CN208633239U - A kind of pre-embedded device at sewer pipeline of toilet - Google Patents

A kind of pre-embedded device at sewer pipeline of toilet Download PDF

Info

Publication number
CN208633239U
CN208633239U CN201821254161.3U CN201821254161U CN208633239U CN 208633239 U CN208633239 U CN 208633239U CN 201821254161 U CN201821254161 U CN 201821254161U CN 208633239 U CN208633239 U CN 208633239U
Authority
CN
China
Prior art keywords
compression bar
waterstop joint
locating rod
embedded device
locating piece
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201821254161.3U
Other languages
Chinese (zh)
Inventor
李德建
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan Xing Chang Construction Engineering Co Ltd
Original Assignee
Sichuan Xing Chang Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan Xing Chang Construction Engineering Co Ltd filed Critical Sichuan Xing Chang Construction Engineering Co Ltd
Priority to CN201821254161.3U priority Critical patent/CN208633239U/en
Application granted granted Critical
Publication of CN208633239U publication Critical patent/CN208633239U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Sewage (AREA)

Abstract

The utility model relates to embedded water stop joint technical fields, disclose the pre-embedded device at a kind of sewer pipeline of toilet, aim to solve the problem that waterstop joint the problem of verticality is easy to appear deviation in concrete vibrating in the prior art, including waterstop joint, the locating rod being connected on slab form is inserted in the waterstop joint vertically, the locating rod is equipped with the compression bar that pressure is set at the top of waterstop joint far from one end of slab form, the locating rod is arranged in setting in the middle part of compression bar, and the compression bar both ends are respectively equipped with to the locating piece for being set to waterstop joint top inner wall;The waterstop joint top cover is equipped with covering component.The utility model passes through the compression bar being pressed at the top of waterstop joint that connects in the locating rod and locating rod that are plugged in waterstop joint, it is butted on fixation of the locating piece realization of waterstop joint inner wall to waterstop joint position on cooperation compression bar, its waterstop joint in concrete vibrating is avoided to deviate.

Description

A kind of pre-embedded device at sewer pipeline of toilet
Technical field
The utility model relates to the pre-buried dresses at embedded water stop joint technical field more particularly to a kind of sewer pipeline of toilet It sets.
Background technique
In floor construction work progress, the leakage at sewer pipeline of toilet is relatively common common quality defect;Tradition Construction after to be installed, recycles artificial molding+iron wire to hang the mode of mould through the mode reserving hole frequently with artificial molding Reserving hole, or first not reserving hole are blocked, set by the way of floor perforation using machinery after the completion of concreting Set hole, to concreting after, dug again, slip casting, filling chink, consume a large amount of manpower and material resources.On Two methods are stated, hidden leakage defect removes difficulties, and leakage problems emerge one after another, and careless slightly in the construction process, just holds It easily causes hole location to misplace, and needs to do over again, reduce construction efficiency.
To solve the above-mentioned problems, currently, the Chinese utility model patent that notification number is CN202530518U discloses one Pre-embedded device at kind sewer pipeline of toilet, the built-in pipe including a Transducers Embedded in Concrete plate, the pre-buried bottom of the tube are equipped with Reserved location structure, the pre-buried tube cavity upper and lower ends are respectively equipped with the pipeline connection knot for accessing lower segment pipe and upper segment pipe Structure, built-in pipe top excircle are equipped with seal ring.
Although this pre-embedded device can be fixed on slab form by self-tapping screw before casting concrete, thus Pre-fix the position of pre-embedded device, still, in the casting process of concrete, process of vibrating and it is subsequent construction be easily destroyed it is pre- The connection for burying device and floor, loosens pre-embedded device, and influences its verticality, and then destroys the construction of pre-embedded device Quality.
Utility model content
In view of the deficienciess of the prior art, the utility model provides the pre-buried dress at a kind of sewer pipeline of toilet It sets, has the advantages that guarantee waterstop joint verticality.
To realize the above-mentioned technical purpose, the pre-embedded device at a kind of sewer pipeline of toilet provided by the utility model includes Following technical solution:
Including waterstop joint, the locating rod being connected on slab form is inserted in the waterstop joint vertically, the locating rod is remote One end from slab form is equipped with the compression bar that pressure is set at the top of waterstop joint, and the locating rod is arranged in setting in the middle part of compression bar, and institute Compression bar both ends are stated to be respectively equipped with to the locating piece for being set to waterstop joint top inner wall;The waterstop joint top cover is equipped with covering component.
By adopting the above technical scheme, the compression bar being fixed on slab form is plugged in waterstop joint, and by connecting on compression bar The compression bar connect pushes down waterstop joint, applies pressure from top, waterstop joint is pressed to slab form;Meanwhile being arranged at the both ends of compression bar Upper holder block, the inner wall of waterstop joint is resisted using briquetting, and cooperation compression bar prevents waterstop joint in vertical side the pressuring action of waterstop joint It is displaced upwards and in horizontal direction, to guarantee in casting concrete and when being vibrated, prevention waterstop joint ontology offset vertical Direction, to improve the construction quality of waterstop joint.
In some embodiments, accommodation groove is provided on the slab form, the locating rod bottom end is equipped with and is connected to appearance The positioning plate in slot is set, the positioning plate is penetrated through and is equipped with the positioning bolt being threaded in slab form.
By using above-mentioned technical proposal, it is empty that the setting of solute slot can provide placement for the positioning plate of locating rod bottom Between, and contact area can be increased, improve the stability of installation;Meanwhile positioning plate being fixed on by the setting of positioning bolt and is determined In the slot of position, so that locating rod is fixed on slab form.
In some embodiments, filling is equipped with adhesive layer between the accommodation groove inner wall and positioning plate periphery wall.
By using above-mentioned technical proposal, eliminates threaded connection bring positioning plate and slab form is connected to outer masterpiece The loosening and position error that will appear under.
In some embodiments, the compression bar slides connection on the securing lever along the vertical direction.
By adopting the above technical scheme, it is connected by the sliding of compression bar and locating rod, realizes that compression bar slides in the vertical direction, The distance between compression bar and slab form are adjusted, to adapt to the waterstop joint of different length.
In some embodiments, the locating rod screw thread is plugged on setting in the middle part of compression bar.
By using above-mentioned technical proposal, the position of compression bar can not only be adjusted, adapts to the waterstop joint of different length, moreover it is possible to Compression bar is adjusted to the pressure of waterstop joint using being threadedly coupled, and is clamped waterstop joint, is improved the stability of waterstop joint.
In some embodiments, it is provided with sliding groove along compression bar length direction, the sliding groove penetrates through pressure along the vertical direction Bar setting, the locating piece sliding are connected in sliding groove, and the setting of compression bar bottom end, the sliding groove are stretched out in the locating piece bottom end In be additionally provided with positioning device for controlling locating piece position.
By adopting the above technical scheme, position of the locating piece on compression bar is realized by the setting of sliding groove, and stretches bottom end The locating piece of compression bar bottom setting can be connected to the inner wall of the waterstop joint of different inner diameters out, improve its applicability.
In some embodiments, the positioning device includes locating piece top spaced two pieces of folders along the vertical direction Plate, from locating piece periphery, horizontal extension is arranged the clamping plate around, and the compression bar of sliding groove length direction two sides is inserted respectively It is connected between two clamping plates of locating piece two sides and is arranged, one clamping plate of perforation is equipped with the fastening bolt for being connected to compression bar side wall.
By using above-mentioned technical proposal, the interval setting of two clamping plates can be clipped in compression bar two sides, can guide-localization block Sliding, moreover it is possible to avoid its from being detached from compression bar, meanwhile, the setting of fastening bolt can be consolidated after locating piece adjusts good position It is fixed, avoid it from the position-limiting action for deviating and influencing locating piece to waterstop joint occur when being butted on waterstop joint inner wall.
In some embodiments, the locating piece cooperates waterstop joint inner wall camber close to waterstop joint inner body wall side Setting.
By using above-mentioned technical proposal, what the locating piece side wall of contact surface adaptation can be more stable is resisted in waterstop joint Wall.
Determined in conclusion the utility model compared with prior art, has the advantage that by being plugged in waterstop joint The compression bar being pressed at the top of waterstop joint connected on position bar and locating rod cooperates the locating piece for being butted on waterstop joint inner wall on compression bar to realize Fixation to waterstop joint position avoids its waterstop joint in concrete vibrating from deviating.
Detailed description of the invention
Fig. 1 is a kind of structural schematic diagram of the pre-embedded device at sewer pipeline of toilet;
Fig. 2 is the cross-sectional view in the direction A-A in Fig. 1;
Fig. 3 is the partial exploded view of locating rod, compression bar and locating piece part.
In figure: 1, slab form;11, accommodation groove;12, adhesive layer;2, waterstop joint;3, locating rod;31, positioning plate;32, fixed Position bolt;4, compression bar;41, threaded hole;42, sliding groove;5, locating piece;51, positioning device;511, clamping plate;512, fastening bolt; 6, covering component;61, cap tube;611, through-hole;612, relief hole;62, nut.
Specific embodiment
The utility model is described in further detail below in conjunction with attached drawing.
Embodiment:
Pre-embedded device at a kind of sewer pipeline of toilet, as shown in Figure 1, including being placed on slab form 1 vertically Waterstop joint 2, and it is inserted with the locating rod 3 being connected on slab form 1 vertically in waterstop joint 2, as shown in Fig. 2, and in locating rod 3 One end far from slab form 1 is provided with the compression bar 4 for being pressed in 2 top of waterstop joint, and here, locating rod 3 is through 4 middle part of compression bar, and 4 both ends of compression bar are connected separately with the locating piece 5 for being against 2 top inner wall of waterstop joint;Meanwhile covering group is stamped on 2 top of waterstop joint Part 6.
In the prior art, directly waterstop joint 2 is placed on slab form 1, and waterstop joint 2 is withstood by self-tapping screw Position is still pouring upper concrete, and when being vibrated, the connection of waterstop joint 2 and slab form 1 is easy under external force It deviates, and influences the verticality of waterstop joint 2;Therefore, it before waterstop joint 2 is installed, is fixed on slab form 1 in advance Compression bar 4 is connected in locating rod 3 by locating rod 3 after covering upper waterstop joint 2 outside locating rod 3, and utilizes compression bar 4 by waterstop joint 2 Slab form 1 is pressed to, the locating piece 5 of cooperation 4 both ends of compression bar setting resists 2 inner wall of waterstop joint, prevents waterstop joint 2 in vertical direction It is displaced in upper and horizontal direction, avoids waterstop joint 2 from deviating in concrete vibrating, to improve the construction quality of waterstop joint 2; In addition, the setting of covering component 6 can block 2 top of waterstop joint, concrete is avoided to enter inside waterstop joint 2.
In order to realize the connection of locating rod 3 and slab form 1, as shown in Fig. 2, accommodation groove 11 is provided on slab form 1, It is equipped with positioning plate 31 in 3 bottom end of locating rod, positioning plate 31 is plugged in accommodation groove 11, and is installed with spiral shell on positioning plate 31 Line is connected to the positioning bolt 32 in slab form 1;Meanwhile the fitting of 11 inner wall of accommodation groove being provided with adhesive layer 12.In this way, Before locating rod 3 is installed, upper gluing dosage form is coated in accommodation groove 11 at adhesive layer 12, then by positioning plate 31 and is pressed into accommodation groove 11 In, and positioning plate 31 is fixed using positioning bolt 32, it realizes the fixation of 3 position of locating rod, avoids it in concrete vibrating It loosens, and influences its positioning action to waterstop joint 2.
And in order to realize compression bar 4 to the pressuring action of waterstop joint 2, as shown in figure 3, perforation is provided with screw thread in the middle part of compression bar 4 Hole 41, and 3 screw thread of locating rod is plugged in threaded hole 41.In this way, pass through the screw thread grafting of locating rod 3 and compression bar 4, it can not only It realizes the sliding of compression bar 4 in the vertical direction, facilitates construction personnel according to 2 length adjustment compression bar of waterstop joint, 4 position, moreover it is possible to utilize Threaded connection facilitates construction personnel to turn compression bar 4 to press to waterstop joint 2, adjust pressing force, guarantee that its makees the positioning of waterstop joint 2 With.
Waterstop joint 2 not only has different length, also has different internal diameters, therefore, as shown in figure 3, being located at threaded hole 41 Two sides are provided with sliding groove 42 along 4 length direction of compression bar, and here, sliding groove 42 penetrates through the setting of compression bar 4 along the vertical direction, and positions The sliding of block 5 is connected in sliding groove 42, and the setting of 4 bottom end of compression bar is stretched out in 5 bottom end of locating piece, meanwhile, it is also set in sliding groove 42 It is equipped with the positioning device 51 for controlling 5 position of locating piece.In this way, the locating piece 5 being slidably connected can be according to 2 internal diameter of waterstop joint It is adjusted, and the setting of positioning device 51 is capable of fixing the position of the locating piece 5 after adjusting, and avoids waterstop joint 2 in level It is deviated on direction.
As shown in figure 3, positioning device 51 includes 5 top of locating piece spaced two clamping plates 511 along the vertical direction, this In, from 5 periphery of locating piece, horizontal extension is arranged clamping plate 511 around, and the compression bar 4 of 42 length direction two sides of sliding groove is inserted respectively It is connected between two clamping plates 511 of 5 two sides of locating piece and is arranged, meanwhile, one clamping plate 511 of perforation, which is installed with, is connected to determining for 4 side wall of compression bar Position bolt 512.In this way, spaced two clamping plate 511 can be clipped in 4 two sides of compression bar, can guide-localization block 5 sliding, also It is avoided that it is detached from compression bar 4, cooperates the extruding of positioning bolt 512, its position is fixed behind the position for regulating locating piece 5, It realizes and supporting for waterstop joint 2 is provided as using.
In addition, as shown in figure 3, cooperating 2 inner wall camber of waterstop joint close to 2 inner body wall side of waterstop joint in locating piece 5 Setting.In this way, contact surface adaptation 5 side wall of locating piece can be more stable resist 2 inner wall of waterstop joint.
After setting locating rod 3, compression bar 4 and locating piece 5, need to connect the lid of covering component 6 at 2 top of waterstop joint, such as Shown in Fig. 2, covering component 6 includes that cap tube 61 is provided with through-hole 611 at 61 center of cap tube, in the bottom end pair of 61 peripheral wall of cap tube here 4 both ends of compression bar are answered to have relief hole 612, and locating rod 3 is arranged across through-hole 611, compression bar 4 stretches out relief hole 612 and is arranged; Also, it is threaded with nut 62 on the part that locating rod 3 stretches out cap tube 61, and 62 low pressure of nut is set at the top of cap tube 61 It sets.In this way, the setting of cap tube 61 can block 2 top of waterstop joint, concrete is avoided to be directly entered inside waterstop joint 2, and nut Cap tube 61 can not only be pressed in 2 top of waterstop joint by 62 setting, avoid its disengaging, moreover it is possible to and cooperate cap tube 61 to compress compression bar 4, into One step stablizes 2 position of waterstop joint.
The above is only the preferred embodiment of the utility model, and the protection scope of the utility model is not limited merely to Above-described embodiment, technical solution belonging to the idea of the present invention belong to the protection scope of the utility model.It should refer to Out, for those skilled in the art, it is without departing from the principle of the utility model it is several improvement and Retouching, these improvements and modifications also should be regarded as the protection scope of the utility model.

Claims (8)

1. the pre-embedded device at a kind of sewer pipeline of toilet, including waterstop joint (2), which is characterized in that in the waterstop joint (2) It is inserted with the locating rod (3) being connected on slab form (1) vertically, the locating rod (3) is equipped with far from the one end of slab form (1) Pressure is set to the compression bar (4) at the top of waterstop joint (2), and the locating rod (3) is arranged in setting in the middle part of compression bar (4), and the compression bar (4) Both ends are respectively equipped with to the locating piece (5) for being set to waterstop joint (2) top inner wall;Waterstop joint (2) top cover is equipped with covering group Part (6).
2. the pre-embedded device at a kind of sewer pipeline of toilet according to claim 1, which is characterized in that the building slab It is provided on plate (1) accommodation groove (11), locating rod (3) bottom end is equipped with the positioning plate (31) being connected in accommodation groove (11), passes through Lead to the positioning plate (31) and is equipped with the positioning bolt (32) being threaded in slab form (1).
3. the pre-embedded device at a kind of sewer pipeline of toilet according to claim 2, which is characterized in that the accommodation groove (11) filling is equipped with adhesive layer (12) between inner wall and positioning plate (31) periphery wall.
4. the pre-embedded device at a kind of sewer pipeline of toilet according to claim 1, which is characterized in that the compression bar (4) sliding is connected on locating rod (3) along the vertical direction.
5. the pre-embedded device at a kind of sewer pipeline of toilet according to claim 4, which is characterized in that the locating rod (3) screw thread is plugged on setting in the middle part of compression bar (4).
6. the pre-embedded device at a kind of sewer pipeline of toilet according to claim 1, which is characterized in that along compression bar (4) Length direction is provided with sliding groove (42), and the sliding groove (42) penetrates through compression bar (4) setting, the locating piece (5) along the vertical direction Sliding is connected in sliding groove (42), and locating piece (5) bottom end is stretched out compression bar (4) bottom end and is arranged, in the sliding groove (42) It is additionally provided with the positioning device (51) for controlling locating piece (5) position.
7. the pre-embedded device at a kind of sewer pipeline of toilet according to claim 6, which is characterized in that the positioning dress Setting (51) includes locating piece (5) top spaced two clamping plates (511) along the vertical direction, and the clamping plate (511) is from positioning Horizontal extension is arranged around for block (5) periphery, and the compression bar (4) of sliding groove (42) the length direction two sides is plugged in positioning respectively It is arranged between two clamping plates (511) of block (5) two sides, perforation one clamping plate (511) is equipped with the fastening bolt for being connected to compression bar (4) side wall (512).
8. the pre-embedded device at a kind of sewer pipeline of toilet according to claim 7, which is characterized in that the locating piece (5) close to waterstop joint (2) inner body wall side cooperation waterstop joint (2) inner wall camber setting.
CN201821254161.3U 2018-08-04 2018-08-04 A kind of pre-embedded device at sewer pipeline of toilet Expired - Fee Related CN208633239U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821254161.3U CN208633239U (en) 2018-08-04 2018-08-04 A kind of pre-embedded device at sewer pipeline of toilet

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821254161.3U CN208633239U (en) 2018-08-04 2018-08-04 A kind of pre-embedded device at sewer pipeline of toilet

Publications (1)

Publication Number Publication Date
CN208633239U true CN208633239U (en) 2019-03-22

Family

ID=65740959

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821254161.3U Expired - Fee Related CN208633239U (en) 2018-08-04 2018-08-04 A kind of pre-embedded device at sewer pipeline of toilet

Country Status (1)

Country Link
CN (1) CN208633239U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110370425A (en) * 2019-09-04 2019-10-25 中国十七冶集团有限公司 Prefabricated wall lower part slip casting area envelope mould rapid-assembling/disassembling mold and application method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110370425A (en) * 2019-09-04 2019-10-25 中国十七冶集团有限公司 Prefabricated wall lower part slip casting area envelope mould rapid-assembling/disassembling mold and application method

Similar Documents

Publication Publication Date Title
CN208633239U (en) A kind of pre-embedded device at sewer pipeline of toilet
CN208364136U (en) A kind of combination fastener of embedded sleeve barrel and rear-mounted conduit
US3173443A (en) Adjustable floor clean-out extension
CN212004593U (en) Fixing device of hydraulic engineering pipe laying
CN203176574U (en) Seepage resistant convenient concrete layer drainage pipe connecting embedding device
CN205938278U (en) Flow adjustable displacement connects
CN207079913U (en) A kind of structure for preventing cast-in-place vertical member bottom spillage
CN208815915U (en) Accurate positioning device for reserved direct-buried sleeve
CN209261011U (en) The laminated floor slab of adjustable terminal box
CN218623381U (en) Grouting construction device
CN217669991U (en) Assembly type component pipeline grooving tool
CN114704293B (en) Tunnel secondary lining vault anti-run-out multi-angle slip casting device
CN207331881U (en) A kind of antiseepage connects Lou adjustable pre-buried standpipe ponding discharger
CN210032718U (en) Anchor rod supporting device for connecting existing masonry wall and new masonry structure
CN209876194U (en) Drain pipe pre-embedding device
CN113013815A (en) Building embedded pipeline fixing device and construction method
CN206918421U (en) A kind of pre-embedded pipeline connecting device
CN213773423U (en) Water sealing device for dewatering well of underground structure
CN208650260U (en) A kind of prefabricated column base pulp layer regulating device
CN110778028A (en) Grouting sleeve assembly and construction method thereof
CN217580494U (en) Prefabricated structure frame of drainage channel
CN216275661U (en) Anti-floating anchor rod convenient to install
CN214696161U (en) Bolt hole mortar filler
CN220521781U (en) Roof rainwater drainage is with adjustable pre-buried formula rainwater fill
CN203256871U (en) Drain valve with adjustable height

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190322