CN208697408U - Steel pipe bearing bracket - Google Patents
Steel pipe bearing bracket Download PDFInfo
- Publication number
- CN208697408U CN208697408U CN201821399402.3U CN201821399402U CN208697408U CN 208697408 U CN208697408 U CN 208697408U CN 201821399402 U CN201821399402 U CN 201821399402U CN 208697408 U CN208697408 U CN 208697408U
- Authority
- CN
- China
- Prior art keywords
- steel pipe
- boss
- gag lever
- lever post
- bearing bracket
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
Steel pipe bearing bracket belongs to steel pipe technical field of memory, purpose is to propose a kind of steel pipe bearing bracket, solve the problems, such as steel pipe of the existing technology put take up a large area, there are security risk, handling process large labor intensity and steel pipes easily to slide, adapt to putting and carrying for the steel pipe of various outer diameter.The utility model includes: to bear plate, and the plate upper surface that bears is uniformly arranged multiple discharging grooves, and multiple discharging grooves are arranged in parallel, and boss is formed between two neighboring containing tank, and each boss upper surface both ends are provided with fixation hole;With any one fixation gag lever post being fixedly connected in two boss of two sides, the fixed gag lever post and the boss are vertically arranged, and the fixed gag lever post is telescopic rod;Placement area adjustment mechanism on an any other boss is set, forms the placement area of steel pipe between the placement area adjustment mechanism and the fixed gag lever post;And the adaptive clamp system at both ends in the slot of each discharging groove is set.
Description
Technical field
The utility model belongs to steel pipe technical field of memory, and in particular to a kind of steel pipe bearing bracket.
Background technique
In steel pipe processing enterprise, the storage of the steel pipe of batch production and transport are relatively difficult, due to the particularity of steel pipe,
Cylinder-like structure, length is longer, arbitrarily stacks, steel pipe, which freely rolls, be easy to cause collapsing, and there are some potential safety problemss, separately
Outside, due to its cylinder-like structure, it is also difficult to stack higher height, take up a large area, work in carrying or transportational process strong
Degree is big, while being easy to produce the phenomenon that single steel pipe is tumbled along degree direction, dangerous, for different requirements.
Utility model content
The purpose of this utility model is that propose a kind of steel pipe bearing bracket, solve steel pipe of the existing technology and put to account for
Ground area is big, there are problems that security risk, handling process large labor intensity and steel pipe easily slide, and adapts to the steel of various outer diameter
Pipe being put and carrying.
To achieve the above object, the steel pipe bearing bracket of the utility model includes:
Plate is born, the plate upper surface that bears is uniformly arranged multiple discharging grooves, and multiple discharging grooves are arranged in parallel, two neighboring
Boss is formed between containing tank, each boss upper surface both ends are provided with fixation hole;
With any one fixation gag lever post being fixedly connected in two boss of two sides, the fixed gag lever post and described
Boss is vertically arranged, and the fixed gag lever post is telescopic rod;
Placement area adjustment mechanism on an any other boss is set, the placement area adjustment mechanism and described
The placement area of steel pipe is formed between fixed gag lever post;
And the adaptive clamp system at both ends in the slot of each discharging groove is set.
The steel pipe bearing bracket further includes adjusting gag lever post, the adjusting gag lever post and the placement area adjustment mechanism
The fixation hole at the boss both ends at place is detachably connected, and the adjusting gag lever post is telescopic rod.
Peripherally disposed in the discharging groove to have adjustment tank, adaptive clamp system described in every group is two and is located at
Arc fixture block in adjustment tank, two arc fixture block one end are rotatably assorted with the connecting shaft for bearing trench bottom setting respectively, another
End is free end, and the side that the free end of each arc fixture block is located in adjustment tank is connected with one end of a spring, institute
Connection inside the other end and the adjustment tank of spring is stated, when nature, two arc fixture block free ends are to bearing groove center
Direction is drawn close.
Two opposite sides of the arc fixture block are provided with rubber layer.
Location hole is provided among each boss upper surface, the placement area adjustment mechanism is and the location hole
The block of detachable connection.
The location hole is threaded hole, and the block and the location hole are threadedly coupled.
Positioning hole number at least two on each boss.
The utility model has the following beneficial effects: the steel pipe bearing bracket of the utility model is held by what is be arranged on bearing plate
It puts slot and realizes the positioning of steel pipe in the same plane, avoid rolling, in addition, the both ends in each discharging groove are provided with adaptive folder
Tight mechanism is realized the clamping of steel pipe amount end by adaptive clamp system, adapts to putting for various sizes of steel pipe;In addition,
When putting a small amount of steel pipe, the adjustment of placement area is realized by the cooperation of the location hole on block and corresponding boss, realizes three
Angular to put, when putting more steel pipe, the both ends of boss where block are correspondingly connected with adjusting gag lever post, make all steel pipes
End is put to be rectangular, in addition, fixed gag lever post and adjusting gag lever post are stretching structure, the adjustable height put, and together
The occupied area of sample increases the amount of putting.
Detailed description of the invention
Fig. 1 is the steel pipe bearing bracket overall structure diagram of the utility model;
Fig. 2 is adaptive clamp system part-structure main view in the steel pipe bearing bracket of the utility model;
Fig. 3 is adaptive clamp system part-structure sectional view in the steel pipe bearing bracket of the utility model;
Wherein: 1, bear plate, 101, discharging groove, 102, boss, 103, fixation hole, 104, location hole, 2, fixed gag lever post,
3, placement area adjustment mechanism, 301, block, 4, adaptive clamp system, 401, fixture block, 402, spring, 403, connecting shaft, 5,
Adjust gag lever post.
Specific embodiment
The embodiments of the present invention is described further with reference to the accompanying drawing.
Referring to attached drawing 1- attached drawing 3, the steel pipe bearing bracket of the utility model includes:
Plate 1 is born, 1 upper surface of plate that bears is uniformly arranged multiple discharging grooves 101, and multiple discharging grooves 101 are arranged in parallel,
Boss 102 is formed between two neighboring containing tank, each 102 upper surface both ends of boss are provided with fixation hole 103;Steel pipe pair
It should be put into discharging groove 101;
With any one fixation gag lever post 2 being fixedly connected in two boss 102 of two sides, the fixed gag lever post 2
It is vertically arranged with the boss 102, the fixed gag lever post 2 is telescopic rod;
Placement area adjustment mechanism 3 on an any other boss 102, the placement area adjustment mechanism 3 are set
The placement area of steel pipe is formed between the fixed gag lever post 2;Blocking limit is carried out to the steel pipe at edge, avoids tumbling;
And the adaptive clamp system 4 at both ends in the slot of each discharging groove 101 is set.
The steel pipe bearing bracket further includes adjusting gag lever post 5, and the adjusting gag lever post 5 adjusts machine with the placement area
The fixation hole 103 at 102 both ends of boss where structure 3 is detachably connected, and the adjusting gag lever post 5 is telescopic rod.It is more putting
When steel pipe, the placement area of cube is formed by adjusting gag lever post 5 and fixed gag lever post 2, increases fixed occupied area steel pipe
The amount of putting.
Peripherally disposed in the discharging groove 101 to have adjustment tank, adaptive clamp system 4 described in every group is two
Arc fixture block 401 in adjustment tank, the connecting shaft that two 401 one end of arc fixture block are arranged with 101 bottom of discharging groove respectively
403 are rotatably assorted, and the other end is free end, and the free end of each arc fixture block 401 is located at the side and one in adjustment tank
One end of a spring 402 connects, connection inside the other end of the spring 402 and the adjustment tank, when nature, two arcs
401 free end of clevis block is drawn close to 101 center position of discharging groove.
Two opposite sides of the arc fixture block 401 are provided with rubber layer.When being put into steel pipe, steel pipe is by arc fixture block
401 squeeze into adjustment tank, and the elastic force of contact friction and spring 402 by rubber layer with steel pipe realizes the folder to steel pipe
Tightly.
It is provided with location hole 104 among each 102 upper surface of the boss, the placement area adjustment mechanism 3 is and institute
State the block 301 of 104 detachable connection of location hole.
The location hole 104 is threaded hole, and the block 301 and the location hole 104 are threadedly coupled.
104 quantity at least two of location hole on each boss 102.
1 front and rear sides of plate that bear can place reel, steel wire is provided in reel, steel wire is placed in reel
Or extraction, the steel wire end after extraction are fixedly connected with fixed gag lever post 2 and adjusting gag lever post 5, realize to the steel pipe put
End limited, avoid vibration fall off.
The utility model can also include fixed bandage, and fixed one end of bandage be fixed on fixed gag lever post 2, the other end from
The steel pipe upper end put bypasses and adjusts gag lever post 5 or bear plate 1 and be fixedly connected, and bundlees to the steel pipe put, guarantees steel
The stability of pipe entirety.
Fixed gag lever post 2 described in the utility model and the adjusting gag lever post 5 are stretching structure, specific constructive form
Can be two-part structure, telescopic fashion be it is following any one:
1, two sections of tubular structures are threadedly coupled realization and elongate or shorten.
2, two sections of tubular structure grafting realize the transformed fixation of length by Top fastening screw.
Claims (7)
1. steel pipe bearing bracket characterized by comprising
It bears plate (1), described plate (1) upper surface that bears is uniformly arranged multiple discharging grooves (101), and multiple discharging grooves (101) are parallel
It is arranged, forms boss (102) between two neighboring containing tank, each boss (102) upper surface both ends are provided with fixation hole
(103);
With any one fixation gag lever post (2) being fixedly connected in two boss (102) of two sides, the fixed gag lever post
(2) it is vertically arranged with the boss (102), the fixed gag lever post (2) is telescopic rod;
Placement area adjustment mechanism (3) on an any other boss (102), the placement area adjustment mechanism are set
(3) placement area of steel pipe is formed between the fixed gag lever post (2);
And the adaptive clamp system (4) at both ends is set in the slot of each discharging groove (101).
2. steel pipe bearing bracket according to claim 1, which is characterized in that the steel pipe bearing bracket further includes adjusting limit
Position bar (5), the fixation hole for adjusting boss (102) both ends where gag lever post (5) and the placement area adjustment mechanism (3)
(103) it is detachably connected, the adjusting gag lever post (5) is telescopic rod.
3. steel pipe bearing bracket according to claim 1 or 2, which is characterized in that circumferentially square in the discharging groove (101)
To adjustment tank is provided with, adaptive clamp system (4) described in every group is two arc fixture blocks (401) being located in adjustment tank,
Connecting shaft (403) of two arc fixture block (401) one end respectively with the setting of discharging groove (101) bottom is rotatably assorted, and the other end is
Free end, one end that the free end of each arc fixture block (401) is located at side and a spring (402) in adjustment tank connect
It connects, connection inside the other end of the spring (402) and the adjustment tank, when nature, two arc fixture blocks (401) are freely
It holds to discharging groove (101) center position and draws close.
4. steel pipe bearing bracket according to claim 3, which is characterized in that two arc fixture blocks (401) are opposite
Side is provided with rubber layer.
5. steel pipe bearing bracket according to claim 1 or 2, which is characterized in that in each boss (102) upper surface
Between be provided with location hole (104), the placement area adjustment mechanism (3) is and the location hole (104) detachable connection
Block (301).
6. steel pipe bearing bracket according to claim 5, which is characterized in that the location hole (104) is threaded hole, described
Block (301) and the location hole (104) are threadedly coupled.
7. steel pipe bearing bracket according to claim 1, which is characterized in that the location hole (104) on each boss (102)
Quantity at least two.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821399402.3U CN208697408U (en) | 2018-08-28 | 2018-08-28 | Steel pipe bearing bracket |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821399402.3U CN208697408U (en) | 2018-08-28 | 2018-08-28 | Steel pipe bearing bracket |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208697408U true CN208697408U (en) | 2019-04-05 |
Family
ID=65944641
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201821399402.3U Expired - Fee Related CN208697408U (en) | 2018-08-28 | 2018-08-28 | Steel pipe bearing bracket |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208697408U (en) |
-
2018
- 2018-08-28 CN CN201821399402.3U patent/CN208697408U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103693449A (en) | C-shaped steel automatic stacking machine | |
CN208697408U (en) | Steel pipe bearing bracket | |
CN209089559U (en) | A kind of lodging-prevention support device for nursery stock | |
CN205496998U (en) | Adjustable multiple spot location machine -building anchor clamps | |
CN207150124U (en) | A kind of damper of adjustable-angle | |
CN207642056U (en) | It is a kind of can automatic charging coiling machine bed | |
CN203843559U (en) | Pipe fixing device | |
CN107695758A (en) | A kind of tilting circular tool magazine | |
CN202701699U (en) | Reinforced bar clamping device for wire mesh welding machine | |
CN204264656U (en) | A kind of carrying roller rack | |
CN210437543U (en) | Packing frame | |
CN209551468U (en) | Bracket for grinding pinch roll | |
CN203892712U (en) | Multipurpose pipeline support frame | |
CN206203583U (en) | Large-scale unwrapping wire wheel apparatus | |
CN205096746U (en) | Material feeding device | |
CN206050824U (en) | A kind of belt conveyor support component | |
CN205471500U (en) | Battery toasts automatic unloading system that goes up of anchor clamps | |
CN104164973A (en) | Steel tube fixing mechanism convenient and fast to disassemble and assemble | |
CN205069909U (en) | Cable clamp and fastening system | |
CN205480072U (en) | Laboratory is with camera, cell -phone support frame | |
CN216152329U (en) | Combined cable reel support | |
CN203624237U (en) | Roller locating device | |
CN213170260U (en) | A loading attachment for dry coiler of branch on christmas | |
CN208994955U (en) | A kind of stainless steel tube hanging device | |
CN204929708U (en) | One grows flax sheller unit |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20190405 Termination date: 20200828 |
|
CF01 | Termination of patent right due to non-payment of annual fee |