CN208898251U - High temperature silk production line postprocessing working procedures steel wire storage device - Google Patents

High temperature silk production line postprocessing working procedures steel wire storage device Download PDF

Info

Publication number
CN208898251U
CN208898251U CN201821452214.2U CN201821452214U CN208898251U CN 208898251 U CN208898251 U CN 208898251U CN 201821452214 U CN201821452214 U CN 201821452214U CN 208898251 U CN208898251 U CN 208898251U
Authority
CN
China
Prior art keywords
upright post
channel steel
wire storage
steel upright
steel wire
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821452214.2U
Other languages
Chinese (zh)
Inventor
郑文青
吴学丙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HENAN REBECCA HAIR PRODUCTS Inc
Original Assignee
HENAN REBECCA HAIR PRODUCTS Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HENAN REBECCA HAIR PRODUCTS Inc filed Critical HENAN REBECCA HAIR PRODUCTS Inc
Priority to CN201821452214.2U priority Critical patent/CN208898251U/en
Application granted granted Critical
Publication of CN208898251U publication Critical patent/CN208898251U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Unwinding Of Filamentary Materials (AREA)

Abstract

High temperature silk production line postprocessing working procedures steel wire storage device, including vertically disposed left channel steel upright post and right channel steel upright post, the opening of left channel steel upright post and right channel steel upright post is oppositely arranged, fixed frame is provided between left channel steel upright post and the top of right channel steel upright post, godet roller there are four being evenly arranged in left-right direction on front side of fixed frame, fixed frame lower horizontal is provided with cross bar between left channel steel upright post and right channel steel upright post, the left end of cross bar is provided with the wheel assembly that rolls left for rolling and being connected to left channel steel upright post inner wall, the right end of cross bar is provided with the right roll wheel assembly for rolling and being connected to right channel steel upright post inner wall, there are three steel wire storage wheels for setting on front side of cross bar, each steel wire storage wheel is respectively positioned on the underface between two neighboring godet roller.The utility model is designed reasonably, simple structure, be easily installed, stability is strong when steel wire storage amount is big, steel wire storage wheel moves up and down, and there is good security reliability.

Description

High temperature silk production line postprocessing working procedures steel wire storage device
Technical field
The utility model belongs to hair technical field of fibre production, and in particular to a kind of high temperature silk production line postprocessing working procedures Steel wire storage device.
Background technique
High temperature silk be one kind can wig resistant to high temperature, high temperature silk wig is resistant to the following high temperature of 180 degree, can secondary moulding, easily It arranges, reflectance is medium, moderate.The post-processing of high temperature silk includes the processes such as drawing-off, cooling, sizing.The tow of high temperature silk It is wound on bobbin after post-processing, after winding full on bobbin, needs replacing bobbin, when more change of bobbins needs certain Between, and therefore steel wire storage device, existing steel wire storage dress is arranged in post treatment production line continuously operation always on front side of bobbin It is poor to set stability, steel wire storage wheel can shake during steel wire storage, and steel wire storage amount is smaller, and slightly slow some steel wire storage wheels are just when change of bobbins It can fall to the ground, lead to wrapping, or even shut down, seriously affect being normally carried out for operation.
Utility model content
The utility model provides that a kind of stability is good, steel wire storage amount is big, can fill to solve shortcoming in the prior art Divide the high temperature silk production line postprocessing working procedures steel wire storage device for meeting the bobbin change time.
In order to solve the above technical problems, the utility model adopts the following technical solution: high temperature silk production line postprocessing working procedures Steel wire storage device, including vertically disposed left channel steel upright post and right channel steel upright post, the opening phase of left channel steel upright post and right channel steel upright post To setting, fixed frame is provided between left channel steel upright post and the top of right channel steel upright post, fixed frame front side is uniform in left-right direction There are four godet rollers for arrangement, and fixed frame lower horizontal is provided with cross bar between left channel steel upright post and right channel steel upright post, cross bar Left end is provided with the wheel assembly that rolls left for rolling and being connected to left channel steel upright post inner wall, and the right end of cross bar is provided with rolling and is connected to right slot The right roll wheel assembly of steel column inner wall, for the setting of cross bar front side there are three steel wire storage wheel, each steel wire storage wheel is respectively positioned on two neighboring seal wire Underface between wheel.
Cross bar includes left pipe and right pipe, and right pipe left side is slideably inserted into the pipe of left by the right end of left pipe, The top and bottom of left pipe right side are threaded with clamping screw, and inner end and the press of right pipe outer wall of clamping screw are matched It closes, three steel wire storage wheels are installed on front side of the pipe of left.
The left part of left pipe is arranged in the wheel assembly that rolls left, and the right part of right pipe is arranged in right roll wheel assembly;Left wheel Component is identical with the construction of right roll wheel assembly and is symmetrical set;
The wheel assembly that rolls left includes first bearing, upper wheel carrier and lower wheel carrier, and round tube is inserted with inside the pipe left end of left, and round tube is left End is extend into left channel steel upright post, and the inner ring of first bearing is mounted on round tube, before first bearing outer ring and left channel steel upright post Side inner wall and rear side inner wall roll connection, and upper wheel carrier is fixedly connected on the top of left pipe left end, and lower wheel carrier is fixedly connected on a left side The left end of the bottom of square tube left end, the left end of upper wheel carrier and lower wheel carrier is provided with second bearing, the outer ring and a left side of second bearing The slot bottom inner wall of channel steel upright post rolls connection.
Upper and lower part in left channel steel upright post is respectively arranged with the upper limit with upper wheel carrier and lower wheel carrier touch fit respectively Bit switch and lower position switch.
By adopting the above technical scheme, the utility model have following originality and the utility model has the advantages that
The tow of high temperature silk successively bypasses the godet roller of the leftmost side from left to right, bypasses the steel wire storage wheel of the leftmost side still further below, Then upwards about second, rear left side godet roller, according to this winding mode, most the godet roller through the rightmost side lays out and twines tow afterwards On bobbin.After bobbin winds full tow, tow is cut, first uses clip temporarily to fix on the head of cutting, will twine The bobbin of full tow is removed, and replaces an empty bobbin, then the tow of cutting head is wound on new bobbin again.It is replacing During bobbin, post treatment production line is not shut down, and in cross bar, three steel wire storage wheels, roll left wheel assembly and right roll wheel assembly itself Under the action of gravity, the tow entered in steel wire storage device is just pulled downwardly, and the first bearing and second bearing in left side are along left slot Steel column moves down, and the first bearing and second bearing on right side are moved down along right channel steel upright post, and tow is just stored into phase Between adjacent steel wire storage wheel and godet roller, after bobbin change, bobbin first improves revolving speed, and the tow of storage is first wound into cylinder as early as possible Guan Shang, tow just will pull cross bar, three steel wire storage wheels, roll left wheel assembly and right roll wheel assembly moves up, to cross bar, three storages Silk wheel rolls left wheel assembly and after right roll wheel assembly is moved upwards up to certain altitude, the revolving speed of bobbin is restored to be produced with post-processing The revolving speed of the tow of line conveying is consistent.
Using left pipe and two section of right pipe, left pipe and right pipe are connected as one cross bar by clamping screw, synchronous to rise Drop.When installation or removal, it can unscrew or tighten clamping screw, right pipe is moved to the left or right, convenient for the wheel assembly that rolls left It protrudes into or takes out out of left channel steel upright post, right roll wheel assembly is protruded into or taken out out of right channel steel upright post.
First bearing can guarantee that cross bar does not move in the longitudinal direction, and setting second bearing can guarantee cross bar in left and right directions On do not move, so that it is guaranteed that stability of the steel wire storage wheel in lifting process.
Upper limit switch and lower position switch play the role of effective protection production line steady production.When upper wheel carrier touches When upper limit switch, the revolving speed of bobbin is reduced at once, when wheel carrier touches lower position switch instantly, to improve bobbin at once Revolving speed.
In conclusion the utility model is designed reasonably, simple structure, be easily installed, steel wire storage amount is big, steel wire storage wheel moves up and down When stability it is strong, and have good security reliability.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the utility model.
Specific embodiment
As shown in Figure 1, the high temperature silk production line postprocessing working procedures steel wire storage device of the utility model, including a vertically disposed left side The opening of channel steel upright post 1 and right channel steel upright post 2, left channel steel upright post 1 and right channel steel upright post 2 is oppositely arranged, left channel steel upright post 1 and the right side Fixed frame 3 is provided between the top of channel steel upright post 2,3 front side of fixed frame is evenly arranged in left-right direction there are four godet roller 4, 3 lower horizontal of fixed frame is provided with cross bar between left channel steel upright post 1 and right channel steel upright post 2, the left end of cross bar is provided with rolling It is connected to the wheel assembly that rolls left of left 1 inner wall of channel steel upright post, the right end of cross bar is provided with rolling and is connected to right 2 inner wall of channel steel upright post Right roll wheel assembly, there are three steel wire storage wheel 5, each steel wire storage wheel 5 is respectively positioned between two neighboring godet roller 4 just the setting of cross bar front side Lower section.
Cross bar includes left pipe 6 and right pipe 7, and pipe 7 left side in right is slideably inserted into left by the right end of left pipe 6 and manages In 6, the top and bottom of 6 right side of left pipe are threaded with clamping screw 8, outside the inner end of clamping screw 8 and right pipe 7 Wall press cooperation, three steel wire storage wheels 5 are installed in 6 front side of left pipe.
The left part of left pipe 6 is arranged in the wheel assembly that rolls left, and the right part of right pipe 7 is arranged in right roll wheel assembly;It rolls left Wheel assembly is identical with the construction of right roll wheel assembly and is symmetrical set;
The wheel assembly that rolls left includes first bearing 9, upper wheel carrier 10 and lower wheel carrier 11, and left pipe is inserted with round tube inside 6 left end, Round tube left end is extend into left channel steel upright post 1, and the inner ring of first bearing 9 is mounted on round tube, 9 outer ring of first bearing and left channel steel The front inner wall and rear side inner wall of column 1 roll connection, and upper wheel carrier 10 is fixedly connected on the top of 6 left end of left pipe, lower wheel carrier 11 are fixedly connected on the bottom of 6 left end of left pipe, and the left end of the left end of upper wheel carrier 10 and lower wheel carrier 11 is provided with second bearing 12, the slot bottom inner wall rolling of the outer ring of second bearing 12 and left channel steel upright post 1 connects.
Upper and lower part in left channel steel upright post 1 be respectively arranged with respectively with upper wheel carrier 10 and lower 11 touch fit of wheel carrier Upper limit switch 13 and lower position switch 14.
The working process of the utility model is as follows: the tow 15 of high temperature silk successively bypasses the godet roller 4 of the leftmost side from left to right, The steel wire storage wheel 5 for bypassing the leftmost side still further below, then upwards about second, rear left side godet roller 4, according to this winding mode, tow 15 most the godet roller 4 through the rightmost side lays out and is wound on bobbin afterwards.After bobbin winds full tow 15, tow 15 is cut, First use clip temporarily to fix on the head of cutting, the bobbin for being wrapped over tow 15 removed, replace an empty bobbin, then again The tow 15 for cutting head is wound on new bobbin.During more change of bobbins, post treatment production line is not shut down, cross bar, Under the action of three steel wire storage wheels 5, roll left wheel assembly and right roll wheel assembly self gravity, tow 15 in steel wire storage device is entered just It is pulled downwardly, the first bearing 9 and second bearing 12 in left side are moved down along left channel steel upright post 1, the first bearing 9 on right side and Two bearings 12 are moved down along right channel steel upright post 2, and tow 15 is just stored between adjacent steel wire storage wheel 5 and godet roller 4, work as cylinder After pipe replacement, bobbin first improves revolving speed, and the tow 15 of storage is first wound on bobbin as early as possible, tow 15 just will pull cross bar, Three steel wire storage wheels 5 roll left wheel assembly and right roll wheel assembly moves up, to cross bar, three steel wire storage wheels 5, roll left wheel assembly and the right side After roll wheel assembly is moved upwards up to certain altitude, the revolving speed of bobbin is restored to the revolving speed with the tow 15 of post treatment production line conveying Unanimously.
Left pipe 6 and right pipe 7 are connected as one by cross bar using left pipe 6 and 7 liang of right pipe sections, clamping screw 8, together Step lifting.When installation or removal, it can unscrew or tighten clamping screw 8, right pipe 7 is moved to the left or right, convenient for rolling left Wheel assembly is protruded into or is taken out out of left channel steel upright post 1, and right roll wheel assembly is protruded into or taken out out of right channel steel upright post 2.
First bearing 9 can guarantee that cross bar does not move in the longitudinal direction, and setting second bearing 12 can guarantee cross bar in left and right It is not moved on direction, so that it is guaranteed that stability of the steel wire storage wheel 5 in lifting process.
Upper limit switch 13 and lower position switch 14 play the role of effective protection production line steady production.When upper wheel carrier 10 When touching upper limit switch 13, the revolving speed that reduce bobbin at once wants horse when wheel carrier 11 touches lower position switch 14 instantly The upper revolving speed for improving bobbin.The structure and limit control principle of upper limit switch 13 and lower position switch 14 are existing mature skill Art specifically repeats no more.
The present embodiment not makes any form of restriction the shape of the utility model, material, structure etc., all foundations The technical essence of the utility model any simple modification, equivalent change and modification to the above embodiments, belong to this reality With the protection scope of new technique scheme.

Claims (4)

1. high temperature silk production line postprocessing working procedures steel wire storage device, it is characterised in that: including vertically disposed left channel steel upright post and the right side The opening of channel steel upright post, left channel steel upright post and right channel steel upright post is oppositely arranged, the top of left channel steel upright post and right channel steel upright post it Between be provided with fixed frame, be evenly arranged in left-right direction on front side of fixed frame there are four godet roller, left channel steel upright post and right channel steel are vertical Fixed frame lower horizontal is provided with cross bar between column, the left end of cross bar is provided with the left side for rolling and being connected to left channel steel upright post inner wall Roll wheel assembly, the right end of cross bar are provided with the right roll wheel assembly for rolling and being connected to right channel steel upright post inner wall, are provided on front side of cross bar Three steel wire storage wheels, each steel wire storage wheel are respectively positioned on the underface between two neighboring godet roller.
2. high temperature silk production line postprocessing working procedures steel wire storage device according to claim 1, it is characterised in that: cross bar includes a left side Square tube and right pipe, right pipe left side are slideably inserted into the pipe of left by the right end of left pipe, the top of left pipe right side It is threaded with clamping screw with bottom, the inner end of clamping screw and the press of right pipe outer wall cooperate, and three steel wire storage wheels are pacified On front side of the pipe of left.
3. high temperature silk production line postprocessing working procedures steel wire storage device according to claim 2, it is characterised in that: roll left wheel assembly The left part of left pipe is set, and the right part of right pipe is arranged in right roll wheel assembly;Roll left wheel assembly and right roll wheel assembly It constructs identical and is symmetrical set;
The wheel assembly that rolls left includes first bearing, upper wheel carrier and lower wheel carrier, is inserted with round tube inside the pipe left end of left, round tube left end is stretched Enter into left channel steel upright post, the inner ring of first bearing is mounted on round tube, in the front side of first bearing outer ring and left channel steel upright post Wall and rear side inner wall roll connection, and upper wheel carrier is fixedly connected on the top of left pipe left end, and lower wheel carrier is fixedly connected on left pipe The left end of the bottom of left end, the left end of upper wheel carrier and lower wheel carrier is provided with second bearing, the outer ring of second bearing and left channel steel The slot bottom inner wall of column rolls connection.
4. high temperature silk production line postprocessing working procedures steel wire storage device according to claim 3, it is characterised in that: left channel steel upright post Interior upper and lower part is respectively arranged with the upper limit switch and lower position switch with upper wheel carrier and lower wheel carrier touch fit respectively.
CN201821452214.2U 2018-09-06 2018-09-06 High temperature silk production line postprocessing working procedures steel wire storage device Active CN208898251U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821452214.2U CN208898251U (en) 2018-09-06 2018-09-06 High temperature silk production line postprocessing working procedures steel wire storage device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821452214.2U CN208898251U (en) 2018-09-06 2018-09-06 High temperature silk production line postprocessing working procedures steel wire storage device

Publications (1)

Publication Number Publication Date
CN208898251U true CN208898251U (en) 2019-05-24

Family

ID=66571580

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821452214.2U Active CN208898251U (en) 2018-09-06 2018-09-06 High temperature silk production line postprocessing working procedures steel wire storage device

Country Status (1)

Country Link
CN (1) CN208898251U (en)

Similar Documents

Publication Publication Date Title
CN203269219U (en) Constant tension active unwinding cone winding machine
CN204124946U (en) A kind of hank rewinder
CN105926048A (en) Silk reeling machine realizing automatic temperature control
CN102756471A (en) Oblique-winding guide device
CN208898251U (en) High temperature silk production line postprocessing working procedures steel wire storage device
CN203578404U (en) Separable spinning head
CN107142535A (en) The threading method and filament yarn winding apparatus of a kind of filament yarn winding apparatus
CN203359661U (en) Silk dividing device of silk dividing machine
CN208200007U (en) A kind of novel spinning winder
CN209723054U (en) A kind of transverse direction of composite geo-membrane gets rid of side device
CN208219083U (en) A kind of carbon fibre stretching device creel
CN207295025U (en) A kind of yarn guiding device of ring spinning frame
CN203112998U (en) Two-for-one twisting wet heating and shaping equipment for artificial silk
CN208444057U (en) Online duplication yarn rolls into a ball device
CN205295594U (en) Add and play machine coarse denier POY precursor backing -off tensions balance device
CN203174228U (en) Self-boosting assembly for preparing fine-denier chinlon
CN105603552B (en) A kind of step lifting head device of spinning high-speed winder one
CN209618494U (en) A kind of winding pneumatic shuttle of needle punched non-woven fabrics
CN204939682U (en) A kind of spandex heavy denier yarn godet system of constant seal wire distance
CN208615344U (en) It is a kind of for manufacturing the fiber rack of basalt fibre multiple tube
CN203612029U (en) Yarn hanging cart
CN203612701U (en) Screen taking-off device for metal screen weaving machine
CN203440510U (en) Yarn-guiding coiling system for heavy denier yarn
CN206396386U (en) A kind of intelligent yarn detects anti-broken yarn spinning frame
CN203284519U (en) Filament catching device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant