CN208762185U - A kind of energy-saving system suitable for handling desulfurization wastewater - Google Patents
A kind of energy-saving system suitable for handling desulfurization wastewater Download PDFInfo
- Publication number
- CN208762185U CN208762185U CN201821451384.9U CN201821451384U CN208762185U CN 208762185 U CN208762185 U CN 208762185U CN 201821451384 U CN201821451384 U CN 201821451384U CN 208762185 U CN208762185 U CN 208762185U
- Authority
- CN
- China
- Prior art keywords
- waste water
- desulfurization wastewater
- energy
- evaporating column
- flue
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P70/00—Climate change mitigation technologies in the production process for final industrial or consumer products
- Y02P70/10—Greenhouse gas [GHG] capture, material saving, heat recovery or other energy efficient measures, e.g. motor control, characterised by manufacturing processes, e.g. for rolling metal or metal working
Abstract
The utility model discloses one kind to be suitable for heat-engine plant desulfurized Wastewater zero-discharge treatment system.For the limitation for overcoming mainstream technology, the energy-saving system that the utility model proposes a kind of suitable for handling desulfurization wastewater.The system is based on fume afterheat and evaporates desulfurization wastewater, has the advantages such as cost of investment is low with low running cost, energy consumption is relatively small, it is contemplated that have preferable application value.This energy-saving desulfurization wastewater treatment system, including deduster, desulfuration absorbing tower and waste water evaporating column.Evaporating column and flue are relatively independent with flue by pipeline connection.Air-introduced machine is set in pipeline, the flue gas in flue is introduced into evaporating column.The lower section of desulfuration absorbing tower couples gypsum dehydration equipment.Plate and frame filter press is set below evaporating column.On the one hand solid matter filters pressing in waste water evaporating column is sludge by plate and frame filter press, outward transport landfill, the filtrate being on the other hand press-filtered out return to surge tank later.It is low with operating cost, cost of investment is low, advantages of simple structure and simple.
Description
Technical field
The utility model relates to desulfurization wastewater processing technology fields, and in particular to one kind is suitable for heat-engine plant desulfurized waste water zero
Discharge treating system.
Background technique
Limestone-gypsum Wet Flue Gas Desulfurization Process technology is the mainstream technology of Present Thermal Power factory desulfurization.But the technology is in desulfurization
Cheng Zhonghui generates a certain amount of desulfurization wastewater, and desulfurization wastewater is high concentration suspended matter, high chlorine root, high saliferous, high concentration metal are useless
Water, processing difficulty are big.In addition, country's in April, 2015 puts into effect " water prevention and cure of pollution action plan " --- how " ten, water " is realized
Desulfurization wastewater zero-emission is the problem that Present Thermal Power industry faces.
The main method of pre-treatment desulfurization wastewater has pretreatment (three headers softening clarification, tubular filter);Concentration decrement (is steamed
MF/RO, UF/RO, UF/NF, UF/RO/ED, UF/RO/FO, UF/RO/MD etc. is concentrated in hair concentration MED, MVR, embrane method);At solidification
It manages (natural evaporation crystallization, evaporation pond, mechanical atomization evaporation, flue spray evaporation etc.).Evaporation technique is to realize desulfurization wastewater zero
The effective technology of discharge, but directly evaporated water is larger, energy consumption cost is high;Film concentration is serious etc. there are low efficiency, fouling membrane
Disadvantage.
Summary of the invention
For the limitation for overcoming the above mainstream technology, the utility model proposes a kind of suitable for handling the energy-saving of desulfurization wastewater
System.The system is based on fume afterheat and evaporates desulfurization wastewater, and it is excellent to have that cost of investment is low with low running cost, energy consumption is relatively small etc.
Gesture, it is contemplated that have preferable application value.
Utility model is achieved through the following technical solutions:
A kind of energy-saving system suitable for handling desulfurization wastewater, including deduster, desulfuration absorbing tower and waste water evaporating column.
Evaporating column and flue are relatively independent with flue by pipeline connection.Air-introduced machine is set in pipeline, the flue gas in flue is introduced into evaporation
In tower.Atomizing spray layer is set in evaporating column, circulating pump, circulating pump and evaporating column inside are provided with outside evaporating column and atomization is sprayed
Drenching layer connection, and the connection position inside circulating pump and waste water evaporating column is located at below atomizing spray layer.
The lower section of desulfuration absorbing tower couples gypsum dehydration equipment, the wet desulphurization waste water warp after gypsum belt dewaterer
Waste water surge tank source of the supernatant as spray water after precipitation is crossed, spray water reaches atomizing spray layer by circulating pump, with
Low-temperature flue gas contact, mixing, the moisture in waste water is taken away by low-temperature flue gas waste heat.In addition, for the level for maintaining desulphurization system
Weighing apparatus, by waste water surge tank, supernatant can also be used as the flushing water of demister after precipitation.
Plate and frame filter press is set below evaporating column, plate and frame filter press simultaneously with waste water evaporating column and waste water surge tank connection.
On the one hand solid matter filters pressing in waste water evaporating column is sludge by plate and frame filter press, later outward transport landfill, another aspect filters pressing
Filtrate out returns to surge tank.
Utility model compared with prior art, has the following advantages and benefits:
(1) this programme utilizes fume afterheat low-temperature evaporation desulfurization wastewater, does not need to consume other external heat sources, energy-saving ring
It protects, operating cost is low;
(2) flue facture is compared, the waste water evaporating column of this programme is independently arranged at outside flue with flue connection, is not required to
Anti-corrosion measure is taken flue inner wall, and cost of investment is lower;
(3) this programme structure is simple, easy to implement.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the utility model:
Wherein: 1- flue, 2- deduster, 3- pipeline, 4- blower, 5- waste water evaporating column, 6- circulating pump, 7- desulfurization absorb
Tower, 8- gypsum dehydration equipment, 9- waste water surge tank, 10- plate and frame filter press, 11- demister.
Specific embodiment
Illustrate the purpose of this utility model, technical solution in order to clearer, it is practical new that Detailed description of the invention sheet will be compareed below
The specific embodiment of type.
As shown in Figure 1, a kind of energy-saving system for handling desulfurization wastewater, including the evaporation of deduster, desulfuration absorbing tower, waste water
Tower, waste water surge tank etc..Demister is provided in desulfuration absorbing tower, demister passes through circulating pump and waste water surge tank connection.It is useless
Be provided with atomizing spray layer in water evaporation tower, atomizing spray layer by circulating pump also with waste water surge tank connection.Waste water surge tank
For storing the waste water after desulfurization is concentrated, the supernatant after precipitating reaches atomizing spray layer by circulating pump, as spraying
The source of water.Atomizing spray layer sprays drop and smoke contacts, utilizes waste heat evaporating waste water drop.To maintain desulphurization system horizontal
Weighing apparatus, the supernatant of waste water surge tank is transported to demister also by circulating pump, for rinsing demister.
Waste water evaporating column is set between deduster and desulfuration absorbing tower, passes through pipeline and flue connection.Setting in pipeline
There is air-introduced machine, the low-temperature flue gas in flue is introduced by air-introduced machine, is evaporated to waste water evaporating column.
The lower part of waste water evaporating column and plate and frame filter press connection, after plate and frame filter press filters pressing, obtained sludge into
Row outward transport landfill disposal.
Above-described specific embodiment has carried out specific description to this case.
Claims (5)
1. a kind of energy-saving system suitable for handling desulfurization wastewater, which is characterized in that including deduster and desulfuration absorbing tower, remove
Waste water evaporating column is provided between dirt device and desulfuration absorbing tower.
2. a kind of energy-saving system suitable for handling desulfurization wastewater according to claim 1, which is characterized in that described to remove
Dirt device and desulfuration absorbing tower are communicated by flue, and by pipeline and flue connection between waste water evaporating column, pipeline is interior to be arranged air inducing
Machine.
3. a kind of energy-saving system suitable for handling desulfurization wastewater according to claim 1, which is characterized in that described useless
It is provided with waste water surge tank, waste water evaporating column and waste water surge tank outside water evaporation tower and passes through circulating pump connection, waste water surge tank
Pass through circulating pump connection with desulfuration absorbing tower.
4. a kind of energy-saving system suitable for handling desulfurization wastewater according to claim 3, which is characterized in that described useless
Plate and frame filter press, waste water evaporating column and half frame filter press are additionally provided with outside water evaporation tower by pipeline connection, plate and frame filter press is logical
Piping and waste water surge tank connection.
5. a kind of energy-saving system suitable for handling desulfurization wastewater according to claim 4, into the cigarette before deduster
Temperature degree general control is between 90 DEG C -140 DEG C.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821451384.9U CN208762185U (en) | 2018-09-06 | 2018-09-06 | A kind of energy-saving system suitable for handling desulfurization wastewater |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821451384.9U CN208762185U (en) | 2018-09-06 | 2018-09-06 | A kind of energy-saving system suitable for handling desulfurization wastewater |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208762185U true CN208762185U (en) | 2019-04-19 |
Family
ID=66135306
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201821451384.9U Expired - Fee Related CN208762185U (en) | 2018-09-06 | 2018-09-06 | A kind of energy-saving system suitable for handling desulfurization wastewater |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208762185U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111675370A (en) * | 2020-05-13 | 2020-09-18 | 国家电投集团远达环保工程有限公司重庆科技分公司 | Method and device for modifying desulfurization wastewater concentrated solution |
CN114699893A (en) * | 2022-02-28 | 2022-07-05 | 华电水务工程有限公司 | Resource utilization method for high sulfate radical nanofiltration concentrated water |
-
2018
- 2018-09-06 CN CN201821451384.9U patent/CN208762185U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111675370A (en) * | 2020-05-13 | 2020-09-18 | 国家电投集团远达环保工程有限公司重庆科技分公司 | Method and device for modifying desulfurization wastewater concentrated solution |
CN114699893A (en) * | 2022-02-28 | 2022-07-05 | 华电水务工程有限公司 | Resource utilization method for high sulfate radical nanofiltration concentrated water |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101417826B (en) | Method and system for processing desulphurization waste water | |
WO2018214350A1 (en) | Wet desulfurization wastewater resource processing system and processing method therefor | |
CN107739119A (en) | - kind of cascade utilization power-plant flue gas waste heat realizes the device of desulfurization wastewater zero-emission | |
CN108006683A (en) | A kind of method and apparatus that desulfurization wastewater zero-emission is realized using full flue gas | |
CN205953746U (en) | Zero discharge system of coal fired power plant waste water | |
CN205556138U (en) | Shell -and -tube desulfurization waste water flue gas evaporative concentration device | |
CN106745427A (en) | A kind of low-temp low-pressure desulfurization wastewater evaporating and technique | |
CN206940653U (en) | Desulphurization for Coal-fired Power Plant waste water zero discharge device | |
CN107986365A (en) | A kind of fluoroplastics falling film evaporator that desulfurization wastewater concentration is carried out using fume afterheat | |
CN105174584A (en) | Zero discharging processing device of desulfurization waste water | |
CN104529038B (en) | The good antiscale property evaporative crystallization treatment process of coal-burning power plant's wet desulphurization waste water and system | |
CN107324430A (en) | A kind of method and apparatus that wastewater zero discharge is realized based on multiple-effect sound wave effect | |
CN208762185U (en) | A kind of energy-saving system suitable for handling desulfurization wastewater | |
CN103553166A (en) | Device and method of treating wastewater with high salt content by utilizing waste heat of circulating water | |
CN206142861U (en) | Concentrated system of thermal power plant's waste water low temperature waste heat | |
CN204356186U (en) | The good antiscale property evaporative crystallization treatment system of coal-burning power plant's wet desulphurization waste water | |
CN109879343A (en) | A kind of processing system and processing method of catalytic cracking and desulfurizing waste water | |
CN213537332U (en) | Comprehensive wastewater treatment system of thermal power plant | |
CN210786877U (en) | Flue gas waste heat evaporation crystallization zero discharge system | |
CN205974125U (en) | Desulfurization waste water zero release processing system | |
CN207933199U (en) | - kind of cascade utilization power-plant flue gas waste heat realizes the device of desulfurization wastewater zero-emission | |
CN111592199A (en) | Low-temperature spraying landfill leachate concentrated solution zero-discharge system | |
CN106865667A (en) | A kind of desulfurization wastewater fume afterheat concentrates abatement system and its technique | |
CN206529366U (en) | leather waste water treatment system | |
CN208454723U (en) | The online desalination of dangerous waste incineration flue gas washes and reclaiming system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20190419 Termination date: 20190906 |
|