CN208968465U - A kind of full grout sleeve anchorage length of steel bar detection device - Google Patents

A kind of full grout sleeve anchorage length of steel bar detection device Download PDF

Info

Publication number
CN208968465U
CN208968465U CN201821870982.XU CN201821870982U CN208968465U CN 208968465 U CN208968465 U CN 208968465U CN 201821870982 U CN201821870982 U CN 201821870982U CN 208968465 U CN208968465 U CN 208968465U
Authority
CN
China
Prior art keywords
reinforcing bar
member reinforcing
grout sleeve
full grout
length
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821870982.XU
Other languages
Chinese (zh)
Inventor
潘春宇
梁刚
袁葵
卓旬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NANJING HUAJIAN INDUSTRIAL EQUIPMENT INSTALLATION DETECTION AND DEBUGGING Co.,Ltd.
China Construction Industrial and Energy Engineering Group Co Ltd
Original Assignee
Nanjing Huajian Industrial Equipment Installation Detection And Debugging Co Ltd
China Construction Industrial Equipment Installation Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanjing Huajian Industrial Equipment Installation Detection And Debugging Co Ltd, China Construction Industrial Equipment Installation Co Ltd filed Critical Nanjing Huajian Industrial Equipment Installation Detection And Debugging Co Ltd
Priority to CN201821870982.XU priority Critical patent/CN208968465U/en
Application granted granted Critical
Publication of CN208968465U publication Critical patent/CN208968465U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses a kind of full grout sleeve anchorage length of steel bar detection devices, it is characterized in that, including grout outlet, be in the milk mouth, upper member reinforcing bar, lower member reinforcing bar, rubber stopper, full grout sleeve, grouting material, direct-flow double bridge, test connects part, the test connects part and is arranged inside the full grout sleeve, the test connects part and is connected on the upper member reinforcing bar, the part that the upper member reinforcing bar stretches out the full grout sleeve is equipped with the first tie point, the part that the lower member reinforcing bar stretches out the full grout sleeve is equipped with the second tie point, the direct-flow double bridge is linked together by conducting wire and first tie point and the second tie point.The test, which connects part, does not influence grouting quality, as long as the anchorage length of reinforcing bar is enough, direct-flow double bridge can show resistance readings when circuit is connected, to realize the on-site test of full grout sleeve anchorage length of steel bar.

Description

A kind of full grout sleeve anchorage length of steel bar detection device
Technical field
The utility model relates to the anchorage length detection field of reinforcing bar more particularly to a kind of full grout sleeve Bar Anchorage are long Spend detection device.
Background technique
Grout sleeve is by the assembly for sleeve, mating grouting material and the reinforcing bar assembling specially processed, and the technology of connection is former Reason is: after reinforcing bar is inserted into sleeve, mating grouting material being poured into sleeve, full of the gap between sleeve and reinforcing bar, grouting material hardening It tightly engages, and the effective force between reinforcing bar and sleeve, i.e., connects two reinforcing bars with reinforcing bar cross rib and sleeve lining formation afterwards It is connected together.Sleeve grouting connector have many advantages, such as reliable performance, applicability extensively, simple installation.Grout sleeve interconnection technique is suitable For engineering fields such as reinforced concrete structure, bridge structures.
The both ends of full grout sleeve connector are all made of grouting way connection reinforcing bar, and it is current that full grout sleeve applicability is wide Most popular one kind sleeve grouting joint form, applies in general to the steel of vertical member (wall, column) and cross member (beam) Muscle connection.
Anchorage length of steel bar refers to that suffered power is passed to concrete by the bonding of concrete and rebar by steel bar stress Required length, if reinforcing steel bar bear cannot effectively pass to anchoring body without enough anchorage lengths, to guarantee reinforcing bar Power transmission effect should specifically anchor condition to the shadow of adhesion strength according to the stress condition of reinforcing bar, protective layer thickness, reinforcing bar form etc. It rings, the anchorage length of reinforcing bar is determined by code requirement.
The anchorage length of reinforcing bar is the key point of assembled arthitecutral structure quality control, is directly related to the entirety of building Structure safety.Based on process control, construction site there is no specific detection method for the detection of anchorage length, lead to not determine Whether the anchorage length of full grout sleeve reinforcing bar meets code requirement, and the stress of reinforcing bar is effectively passed to anchor to not can guarantee Solid.
Utility model content
The purpose of this utility model is to provide a kind of full grout sleeve anchorage length of steel bar detection devices, which can be real The now construction site detection of full grout sleeve anchorage length.
The utility model provides a kind of full grout sleeve anchorage length of steel bar detection device, which is characterized in that including going out Starch mouth, grouting mouth, upper member reinforcing bar, lower member reinforcing bar, rubber stopper, full grout sleeve, grouting material, direct-flow double bridge, test Connect part, wherein the full grout sleeve includes prefabricated components end and situ configuration end, the outside at the prefabricated components end Top is provided with the grout outlet, and the outer lower end at the situ configuration end is provided with the grouting mouth, the prefabricated components end Inside top is sealed by the rubber stopper;The upper member reinforcing bar and the lower member reinforcing bar are placed on the full grout sleeve Inside, there are cavity between the upper member reinforcing bar and the lower member reinforcing bar, the test connects part and is arranged described In cavity, the upper member reinforcing bar passes through conducting wire with the described one end of lower member reinforcing bar far from the cavity respectively and is connected to, described The direct-flow double bridge is provided on conducting wire.
Further, it is the first extension that the upper member reinforcing bar, which stretches out the prefabricated components end, is located at described pre- It is the first reservation part inside member end processed, it is the second extension that the lower member reinforcing bar, which stretches out the situ configuration end, Point, it is second to retain part inside the situ configuration end, the test contact connectio part is fixedly connected on described the One retains on part;First extension is provided with the first tie point, and second extension is provided with the second connection Point, the direct-flow double bridge are linked together by conducting wire and first tie point and the second tie point.
Using grouting connection type between prefabricated components end and upper member reinforcing bar, between situ configuration end and lower member reinforcing bar Using grouting connection type;When factory-made component, by abrasive machine, the protective paint of upper member steel bar end is polished;Pacifying Before dress, the reserved lower member in construction site is end reinforced to be also required to polish protective paint, with this guarantee upper and lower member reinforcing steel bar with Test connects being reliably connected between part, and upper member reinforcing bar, lower member reinforcing bar, test is allowed to connect part and direct current both arms Galvanic circle is formed between electric bridge, reduces the resistance between upper and lower member reinforcing steel bar and test contact connectio part.
Further, a kind of structure that the test connects part is only made of spring, when use the spring and institute It states the first reservation part to be reliably connected, guarantees that the test during transportation and construction connects part and will not fall off.
Further, another structure that the test connects part is made of spring and reinforced cap, wherein the steel Muscle cap is made of tagger, and the tagger thickness is about 1mm, and has screw thread, and the inside and surface of the reinforced cap exist Described the first of screw thread retains part and connects, while the outboard end of the reinforced cap is attached with the spring, is guaranteed Test described in transport and work progress connects part and will not fall off.
It is only to test dedicated that test, which connects part, does not undertake any load.Test connects part setting and is being in the milk entirely Upper member reinforcing bar is connected together with lower member reinforcing bar with spring, has no effect on grouting quality by the inside of sleeve.
Further, the length when spring is non-telescope is L2+2mm, and wherein L2 is the length of the cavity.
The rigidity of spring is enough, guarantees that the position changing of the relative positions or deformation do not occur for spring in filling process.Once spring is filling The position changing of the relative positions or deformation occur during slurry, it will causing upper and lower member reinforcing steel bar and test to connect between part cannot can The connection leaned on, and then circuit breaker, direct-flow double bridge can not show resistance readings, be unfavorable for the detection of anchorage length.
Further, after the grouting material enters the full grout sleeve from the grouting mouth, the upper member reinforcing bar The length contacted with the grouting material is the first anchorage length, and the length that the lower member reinforcing bar is contacted with the grouting material is the Two anchorage lengths, second anchorage length are the anchorage length to be detected.
After grouting is completed and grouting material reaches some strength, by conducting wire by the first tie point and the second tie point and Direct-flow double bridge links together.The length of full grout sleeve can measure, and the first anchorage length can be before construction according to specification It is required that pre-setting.When execute-in-place, when the second anchorage length is the length for meeting code requirement, test connects part It contacting with lower member reinforcing bar, whole device is a system at this time, and the external direct-flow double bridge can show resistance readings, this The anchorage length of Shi Yaoqiu detection can be subtracted the anchorage length of upper member reinforcing bar by the length of full grout sleeve, then subtract cavity It is obtained after length.
The beneficial effects of the utility model are:
The utility model proposes test connect part the inside of full grout sleeve be set, with spring by upper member steel Muscle is connected together with lower member reinforcing bar, has no effect on grouting quality;The rigidity of spring is enough, guarantees that spring is not in filling process The position changing of the relative positions or deformation occurs.
After grouting is completed and the grouting material reaches some strength, connected by the first tie point described in conducting wire and second Point and direct-flow double bridge link together, if upper member reinforcing bar and the anchorage length of lower member reinforcing bar are enough, test Connecting part can contact with lower member reinforcing bar, and whole device is a system at this time, and external direct-flow double bridge can show electricity Resistance reading.When direct-flow double bridge shows resistance readings, the circuit for illustrating that the utility model designs is switched on, because of test contact The rigidity of spring in connector is enough, guarantees that the position changing of the relative positions or deformation do not occur for spring in filling process, circuit connects meaning Taste the length of cavity at this time be the length set in advance according to code requirement, then the full grout sleeve of measurement can be passed through Length, then subtract the length of cavity at this time, then subtract the anchorage length of upper member reinforcing bar, so that it may detect the second anchoring Whether length is the anchorage length for meeting code requirement.
What the utility model used is the method that measures indirectly to detect the anchorage length of full grout sleeve reinforcing bar, with this side Method can determine whether anchorage length of steel bar is enough inside full grout sleeve, build to realize and pour the above assembled of thickness 300mm Build the on-site test of the full grout sleeve anchorage length of steel bar of connecting elements.
Detailed description of the invention
The present invention will be further described with reference to the accompanying drawing.
Fig. 1 is a kind of structural schematic diagram of full grout sleeve anchorage length of steel bar detection device of the utility model;
Fig. 2 is the case study on implementation one that test described in the utility model connects part;
Fig. 3 is the case study on implementation two that test described in the utility model connects part.
In figure: 1- grout outlet, 2- grouting mouth, 3- upper member reinforcing bar, 4- lower member reinforcing bar, 5- rubber stopper, 6- are in the milk set entirely Cylinder, 7- grouting material, 8- direct-flow double bridge, 9- test contact connectio part, 91- spring, 92- reinforced cap, 10- cavity, 61- are prefabricated Member end, 62- situ configuration end, the first extension of 31-, 32- first retain part, the second extension of 41-, 42- second Retain part, the first tie point of 301-, the second tie point of 401-.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work Every other embodiment obtained, fall within the protection scope of the utility model.
Fig. 1~3 are please referred to, the purpose of this utility model is to provide a kind of full grout sleeve anchorage length of steel bar detection dresses It sets, which is characterized in that including grout outlet 1, grouting mouth 2, upper member reinforcing bar 3, lower member reinforcing bar 4, rubber stopper 5, full grout sleeve 6, grouting material 7, direct-flow double bridge 8, test connect part 9, wherein the full grout sleeve 6 includes prefabricated components end 61 With situ configuration end 62, the outer tip end at the prefabricated components end 61 is provided with the grout outlet 1, the situ configuration end 62 Outer lower end is provided with the grouting mouth 2, and the 61 inside top of prefabricated components end is sealed by the rubber stopper 5;The upper structure Part reinforcing bar 3 and the lower member reinforcing bar 4 are placed on the inside of the full grout sleeve 6, the upper member reinforcing bar 3 and the lower structure There are cavity 10 between part reinforcing bar 4, the test connects part 9 and is arranged in the cavity 10,3 He of upper member reinforcing bar The one end of the lower member reinforcing bar 4 far from the cavity 10 is connected to by conducting wire respectively, is provided with the direct current on the conducting wire Double bridge 8.
It is the first extension 31 that the upper member reinforcing bar 3, which stretches out the prefabricated components end 61, is located at the prefabricated structure It is the first reservation part 32 inside part end 61, it is the second stretching that the lower member reinforcing bar 4, which stretches out the situ configuration end 62, Part 41, is the second reservation part 42 inside the situ configuration end 62, and the test connects part 9 and is fixedly connected Retain on part 32 described first;First extension 31 is provided with the first tie point 301, second extension 41 are provided with the second tie point 401, and the direct-flow double bridge 8 is connect by conducting wire with first tie point 301 and second Point 401 links together.
Using grouting connection type, situ configuration end 62 and lower member steel between prefabricated components end 61 and upper member reinforcing bar 3 Using grouting connection type between muscle 4;When factory-made component, by abrasive machine, the protective paint of 3 end of upper member reinforcing bar is ground Light;Before the mounting, reserved 4 end of lower member reinforcing bar in construction site is also required to polish protective paint, guarantees upper and lower structure with this Part reinforcing bar and test connect being reliably connected between part 9, and upper member reinforcing bar 3, lower member reinforcing bar 4, test is allowed to connect Galvanic circle is formed between part 9 and direct-flow double bridge 8, reduces the electricity between upper and lower member reinforcing steel bar and test contact connectio part 9 Resistance.
Test connects part 9 and links together there are two types of mode with upper member reinforcing bar 3 or lower member reinforcing bar 4, a kind of Mode is will to test to connect on the upper member reinforcing bar 3 after part 9 is connected to polishing, then prefabricated together with full grout sleeve 6; Another way is will to test contact connectio part 9 to connect with lower member reinforcing bar at the construction field (site).
A kind of structure that the test connects part 9 is only made of spring 91, and the spring 91 retains with described first Part 32 is reliably connected, and guarantees that the test during transportation and construction connects part and will not fall off.
Another structure that the test connects part 9 is made of spring 91 and reinforced cap 92, wherein the reinforced cap 92 are made of tagger, and the tagger thickness is about 1mm, and have screw thread, and the inside and surface of the reinforced cap 92 exist The upper member reinforcing bar 3 of screw thread connects, while the outboard end of the reinforced cap 92 is attached with the spring 91, guarantees The test connects part and will not fall off during transportation and construction.
It is only to test dedicated that test, which connects part 9, does not undertake any load, test connects the setting of part 9 and filling entirely The inside for starching sleeve 6, upper member reinforcing bar 3 is connected together, have no effect on grouting quality with spring 91 with lower member reinforcing bar 4.
The length when spring 91 is non-telescope is L2+2mm, and wherein L2 is the length of the cavity 10.
The rigidity of spring is enough, guarantees that the position changing of the relative positions or deformation do not occur for spring in filling process.Once spring is filling The position changing of the relative positions or deformation occur during slurry, it will causing upper and lower member reinforcing steel bar and test to connect between part cannot can The connection leaned on, and then circuit breaker, direct-flow double bridge can not show resistance readings, be unfavorable for the detection of anchorage length.
When the grouting material 7 from the grouting mouth 2 enter full grout sleeve 6 after, the upper member reinforcing bar 3 with it is described The length that grouting material 7 contacts is the first anchorage length, and the length that the lower member reinforcing bar 4 is contacted with the grouting material 7 is second Anchorage length, second anchorage length are the anchorage length to be detected.
After grouting is completed and grouting material reaches some strength, by conducting wire by the first tie point and the second tie point and Direct-flow double bridge links together.The length of full grout sleeve can measure, and the first anchorage length can be before construction according to specification It is required that pre-setting.When execute-in-place, when the second anchorage length is the length for meeting code requirement, test connects part It contacting with lower member reinforcing bar, whole device is a system at this time, and the external direct-flow double bridge can show resistance readings, this The anchorage length of Shi Yaoqiu detection can be subtracted the anchorage length of upper member reinforcing bar by the length of full grout sleeve, then subtract cavity It is obtained after length.
The working principle of the utility model is:
The utility model proposes test connect part the inside of full grout sleeve be set, with spring by upper member steel Muscle is connected together with lower member reinforcing bar, has no effect on grouting quality;The rigidity of spring is enough, guarantees that spring is not in filling process The position changing of the relative positions or deformation occurs.
After grouting is completed and the grouting material reaches some strength, connected by the first tie point described in conducting wire and second Point and direct-flow double bridge link together, if upper member reinforcing bar and the anchorage length of lower member reinforcing bar are enough, test Connecting part can contact with lower member reinforcing bar, and whole device is a system at this time, and external direct-flow double bridge can show electricity Resistance reading.When direct-flow double bridge shows resistance readings, the circuit for illustrating that the utility model designs is switched on, because of test contact The rigidity of spring in connector is enough, guarantees that the position changing of the relative positions or deformation do not occur for spring in filling process, circuit connects meaning Taste the length of cavity at this time be the length set in advance according to code requirement, then the full grout sleeve of measurement can be passed through Length, then subtract the length of cavity at this time, then subtract the anchorage length of upper member reinforcing bar, so that it may detect lower member steel Whether the anchorage length of muscle is the anchorage length for meeting code requirement.
What the utility model used is the method that measures indirectly to detect the anchorage length of full grout sleeve reinforcing bar, with this side Method can determine whether anchorage length of steel bar is enough inside full grout sleeve, build to realize and pour the above assembled of thickness 300mm Build the on-site test of the full grout sleeve anchorage length of steel bar of connecting elements.
It is obvious to a person skilled in the art that the present invention is not limited to the details of the above exemplary embodiments, and And without departing substantially from the spirit or essential attributes of the utility model, it can realize that this is practical new in other specific forms Type.Therefore, in all respects, the present embodiments are to be considered as illustrative and not restrictive, this is practical new The range of type is indicated by the appended claims rather than the foregoing description, it is intended that containing for the equivalent requirements of the claims will be fallen in All changes in justice and range are embraced therein.It should not treat any reference in the claims as limiting Related claim.

Claims (6)

1. a kind of full grout sleeve anchorage length of steel bar detection device, which is characterized in that including grout outlet (1), grouting mouth (2), Upper member reinforcing bar (3), lower member reinforcing bar (4), rubber stopper (5), full grout sleeve (6), grouting material (7), direct-flow double bridge (8), test connects part (9), wherein the full grout sleeve (6) includes prefabricated components end (61) and situ configuration end (62), the outer tip end of the prefabricated components end (61) is provided with the grout outlet (1), the outside of the situ configuration end (62) Bottom end is provided with the grouting mouth (2), and top is sealed by the rubber stopper (5) on the inside of the prefabricated components end (61);On described Member reinforcing steel bar (3) and the lower member reinforcing bar (4) are arranged in the inside of the full grout sleeve (6), the upper member reinforcing bar (3) There are cavity (10) between the lower member reinforcing bar (4), the test connects part (9) and is arranged in the cavity (10) Interior, the one end of the upper member reinforcing bar (3) and the lower member reinforcing bar (4) far from the cavity (10) is connected by conducting wire respectively It is logical, the direct-flow double bridge (8) are provided on the conducting wire.
2. a kind of full grout sleeve anchorage length of steel bar detection device according to claim 1, which is characterized in that on described It is the first extension (31) that member reinforcing steel bar (3), which stretches out the prefabricated components end (61), is located at the prefabricated components end (61) Inside is the first reservation part (32), and it is the second stretching that the lower member reinforcing bar (4), which stretches out the situ configuration end (62), Partially (41), being located inside the situ configuration end (62) is the second reservation part (42), and the test connects part (9) Described first is fixedly connected on to retain on part (32);First extension (31) is provided with the first tie point (301), institute It states the second extension (41) to be provided with the second tie point (401), the direct-flow double bridge (8) passes through conducting wire and described first Tie point (301) and the second tie point (401) link together.
3. a kind of full grout sleeve anchorage length of steel bar detection device according to claim 2, which is characterized in that the survey It tries and touches connector (9) and be made of spring (91), the spring (91) retains part (32) with described first and is attached.
4. a kind of full grout sleeve anchorage length of steel bar detection device according to claim 2, which is characterized in that the survey It tries and touches connector (9) and be made of spring (91) and reinforced cap (92), the reinforced cap (92) and the spring (91) are fixed connects It connects, the reinforced cap (92) retains part (32) with described first and is connected through a screw thread.
5. a kind of full grout sleeve anchorage length of steel bar detection device according to claim 4, which is characterized in that the bullet The length of spring (91) is L2+2mm, and L2 is the length of the cavity (10).
6. a kind of full grout sleeve anchorage length of steel bar detection device according to claim 5, which is characterized in that when described After grouting material (7) is from the grouting mouth (2) into the full grout sleeve (6), the upper member reinforcing bar (3) and the grouting material (7) length contacted is the first anchorage length (L0), and the length that the lower member reinforcing bar (4) contacts with the grouting material (7) is Second anchorage length (L1), second anchorage length (L1) are the anchorage length to be detected.
CN201821870982.XU 2018-11-13 2018-11-13 A kind of full grout sleeve anchorage length of steel bar detection device Active CN208968465U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821870982.XU CN208968465U (en) 2018-11-13 2018-11-13 A kind of full grout sleeve anchorage length of steel bar detection device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821870982.XU CN208968465U (en) 2018-11-13 2018-11-13 A kind of full grout sleeve anchorage length of steel bar detection device

Publications (1)

Publication Number Publication Date
CN208968465U true CN208968465U (en) 2019-06-11

Family

ID=66765322

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821870982.XU Active CN208968465U (en) 2018-11-13 2018-11-13 A kind of full grout sleeve anchorage length of steel bar detection device

Country Status (1)

Country Link
CN (1) CN208968465U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109387141A (en) * 2018-11-13 2019-02-26 中建安装工程有限公司 A kind of full grout sleeve anchorage length of steel bar detection device

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109387141A (en) * 2018-11-13 2019-02-26 中建安装工程有限公司 A kind of full grout sleeve anchorage length of steel bar detection device
CN109387141B (en) * 2018-11-13 2024-03-08 中建安装工程有限公司 Full grouting sleeve steel bar anchoring length detection device

Similar Documents

Publication Publication Date Title
CN106501495B (en) The detection device and detection method of grouting material compactness in a kind of sleeve
CN104153287B (en) There is the section assembling concrete frame bridge pier system and method for self-resetting capability
CN208968464U (en) A kind of half grout sleeve anchorage length of steel bar detection device
CN108978449A (en) A kind of connector uses the spigot-and-socket construction precast assembly bridge pier of grout sleeve
CN103590414B (en) A kind of attachment structure of concrete tubular pile and cushion cap
CN208105022U (en) Assembled bridge pier and prefabricated assembled beam bridge
CN208968465U (en) A kind of full grout sleeve anchorage length of steel bar detection device
CN110409304A (en) A kind of precast segment bent cap free cantilever erection construction method
CN109579679A (en) A kind of half grout sleeve anchorage length of steel bar detection device
CN205617661U (en) Short sleeve grout steel bar connection connects and connecting sleeve and pressure -bearing ring that have thereof
CN108411769A (en) A kind of assembled device of prefabricated pier shaft and prefabricated bent cap
CN110185199A (en) A kind of half grouting connection sleeve of the automatic deviation correction for prefabricated post wall
CN204435906U (en) Planting reinforced bar into concrete device
CN104790388B (en) A kind of prefabricated pile mechanical connecting structure and attaching method thereof
CN106522272A (en) Design and construction method of underground pipe rack based on plate with adhesive prestress on cross section
CN111764931A (en) High-ground-stress weak surrounding rock tunnel supporting structure and construction method thereof
CN108442236A (en) Assembled bridge pier and construction method, prefabricated assembled beam bridge
CN107560950B (en) Device for measuring shear stress of interface of prestressed anchor rod and test method thereof
CN104912000B (en) A kind of method realizing bridge pad scene fast-assembling
CN109024973B (en) Connecting structure for prefabricated shear wall and construction method thereof
CN109387141A (en) A kind of full grout sleeve anchorage length of steel bar detection device
CN109611135A (en) A kind of Novel hollow cross grouting anchor rod device and application method
CN209603183U (en) A kind of precast assembly pipe gallery groove and tognue type joint waterproofing construction
US20190119819A1 (en) Method for laying an anode system for cathodic corrosion protection
CN106245765A (en) Slip casting joint steel pipe apparatus structure and method of attachment

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 210023 Zhongjian Building, No. 6 Wenlan Road, Qixia District, Nanjing City, Jiangsu Province

Co-patentee after: NANJING HUAJIAN INDUSTRIAL EQUIPMENT INSTALLATION DETECTION AND DEBUGGING Co.,Ltd.

Patentee after: CHINA CONSTRUCTION INDUSTRIAL & ENERGY ENGINEERING GROUP Co.,Ltd.

Address before: 210023 Zhongjian Building, No. 6 Wenlan Road, Qixia District, Nanjing City, Jiangsu Province

Co-patentee before: NANJING HUAJIAN INDUSTRIAL EQUIPMENT INSTALLATION DETECTION AND DEBUGGING Co.,Ltd.

Patentee before: CCEED INDUSTRIAL EQUIPMENT INSTALLATION Co.,Ltd.