CN208791236U - One kind is for metallurgical extraction separation device - Google Patents

One kind is for metallurgical extraction separation device Download PDF

Info

Publication number
CN208791236U
CN208791236U CN201820991939.2U CN201820991939U CN208791236U CN 208791236 U CN208791236 U CN 208791236U CN 201820991939 U CN201820991939 U CN 201820991939U CN 208791236 U CN208791236 U CN 208791236U
Authority
CN
China
Prior art keywords
process tank
heating chamber
outlet tube
separation device
extraction separation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820991939.2U
Other languages
Chinese (zh)
Inventor
秦小梅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangxi Chenfei Copper Industry Co Ltd
Original Assignee
Jiangxi Chenfei Copper Industry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangxi Chenfei Copper Industry Co Ltd filed Critical Jiangxi Chenfei Copper Industry Co Ltd
Priority to CN201820991939.2U priority Critical patent/CN208791236U/en
Application granted granted Critical
Publication of CN208791236U publication Critical patent/CN208791236U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Extraction Or Liquid Replacement (AREA)

Abstract

The utility model discloses one kind for metallurgical extraction separation device, including process tank, jet pipe and outlet tube, heating chamber is provided on the outside of the process tank, and water filling port is installed on the left of heating chamber, aspiration pump is installed above the gas pipeline, the left side of the fixing pipe is equipped with feed hopper, the right surface of the process tank is run through by sealing element, the upper end of the outlet tube is run through from the inside of spacing collar, hose is provided with above the outlet tube, and hose runs through from the right surface of process tank, drainage conduit is installed below the process tank, and drainage conduit runs through from the lower surface of heating chamber.This is used for metallurgical extraction separation device, and stoste and extract liquor can be injected into the lower section inside process tank by fixing pipe, after gas is injected in inside, while gas floats up, the middle organic matter of stoste is adsorbed, convenient for organic matter to be gathered in the upper layer of liquid, improves the efficiency of liquid extraction.

Description

One kind is for metallurgical extraction separation device
Technical field
It is specially a kind of for metallurgical extraction separation device the utility model relates to metallurgical abstraction technique field.
Background technique
In metallurgical technology, a large amount of waste water is generated, containing miscellaneous a large amount of organic matter and all kinds of metal ions in waste water, It when handling waste water, needs to use the method for extraction, internal metal ion is classified and is taken out, but existing extraction equipment In extraction, takes a long time, cause extraction efficiency low, and the liquid after stratification can only be by discharge nozzle according to layering It successively takes out, efficiency is lower.
Utility model content
The purpose of this utility model is to provide one kind for metallurgical extraction separation device, to solve in above-mentioned background technique It proposes but existing extraction equipment is in extraction, take a long time, cause extraction efficiency low, and the liquid after stratification is only It can successively be taken out by discharge nozzle according to layering, the lower problem of efficiency.
To achieve the above object, the utility model provides the following technical solutions: one kind is for metallurgical extraction separation device, packet Process tank, jet pipe and outlet tube are included, heating chamber is provided on the outside of the process tank, and water filling is installed on the left of heating chamber Mouthful, and water outlet is provided on the right side of heating chamber, the center of the process tank is fixed pipe and runs through, and the inside of fixing pipe is inserted Entering gas pipeline, aspiration pump is installed above the gas pipeline, the left side of the fixing pipe is equipped with feed hopper, and into Hopper runs through from the upper surface of process tank, and the middle position of the jet pipe upper surface is connected with gas pipeline, and the side of jet pipe Stomata is offered, the right surface of the process tank is run through by sealing element, and the inside of sealing element is equipped with rotation axis, the liquid out The upper end of pipe is run through from the inside of spacing collar, and the right surface of spacing collar is rotated axis and runs through, while the right side of spacing collar The inner wall of lower section and process tank is connected with each other, and is provided with hose above the outlet tube, and hose is from the right surface of process tank Run through, the surface of the outlet tube opens up fluted, and the side of groove is provided with fixed tooth, the left side installation of the rotation axis Have a transmission gear, and transmission gear and fixed tooth are connected with each other, drainage conduit be installed below the process tank, and drainage conduit from The lower surface of heating chamber is run through, and is equipped with observation window on the left of the heating chamber.
Preferably, the height of the water filling port is lower than the height of water outlet, and the two is symmetrical about the center line of process tank Distribution.
Preferably, the jet pipe is set as " ten " font structure, and its side is equidistantly arranged with stomata, and jet pipe with The bottom end seal of fixing pipe connects.
Preferably, the outlet tube and spacing collar constitute slide construction, and spacing collar and rotation axis constitute rotation knot Structure.
Preferably, the fixed tooth equally arranges in groove, and fixed tooth engages connection with transmission gear, and Transmission gear installation by adhering is in the inside of groove.
Preferably, the observation window installation by adhering is on the surface of heating chamber, and observation window and process tank are connected with each other, and And process tank and heating chamber constitute sealing structure.
Compared with prior art, the utility model has the beneficial effects that this is used for metallurgical extraction separation device,
1. heating chamber is provided on the outside of process tank, so that hot oil is injected in the inside of heating chamber, convenient for process tank Outer wall is preheated, convenient for improving the reaction efficiency of extractant and stoste, to improve the efficiency of extraction;
2. the side of outlet tube is provided with the fixation tooth equidistantly arranged, to drive fixed tooth by the rotation axis of rotation It moves up and down, consequently facilitating adjusting the height of outlet tube, convenient for extracting the liquid of layering out from top, being not necessarily to will for such setting Liquid is successively sucked out from below, facilitates operation;
3. gas pipeline runs through from fixing pipe, so that stoste and extract liquor can be injected into inside process tank by fixing pipe Lower section, and air is entered in process tank by gas pipeline, and gas forms bubble and floats up in a liquid, and bubble floats upwards While floating, the middle organic matter of stoste is adsorbed, convenient for organic matter to be gathered in the upper layer of liquid, improves liquid extraction Efficiency.
Detailed description of the invention
Fig. 1 is the utility model schematic diagram of internal structure;
Fig. 2 is the utility model fixing pipe schematic diagram of internal structure;
Fig. 3 is the utility model outlet tube and spacing collar mounting structure schematic diagram;
Fig. 4 is the utility model outlet tube side structure schematic diagram;
Fig. 5 is the utility model jet pipe overlooking structure diagram;
Fig. 6 is side structure schematic view outside the utility model.
In figure: 1, process tank;2, heating chamber;3, water filling port;4, water outlet;5, fixing pipe;6, gas pipeline;7, it is evacuated Pump;8, feed hopper;9, jet pipe;10, stomata;11, sealing element;12, rotation axis;13, outlet tube;14, groove;15, fixed tooth; 16, transmission gear;17, spacing collar;18, hose;19, drainage conduit;20, observation window.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work Every other embodiment obtained, fall within the protection scope of the utility model.
Please refer to Fig. 1-6, the utility model provides a kind of technical solution: one kind being used for metallurgical extraction separation device, including Process tank 1, heating chamber 2, water filling port 3, water outlet 4, fixing pipe 5, gas pipeline 6, aspiration pump 7, feed hopper 8, jet pipe 9, stomata 10, sealing element 11, rotation axis 12, outlet tube 13, groove 14, fixed tooth 15, transmission gear 16, spacing collar 17, hose 18, row Expects pipe 19, observation window 20, the outside of process tank 1 is provided with heating chamber 2, and the left side of heating chamber 2 is equipped with water filling port 3, and The right side of heating chamber 2 is provided with water outlet 4, and the height of water filling port 3 is lower than the height of water outlet 4, and the two is about process tank 1 Center line is symmetrical, so that hot oil is gradually injected to a high position from low level, improves stability when heat height injection, hot oil is avoided to exist The inside of heating chamber 2 is splash, and improves the stability of heat transfer;
The center of process tank 1 is fixed pipe 5 and runs through, and fixing pipe 5 inside be inserted into gas pipeline 6, gas pipeline 6 it is upper Side is equipped with aspiration pump 7, and the left side of fixing pipe 5 is equipped with feed hopper 8, and feed hopper 8 runs through from the upper surface of process tank 1, The middle position of 9 upper surface of jet pipe is connected with gas pipeline 6, and the side of jet pipe 9 offers stomata 10, and jet pipe 9 is set as " ten " font structure, and its side is equidistantly arranged with stomata 10, and jet pipe 9 is connect with the bottom end seal of fixing pipe 5, thus After stoste can only flow out after flowing into fixing pipe 5 from its left side, and gas enters jet pipe 9, final gas is dispersed by stomata 10 It sprays, the inside of process tank 1 is dispersed into convenient for gas;
The right surface of process tank 1 is run through by sealing element 11, and the inside of sealing element 11 is equipped with rotation axis 12, outlet tube 13 upper end is run through from the inside of spacing collar 17, and the right surface of spacing collar 17 is rotated axis 12 and runs through, while limit sleeve The lower right of cylinder 17 and the inner wall of process tank 1 are connected with each other, and outlet tube 13 and spacing collar 17 constitute slide construction, and limit sleeve Cylinder 17 constitutes rotational structure with rotation axis 12, and when rotation axis 12 rotates, rotation axis 12 is rotated on the surface of spacing collar 17, It not will drive spacing collar 17 simultaneously to be rotated, improve stability, and when the position of outlet tube 13 is changed, out Liquid pipe 13 is moved up and down in the inside of spacing collar 17, and outlet tube 13 is fixed in spacing collar 17, avoids outlet tube 13 left Right swing;
The top of outlet tube 13 is provided with hose 18, and hose 18 runs through from the right surface of process tank 1, the table of outlet tube 13 Face opens up fluted 14, and the side of groove 14 is provided with fixed tooth 15, and fixed tooth 15 equally arranges in groove 14, And fixed tooth 15 engages connection with transmission gear 16, and 16 installation by adhering of transmission gear is in the inside of groove 14, rotation Transmission gear 16 drives fixed tooth 15 to be rotated, so that fixed tooth 15 drives outlet tube 13 to move up and down, convenient for adjusting The height of outlet tube 13;
The left side of rotation axis 12 is equipped with transmission gear 16, and transmission gear 16 and fixed tooth 15 are connected with each other, process tank 1 Lower section drainage conduit 19 is installed, and drainage conduit 19 runs through from the lower surface of heating chamber 2, and the left side of heating chamber 2 is equipped with observation Window 20,20 installation by adhering of observation window is on the surface of heating chamber 2, and observation window 20 and process tank 1 are connected with each other, and process tank 1 constitutes sealing structure with heating chamber 2, so that the delamination inside process tank 1 is observed by observation window 20, convenient for Liquid level after knowing the layering of internal solution.
Water filling port 3: according to Figure of description 1, being accessed external hot oil supply source by working principle, so that hot oil is from water filling port 3 enter the inside of heating chambers 2, until height of the hot oil liquid level inside heating chamber 2 higher than water outlet 4, hot oil is from water outlet Mouth 4 is discharged, so that hot oil preheats process tank 1;
The upper end of hose 18 is connected after the external pump housing, stoste is injected into process tank 1 by feed hopper 8 later Inside, as shown in Figure of description 2-3, stoste is trickled in fixing pipe 5, is finally trickled from the left side of fixing pipe 5 to fixing pipe 5 Extractant is injected into after hopper 8 equally trickling to fixing pipe 5 later by inside, and after starting aspiration pump 7, aspiration pump 7 takes out air Into gas pipeline 6, so that air is entered in jet pipe 9 by gas pipeline 6, final air is discharged from stomata 10, and air Form bubble in the inside of solution, subsequent bubble ramps up in the inside of liquid, while the organic matter in bubbles entrain liquid at Divide and floats up aggregation, so that organic matter constituents swim in the top inside process tank 1,
As shown in specification 3-4, after extraction reaction, 13 lower end surface of outlet tube is adjusted according to the height of liquid level layering Height, i.e., hand-held rotation axis 12 rotated, and rotation axis 12 is rotated in the inside of sealing element 11, and 12 band of rotation axis Nutating gear 16 is rotated, i.e., transmission gear 16 drives fixed tooth 15 to be rotated, so that fixed tooth 15 moves up, from And fix tooth 15 and outlet tube 13 is driven to move up, outlet tube 13 is moved up in the inside of spacing collar 17, passes through observation window 20 are observed, until starting the pump housing of 18 outer end of hose, inside process tank 1 after 13 lower end height of outlet tube is suitble to The sewage on upper layer is sucked out, and can hold again rotation axis 12 later and be rotated, and changes the height of 13 lower end of outlet tube, thus just It is taken out in 1 internal liquid of process tank to be layered, furthermore also internal liquid is discharged in openable drainage conduit 19, increases whole The practicability of body.
While there has been shown and described that the embodiments of the present invention, for the ordinary skill in the art, It is understood that these embodiments can be carried out with a variety of variations in the case where not departing from the principles of the present invention and spirit, repaired Change, replacement and variant, the scope of the utility model is defined by the appended claims and the equivalents thereof.

Claims (6)

1. one kind is for metallurgical extraction separation device, including process tank (1), jet pipe (9) and outlet tube (13), it is characterised in that: It is provided with heating chamber (2) on the outside of the process tank (1), and water filling port (3) is installed, and heat on the left of heating chamber (2) It is provided on the right side of chamber (2) water outlet (4), the center of the process tank (1) is fixed pipe (5) and runs through, and fixing pipe (5) is interior Portion is inserted into gas pipeline (6), is equipped with aspiration pump (7) above the gas pipeline (6), the left side of the fixing pipe (5) It is equipped with feed hopper (8), and feed hopper (8) runs through from the upper surface of process tank (1), the interposition of jet pipe (9) upper surface It sets and is connected with gas pipeline (6), and the side of jet pipe (9) offers stomata (10), the right surface of the process tank (1) is sealed Part (11) runs through, and the inside of sealing element (11) is equipped with rotation axis (12), and the upper end of the outlet tube (13) is from spacing collar (17) inside is run through, and the right surface of spacing collar (17) is rotated axis (12) and runs through, while the bottom right of spacing collar (17) The inner wall of side and process tank (1) is connected with each other, and is provided with hose (18) above the outlet tube (13), and hose (18) is from The right surface of reason tank (1) is run through, and the surface of the outlet tube (13) opens up fluted (14), and the side of groove (14) is provided with It fixes tooth (15), is equipped with transmission gear (16) on the left of the rotation axis (12), and transmission gear (16) and fixed tooth (15) It is connected with each other, is equipped with drainage conduit (19) below the process tank (1), and drainage conduit (19) is from the lower surface of heating chamber (2) Run through, observation window (20) are installed on the left of the heating chamber (2).
2. according to claim 1 a kind of for metallurgical extraction separation device, it is characterised in that: the water filling port (3) Height is lower than the height of water outlet (4), and the two is symmetrical about the center line of process tank (1).
3. according to claim 1 a kind of for metallurgical extraction separation device, it is characterised in that: jet pipe (9) setting For " ten " font structure, and its side is equidistantly arranged with stomata (10), and the bottom end seal of jet pipe (9) and fixing pipe (5) Connection.
4. according to claim 1 a kind of for metallurgical extraction separation device, it is characterised in that: the outlet tube (13) with Spacing collar (17) constitutes slide construction, and spacing collar (17) and rotation axis (12) constitute rotational structure.
5. according to claim 1 a kind of for metallurgical extraction separation device, it is characterised in that: the fixed tooth (15) exists It is equally arranged in groove (14), and fixed tooth (15) engage connection with transmission gear (16), and transmission gear (16) is embedding Enter the inside that formula is mounted on groove (14).
6. according to claim 1 a kind of for metallurgical extraction separation device, it is characterised in that: the observation window (20) is embedding Enter the surface that formula is mounted on heating chamber (2), and observation window (20) and process tank (1) are connected with each other, and process tank (1) and heating Chamber (2) constitutes sealing structure.
CN201820991939.2U 2018-06-26 2018-06-26 One kind is for metallurgical extraction separation device Expired - Fee Related CN208791236U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820991939.2U CN208791236U (en) 2018-06-26 2018-06-26 One kind is for metallurgical extraction separation device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820991939.2U CN208791236U (en) 2018-06-26 2018-06-26 One kind is for metallurgical extraction separation device

Publications (1)

Publication Number Publication Date
CN208791236U true CN208791236U (en) 2019-04-26

Family

ID=66201495

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820991939.2U Expired - Fee Related CN208791236U (en) 2018-06-26 2018-06-26 One kind is for metallurgical extraction separation device

Country Status (1)

Country Link
CN (1) CN208791236U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115364793A (en) * 2022-02-17 2022-11-22 江苏赛科化学有限公司 Preparation method and device of fatty secondary alcohol polyoxyethylene ether

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115364793A (en) * 2022-02-17 2022-11-22 江苏赛科化学有限公司 Preparation method and device of fatty secondary alcohol polyoxyethylene ether

Similar Documents

Publication Publication Date Title
CN208791236U (en) One kind is for metallurgical extraction separation device
CN207417598U (en) A kind of flotation fuel-discharging device of oil tank
CN106159188B (en) Through type liquid injection method and device for lithium ion battery
CN206334891U (en) Liquid-transfering gun pipette tips cleaning box
CN218115381U (en) Safflower seed oil extraction equipment
CN209481663U (en) A kind of fermentor return stirring device
CN114941510B (en) Circulating blocking-removing sand-fishing process system
CN205164202U (en) Vertical deaeration machine
CN203544822U (en) Storage tank sealing device
CN209735047U (en) Oral liquid alcohol precipitation device that stews
CN209393635U (en) A kind of novel steam generator secondary side tube sheet body refuse suction system
CN206660678U (en) A kind of sewage delivery device
CN206113757U (en) Rubber ball cleaning system with receive ball counting assembly
CN207627984U (en) A kind of gas-liquid separation regards cup device
CN208057370U (en) A kind of deacidification tank on vacuum pump
CN106268193B (en) High-sulfur naphtha desulfurization anti-reflux device
CN205222753U (en) Resin loader
CN206708038U (en) One kind is lower to inhale submersible pump
CN205368258U (en) Floating collecting device for intermediate layer transition zone of crude oil secondary settling tank
CN206219179U (en) A kind of oral liquid filling device
CN102894881A (en) Water level and air intake control device of multiple-bottle water dispenser and multiple-bottle water dispenser
CN213775710U (en) Liquid pumping device
CN213433771U (en) Waste gas treatment device of sewage treatment tank
CN221235305U (en) Oil removal lifting integrated equipment
CN217350791U (en) Full-automatic integrated wastewater treatment dosing device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190426

Termination date: 20210626

CF01 Termination of patent right due to non-payment of annual fee