CN208860909U - A kind of overhead transmission line short-circuit impedance measuring device based on synchronous vector - Google Patents

A kind of overhead transmission line short-circuit impedance measuring device based on synchronous vector Download PDF

Info

Publication number
CN208860909U
CN208860909U CN201820822555.8U CN201820822555U CN208860909U CN 208860909 U CN208860909 U CN 208860909U CN 201820822555 U CN201820822555 U CN 201820822555U CN 208860909 U CN208860909 U CN 208860909U
Authority
CN
China
Prior art keywords
phase
transmission line
impedance relay
overhead transmission
impedance
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820822555.8U
Other languages
Chinese (zh)
Inventor
秦川
杨建伟
张耀宇
孔祥轩
刘杰荣
孙广慧
王伟冠
黄焯麒
何其淼
陆凯烨
陈君宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Power Grid Co Ltd
Foshan Power Supply Bureau of Guangdong Power Grid Corp
Original Assignee
Guangdong Power Grid Co Ltd
Foshan Power Supply Bureau of Guangdong Power Grid Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Power Grid Co Ltd, Foshan Power Supply Bureau of Guangdong Power Grid Corp filed Critical Guangdong Power Grid Co Ltd
Priority to CN201820822555.8U priority Critical patent/CN208860909U/en
Application granted granted Critical
Publication of CN208860909U publication Critical patent/CN208860909U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications
    • Y04S10/52Outage or fault management, e.g. fault detection or location

Landscapes

  • Emergency Protection Circuit Devices (AREA)

Abstract

The utility model relates to a kind of power system measuring devices, its measurement for being mainly used for all kinds of short-circuit impedances of overhead transmission line in electric system, it include three-phase impedance relay device, interphase impedance relay-set, three-phase impedance relay device, interphase impedance relay-set is electrically connected with current transformer and voltage transformer, current transformer and voltage transformer are electrically connected with synchronized phase measurement device, three-phase impedance relay device, interphase impedance relay-set is connected with the first processing unit, realize the measurement of all kinds of short-circuit voltages and electric current that overhead transmission line occurs, it is handled by the Current Voltage vector analysis to synchro measure, determine whether impedance relay acts, computing impedance is analyzed and determines fault type and fault location.

Description

A kind of overhead transmission line short-circuit impedance measuring device based on synchronous vector
Technical field
The utility model relates to a kind of power system measuring devices, and it is each to be mainly used for overhead transmission line in electric system The measurement of class short-circuit impedance.
Background technique
With the continuous development of smart grid, power distribution network operation scale is continued to increase, and operating structure is constantly complicated, and system is defeated The frequency that short trouble occurs in electric line is increasing.The situation that short circuit occurs in transmission line of electricity can be divided into following several: single-phase Shorted to earth, two relative ground circuits, phase fault and three-phase shortcircuit.The system (secondary network) of isolated neutral can be Operate with failure when single-phase short circuit 1-2 hours, and other short troubles occur when should all require the correct quick acting of breaker with Guarantee system safety.Moreover, system can be excluded by automatic reclosing for temporary short trouble, and it is some permanent Failure must be by manually excluding, and this requires systems, and fault point can be accurately positioned.The short trouble of conventional electrical distribution net Detection and location technology are suitable only for radiation type distribution network, are not suitable for network-type power distribution network.Meanwhile it is differential for bus current For protection, the current synchronization measuring problem at bus both ends is particularly important, as not being difference current mistake caused by synchro measure Accident that is big and then causing bus current differential protection to act happens occasionally.Therefore, short circuit fault of power distribution network orientation problem and The synchro measure problem of bus current voltage is to ensure that the key that circuit relay protection correctly acts.
Utility model content
The utility model in order to overcome at least one of the drawbacks of the prior art described above, provides a kind of based on synchronous vector Transmission line of electricity short-circuit impedance measuring device is handled by the Current Voltage vector analysis to synchro measure, determines impedance relay Whether act, computing impedance is analyzed and determines fault type and fault location.
In order to solve the above technical problems, the technical solution adopted in the utility model is: a kind of based on the aerial of synchronous vector Transmission line of electricity short-circuit impedance measuring device, wherein it include three-phase impedance relay device, interphase impedance relay-set, three Phase of impedance relay-set, interphase impedance relay-set are electrically connected with current transformer and voltage transformer, Current Mutual Inductance Device and voltage transformer are electrically connected with synchronized phase measurement device, three-phase impedance relay device, interphase impedance relay-set It is connected with the first processing unit, realizes the measurement of all kinds of short-circuit voltages and electric current that overhead transmission line occurs.
In the utility model, the sampling synchronized by synchronized phase measurement device to route both ends Current Voltage is kept away The work of the protective relaying maloperation as caused by data sampling asynchronous is exempted from.Pass through three-phase impedance relay device, interphase impedance relay Device differentiates all kinds of short troubles that overhead transmission line occurs, and judges whether breaker acts.Three phase of impedance after Electrical installation, interphase impedance relay-set are connected with the first processing unit, and the first processing unit receives three phase of impedance relays The electric signal of device device, interphase impedance relay-set, the first processing unit calculate short dot position by short-circuit impedance.
In one embodiment, synchronized phase measurement device is equipped with clock module, second processing device.
Preferably, the first processing unit and second processing device are equipped with processor and display device.First processing unit Processing result is shown with second processing device by processor processes information and by display device.
Preferably, clock module is equipped with clock, external GPS, inside GPS, cable 1PPS, optical fiber 1PPS on plate, and It is electrically connected with host CPU.
The effect of internal GPS is to ensure that equipment internal time is consistent.External GPS ensures GPS time and Coordinated Universal Time(UTC) UTC can be synchronized to nanosecond order.Cable 1PPS, optical fiber 1PPS are for providing PUM and telemechanical communication channel.Host CPU is based on Calculate and handle the data of measurement.
In one embodiment, three-phase impedance relay device, interphase impedance relay-set are all made of multiphase formula width It is worth circle characteristic impedance relay.
In one embodiment, current transformer model is LZZBJ9-10.
Preferably, three-phase impedance relay device, single-phase, voltage between phases measured by interphase impedance relay-set and Electric current is converted into electric signal transmission to host CPU.Host CPU receives three-phase impedance relay device, interphase impedance relay-set After the electric signal of transmission, by the way that short dot position is calculated.
Preferably, three-phase impedance relay device, single-phase, voltage between phases measured by interphase impedance relay-set and Electric current is converted into electric signal transmission to the first processing unit.First processing unit receive electric signal after, by electric signal into Row calculates, and realizes the judgement to fault point.
Preferably, the model Intel Xeon E5-2650 v4 of the first processing unit.
The utility model compared with prior art, has the following characteristics that three-phase impedance relay and interphase impedance relay Device completion differentiates all kinds of short troubles that overhead transmission line occurs, and determines whether breaker acts;And it is synchronous to Measuring device carries out the sample-synchronous of route both ends Current Voltage, avoids the guarantor of the relay as caused by data sampling asynchronous Shield malfunction.This device provides effective line fault method of discrimination, has to the accurate judgement of localization of fault and failure It helps, to improve the power supply reliability of power distribution network.
Detailed description of the invention
Fig. 1 is measuring device schematic illustration in the utility model embodiment.
Fig. 2 is synchronized phase measurement module composition schematic diagram in the utility model embodiment.
Specific embodiment
Attached drawing only for illustration, should not be understood as limiting the present invention;In order to more preferably illustrate this implementation Example, the certain components of attached drawing have omission, zoom in or out, and do not represent the size of actual product;For those skilled in the art For, the omitting of some known structures and their instructions in the attached drawings are understandable.Positional relationship is described in attached drawing to be only used for Exemplary illustration should not be understood as limiting the present invention.
Embodiment 1:
As shown in Figure 1, CT is current transformer, VT is voltage transformer, and PMU is synchronized phase measurement device.X is three-phase Impedance relay, Y are interphase impedance relay.
The utility model provides a kind of overhead transmission line short-circuit impedance measuring device based on synchronous vector, includes three Phase of impedance relay-set and interphase impedance relay-set, three-phase impedance relay device and interphase impedance relay-set point It is not electrically connected with the first processing unit, is communicated with the first processing unit.
Three-phase impedance relay device is connected with current transformer and voltage transformer, and interphase impedance relay-set also connects It is connected to current transformer and voltage transformer, current transformer and voltage transformer are connect with synchronized phase measurement device.
The synchronized sampling of current transformer and voltage transformer, synchronized phase measurement are controlled by synchronized phase measurement device Device and current transformer and voltage transformer are fitted to overhead transmission line two sides, to overhead transmission line two sides Voltage vector and current vector synchronize sampling.
Each phase current and voltage are converted into corresponding electric signal, and associated electrical signals focus on and are conveyed to three phase of impedance relays Device device and interphase impedance relay-set judge that route is sent out by three-phase impedance relay device and interphase impedance relay-set Which kind of type is raw failure belong to.Three-phase impedance relay device and interphase impedance relay-set are by electric signal transmission to first Processing unit carries out short-circuit impedance calculating by the first processing unit, realizes the judgement to short dot position.
Three-phase impedance relay device, interphase impedance relay-set are all made of multiphase formula amplitude circle characteristic impedance relay Device.
In the present embodiment, synchronized phase measurement device is equipped with clock module, second processing device.
First processing unit and second processing device are equipped with processor and display device, at the first processing unit and second Reason device shows processing result by processor processes information and by display device.
As shown in Fig. 2, clock module is equipped with clock, external GPS, inside GPS, cable 1PPS, optical fiber 1PPS on plate, and It is electrically connected with second processing device.The effect of internal GPS is to ensure that equipment internal time is consistent.When external GPS ensures GPS Between with Coordinated Universal Time(UTC) UTC can be synchronized to nanosecond order.Cable 1PPS, optical fiber 1PPS are logical for providing PUM and telemechanical communication Road.Second processing device is used to calculate and handle the data of measurement.
In the present embodiment, current transformer model is LZZBJ9-10, the model Intel Xeon of the first processing unit E5-2650 v4。
Obviously, the above embodiments of the present invention is merely examples for clearly illustrating the present invention, and It is not limitations of the embodiments of the present invention.For those of ordinary skill in the art, in above description On the basis of can also make other variations or changes in different ways.There is no need and unable to give all embodiments Exhaustion.Any modifications, equivalent replacements, and improvements made within the spirit and principle of the present invention etc., should be included in Within the protection scope of the utility model claims.

Claims (8)

1. a kind of overhead transmission line short-circuit impedance measuring device based on synchronous vector, which is characterized in that include three phase resistances Reactance relay device, interphase impedance relay-set, the three-phase impedance relay device, interphase impedance relay-set are electric It is connected with current transformer and voltage transformer, the current transformer and voltage transformer are electrically connected with synchronized phase measurement dress It sets, the three-phase impedance relay device, interphase impedance relay-set are connected with the first processing unit, realize defeated to making somebody a mere figurehead The measurement of all kinds of short-circuit voltages and electric current that electric line occurs.
2. the overhead transmission line short-circuit impedance measuring device according to claim 1 based on synchronous vector, feature exist In the synchronized phase measurement device is equipped with clock module, second processing device.
3. the overhead transmission line short-circuit impedance measuring device according to claim 2 based on synchronous vector, feature exist In first processing unit and second processing device are equipped with processor and display device.
4. the overhead transmission line short-circuit impedance measuring device according to claim 2 based on synchronous vector, feature exist Clock, external GPS, inside GPS, cable 1PPS, optical fiber 1PPS on plate are equipped in, the clock module, and with described the The electrical connection of two processing units.
5. the overhead transmission line short-circuit impedance measuring device according to claim 1 based on synchronous vector, feature exist In the three-phase impedance relay device, interphase impedance relay-set are all made of multiphase formula amplitude circle characteristic impedance relay.
6. the overhead transmission line short-circuit impedance measuring device according to claim 1 based on synchronous vector, feature exist In the current transformer model is LZZBJ9-10, voltage transformer model JDZX10-10.
7. the overhead transmission line short-circuit impedance measuring device according to any one of claims 1 to 6 based on synchronous vector, It is characterized in that, single-phase, voltage between phases and electric current measured by three-phase impedance relay device, interphase impedance relay-set Electric signal transmission is converted into the first processing unit.
8. the overhead transmission line short-circuit impedance measuring device according to any one of claims 1 to 6 based on synchronous vector, It is characterized in that, the model Intel Xeon E5-2650 v4 of first processing unit.
CN201820822555.8U 2018-05-30 2018-05-30 A kind of overhead transmission line short-circuit impedance measuring device based on synchronous vector Active CN208860909U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820822555.8U CN208860909U (en) 2018-05-30 2018-05-30 A kind of overhead transmission line short-circuit impedance measuring device based on synchronous vector

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820822555.8U CN208860909U (en) 2018-05-30 2018-05-30 A kind of overhead transmission line short-circuit impedance measuring device based on synchronous vector

Publications (1)

Publication Number Publication Date
CN208860909U true CN208860909U (en) 2019-05-14

Family

ID=66411468

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820822555.8U Active CN208860909U (en) 2018-05-30 2018-05-30 A kind of overhead transmission line short-circuit impedance measuring device based on synchronous vector

Country Status (1)

Country Link
CN (1) CN208860909U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108427058A (en) * 2018-05-30 2018-08-21 广东电网有限责任公司 It is a kind of based on synchronize vector overhead transmission line short-circuit impedance measuring device

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108427058A (en) * 2018-05-30 2018-08-21 广东电网有限责任公司 It is a kind of based on synchronize vector overhead transmission line short-circuit impedance measuring device

Similar Documents

Publication Publication Date Title
CN101943737B (en) Single-phase earth fault diagnosis method and device
CN101741070B (en) Method for pilot protection of circuit based on current capacity and voltage capacity at two ends
CN103814300B (en) For being monitored the system and method for electric power facility state by on-line measurement circuit parameter
CN106093700B (en) A kind of fault wave recording device and distance measuring method based on voltage traveling wave principle
CN102386678A (en) Fault positioning monitoring system for distribution network
CN102279323B (en) Secondary accurate phasing method for intelligent transformer station
CN106505533B (en) A kind of distance protection system and its control method suitable for half-wave power transmission route
CN110426593A (en) A kind of method for locating single-phase ground fault based on residual voltage starting
CN107462805A (en) A kind of short circuit fault of power distribution network protection and localization method
CN111044843B (en) Power transmission line fault positioning method based on multi-source data
CN109444657A (en) Method for positioning high-resistance grounding fault section of power distribution network
CN104820133A (en) Online measurement method for impedance parameter of three-phase asymmetric power transmission line
CN208860909U (en) A kind of overhead transmission line short-circuit impedance measuring device based on synchronous vector
CN108427058A (en) It is a kind of based on synchronize vector overhead transmission line short-circuit impedance measuring device
CN102540009A (en) Fault locating system of power distribution network
CN100563075C (en) Same lever/parallel double loop high resistance earthing protecting method and device
CN110907756B (en) System and method for positioning out-of-step oscillation center based on wide-area measurement impedance angle information
CN109596934A (en) A kind of double split-core type meter mensurations of secondary circuit multipoint earthing
CN104701830A (en) System and method for identifying overloads and system and method for protecting distances
CN106249108B (en) A kind of Fault Locating Method and positioning device of the AC in the DC system
JP2013090445A (en) Power system protection system
CN103424628A (en) Method for measuring parallel grid line positive sequence impedance
CN103199509B (en) Transmission line malfunction relay protecting method based on both-end positive sequence fundamental component
CN203811747U (en) A small current grounding line selection system
CN113346462B (en) Petal type power distribution network contact line protection method based on predicted voltage amplitude

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant