CN208792343U - The slope protective device of architectural engineering - Google Patents

The slope protective device of architectural engineering Download PDF

Info

Publication number
CN208792343U
CN208792343U CN201820956656.4U CN201820956656U CN208792343U CN 208792343 U CN208792343 U CN 208792343U CN 201820956656 U CN201820956656 U CN 201820956656U CN 208792343 U CN208792343 U CN 208792343U
Authority
CN
China
Prior art keywords
substrate
spring leaf
wall
intubation
protective device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820956656.4U
Other languages
Chinese (zh)
Inventor
乐颖辉
陈祖泽
杨春晓
阳柳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangxi Vocational Technical College of Industrial Engineering
Original Assignee
Jiangxi Vocational Technical College of Industrial Engineering
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangxi Vocational Technical College of Industrial Engineering filed Critical Jiangxi Vocational Technical College of Industrial Engineering
Priority to CN201820956656.4U priority Critical patent/CN208792343U/en
Application granted granted Critical
Publication of CN208792343U publication Critical patent/CN208792343U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses a kind of novel in structural design, easy to use, the slope protective device of architectural engineering that is easily assembled to, it includes the Slope protection plate being attached on foundation pit inner wall, through Slope protection plate and is inserted in the fixation kit of pars intramuralis in foundation pit, and the Slope protection plate is fixed on foundation pit inner wall by fixation kit.

Description

The slope protective device of architectural engineering
Technical field
The present invention relates to foundation pit protection technology field more particularly to a kind of slope protective devices of architectural engineering.
Background technique
In the prior art, carry out foundation pit excavation supporting in, the design of pattern foundation pit supporting structure directly influence the quality of engineering, Safety, efficiency and cost.And existing support system is mainly cast-in-situ steel reinforced concrete support and bracing members, cast in place reinforced bar coagulation Native support stiffness is high, deformation is small, safe and reliable, but its major defect is that construction period length, dismounting difficulty, material can not be multiple It reuses.And bracing members are with advantage detachable after installation, reusable, the development side of complying with standard and mechanization To although the larger defect there is also rigidity compared with little Yi unstability of bracing members intensity, due to the easy unstability of bracing members, in the branch of foundation pit It is frequently used for excavating shape in shield into narrow and strip stake foundation pit, the mode of another steel pipe bearing diagonal are as follows: complete first At going along with sb. to guard him for support pile, then slope is excavated on the inside of foundation pit, building outside slope sideline of constructing when being excavated to bottom of foundation ditch Main body is built, does steel pipe diagonal brace support at bottom plate after the completion of floor structure, then steel pipe diagonal brace is installed, finally excavates diagonal brace position Earthen platform reserved when slope is put, which is also applied for the shallow foundation pit of cutting depth, and since the pedestal of steel pipe support is being built It on the bottom plate of building structure, results in that the construction period is long, will drive the position of building bottom plate when foundation pit side-wall bears larger soil pressure It moves.
Summary of the invention
It is an object of the invention to overcome the deficiencies in the prior art, adapt to reality and need, provide a kind of novel in structural design, The slope protective device of architectural engineering that is easy to use, being easily assembled to.
In order to achieve the object of the present invention, the technical scheme adopted by the invention is as follows:
A kind of slope protective device of architectural engineering is designed, it includes the Slope protection plate being attached on foundation pit inner wall, runs through Slope protection plate and the fixation kit for being inserted in pars intramuralis in foundation pit, the Slope protection plate are fixed on foundation pit inner wall by fixation kit;
The fixation kit includes the perforation being opened on Slope protection plate, is coaxially disposed with perforation and is fixed on perforation outboard end Fixture nut in portion further includes an intubation, and it is hollow structure in intubation, and tail end is equipped with that the front end of the intubation, which is pointed, The socket being connected to inner hollow;The tail end of intubation is equipped with a fixing pipe, and fixing pipe and intubation are coaxially disposed, under fixing pipe Outer wall is held to be equipped with external screw thread, the upper end outer wall of fixing pipe is in positive hexagonal prism shape, and the inner wall of fixing pipe is equipped with internal screw thread;
The fixing pipe side wall is equipped at least two perforated tapes, is respectively equipped with a spring leaf, spring leaf in each perforated tape Lower end be fixedly connected with the lower end inner wall of perforated tape, the upper end of spring leaf is inserted in the intubation in perforated tape upper end, the bullet Reed is in the arcuation that middle part is arched upward, and the position arched upward in the middle part of spring leaf can be protruding to perforated outer by perforated tape;The bullet The lateral wall of reed is equipped with several burs;
Further include cylindrical pushing block, be equipped with interior hexagonal shrinkage pool in the tail end of the pushing block, on the side wall of the pushing block Equipped with screw thread, the pushing block is set in fixing pipe and connect with fixing pipe inner thread, and the end of the pushing block is against spring The end of piece, when the pushing block is promoted into intubation, the pushing block push the spring piece compression promotes to arch upward in the middle part of spring leaf And intubation outside is protruded by perforated tape.
It further include the push rod being connect with pushing block, the push rod is located in intubation, and the push rod is equipped with limited block, the limit Position block is located at the position in the middle part of spring leaf and is located inside the enclosed region of spring leaf.
The limited block is in ellipticity or spherical.
It is equipped with the spherical groove being recessed inwardly with the end of the pushing block of the spring leaf contact position, the end of spring leaf is against Inside of spherical groove.
The bur is obliquely installed, and the end of the bur is tilted to the direction of fixing pipe.
The perforated tape is symmetrical arranged.
The Slope protection plate is spliced by least two substrates;The fixation kit is set on substrate;The substrate Upper end is equipped with one be at least made of two through-holes and arranges the first fixation hole group;The lower end of the substrate is equipped with a connecting plate, described With width, the connecting plate is fixed on the side wall of substrate lower end and extends to the outside of substrate for connecting plate and the substrate, and The lower end of the substrate constitutes step-like with the connecting plate;The connecting plate be equipped with in the first fixation hole group The one-to-one second fixation hole group of through-hole;
Two substrates of neighbouring setting are connected by connecting plate, when connection, the connecting plate pressure that is located above on substrate At the step that the top on the top of lower substrate, and lower substrate is against upper substrate lower part, at this point, being connected in upper substrate Through-hole corresponds in the second fixation hole group on plate and the first fixation hole group on lower substrate top, and the after one-to-one correspondence Fixed pin bar is inserted in through-hole in one fixation hole group and the second fixation hole group.
The inner wall of the substrate is equipped at least one plus resistance item, and described plus resistance item is laterally arranged, and described plus resistance item The rectangular triangle in section adds the right-angle side of resistance item to be located below.
It further include upper guard board, the end of the upper guard board is hinged with a plate, and the section of the plate is in inverted U-shape, inserts Plate, which is equipped with, is inserted in position by internal U-lag with the one-to-one fixation hole of through-hole in the first fixation hole group, the plate In the end of the top substrate, at this point, through-hole in the first fixation hole group and the fixation hole correspond, and described the Fixing axle is inserted in through-hole and the fixation hole in one fixation hole group.
The lower wall of the upper guard board is equipped at least two stringer boards, and the lower end of the stringer board is blade-like.
The left end of the upper guard board is equipped with the first table top, and the right-hand end of the upper guard board is equipped with inverted and with the Matched second table top of one table top, two adjacent upper guard boards of left and right are connected by the first table top and the second table top, at this point, being located at The second table top on the upper guard board right part of left side is pressed on the first table top on the upper guard board left part of right side.
Same substrate is fixed by least one fixation kit.
The beneficial effects of the present invention are:
The use of the present apparatus can meet different complex geological conditions simultaneously, and easy for assemble or unload, material repeats It utilizes, meanwhile, the use of the present apparatus can satisfy supporting requirement of the adjacent perimeter region there are building, and in use The requirement for eliminating existing steel pipe bearing diagonal, can greatly increase the area of bottom of foundation ditch, provide for bottom of foundation ditch construction advantageous Condition, furthermore, the present apparatus uses the design of fixation kit structure, can solve asking for existing support system unstability significantly in use Topic, relative to traditional supporting construction, the design can guarantee the stabilization and safety of support system.
Detailed description of the invention
Fig. 1 is use state primary structure schematic diagram of the invention;
Fig. 2 is the upper guard board primary structure schematic diagram in the present invention;
Fig. 3 is the single substrate primary structure schematic diagram in the present invention;
The structural schematic diagram after substrate and upper guard board combination in this present invention of Fig. 4;
Fig. 5 is the single substrate back structures schematic diagram in the present invention;
Fig. 6 is the portion A enlarged structure schematic diagram in Fig. 5;
Fig. 7 is the fixation kit profile status structural schematic diagram in the present invention;
Fig. 8 is the fixation kit primary structure schematic diagram in the present invention;
Fig. 9 is the pushing block cross section structure schematic diagram in the present invention;
Figure 10 is the spring leaf partial side status architecture schematic diagram in the present invention;
Figure 11 is the fixation kit use state cross section structure schematic diagram in the present invention.
Specific embodiment
Present invention will be further explained below with reference to the attached drawings and examples:
Embodiment 1: a kind of slope protective device of architectural engineering, referring to Fig. 1 to Figure 11.
Firstly, referring to Fig. 1,3-6;It includes the Slope protection plate 100 being attached on foundation pit inner wall, through Slope protection plate 100 and inserts The fixation kit 200 of pars intramuralis in foundation pit, the Slope protection plate 100 are fixed on foundation pit inner wall by fixation kit 200.
Specifically, participating in Fig. 1,3-6;The Slope protection plate 100 is spliced by least two substrates 101;Described fixed group Part is set on substrate 101, and same substrate 101 is fixed by least one fixation kit;The upper end of the substrate 101 is equipped with extremely Few one be made of two through-holes 102 arranges the first fixation hole group;The lower end of the substrate 101 is equipped with a connecting plate 103, the company With width, the connecting plate 103 is fixed on the side wall of substrate lower end and extends to substrate 101 for fishplate bar 103 and the substrate 101 Outside, and the lower end of the substrate 101 constituted with the connecting plate 103 it is step-like;Meanwhile the connecting plate be equipped with The one-to-one second fixation hole group 104 of through-hole in the first fixation hole group.
In connection, two substrates 101 of neighbouring setting are connected upper and lower two substrates by connecting plate 103, specifically , when connection, the connecting plate 103 being located above on substrate 101 is pressed in the top of lower substrate, and the top of lower substrate is against At the step of upper substrate lower part, at this point, in the second fixation hole group 104 and lower substrate top on upper substrate upper junction plate The first fixation hole group on through-hole correspond, in the through-hole in the first fixation hole group and the second fixation hole group after one-to-one correspondence It is inserted with fixed pin rod, is fixedly connected on two substrates together by fixed pin rod.
Further, the design is equipped at least one plus resistance item 107 also on the inner sidewall of the substrate 101, described to add The laterally setting of item 107, and described plus resistance item 107 the rectangular triangle in section are hindered, adds the right-angle side of resistance item to be located below, in this way When on the soil layer that substrate is pressed in foundation pit inner wall, a plurality of plus resistance item 107 can be pressed against in soil layer, in this way by adding resistance item to adopt The right-angle side (shown in Fig. 6) of lower section increases resistance when substrate moves down, this design may insure that substrate is attached on foundation pit inner wall, Substrate is avoided to move down.
Further, the design it further include upper guard board 300, the end of the upper guard board plate body 301 passes through articulated shaft 304 It is hinged with a plate 302, the section of the plate 302 is in inverted U-shape, and plate 302 is equipped with and leading in the first fixation hole group The one-to-one fixation hole 305 in hole 102, the plate 302 are inserted in by internal U-lag 304 positioned at the top substrate 101 End, at this point, the through-hole 102 and the fixation hole 305 in the first fixation hole group correspond, and first fixation hole It is inserted with fixing axle in through-hole and the fixation hole 305 in group, upper guard board and substrate can be attached by fixing axle in this way.
Further, the design is equipped at least two stringer boards 306, institute also in the lower wall of the upper guard board plate body 301 State stringer board 306 lower end be blade-like, in this way when upper guard board is placed in foundation pit top surface, stringer board can be pressed against ground with Under, by upper guard board can prevent foundation pit top edge collapse and rainwater washes away top edge.
Further, the design also the left end of the upper guard board plate body 301 be equipped with the first table top 307, it is described on The right-hand end of backplate be equipped with it is inverted and with matched second table top 308 of the first table top, the second table top 308 is to upper guard board plate body It is external extend, two adjacent upper guard boards of left and right are connected by the first table top and 307 second table tops 308, at this point, being located at left side The second table top on upper guard board right part is pressed on the first table top on the upper guard board left part of right side, such left and right settings Two upper guard boards can realize overlap joint, prevent the gap occurred when the two upper guard board connections in left and right.
Similarly, according to the connection relationship of above-mentioned two upper guard boards in left and right, the design equally can be in the left and right sides of substrate A table top is respectively set, in this way when two substrates that left and right is disposed adjacent connect, again may be by the table top and realize nothing Seam connection prevents the gap occurred between two substrates in left and right.
Specifically, the fixation kit 200 includes the perforation being opened on substrate and perforation 106 referring to Fig. 3,5,7-10 The fixture nut 105 for being coaxially disposed and being fixed in perforation outboard end, further includes an intubation 201, the front end of the intubation 201 It is pointed, is hollow structure in intubation 201, and tail end is equipped with the socket being connected to inner hollow;It is set on the tail end socket of intubation There are a fixing pipe 204,201 coaxial arrangement of fixing pipe 204 and intubation, the lower end outer wall of fixing pipe 204 is equipped with external screw thread 205, The upper end outer wall 206 of fixing pipe is in positive hexagonal prism shape, and the inner wall of fixing pipe 204 is equipped with internal screw thread.
Specifically, 204 side wall of fixing pipe is equipped at least two perforated tapes 203, it is respectively equipped in each perforated tape 203 One spring leaf 207, the lower end of spring leaf 207 are fixedly connected with the lower end inner wall of perforated tape, and the upper end of spring leaf 207 is inserted in perforation With in the intubation in upper end, the spring leaf 207 is in the arcuation that middle part is arched upward, and the position arched upward in the middle part of spring leaf can be by wearing Pore area is protruding to perforated outer;The lateral wall of the spring leaf 207 is equipped with several burs 214, and the tip of bur 214 is to inserting The tail end direction (fixing pipe direction) of pipe tilts.
Further, it further includes cylindrical pushing block 210, is equipped with interior hexagonal shrinkage pool in the tail end of the pushing block 210 211, the side wall of the pushing block is equipped with screw thread, and the pushing block is set in fixing pipe and connect with fixing pipe inner thread, with The end of the pushing block 210 of 207 contact position of spring leaf is equipped with the spherical groove 213 being recessed inwardly, and the end of spring leaf is against Inside of spherical groove is jumped out out of this spherical groove 213 by the end that the spherical groove 213 can avoid spring leaf, prior When can avoid the end of spring leaf 207 and be clipped in the gap between pushing block and fixed inside pipe wall and cause that pushing block is stuck, it is difficult to promote The problem of occur.When the pushing block is promoted into intubation, the pushing block push the spring piece compression promotes the middle part of spring leaf to encircle It rises and intubation outside is protruded by perforated tape.
Further, it further includes the push rod 208 connecting with pushing block 210, and the push rod 208 is located in intubation, described to push away Bar is equipped with limited block 209, and the limited block 209 is located at the position in the middle part of spring leaf and is located inside the enclosed region of spring leaf, Meanwhile the limited block is in ellipticity or spherical, can prevent the middle part of spring leaf from excessively inwardly bouncing back now by the limited block 209 As generation is (because spring leaf has elasticity, when the portion that arches upward in the middle part of spring leaf is excessively caused to cannula interior bending in the middle part of spring leaf After position opposite direction is bent to cannula interior, when pushing block push the spring piece end, the middle part of spring leaf will arch upward to cannula interior, At this point, spring leaf cannot be jacked up out of be intubated, the due effect of spring leaf is just lost at this time, and when spring leaf has excessively When aduncate trend, the middle part of spring leaf can be against on this limited block the generation for preventing above-mentioned phenomenon).
The present apparatus when in use, first to the installation of Slope protection plate, when installation according to sequence from the bottom to top, from right to left according to Secondary installation first installs the single substrate for being located at the bottom, when installation, by substrate pressing on foundation pit inner wall, then Intubation on fixation kit is inserted in base after fixture nut and perforation (cannula diameter is less than fixture nut and penetration hole diameter) It cheats on inner wall (pushing block is located in fixing pipe at this time), then taps fixing pipe and intubation is embedded on foundation pit inner wall, when intubation tail end Fixing pipe and fixture nut when contacting, stop tapping, then fixing pipe be threaded in fixture nut using spanner, lead to The connection for crossing fixing pipe and fixture nut is realized intubation with substantially into being fixedly connected, and then, is pushed away by allen wrench rotation Block, by pushing block, extreme direction is pushed to before being intubated, and when pushing block is pushed ahead, the top of pushing block withstands on spring leaf end and to spring leaf Apply thrust, at this point, arched part is jacked up out of perforated tape 203 and is against in soil layer in the middle part of spring leaf, at this time on spring leaf Bur is realized and the close contact of soil layer, the in this way bur by spring leaf and thereon and achievable to will insert with the cooperation of intubation Pipe is firmly fixed in soil layer, and substrate so can be firmly fixed on to foundation pit surface.
Then installation base plate again upwards, two fixation hole groups 104 on connecting plate and lower section when installation, in upper substrate Through-hole corresponds in the first fixation hole group on substrate top, the first fixation hole group and the second fixation hole group after one-to-one correspondence It is inserted with fixed pin bar in interior through-hole, is fixedly connected on two substrates together by fixed pin rod, then according to above-mentioned first The mounting means of block substrate installs fixation kit.It repeats the above steps and successively installs substrate to base by the bottom of foundation pit Hole top.
Then to the installation of upper guard board, when installation, the plate 302 is inserted in by internal U-lag 304 positioned at the top The end of substrate 101, at this point, the through-hole 102 and the fixation hole 305 in the first fixation hole group correspond, and described It is inserted with fixing axle in through-hole and the fixation hole 305 in first fixation hole group, it in this way can be by upper guard board and base by fixing axle Plate is attached, and is then downwardly applied to pressure to upper guard board, and stringer board is promoted to be pressed against below ground, in this way can by upper guard board Prevent foundation pit top edge collapse and rainwater washes away top edge.
So it is achievable to foundation pit by the installation of bottom to top.
What the embodiment of the present invention was announced is preferred embodiment, and however, it is not limited to this, the ordinary skill people of this field Member, easily according to above-described embodiment, understands spirit of the invention, and make different amplification and variation, but as long as not departing from this The spirit of invention, all within the scope of the present invention.

Claims (10)

1. a kind of slope protective device of architectural engineering, it is characterised in that: it include the Slope protection plate being attached on foundation pit inner wall, Through Slope protection plate and it is inserted in the fixation kit of pars intramuralis in foundation pit, the Slope protection plate is fixed on foundation pit inner wall by fixation kit On;
The fixation kit includes the perforation being opened on Slope protection plate, is coaxially disposed with perforation and is fixed in perforation outboard end Fixture nut, further include an intubation, it is hollow structure in intubation that the front end of the intubation, which is pointed, and tail end be equipped with it is interior The socket of the hollow connection in portion;The tail end of intubation is equipped with a fixing pipe, and fixing pipe and intubation are coaxially disposed, outside the lower end of fixing pipe Wall is equipped with external screw thread, and the upper end outer wall of fixing pipe is in positive hexagonal prism shape, and the inner wall of fixing pipe is equipped with internal screw thread;
The fixing pipe side wall is equipped at least two perforated tapes, is respectively equipped with a spring leaf in each perforated tape, under spring leaf End is fixedly connected with the lower end inner wall of perforated tape, and the upper end of spring leaf is inserted in the intubation in perforated tape upper end, the spring leaf The arcuation to arch upward in middle part, and the position arched upward in the middle part of spring leaf can be protruding to perforated outer by perforated tape;
The lateral wall of the spring leaf is equipped with several burs;
Further include cylindrical pushing block, is equipped with interior hexagonal shrinkage pool in the tail end of the pushing block, the side wall of the pushing block is equipped with Screw thread, the pushing block are set in fixing pipe and connect with fixing pipe inner thread, and the end of the pushing block is against spring leaf End, when the pushing block is promoted into intubation, the pushing block push the spring piece compression promotes to arch upward and lead in the middle part of spring leaf It is external to cross perforated tape protrusion intubation.
2. the slope protective device of architectural engineering as described in claim 1, it is characterised in that: further include being connect with pushing block Push rod, the push rod are located in intubation, and the push rod is equipped with limited block, and the limited block is located at the position in the middle part of spring leaf simultaneously Inside the enclosed region of spring leaf.
3. the slope protective device of architectural engineering as claimed in claim 2, it is characterised in that: the limited block is in ellipticity Or it is spherical;The perforated tape is symmetrical arranged.
4. the slope protective device of architectural engineering as claimed in claim 3, it is characterised in that: with the spring leaf contact position The end of pushing block be equipped with the spherical groove that is recessed inwardly, the end of spring leaf is against inside of spherical groove;The bur inclination is set It sets, and the end of the bur is tilted to the direction of fixing pipe.
5. the slope protective device of architectural engineering as claimed in claim 4, it is characterised in that: the Slope protection plate is by least two A substrate is spliced;The fixation kit is set on substrate;The upper end of the substrate is equipped with and is at least made of two through-holes One arrange the first fixation hole group;The lower end of the substrate is equipped with a connecting plate, the connecting plate and the substrate with wide, the company Fishplate bar is fixed on the side wall of substrate lower end and extends to the outside of substrate, and the lower end of the substrate and the connecting plate It constitutes step-like;The connecting plate is equipped with and the one-to-one second fixation hole group of through-hole in the first fixation hole group;
Two substrates of neighbouring setting are connected by connecting plate, and when connection, the connecting plate being located above on substrate is pressed in down The top of square substrate, and the top of lower substrate is against at the step of upper substrate lower part, at this point, on upper substrate upper junction plate The second fixation hole group and lower substrate top on the first fixation hole group on through-hole correspond, first after one-to-one correspondence is solid Determine to be inserted with fixed pin bar in the through-hole in hole group and the second fixation hole group.
6. the slope protective device of architectural engineering as claimed in claim 5, it is characterised in that: set on the inner wall of the substrate There are at least one plus resistance item, described plus resistance item is laterally arranged, and described plus resistance item the rectangular triangle in section, adds the straight of resistance item The arm of angle is located below.
7. the slope protective device of architectural engineering as claimed in claim 5, it is characterised in that: it further include upper guard board, it is described The end of upper guard board is hinged with a plate, and the section of the plate is in inverted U-shape, plate be equipped with in the first fixation hole group The one-to-one fixation hole of through-hole, the plate is inserted in by internal U-lag positioned at the end of the top substrate, at this point, institute State through-hole in the first fixation hole group and the fixation hole correspond, and the through-hole in the first fixation hole group with it is described solid Determine to be inserted with fixing axle in hole.
8. the slope protective device of architectural engineering as claimed in claim 7, it is characterised in that: the lower wall of the upper guard board At least two stringer boards are equipped with, the lower end of the stringer board is blade-like.
9. the slope protective device of architectural engineering as claimed in claim 7, it is characterised in that: the left-hand end of the upper guard board Portion is equipped with the first table top, the right-hand end of the upper guard board be equipped with it is inverted and with matched second table top of the first table top, left and right Two adjacent upper guard boards are connected by the first table top and the second table top, at this point, being located at second on left side upper guard board right part Table top is pressed on the first table top on the upper guard board left part of right side.
10. the slope protective device of architectural engineering as claimed in claim 5, it is characterised in that: same substrate is by least One fixation kit is fixed.
CN201820956656.4U 2018-06-21 2018-06-21 The slope protective device of architectural engineering Expired - Fee Related CN208792343U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820956656.4U CN208792343U (en) 2018-06-21 2018-06-21 The slope protective device of architectural engineering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820956656.4U CN208792343U (en) 2018-06-21 2018-06-21 The slope protective device of architectural engineering

Publications (1)

Publication Number Publication Date
CN208792343U true CN208792343U (en) 2019-04-26

Family

ID=66201238

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820956656.4U Expired - Fee Related CN208792343U (en) 2018-06-21 2018-06-21 The slope protective device of architectural engineering

Country Status (1)

Country Link
CN (1) CN208792343U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108677974A (en) * 2018-06-21 2018-10-19 江西工业工程职业技术学院 The slope protective device that architectural engineering is used for
CN111042181A (en) * 2019-12-12 2020-04-21 南京辉强新能源科技有限公司 Construction method and construction matching tool for foundation of wind power generation equipment in mountainous area
CN112031000A (en) * 2020-08-28 2020-12-04 浙江钱塘江水利建筑工程有限公司 Water conservancy side slope excavation is support device in advance
CN113718801A (en) * 2021-09-02 2021-11-30 王冲 Honeycomb soil nail soil body reinforcing accessory for improving slope stability

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108677974A (en) * 2018-06-21 2018-10-19 江西工业工程职业技术学院 The slope protective device that architectural engineering is used for
CN108677974B (en) * 2018-06-21 2023-07-25 江西工业工程职业技术学院 Slope protection device for constructional engineering
CN111042181A (en) * 2019-12-12 2020-04-21 南京辉强新能源科技有限公司 Construction method and construction matching tool for foundation of wind power generation equipment in mountainous area
CN112031000A (en) * 2020-08-28 2020-12-04 浙江钱塘江水利建筑工程有限公司 Water conservancy side slope excavation is support device in advance
CN113718801A (en) * 2021-09-02 2021-11-30 王冲 Honeycomb soil nail soil body reinforcing accessory for improving slope stability

Similar Documents

Publication Publication Date Title
CN208792343U (en) The slope protective device of architectural engineering
CN106193118B (en) The tall and big side wall unilateral side formwork erection of open trench tunnel agent structure and its construction technology
CN108677974A (en) The slope protective device that architectural engineering is used for
CN105888236B (en) frame template system
CN210597622U (en) Novel can dismantle simple and easy house structure
CN104120874A (en) Assembly type scaffold and wall connecting piece
CN204001665U (en) A kind of scaffold assembling wall-connecting piece
CN217811068U (en) Throw and prop angle connecting piece
CN209468842U (en) High-building construction floor intercepts water drainage arrangement
CN208039262U (en) A kind of anti-drop device of shallow foundation hole support plate
CN206815533U (en) A kind of prefabricated component and the connecting node on basis
CN214329278U (en) Steel structure beam column connecting and assembling structure
CN207846461U (en) One kind plus pier Foundation Supported with Composite Soil Nailing
CN212128866U (en) Traceless large-tonnage high pier bracket anchor structure
CN212477760U (en) Pipeline groove supporting construction
JP2007231596A (en) Column base fixture, column base fixing structure and column base fixing method
CN211923034U (en) Building steel structure connecting piece
CN210152680U (en) Prestressing force strutting arrangement who uses when tunnel connection passageway excavates
CN208733817U (en) A kind of assembling type steel structure building Special-Shaped Column
CN218952261U (en) Steel plate water stop belt structure
CN213979918U (en) Structure column formwork support structure
CN111321667A (en) Traceless large-tonnage high pier bracket and anchoring structure thereof
CN218374606U (en) Connection structure of different height metal roofing and concrete roofing
CN217811373U (en) Novel buried type field assembled fire-fighting water tank
CN217896520U (en) Large-span shaped steel integrated configuration that excavation supporting used

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190426

Termination date: 20200621

CF01 Termination of patent right due to non-payment of annual fee