CN208701448U - A kind of ventilating drainage type plastic cement race track - Google Patents

A kind of ventilating drainage type plastic cement race track Download PDF

Info

Publication number
CN208701448U
CN208701448U CN201721600825.2U CN201721600825U CN208701448U CN 208701448 U CN208701448 U CN 208701448U CN 201721600825 U CN201721600825 U CN 201721600825U CN 208701448 U CN208701448 U CN 208701448U
Authority
CN
China
Prior art keywords
layer
plastic cement
silica gel
race track
cement race
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721600825.2U
Other languages
Chinese (zh)
Inventor
张书申
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Sheng Tian Sports Ltd By Share Ltd
Original Assignee
Guangdong Sheng Tian Sports Ltd By Share Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Sheng Tian Sports Ltd By Share Ltd filed Critical Guangdong Sheng Tian Sports Ltd By Share Ltd
Priority to CN201721600825.2U priority Critical patent/CN208701448U/en
Application granted granted Critical
Publication of CN208701448U publication Critical patent/CN208701448U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Road Paving Structures (AREA)

Abstract

The utility model discloses a kind of ventilating drainage type plastic cement race tracks, including plastic layer, layer of silica gel, buffer layer, boulder bed, rubber slab, steel screen layer and concrete layer, the bottom of plastic layer is provided with layer of silica gel, several apertures are offered in plastic layer and layer of silica gel, buffer layer is provided with below layer of silica gel, foam core is uniformly provided in buffer layer, the bottom of buffer layer is provided with the first wearing layer, the bottom of first wearing layer is provided with boulder bed, the bottom of boulder bed is provided with the second wearing layer, rubber slab is provided with below second wearing layer, by the way that aperture is arranged, ponding can not only effectively be arranged, and increase gas permeability, when runway is squeezed, the gas that lower section squeezes out can be discharged by aperture, the foam core of setting has heat-insulated, sound-absorbing, shock-absorbing function, and quality is lighter, by the way that boulder bed is arranged, both it can increase plastic cement The robustness of runway, and facilitate draining, wearing layer solves the problems, such as that cobble hardness is larger and is prone to wear upper and lower level.

Description

A kind of ventilating drainage type plastic cement race track
Technical field
The utility model relates to a kind of plastic cement race tracks, more particularly, to a kind of ventilating drainage type plastic cement race track.
Background technique
Plastic cement race track is also known as round-the-clock athletics tracks, it by base polyurethane prepolymer for use as, admixtured polyether, scrap tire rubber, EPDM rubber grain or PU particle, pigment, auxiliary agent, filler composition.Plastic cement race track is with flatness is good, compression strength is high, hardness bullet Property appropriate, stable physical property characteristic, be conducive to the performance of sportsman's speed and technology, effectively improve sports achievement, drop Low tumble injury rate.Plastic cement race track is made of materials such as polyurethane rubbers, has certain elasticity and color, has certain resist UV resistance and ageing-resistant power are best all-weather outdoor athletic ground terrace materials generally acknowledged in the world.
Existing plastic cement race track is to be beforehand with into coiled material mostly, and coiled material is transported on sports ground by truck, then is borrowed A large amount of human and material resources are helped to go to carry and construct.Coiled material is the main part of plastic cement race track, and material used in coiled material decides the modeling The overall performance of glue runway, and plastic cement race track is laid on outdoor occasion mostly, existing plastic cement race track drainage is poor, and runway is easy Ponding influences the normal use of runway, it is therefore desirable to a kind of ventilating drainage type plastic cement race track.
Utility model content
Problem to be solved in the utility model is to overcome existing plastic cement race track drainage poor, and runway is easy ponding, is influenced The defect of the normal use of runway provides a kind of ventilating drainage type plastic cement race track, to solve the above problems.
To achieve the above object, the utility model provides the following technical solutions: a kind of ventilating drainage type plastic cement race track, including The bottom of plastic layer, layer of silica gel, buffer layer, boulder bed, rubber slab, steel screen layer and concrete layer, the plastic layer is provided with Layer of silica gel offers several apertures in the plastic layer and layer of silica gel, buffer layer is provided with below the layer of silica gel, described Foam core is uniformly provided in buffer layer, the bottom of the buffer layer is provided with the first wearing layer, the bottom of first wearing layer It is provided with boulder bed, the bottom of the boulder bed is provided with the second wearing layer, is provided with rubber below second wearing layer Plate is provided with steel screen layer below the rubber slab, and the bottom of the steel screen layer is provided with concrete layer.
As a kind of optimal technical scheme of the utility model, the aperture is equidistant to be evenly distributed on plastic layer and silica gel In layer.
As a kind of optimal technical scheme of the utility model, the foam core is cubic shaped.
As a kind of optimal technical scheme of the utility model, the plastic layer is by granular polyurethane and epoxy resin Glue is made.
As a kind of optimal technical scheme of the utility model, the foam core is entwined by polyethylene film.
As a kind of optimal technical scheme of the utility model, first wearing layer and the second wearing layer are by identical Wear-resistant material is made.
As a kind of optimal technical scheme of the utility model, the steel wire diameter of the steel screen layer is in 1.2-2mm.
As a kind of optimal technical scheme of the utility model, hard polyurethane foam modeling is provided in the buffer layer Material.
Compared with current technology, the beneficial effects of the utility model are: this kind of ventilating drainage type plastic cement race track, structure design It is complete compact, by setting aperture, ponding can not only be effectively arranged, and increase gas permeability, when runway is squeezed, lower section The gas of extrusion can be discharged by aperture, and the foam core of setting has heat-insulated, sound-absorbing, shock-absorbing function, and quality is lighter, be reduced The weight of runway not only can increase the robustness of plastic cement race track, but also facilitate draining, wearing layer solves ovum by the way that boulder bed is arranged Stone hardness larger the problem of being prone to wear upper and lower level, greatly strengthens sound absorption function, reduces plastic cement race track by the way that rubber slab is arranged On noise, the elasticity of steel screen layer is big, increases buffering, can effectively reduce the probability of people's tumble injury, and the utility model designs Reasonable and practical is suitble to promote the use of.
Detailed description of the invention
Attached drawing is used to provide a further understanding of the present invention, and constitutes part of specification, practical with this Novel embodiment is used to explain the utility model together, does not constitute limitations of the present invention.In the accompanying drawings:
Fig. 1 is the structural schematic diagram of the utility model;
In figure: 1, plastic layer;2, layer of silica gel;3, buffer layer;4, foam core;5, boulder bed;6, the first wearing layer;7, second Wearing layer;8, rubber slab;9, steel screen layer;10, concrete layer;11, aperture.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment, based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work Every other embodiment obtained, fall within the protection scope of the utility model.
Referring to Fig. 1, the utility model provides a kind of technical solution: a kind of ventilating drainage type plastic cement race track, including plastic cement Layer 1, layer of silica gel 2, buffer layer 3, boulder bed 5, rubber slab 8, steel screen layer 9 and concrete layer 10, the bottom of plastic layer 1 are provided with Several apertures 11 are offered in layer of silica gel 2, plastic layer 1 and layer of silica gel 2, the lower section of layer of silica gel 2 is provided with buffer layer 3, buffering It is uniformly provided with foam core 4 in layer 3, the bottom of buffer layer 3 is provided with the first wearing layer 6, and the bottom of the first wearing layer 6 is provided with ovum Rock layers 5, the bottom of boulder bed 5 are provided with the second wearing layer 7, and the lower section of the second wearing layer 7 is provided with rubber slab 8, rubber slab 8 Lower section is provided with steel screen layer 9, and the bottom of steel screen layer 9 is provided with concrete layer 10.
Aperture 11 is equidistant to be evenly distributed in plastic layer 1 and layer of silica gel 2, and foam core 4 is cubic shaped, plastic layer 1 It is made of granular polyurethane and epoxy resin glue, foam core 4 is entwined by polyethylene film, 6 He of the first wearing layer Second wearing layer 7 is made of identical wear-resistant material, the setting in 1.2-2mm, buffer layer 3 of the steel wire diameter of steel screen layer 9 There is polyurethane rigid foam plastic.
Concrete principle: when using the ventilating drainage type plastic cement race track, rainy day, rainwater can penetrate into buffering by aperture 11 Layer 3, the polyurethane rigid foam plastic in buffer layer 3 have heat insulation function, can avoid icing on runway, foam core 4 have damping, Light feature can reduce impact force, avoid injury when people tumble on runway, and rainwater may penetrate into boulder bed 5, keep away Exempt from the ponding on plastic layer 1, the sound absorption function of rubber slab 8 is stronger, reduce confused noise of the people on runway, steel screen layer 9 It is elastic big, equally increase cushion effect.
This kind of ventilating drainage type plastic cement race track, structure design is complete compact, by the way that aperture 11 is arranged, can not only effectively arrange product Water, and gas permeability is increased, when runway is squeezed, the gas that lower section squeezes out can be discharged by aperture 11, the bubble of setting Foam core 4 has heat-insulated, sound-absorbing, shock-absorbing function, and quality is lighter, reduces the weight of runway, can by the way that boulder bed 5 is arranged Increasing the robustness of plastic cement race track, and facilitates draining, wearing layer solves the problems, such as that cobble hardness is larger and is prone to wear upper and lower level, By the way that rubber slab 8 is arranged, sound absorption function is greatly strengthened, the noise on plastic cement race track is reduced, the elasticity of steel screen layer 9 is big, increases Big buffering, can effectively reduce the probability of people's tumble injury, the utility model is designed reasonably and practical, be suitble to promote the use of.
Finally, it should be noted that the above descriptions are merely preferred embodiments of the present invention, it is not limited to this Utility model, although the utility model is described in detail with reference to the foregoing embodiments, for those skilled in the art For, it is still possible to modify the technical solutions described in the foregoing embodiments, or to part of technical characteristic It is equivalently replaced, within the spirit and principle of the utility model, any modification, equivalent replacement, improvement and so on, It should be included within the scope of protection of this utility model.

Claims (7)

1. a kind of ventilating drainage type plastic cement race track, including plastic layer (1), layer of silica gel (2), buffer layer (3), boulder bed (5), rubber Plate (8), steel screen layer (9) and concrete layer (10), which is characterized in that the bottom of the plastic layer (1) is provided with layer of silica gel (2), it offers several apertures (11) in the plastic layer (1) and layer of silica gel (2), is provided with below the layer of silica gel (2) Buffer layer (3), the buffer layer (3) is interior to be uniformly provided with foam core (4), and it is wear-resisting that the bottom of the buffer layer (3) is provided with first Layer (6), the bottom of first wearing layer (6) are provided with boulder bed (5), and it is resistance to that the bottom of the boulder bed (5) is provided with second It grinds layer (7), is provided with rubber slab (8) below second wearing layer (7), is provided with steel wire below the rubber slab (8) The bottom of stratum reticulare (9), the steel screen layer (9) is provided with concrete layer (10).
2. a kind of ventilating drainage type plastic cement race track according to claim 1, which is characterized in that the aperture (11) is equidistant It is evenly distributed in plastic layer (1) and layer of silica gel (2).
3. a kind of ventilating drainage type plastic cement race track according to claim 1, which is characterized in that the foam core (4) is vertical Cube shape.
4. a kind of ventilating drainage type plastic cement race track according to claim 1, which is characterized in that the foam core (4) is by gathering Vinyl film is entwined.
5. a kind of ventilating drainage type plastic cement race track according to claim 1, which is characterized in that first wearing layer (6) It is made with the second wearing layer (7) of identical wear-resistant material.
6. a kind of ventilating drainage type plastic cement race track according to claim 1, which is characterized in that the steel screen layer (9) Steel wire diameter is in 1.2-2mm.
7. a kind of ventilating drainage type plastic cement race track according to claim 1, which is characterized in that set in the buffer layer (3) It is equipped with polyurethane rigid foam plastic.
CN201721600825.2U 2017-11-27 2017-11-27 A kind of ventilating drainage type plastic cement race track Expired - Fee Related CN208701448U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721600825.2U CN208701448U (en) 2017-11-27 2017-11-27 A kind of ventilating drainage type plastic cement race track

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721600825.2U CN208701448U (en) 2017-11-27 2017-11-27 A kind of ventilating drainage type plastic cement race track

Publications (1)

Publication Number Publication Date
CN208701448U true CN208701448U (en) 2019-04-05

Family

ID=65912060

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721600825.2U Expired - Fee Related CN208701448U (en) 2017-11-27 2017-11-27 A kind of ventilating drainage type plastic cement race track

Country Status (1)

Country Link
CN (1) CN208701448U (en)

Similar Documents

Publication Publication Date Title
CN203923854U (en) A kind of chinampa of built-in groove
CN206858995U (en) A kind of plastic cement race track layer structure
CN208701448U (en) A kind of ventilating drainage type plastic cement race track
CN209039915U (en) A kind of weeping plastic track
CN105507116A (en) Novel, environment-friendly and breathable plastic playground
CN207227895U (en) A kind of high strength plastic runway
CN212000468U (en) Self-knotting course with wavy lines
CN205387654U (en) Structure of mating formation of permeating water
CN206752248U (en) A kind of vapor-permeable type plastic cement race track
CN209555701U (en) A kind of novel ventilated plastic cement race track
CN110904777A (en) Ventilative plastic course
CN208857621U (en) A kind of fluorescence body-building pavement
CN209907151U (en) Novel artificial turf of infiltration structure
CN215482092U (en) Hydrophobic plastic course structure
CN211420768U (en) Environment-friendly high-elasticity self-knotting track
CN208517769U (en) A kind of silicon PU plastic sports ground
CN206692984U (en) A kind of no-solvent type wood grain type silicon PU runways
CN206752251U (en) A kind of KPU is modified playground
CN211972972U (en) Prefabricated type plastic course
CN217948653U (en) Anti ultraviolet mixed type athletic ground runway
CN217781627U (en) Water-permeable and breathable multifunctional rubber runway
CN209194276U (en) A kind of high rebound mixed type runway
CN211171491U (en) Anti-aging self-knotting runway
CN213233022U (en) Ventilative type plastic course with drainage function
CN205934651U (en) Ventilative drainage type sport field ground

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190405

Termination date: 20211127

CF01 Termination of patent right due to non-payment of annual fee