U (en) 2018-07-02 2018-07-02 Synchronization lifting mechanism and desk

Publications (1)

Publication Number Publication Date
CN209017982U true CN209017982U (en) 2019-06-25

Family

ID=66870033

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821038979.1U Active CN209017982U (en) 2018-07-02 2018-07-02 Synchronization lifting mechanism and desk

Country Status (1)

Country Link
CN (1) CN209017982U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108703495A (en) * 2018-07-02 2018-10-26 江苏捷尔特智能气动系统有限公司 Synchronous lifting mechanism and table
US11160365B2 (en) * 2019-04-16 2021-11-02 Jiangsu Jelt Lifting System Co., Ltd. Synchronizing lifter and lifting table

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108703495A (en) * 2018-07-02 2018-10-26 江苏捷尔特智能气动系统有限公司 Synchronous lifting mechanism and table
US11160365B2 (en) * 2019-04-16 2021-11-02 Jiangsu Jelt Lifting System Co., Ltd. Synchronizing lifter and lifting table

Similar Documents

Publication Publication Date Title
CN108703495A (en) Synchronous lifting mechanism and table
CN209017982U (en) Synchronization lifting mechanism and desk
CN110051116A (en) Synchronous lifter and lifting table
CN100419205C (en) Constant force actuator
CN109315925A (en) Synchronous lifting mechanism
CN108555881A (en) One kind can minor-circle turn hanger rail robot climbing apparatus
CN101683295B (en) Automatic turnover bed
CN105819366A (en) Lifting device
CN101392793A (en) Cycle rolling guiding mechanism and cycle ball guide apparatus
CN209463542U (en) Synchronization lifting mechanism
CN102950600A (en) Manipulator
CN205441785U (en) Transfer chain elevating gear
CN208514488U (en) One kind can minor-circle turn hanger rail robot climbing apparatus
CN210407552U (en) Synchronous lifter and lifting table
CN215756184U (en) Robot loading elevating gear
CN213838203U (en) Window glass lifter and vehicle
CN102588423A (en) Chained flexible push rod
CN105538319A (en) Lion dance robot
CN204591235U (en) A kind of chain drive commutates short support times journey long stroke pumping unit
CN204038305U (en) Semi-automatic lifting shelf
CN105909763B (en) Rack assembly and conveying line assembly
CN210029075U (en) Novel turning machine
CN217483720U (en) Electric actuator output interface device with upset function
CN207432862U (en) A kind of drag chain cladding system
CN200989122Y (en) Automatic springback rotary door

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20220525

Address after: 213000 No. 18, Fuxing South Road, Jintan District, Changzhou City, Jiangsu Province

Patentee after: Jiangsu Jiete Intelligent Furniture Co.,Ltd.

Address before: 213000 168 Huacheng Road, Jintan District, Changzhou, Jiangsu

Patentee before: JIANGSU JELT LIFTING SYSTEM Co.,Ltd.

TR01 Transfer of patent right