CN208734116U - A kind of steel pipe tower bracing means - Google Patents

A kind of steel pipe tower bracing means Download PDF

Info

Publication number
CN208734116U
CN208734116U CN201821305645.6U CN201821305645U CN208734116U CN 208734116 U CN208734116 U CN 208734116U CN 201821305645 U CN201821305645 U CN 201821305645U CN 208734116 U CN208734116 U CN 208734116U
Authority
CN
China
Prior art keywords
fixed plate
tower body
steel pipe
wall
fixing piece
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201821305645.6U
Other languages
Chinese (zh)
Inventor
宋珺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
GUANGDONG JIDA TOWER TECHNOLOGY Co Ltd
Original Assignee
GUANGDONG JIDA TOWER TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GUANGDONG JIDA TOWER TECHNOLOGY Co Ltd filed Critical GUANGDONG JIDA TOWER TECHNOLOGY Co Ltd
Priority to CN201821305645.6U priority Critical patent/CN208734116U/en
Application granted granted Critical
Publication of CN208734116U publication Critical patent/CN208734116U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Suspension Of Electric Lines Or Cables (AREA)

Abstract

The utility model discloses a kind of steel pipe tower bracing means, including tower body, clamping plate and fixing piece, the lower end surrounding of the tower body is connected with reinforcing rib, and the lower end outer wall of tower body is equipped with fixed plate, the inside both ends of the fixed plate are fixed with sealing ring, and the inner wall surrounding of fixed plate inlays with teeth piece, the clamping plate is set to the two sides of fixed plate, and the middle inside of clamping plate is through there is wirerope, the fixing piece is connected to the end two sides of wirerope, and cylinder is installed on the left of fixing piece, the bottom of the cylinder is inlaid with pedestal.The steel pipe tower bracing means is provided with fixed plate, fixed plate is bonded to each other by the outer wall of tooth block and tower body, fixed plate plays the role of good fix to clamp, when user installs fixed plate to tower body, tooth block is mutually twisted with tower body outer wall, fixed plate is in coniform coniform identical as tower body simultaneously, and when user installs fixed plate into tower body, fixed plate can be fitted closely with tower body.

Description

A kind of steel pipe tower bracing means
Technical field
The utility model relates to steel pipe tower technical field, specially a kind of steel pipe tower bracing means.
Background technique
Steel pipe tower: main component steel pipe, the lattice tower of the compositions such as other component steel pipes or fashioned iron, is aerial Transmission line of electricity supports the support structure of conducting wire and lightning conducter, so that conducting wire is met range line requirement to ground, atural object, and can bear to lead Line, lightning conducter and the load of itself and external load, device for reinforcing bottom determine steel pipe tower construction height, and bracing means is being built Play the role of when steel pipe tower vital.
Existing bracing means is mostly easy welding reinforcing rib to steel pipe tower progress consolidation process in use, so that Consolidation effect is bad, at the same when steel pipe tower for a long time use may occur slight shift in use cannot to steel pipe tower into The subtle adjustment of row, makes troubles to user, for this purpose, it is proposed that a kind of steel pipe tower bracing means.
Utility model content
The purpose of this utility model is to provide a kind of steel pipe tower bracing means, to solve to propose in above-mentioned background technique Bracing means be in use mostly that easy welding reinforcing rib carries out consolidation process to steel pipe tower so that consolidation effect is not It is good, while when slight shift may occur for steel pipe tower use for a long time subtle tune cannot be carried out to steel pipe tower in use It is whole, the problem of making troubles to user.
To achieve the above object, the utility model provides the following technical solutions: a kind of steel pipe tower bracing means, including tower Body, clamping plate and fixing piece, the lower end surrounding of the tower body is connected with reinforcing rib, and the lower end outer wall of tower body is equipped with fixed plate, The inside both ends of the fixed plate are fixed with sealing ring, and the inner wall surrounding of fixed plate inlays with teeth piece, and the clamping plate is set to The two sides of fixed plate, and the middle inside of clamping plate, through there is wirerope, the fixing piece is connected to the end two sides of wirerope, and Cylinder is installed, the bottom of the cylinder is inlaid with pedestal, and the top two sides of pedestal are fixed with screw, institute on the left of fixing piece It states and is provided with mounting plate in the middle part of the outer wall of tower body, and the outer wall surrounding of mounting plate is connected with connection ring, the two sides of the connection ring Connecting rod is installed, the middle inside of the connection ring, which runs through, screw rod, and the two sides of screw rod are inlaid with bolt.
Preferably, the fixed plate is in coniform, and fixed plate is bonded to each other by the outer wall of tooth block and tower body.
Preferably, the fixing piece is distributed in eight shape, and fixing piece is fixedly connected by clamping plate with fixed plate.
Preferably, the perpendicular shape distribution of the cylinder, and cylinder is symmetrical along the central axes of tower body.
Preferably, the equidistant middle inside for being evenly distributed on connection ring of the screw rod, and connection ring passes through bolt and silk Bar, which is constituted, to be threadedly coupled.
Preferably, the sealing ring is bonded to each other along the inner wall of fixed plate, and is Nian Jie between sealing ring and fixed plate.
Compared with prior art, the utility model has the beneficial effects that the steel pipe tower bracing means is provided with fixed plate, Fixed plate is bonded to each other by the outer wall of tooth block and tower body, fixed plate play the role of it is good fix to clamp, when user will consolidate When fixed board is installed to tower body, tooth block is mutually twisted with tower body outer wall, while fixed plate is in coniform coniform identical as tower body, When user installs fixed plate into tower body, fixed plate can be fitted closely with tower body, reduced and stitched between fixed plate and tower body Gap facilitates subsequent installation, and the inside both ends of fixed plate are fixed with sealing ring, is Nian Jie, sealing ring between sealing ring and fixed plate It is made up of rubber material, there is certain elasticity, gap between tower body and fixed plate can be effectively reduced, guarantee whole device The stability of structure, while can also prevent rainwater from flowing into from gap, fixed plate inner wall is corroded, the left side of fixing piece Cylinder fixing piece is installed and is fixedly connected by clamping plate with fixed plate, two fixing pieces form a complete splayed configuration and fix Part prevents single fixing piece fixed-area in use inadequate, easily leads to fixing piece and fall off from cylinder outer wall, the bottom edge of cylinder Embedded with pedestal, cylinder is symmetrical along the central axes of tower body, and infrastructure device of the cylinder as fixed device plays good load-bearing The effect of fixed limit, two cylinders, which are arranged, can effectively ensure that stability in solid timing architecture, prevent single in use The case where cylinder effectively can not be fixed tower body, tower body is caused to collapse.
Detailed description of the invention
Fig. 1 is this Practical obverse new structure schematic diagram;
Fig. 2 is the utility model connection ring attachment structure schematic diagram;
Fig. 3 is the utility model fixed plate cross section structure schematic diagram.
In figure: 1, tower body;2, reinforcing rib;3, fixed plate;4, clamping plate;5, wirerope;6, fixing piece;7, cylinder;8, pedestal; 9, screw;10, mounting plate;11, connection ring;12, connecting rod;13, screw rod;14, bolt;15, sealing ring;16, tooth block.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work Every other embodiment obtained, fall within the protection scope of the utility model.
Fig. 1-3 is please referred to, the utility model provides a kind of technical solution: a kind of steel pipe tower bracing means, including tower body 1, reinforcing rib 2, fixed plate 3, clamping plate 4, wirerope 5, fixing piece 6, cylinder 7, pedestal 8, screw 9, mounting plate 10, connection ring 11, Connecting rod 12, screw rod 13, bolt 14, sealing ring 15 and tooth block 16, the lower end surrounding of tower body 1 are connected with reinforcing rib 2, and tower body 1 Lower end outer wall is equipped with fixed plate 3, and fixed plate 3 is in coniform, and fixed plate 3 is mutually pasted by tooth block 16 and the outer wall of tower body 1 Close, fixed plate 3 play the role of it is good fix to clamp, when user by the installation of fixed plate 3 in tower body 1 when, tooth block 16 and tower 1 outer wall of body is mutually twisted, while fixed plate 3 is in coniform coniform identical as tower body 1, when user by fixed plate 3 install into When tower body 1, fixed plate 3 can be fitted closely with tower body 1, reduced gap between fixed plate 3 and tower body 1, facilitated subsequent installation, Gu The inside both ends of fixed board 3 are fixed with sealing ring 15, and the inner wall surrounding of fixed plate 3 inlays with teeth piece 16, and sealing ring 15 is along fixation The inner wall of plate 3 is bonded to each other, and to be Nian Jie between sealing ring 15 and fixed plate 3, sealing ring 15 is made up of rubber material, has Certain elasticity can effectively reduce gap between tower body 1 and fixed plate 3, guarantee the stability of whole device structure, while It can prevent rainwater from flowing into from gap, 3 inner wall of fixed plate is corroded, clamping plate 4 is set to the two sides of fixed plate 3, and presss from both sides For the middle inside of plate 4 through there is wirerope 5, fixing piece 6 is connected to the end two sides of wirerope 5, and the left side installation of fixing piece 6 There is cylinder 7, fixing piece 6 is distributed in eight shape, and fixing piece 6 is fixedly connected by clamping plate 4 with fixed plate 3, and two 6 groups of fixing piece At a complete splayed configuration fixing piece 6, prevent in use single 6 fixed-area of fixing piece it is inadequate, easily lead to fixing piece 6 from 7 outer wall of cylinder falls off, and the bottom of cylinder 7 is inlaid with pedestal 8, and the top two sides of pedestal 8 are fixed with screw 9, and cylinder 7 is perpendicular Shape distribution, and cylinder 7 is symmetrical along the central axes of tower body 1, infrastructure device of the cylinder 7 as fixed device plays good The effect of the fixed limit of load-bearing, two cylinders 7, which are arranged, can effectively ensure that stability in solid timing architecture, prevent in use The outer wall middle part of the case where single cylinder 7 effectively can not be fixed tower body 1, tower body 1 is caused to collapse, tower body 1 is provided with peace Loading board 10, and the outer wall surrounding of mounting plate 10 is connected with connection ring 11, the two sides of connection ring 11 are equipped with connecting rod 12, connection ring 11 Middle inside through there is screw rod 13, and the two sides of screw rod 13 are inlaid with bolt 14, and screw rod 13 is equidistant to be evenly distributed on connection The middle inside of ring 11, and connection ring 11 is threadedly coupled by bolt 14 with the composition of screw rod 13, when the use of 1 long-time of tower body may Subtle inclination occurs, user can rotate bolt 14 at this time, and bolt 14 drives connection ring 11 inwardly to be collapsed, when tower body 1 When tilting to the left, user can rotate right side bolt 14, and connection ring 11 inwardly collapses, and tower body 1 is tilted to the right, uses at this time Person is detected using horizontal ruler, until the perpendicular shape of tower body 1 is distributed.
Working principle: this kind of steel pipe tower bracing means is placed on by the cylinder 7 that will have been built in advance first 1 two sides of tower body, the perpendicular shape of cylinder 7 are put, and fixed plate 3 is inserted in tower body 1, and tooth block 16 is mutually twisted with 1 outer wall of tower body, simultaneously Fixed plate 3 is in coniform coniform identical as tower body 1, and when user installs fixed plate 3 into tower body 1, fixed plate 3 can be with Tower body 1 fits closely, and sealing ring 15 is bonded to each other with 1 outer wall of tower body, and user's clamping plate 4 is welded into 3 two sides of fixed plate at this time, will Wirerope 5 penetrates in clamping plate 4 and fixing piece 6, then welds mounting plate 10 and tower body 1, connection ring 11 is put into installation 10 surrounding of plate is connected by connecting rod 12 with cylinder 7, when after the installation is completed, user examines tower body 1 by horizontal ruler It surveys, when subtle inclination may occur for 1 long-time use of tower body, user can rotate bolt 14 at this time, and bolt 14 drives connection Ring 11 is inwardly collapsed, and when tower body 1 tilts to the left, user can rotate right side bolt 14, and connection ring 11 is inwardly received Hold together, tower body 1 is tilted to the right, until the perpendicular shape of tower body 1 is distributed, last user is by rechecking tower body 1, when tower body 1 When perpendicular shape is distributed, user can be safe to use, completes the use process of entire steel pipe tower bracing means like this.
While there has been shown and described that the embodiments of the present invention, for the ordinary skill in the art, It is understood that these embodiments can be carried out with a variety of variations in the case where not departing from the principles of the present invention and spirit, repaired Change, replacement and variant, the scope of the utility model is defined by the appended claims and the equivalents thereof.

Claims (6)

1. a kind of steel pipe tower bracing means, including tower body (1), clamping plate (4) and fixing piece (6), it is characterised in that: the tower body (1) lower end surrounding is connected with reinforcing rib (2), and the lower end outer wall of tower body (1) is equipped with fixed plate (3), the fixed plate (3) Inside both ends be fixed with sealing ring (15), and the inner wall surrounding of fixed plate (3) is inlayed with teeth piece (16), and the clamping plate (4) sets The two sides of fixed plate (3) are placed in, and the middle inside of clamping plate (4), through having wirerope (5), the fixing piece (6) is connected to steel The end two sides of cord (5), and cylinder (7) are installed on the left of fixing piece (6), the bottom of the cylinder (7) is inlaid with pedestal (8), and the top two sides of pedestal (8) are fixed with screw (9), are provided with mounting plate (10) in the middle part of the outer wall of the tower body (1), and The outer wall surrounding of mounting plate (10) is connected with connection ring (11), and the two sides of the connection ring (11) are equipped with connecting rod (12), described The middle inside of connection ring (11), which runs through, to be had screw rod (13), and the two sides of screw rod (13) are inlaid with bolt (14).
2. a kind of steel pipe tower bracing means according to claim 1, it is characterised in that: the fixed plate (3) is in circular cone Shape, and fixed plate (3) is bonded to each other by tooth block (16) and the outer wall of tower body (1).
3. a kind of steel pipe tower bracing means according to claim 1, it is characterised in that: the fixing piece (6) is in eight words Shape distribution, and fixing piece (6) is fixedly connected by clamping plate (4) with fixed plate (3).
4. a kind of steel pipe tower bracing means according to claim 1, it is characterised in that: the perpendicular shape of the cylinder (7) Distribution, and cylinder (7) is symmetrical along the central axes of tower body (1).
5. a kind of steel pipe tower bracing means according to claim 1, it is characterised in that: the screw rod (13) is equidistant The even middle inside for being distributed in connection ring (11), and connection ring (11) is made up of with screw rod (13) bolt (14) and is threadedly coupled.
6. a kind of steel pipe tower bracing means according to claim 1, it is characterised in that: the sealing ring (15) is along fixation The inner wall of plate (3) is bonded to each other, and is Nian Jie between sealing ring (15) and fixed plate (3).
CN201821305645.6U 2018-08-13 2018-08-13 A kind of steel pipe tower bracing means Expired - Fee Related CN208734116U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821305645.6U CN208734116U (en) 2018-08-13 2018-08-13 A kind of steel pipe tower bracing means

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821305645.6U CN208734116U (en) 2018-08-13 2018-08-13 A kind of steel pipe tower bracing means

Publications (1)

Publication Number Publication Date
CN208734116U true CN208734116U (en) 2019-04-12

Family

ID=66029274

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821305645.6U Expired - Fee Related CN208734116U (en) 2018-08-13 2018-08-13 A kind of steel pipe tower bracing means

Country Status (1)

Country Link
CN (1) CN208734116U (en)

Similar Documents

Publication Publication Date Title
CN203795942U (en) Tower reinforcing support structure
CN208521742U (en) A kind of device for fixing transformer
CN208734116U (en) A kind of steel pipe tower bracing means
CN107339012A (en) A kind of high construction enclosing of security performance
CN206785083U (en) A kind of combined pole with high firm support performance
CN210622322U (en) Detachable temporary support for constructional engineering construction
CN201665991U (en) Combined supporting frame
CN204168835U (en) Green house moulded by a kind of wood
CN104005410A (en) Tensioning and anchoring device based on unbonded prestress reinforced soil technology
CN210316624U (en) Precast beam bracing structure
CN209179513U (en) Spacer is used in a kind of binding of reinforcing bar
CN209114879U (en) Coagulation pump pipe fixing device can be had enough to meet the need
CN203891022U (en) Tensioning and anchoring device based on unbonded prestressing reinforced soil technology
CN208981886U (en) A kind of admixture high energy fiber-reactive powder concrete electrical pole
CN207729053U (en) A kind of natural gas tube channel fixing device
CN209244372U (en) A kind of high intensity wind resistance electric power tower
CN207277160U (en) Road rehabilitation device
CN217076777U (en) Tower crane attachment system for frame structure
CN209313392U (en) A kind of cable bearer for municipal works
CN204418635U (en) Bracing frame is combined bottom a kind of scaffold for building
CN207957567U (en) A kind of prefabricated hanging beam structure of building industrialization for anti-macroseism
CN204920416U (en) Simple and easy transmission tower structure
CN213062839U (en) Scaffold frame for building engineering that security performance is high
CN211500005U (en) Distribution network construction is with strutting bearing diagonal structure
CN214100770U (en) Cable supporting mechanism convenient for cable installation

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190412

Termination date: 20190813