CN208900854U - Insulated wall wall pipe waterproof construction - Google Patents
Insulated wall wall pipe waterproof construction Download PDFInfo
- Publication number
- CN208900854U CN208900854U CN201821389315.XU CN201821389315U CN208900854U CN 208900854 U CN208900854 U CN 208900854U CN 201821389315 U CN201821389315 U CN 201821389315U CN 208900854 U CN208900854 U CN 208900854U
- Authority
- CN
- China
- Prior art keywords
- wall
- anchor ear
- wall pipe
- support frame
- insulated
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Building Environments (AREA)
Abstract
The utility model relates to the realm of building construction, aiming at the problem that the waterproof thermal-insulated leakproofness of existing insulated wall wall pipe, provide a kind of insulated wall wall pipe waterproof construction, the technical solution is as follows: a kind of insulated wall wall pipe waterproof construction, including wall and wall pipe, anchor ear is socketed on the wall pipe, support frame is extended on the anchor ear, the support frame as described above other end is fixedly connected with pedestal, it is hollow structure in shown anchor ear and support frame, support frame as described above is equipped with several discharge holes, is additionally provided with grouting port on support frame as described above.By adopting the above technical scheme, water-proof thermal insulation material is injected in anchor ear by grouting port, and then is squeezed out from the discharge hole of anchor ear, to be full of entire mounting hole, make to improve waterproof thermal-insulated effect full of water-proof thermal insulation material between mounting hole and wall pipe.
Description
Technical field
The utility model relates to the realm of building construction, more specifically, it relates to a kind of insulated wall wall pipe waterproof construction.
Background technique
In Contemporary Architecture, it is often necessary to have the laying of cable tubing or the installation of water pipe, be needed in these pipelines
When installation is with being laid with, the case where pipeline is run through wall in need sometimes, occurs, therefore especially wears on insulated wall
Wall pipe, need to sealing and waterproof work have higher requirement.
But during installing due to wall pipe, need first to punch in the prior art general, and due to construction
Reason inevitably has some gaps between mounting hole and wall pipe, even if having filled up water-proof thermal insulation material, be also difficult to be filled up completely
In gap between mounting hole and wall pipe, so cause to be extremely difficult to maintain between hole and wall pipe very high waterproof with
And heat insulation effect, therefore in this aspect, still there is certain room for improvement.
Utility model content
In view of the deficienciess of the prior art, the purpose of this utility model is to provide a kind of insulated wall wall pipe waterproof knots
Structure has the advantages that water-proof thermal insulation material can be made to be sufficient filling with full mounting hole.
To achieve the above object, the utility model provides following technical solution:
A kind of insulated wall wall pipe waterproof construction, including wall and wall pipe are socketed with anchor ear on the wall pipe, institute
It states and is extended with support frame on anchor ear, the support frame as described above other end is fixedly connected with pedestal, and it is hollow that shown anchor ear is interior with support frame
Structure, support frame as described above are equipped with several discharge holes, are additionally provided with grouting port on support frame as described above.
By adopting the above technical scheme, wall pipe is fixed by anchor ear and wall is fixed on by the support frame that anchor ear extends
In the hole accomplished fluently, so that wall pipe be enabled to be capable of fixing the position in hole, make wall pipe will not downward shift, then pass through grouting port
Water-proof thermal insulation material is injected in anchor ear, and then is squeezed out from the discharge hole on support frame, since support frame is located at the peace of wall
It fills in hole, so that water-proof thermal insulation material is full of entire mounting hole, makes between the inner wall of mounting hole and wall pipe full of waterproof
Heat-barrier material greatly improves waterproof thermal-insulated effect.
Preferably, support frame as described above is retractable structure.
By adopting the above technical scheme, the different situation in aperture caused by different Construction Conditions can be adapted to.
Preferably, the retractable structure includes rod set, the body of rod and the elastic component in compressive state, and the rod set is remote
One end from anchor ear is fixedly connected with pedestal, and the elastic component drives rod set to separate with the body of rod.
By adopting the above technical scheme, it is acted on using the elastic force of elastic component, enables rod set that can offset with hole wall with pedestal, improve
Whole support performance, can also there is certain positioning action to wall pipe.
Preferably, the rod set has a flange close to one end fold inward of anchor ear, the one end of the body of rod far from anchor ear to
Outer fold has chimb.
By adopting the above technical scheme, when making not falling out between rod set and the body of rod, while slip casting can be improved, the connection
The leakproofness of position also can increase the capacity for the waterproof and sealing material filled in support frame, improve steady after the completion of Cementer is made
It is qualitative.
Preferably, the anchor ear and support frame are provided with 2 along the axial direction of wall pipe.
By adopting the above technical scheme, the stress of wall pipe can be made more evenly, and two anchor ears carry out slip casting simultaneously, also can
Improve the efficiency of overall work.
Preferably, connecting rod is connected between the anchor ear, the connecting rod is hollow structure, and the connecting rod is connected to anchor ear
It is interior.
By adopting the above technical scheme, the internal cavities between anchor ear are connected by connecting rod, and then only need to be to anchor ear
Grouting port carries out slip casting work, and slip casting work can be completed.
Preferably, the connecting rod includes outer bar and interior bar, and the outer bar is socketed in outside interior bar, the inner wall of the outer bar with it is interior
The outer wall of bar is bonded.
By adopting the above technical scheme, connecting rod use stretching structure, can be adapted to different wall thicknesses be adjusted its anchor ear it
Between distance.
Preferably, the wall pipe is equipped with water deflector cover, and described water deflector cover one end offsets with wall, and the water deflector cover passes through
Screw is fixed on the wall.
By adopting the above technical scheme, using water deflector cover by the gap between wall pipe and mounting hole, so reduce water from its
In a possibility that leaking into.
Preferably, gasket is provided between the water deflector cover and wall.
By adopting the above technical scheme, enhance the sealing performance between water deflector cover and wall.
Preferably, the outer wall of the wall is equipped with insulating layer.
By adopting the above technical scheme, the intracorporal temperature of wall is enable to preferably keep.
In conclusion the utility model has the following beneficial effects:
Fixed 1. being supported using anchor ear to wall pipe, make wall pipe will not due to its gravity and completely by the material filled into
Row support, it, which is effectively reduced, leads to the separation of link position due to deformation;
2. using the cavity structure and grouting port and discharge hole of anchor ear to being filled water-proof thermal insulation material in mounting hole,
Being filled from inside makes filling substantially reduce the discontented probability of filling;
3. being supported by two anchor ears to wall pipe and being filled to mounting hole, improve efficiency;
4. the support frame of anchor ear uses retractable structure, it can be adapted to different size of mounting hole, construction is reduced and cause
Error;
5. insulating layer is added and water deflector cover improves integral heat insulation and waterproof performance.
Detailed description of the invention
Fig. 1 is the schematic diagram of internal structure of the utility model;
Fig. 2 is part A enlarged diagram in Fig. 1;
Fig. 3 is the utility model anchor ear part overall schematic.
Appended drawing reference: 1, wall;11, insulating layer;2, wall pipe;31, gasket;32, water deflector cover;4, anchor ear;41, it supports
Frame;411, rod set;412, the body of rod;42, pedestal;43, discharge hole;44, grouting port;5, connecting rod;51, outer bar;52, interior bar;6, bullet
Property part;61, compressed spring.
Specific embodiment
With reference to the accompanying drawings and embodiments, the utility model is described in further detail.
A kind of 2 waterproof construction of insulated wall wall pipe, referring to Fig.1 and Fig. 3, including wall 1 and wall pipe 2, on wall 1
The mounting hole passed through for wall pipe 2 is offered, anchor ear 4 is socketed on wall pipe 2,4 support frames 41 are extended on anchor ear 4, is propped up
Support 41 is fixedly connected with pedestal 42 far from one end of anchor ear 4, and pedestal 42 and the hole wall of mounting hole offset.Referring to Fig.1 and scheme
2, anchor ear 4 and support frame 41 are hollow structure, several discharge holes 43 and a grouting port 44 are offered on support frame 41,
The through-hole being connected to grouting port 44 is offered on wall 1.
It is also equipped with insulating layer 11 on the outer wall of wall 1, and is stamped at the connection gap of wall 1 and wall pipe 2
Water deflector cover 32 is lined with gasket 31 between water deflector cover 32 and wall 1, and benefit is screwed just on wall 1.
Anchor ear 4 is symmetrically arranged with 2 in mounting hole, and connecting rod 5 is connected between anchor ear 4, and connecting rod 5 is all hollow structure,
And it is connected to the cavity of two anchor ears 4.Connecting rod 5 includes outer bar 51 and interior bar 52, and outer bar 51 is socketed at the outer wall of interior bar 52, makes
Connecting rod 5 is retractable structure.
The support frame 41 of anchor ear 4 is also retractable structure, and support frame 41 is including rod set 411, the body of rod 412 and in compression
The elastic component 6 of state, rod set 411 are set in the outside of the body of rod 412 and one end far from anchor ear 4 and are fixedly connected with pedestal 42,
Interior bar 52 is fixedly connected and is connected to anchor ear 4 close to one end of anchor ear 4.Rod set 411 is close to one end of anchor ear 4 into rod set 411
Portion's fold has flange, and interior bar 52 thinks that fold has chimb, the edge and rod set 411 of chimb outside interior bar 52 far from one end of anchor ear 4
Inner wall fitting.Elastic component 6 is located in rod set 411 and in compressive state, and one end of elastic component 6 is in rod set 411 and pedestal
42 offset, and the other end offsets with interior bar 52 far from one end of anchor ear 4.In the present embodiment, elastic component 6 is compressed spring 61.
Water swelling sealing strip material can be used in 31 material of gasket, the material in the dry state with it is general solid close
Seal strip is no difference, and upon contact with water, can be absorbed moisture and be expanded rapidly, can sufficiently block water deflector cover 32 and wall 1
Between gap, to improve its waterproof performance.
The operating condition and principle of the present embodiment are as follows:
When installation, mounting hole is opened up on wall 1 first, after then anchor ear 4 is socketed on wall pipe 2, is led to
It crosses and manually 4 support frame 41 of anchor ear is squeezed, pack up support frame 41 and be put into mounting hole.When anchor ear 4 and support frame 41
After being put into mounting hole, the rod set 411 of support frame 41 is since the elastic force of compressed spring 61 acts on, and to the side far from anchor ear 4
To stretching, offset with mounting hole.And another anchor ear 4 is put into also with same method to mounting hole, then utilizes connecting rod 5
Retractable structure adjusts 4 position of anchor ear, is symmetrically in it more in wall 1, installs preparation at this time and completes.
Later only need to be by the way that water-proof thermal insulation material to be injected from grouting port 44, after injection, water-proof thermal insulation material is not due to
It is disconnected to be pushed, it is circulated in two anchor ears 4, and squeeze out from the discharge hole 43 on anchor ear 4 to mounting hole, and then fill full peace
Fill the gap in hole.And support frame 41 is also due to receiving the extruding of water-proof thermal insulation material, and then its retractable structure is pushed,
So that maintaining a certain distance between rod set 411 and the body of rod 412, enable the gravity of wall pipe 2 will not be completely by full of in mounting hole
Water-proof thermal insulation material bear, improve its whole structural behaviour, be able to maintain the structure more permanent.
It is last water deflector cover 32 and gasket 31 only to be installed to wall 1, by the gap between wall pipe 2 and wall 1
It blocks, carries out last waterproof sealing, overall structure can be completed.
The final waterproof construction includes wall 1 and wall pipe 2, and anchor ear 4 is supported by between wall pipe 2 and wall 1, and
And filled out between wall pipe 2 and wall 1 and be filled with water-proof thermal insulation material, 1 outer wall of wall is equipped with insulating layer 11, the outer wall of wall 1
Gasket 31 and water deflector cover 32 are stamped at inner wall and 2 link position of wall pipe.
This specific embodiment is only the explanation to the utility model, is not limitations of the present invention, ability
Field technique personnel can according to need the modification that not creative contribution is made to the present embodiment after reading this specification, but
As long as all by the protection of Patent Law in the scope of the claims of the utility model.
Claims (10)
1. a kind of insulated wall wall pipe waterproof construction, including wall (1) and wall pipe (2), it is characterized in that: the wall pipe
(2) it is socketed on anchor ear (4), is extended with support frame (41) on the anchor ear (4), support frame as described above (41) other end is fixedly connected
Have pedestal (42), is hollow structure in shown anchor ear (4) and support frame (41), support frame as described above (41) is equipped with several dischargings
Hole (43) is additionally provided with grouting port (44) on support frame as described above (41).
2. insulated wall wall pipe waterproof construction according to claim 1, it is characterized in that: support frame as described above (41) is scalable
Structure.
3. insulated wall wall pipe waterproof construction according to claim 2, it is characterized in that: the retractable structure includes rod set
(411), the body of rod (412) and the elastic component (6) in compressive state, the rod set (411) one end and bottom far from anchor ear (4)
Seat (42) is fixedly connected, and the elastic component (6) drives rod set (411) to separate with the body of rod (412).
4. insulated wall wall pipe waterproof construction according to claim 3, it is characterized in that: the rod set (411) is close to anchor ear
(4) one end fold inward has flange, and the body of rod (412) turns down outward far from the one end of anchor ear (4) chimb.
5. insulated wall wall pipe waterproof construction according to claim 1, it is characterized in that: the anchor ear (4) and support frame
(41) axial direction of wall pipe (2) is provided with 2.
6. insulated wall wall pipe waterproof construction according to claim 5, it is characterized in that: being connected between the anchor ear (4)
Connecting rod (5), the connecting rod (5) are hollow structure, and the connecting rod (5) is connected in anchor ear (4).
7. insulated wall wall pipe waterproof construction according to claim 6, it is characterized in that: the connecting rod (5) includes outer bar
(51) with interior bar (52), the outer bar (51) is socketed in interior bar (52) outside, the inner wall of the outer bar (51) and interior bar (52) it is outer
Wall fitting.
8. insulated wall wall pipe waterproof construction according to claim 1, it is characterized in that: the wall pipe (2) is equipped with gear
Water cover (32), described water deflector cover (32) one end offset with wall (1), and the water deflector cover (32) is fixed by screws in wall (1)
On.
9. insulated wall wall pipe waterproof construction according to claim 8, it is characterized in that: the water deflector cover (32) and wall
(1) gasket (31) are provided between.
10. insulated wall wall pipe waterproof construction according to claim 1, it is characterized in that: the outer wall of the wall (1) is laid with
There are insulating layer (11).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821389315.XU CN208900854U (en) | 2018-08-25 | 2018-08-25 | Insulated wall wall pipe waterproof construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821389315.XU CN208900854U (en) | 2018-08-25 | 2018-08-25 | Insulated wall wall pipe waterproof construction |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208900854U true CN208900854U (en) | 2019-05-24 |
Family
ID=66570527
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201821389315.XU Expired - Fee Related CN208900854U (en) | 2018-08-25 | 2018-08-25 | Insulated wall wall pipe waterproof construction |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208900854U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110886908A (en) * | 2019-12-10 | 2020-03-17 | 泰能天然气有限公司 | High-stability stainless steel corrugated hose wall outlet device for gas conveying |
-
2018
- 2018-08-25 CN CN201821389315.XU patent/CN208900854U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110886908A (en) * | 2019-12-10 | 2020-03-17 | 泰能天然气有限公司 | High-stability stainless steel corrugated hose wall outlet device for gas conveying |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110409635B (en) | Outer wall expansion joint structure and installation method thereof | |
CN205047833U (en) | Waterproof seal structure | |
CN203891899U (en) | Hollow filling-type rubber gasket | |
CN208900854U (en) | Insulated wall wall pipe waterproof construction | |
CN106088982A (en) | A kind of novel aluminum alloy fire window | |
CN204214191U (en) | A kind of door seal structure for refrigeration plant | |
CN103115205A (en) | Sliding-compact-type pipe fitting for aluminum-plastic pipe | |
CN206815627U (en) | Curtain wall installs node structure | |
CN107700537A (en) | The mobile water-stopping system and application method of FS final spice | |
CN110106987A (en) | A kind of the heat retaining and insulated waterproof device and its application method of the vertical edge joint position of PC wallboard | |
CN209163124U (en) | A kind of wall male and female collection structure of good heat insulating | |
CN201376600Y (en) | Aluminum profile for sealing expansion module | |
CN203718249U (en) | Conduit joint with threaded insert | |
CN208535155U (en) | A kind of combined sealed device | |
CN206055936U (en) | A kind of frost-cracking-preventing heater | |
CN205445414U (en) | Sealing device at bottom of high leakproofness door | |
CN209144656U (en) | It is a kind of suitable for PE sheath expands with heat and contract with cold outside drag-line water-tight device | |
CN204089101U (en) | Cordwood system type cable penetration holes blocking | |
CN209538420U (en) | A kind of waterproof construction of assembled integrated house | |
CN216078634U (en) | Pipeline wall-penetrating sealing device for building structure | |
CN206448407U (en) | A kind of external decoration Glass Rib | |
CN205977015U (en) | Indoor silence door assembly | |
CN209724155U (en) | A kind of sealing structure of outdoor window | |
CN205689965U (en) | Pipe joint and connecting line | |
CN211902012U (en) | PE manages leak protection connection structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20190524 Termination date: 20200825 |