CN208614311U - A kind of building pipe clamping device - Google Patents
A kind of building pipe clamping device Download PDFInfo
- Publication number
- CN208614311U CN208614311U CN201820851256.7U CN201820851256U CN208614311U CN 208614311 U CN208614311 U CN 208614311U CN 201820851256 U CN201820851256 U CN 201820851256U CN 208614311 U CN208614311 U CN 208614311U
- Authority
- CN
- China
- Prior art keywords
- connecting rod
- supporting block
- shell
- building pipe
- bottom end
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Earth Drilling (AREA)
Abstract
The utility model discloses a kind of building pipe clamping devices, including pedestal, first shell is connected on the right side of the top of the pedestal, surface bottom end offers sliding slot at left and right sides of the inner cavity of the first shell, the inner cavity bottom end of the first shell is connected with spring, the top of the spring is connected with first connecting rod, and the outer wall bottom end of the first connecting rod is socketed with support base, and the left and right sides of the support base is connected with the sliding block to match with sliding slot.The building pipe clamping device, spring is squeezed while first connecting rod moves downward, buffer function can be played to the building pipe being put into the first supporting block by spring, it avoids tubing overweight moment from contacting with the first supporting block to damage device by pressure, it can prevent the tubing in cutting process from shifting, building pipe is fixed by hydraulic pump, reduces the labor intensity of staff, it improves work efficiency, uses manpower and material resources sparingly.
Description
Technical field
The utility model relates to technical field of buildings, specially a kind of building pipe clamping device.
Background technique
Tubing is exactly the material for making pipe fitting, and the quality of the different material of different pipe fittings, tubing directly determines
The quality of pipe fitting, architectural engineering, power plant and chemical plant etc. are mostly used such tubing, need to use various pipes in construction
Material needs to carry out these tubing to weld the processing such as cutting, when handling tubing, mostly uses manual clamping, cutting
It is easy to happen offset, and large labor intensity in the process, working efficiency is low, wasting manpower and material resources.
Utility model content
The purpose of this utility model is to provide a kind of building pipe clamping devices, to solve to propose in above-mentioned background technique
The problem of.
To achieve the above object, the utility model provides the following technical solutions: a kind of building pipe clamping device, including bottom
The top right side of seat, the pedestal is connected with first shell, and surface bottom end opens up at left and right sides of the inner cavity of the first shell
There is a sliding slot, the inner cavity bottom end of the first shell is connected with spring, and the top of the spring is connected with first connecting rod, and described
The outer wall bottom end of one connecting rod is socketed with support base, and the left and right sides of the support base is connected with the cunning to match with sliding slot
Block, the top of the first connecting rod is connected with connecting column, and first shell is extended on the top of connecting column, the connecting column
Top is connected with the first supporting block, and the top left hand of the pedestal is connected with support column, and the top of the support column is connected with top
The bottom end right side of seat, the footstock is connected with second shell, and the inner cavity of the second shell is plugged with hydraulic pump, the hydraulic pump
Bottom end support rod is welded with by hydraulic stem, the bottom dead center position of the support rod is connected with third supporting block, the branch
The inside of strut opens up fluted, and the inner cavity of the groove is plugged with the second connecting rod, and the support rod passes through bolt precession spiral shell
Rod locking is connected by second in hole, the bottom end of second connecting rod is connected with the second supporting block.
Preferably, the screw hole is gap arrangement at left and right sides of the top of support rod, and the spacing between the screw hole is
cm。
Preferably, second connecting rod is in T-shaped.
Preferably, the quantity of second supporting block is two.
Preferably, first supporting block is in " arc " shape.
Compared with prior art, the utility model has the beneficial effects that the building pipe clamping device, 1, by that will build
Tubing is placed into the first supporting block, and the first supporting block stress drives connecting column to move downward in first shell, connecting column band
Dynamic first connecting rod and support base move downward, and spring is squeezed while first connecting rod moves downward, can be right by spring
The building pipe being put into the first supporting block plays buffer function, and tubing overweight moment is avoided to contact with the first supporting block by device
It damages by pressure, extends the service life of the device;
2, by powering on, hydraulic pump is worked normally, hydraulic pump is made to drive support rod and third branch by hydraulic stem
Bracer moves downward, and drives the second connecting rod and the second supporting block to move downward while support rod moves downward, when third branch
Bracer is moved to contacted with building pipe outer wall after stop, moving inward the second connecting rod, the second connecting rod drives second
Bracer moves inward to the second supporting block contacted with building pipe outer wall after stop, by bolt precession screw hole and the second connecting rod
It is inside fixed, by the fixation to building pipe surrounding, can prevent the tubing in cutting process from shifting, effectively mention
The high precision of cutting, is fixed building pipe by hydraulic pump, reduces the labor intensity of staff, improve work
Make efficiency, uses manpower and material resources sparingly.
Detailed description of the invention
FIG. 1 is a schematic structural view of the utility model;
Fig. 2 is structural schematic diagram at the A of the utility model.
In figure: 1, pedestal, 2, spring, 3, support base, 4, first shell, 5, support column, 6, footstock, 7, hydraulic pump, 8,
Two shells, the 9, first supporting block, 10, connecting column, 11, first connecting rod, 12, sliding block, 13, sliding slot, 14, bolt, 15, screw hole,
16, the second connecting rod, the 17, second supporting block, 18, third supporting block, 19, groove, 20, support rod.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model
Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole
Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work
Every other embodiment obtained, fall within the protection scope of the utility model.
The utility model provides a kind of technical solution referring to FIG. 1-2: a kind of building pipe clamping device, including pedestal
1, the top right side of pedestal 1 is connected with first shell 4, and surface bottom end offers sliding slot at left and right sides of the inner cavity of first shell 4
13, the inner cavity bottom end of first shell 4 is connected with spring 2, and the top of spring 2 is connected with first connecting rod 11, first connecting rod 11
Outer wall bottom end be socketed with support base 3, the left and right sides of support base 3 is connected with the sliding block 12 to match with sliding slot 13, first
The top of connecting rod 11 is connected with connecting column 10, and first shell 4, the top card of connecting column 10 are extended in the top of connecting column 10
It is connected to the first supporting block 9, by the way that building pipe to be placed into the first supporting block 9,9 stress of the first supporting block drives connecting column 10
It is moved downward in first shell 4, connecting column 10 drives first connecting rod 11 and support base 3 to move downward, and support base 3 is transported downwards
The band slide downward in sliding slot 13 of movable slider 12 while dynamic, squeezes spring 2, spring while first connecting rod 11 moves downward
2 stress and deformations tighten the power upward to first connecting rod 11, can be to the building pipe being put into the first supporting block 9 by spring 2
Material plays buffer function, avoids tubing overweight moment from contacting with the first supporting block 9 and damages device by pressure, extends the use of the device
Service life, the first supporting block 9 are in " arc " shape, are sufficiently contacted with building pipe surface, and the top left hand of pedestal 1 is connected with support column 5,
The top of support column 5 is connected with footstock 6, is connected with second shell 8 on the right side of the bottom end of footstock 6, the inner cavity of second shell 8 is plugged with
Hydraulic pump 7, the model YYB-AB6/48B of the hydraulic pump work normally hydraulic pump 7, make hydraulic pump 7 by powering on
It drives support rod 20 and third supporting block 18 to move downward by hydraulic stem, drives second to connect while support rod 20 moves downward
Extension bar 16 and the second supporting block 17 move downward, and stop when third supporting block 18 is moved to after the contact of building pipe outer wall, will
Bolt 14 screws out in screw hole 15, moves inward the second connecting rod 16, and the second connecting rod 16 drives the second supporting block 17 inwardly
Side, which is moved to after the second supporting block 17 is contacted with building pipe outer wall, to stop, by 14 precession screw hole 15 of bolt and the second connecting rod 16
It is inside fixed, by the fixation to building pipe surrounding, can prevent the tubing in cutting process from shifting, effectively mention
The high precision of cutting, is fixed building pipe by hydraulic pump 7, reduces the labor intensity of staff, improve
Working efficiency uses manpower and material resources sparingly, and the bottom end of hydraulic pump 7 is welded with support rod 20 by hydraulic stem, in the bottom end of support rod 20
Heart position is connected with third supporting block 18, and the inside of support rod 20 opens up fluted 19, and the inner cavity of groove 19 is plugged with the second company
Extension bar 16, the second connecting rod 16 prevent the second connecting rod from falling in groove 19 in T-shaped, and support rod 20 passes through bolt 14
Second connecting rod 16 is locked in precession screw hole 15, screw hole 15 is gap arrangement at left and right sides of the top of support rod 20, screw hole
Spacing between 15 is 2cm, and the bottom end of the second connecting rod 16 is connected with the second supporting block 17, and the quantity of the second supporting block 17 is two
It is a, building pipe can preferably be fixed.
Building pipe is placed into the first supporting block 9,9 stress of the first supporting block drives connecting column 10 in first shell 4
It inside moves downward, connecting column 10 drives first connecting rod 11 and support base 3 to move downward, band while support base 3 moves downward
The slide downward in sliding slot 13 of movable slider 12 squeezes spring 2,2 stress and deformation of spring while first connecting rod 11 moves downward
The power upward to first connecting rod 11 is tightened, buffering can be played to the building pipe being put into the first supporting block 9 by spring 2
Effect, avoids tubing overweight moment from contacting with the first supporting block 9 and damages device by pressure, extend the service life of the device, pass through
Power on, work normally hydraulic pump 7, hydraulic pump 7 is made to drive support rod 20 and third supporting block 18 downward by hydraulic stem
Movement, support rod 20 drive the second connecting rod 16 and the second supporting block 17 to move downward while moving downward, when third supports
Block 18 is moved to contacted with building pipe outer wall after stop, bolt 14 is screwed out in screw hole 15, moves inward the second connection
Bar 16, after the second connecting rod 16 drives the second supporting block 17 to move inward to the second supporting block 17 and contact with building pipe outer wall
Stop, being fixed in 14 precession screw hole 15 of bolt and the second connecting rod 16, it, can be with by the fixation to building pipe surrounding
It prevents the tubing in cutting process from shifting, building pipe is fixed by hydraulic pump 7, reduce the labor of staff
Fatigue resistance improves work efficiency.
Claims (5)
1. a kind of building pipe clamping device, including pedestal (1), it is characterised in that: be connected on the right side of the top of the pedestal (1)
The inner cavity left and right sides surface bottom end of first shell (4), the first shell (4) offers sliding slot (13), the first shell
The inner cavity bottom end of body (4) is connected with spring (2), and the top of the spring (2) is connected with first connecting rod (11), and described first connects
The outer wall bottom end of extension bar (11) is socketed with support base (3), and the left and right sides of the support base (3) is connected with and sliding slot (13) phase
The top of matched sliding block (12), the first connecting rod (11) is connected with connecting column (10), and the top of connecting column (10) is prolonged
It stretches out first shell (4), the top of the connecting column (10) is connected with the first supporting block (9), the top left hand of the pedestal (1)
It is connected with support column (5), the top of the support column (5) is connected with footstock (6), is connected on the right side of the bottom end of the footstock (6)
The inner cavity of second shell (8), the second shell (8) is plugged with hydraulic pump (7), and the bottom end of the hydraulic pump (7) passes through hydraulic
Bar is welded with support rod (20), and the bottom dead center position of the support rod (20) is connected with third supporting block (18), the support
The inside of bar (20) opens up fluted (19), and the inner cavity of the groove (19) is plugged with the second connecting rod (16), the support rod
(20) by locking the second connecting rod (16) in bolt (14) precession screw hole (15), the bottom end card of second connecting rod (16)
It is connected to the second supporting block (17).
2. a kind of building pipe clamping device according to claim 1, it is characterised in that: the screw hole (15) is gap row
It is listed at left and right sides of the top of support rod (20), the spacing between the screw hole (15) is 2cm.
3. a kind of building pipe clamping device according to claim 1, it is characterised in that: second connecting rod (16) is in
It is T-shaped.
4. a kind of building pipe clamping device according to claim 1, it is characterised in that: second supporting block (17)
Quantity is two.
5. a kind of building pipe clamping device according to claim 1, it is characterised in that: first supporting block (9) is in
" arc " shape.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820851256.7U CN208614311U (en) | 2018-06-02 | 2018-06-02 | A kind of building pipe clamping device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820851256.7U CN208614311U (en) | 2018-06-02 | 2018-06-02 | A kind of building pipe clamping device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208614311U true CN208614311U (en) | 2019-03-19 |
Family
ID=65701449
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820851256.7U Expired - Fee Related CN208614311U (en) | 2018-06-02 | 2018-06-02 | A kind of building pipe clamping device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208614311U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112456380A (en) * | 2020-12-01 | 2021-03-09 | 徐州东宏机械制造有限公司 | Clamping and lifting equipment for mechanical engineering |
CN114733991A (en) * | 2022-04-01 | 2022-07-12 | 苏州富力诚精密部件有限公司 | Height shaping and adjusting clamp for cold-heading thin-wall sleeve part |
-
2018
- 2018-06-02 CN CN201820851256.7U patent/CN208614311U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112456380A (en) * | 2020-12-01 | 2021-03-09 | 徐州东宏机械制造有限公司 | Clamping and lifting equipment for mechanical engineering |
CN114733991A (en) * | 2022-04-01 | 2022-07-12 | 苏州富力诚精密部件有限公司 | Height shaping and adjusting clamp for cold-heading thin-wall sleeve part |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN208614311U (en) | A kind of building pipe clamping device | |
CN206425755U (en) | A kind of central air-conditioning discharge positioning welding auxiliary mould | |
CN206702675U (en) | A kind of intermetallic composite coating fixing device | |
CN107830260A (en) | A kind of fixing device for pipe fitting | |
CN105033696B (en) | A kind of flange processing platform | |
CN107350711A (en) | A kind of architectural engineering butt welding machine | |
CN204657620U (en) | For the auxiliary holding device of metal pipe material processing | |
CN106239020A (en) | A kind of novel pipe fitting welder | |
CN207104361U (en) | A kind of fixture | |
CN208880567U (en) | Insulating tube produces adjustable steel pipe clamp | |
CN216344303U (en) | Water conservancy water and electricity construction fastening processing apparatus | |
CN213889655U (en) | Anti-deformation clamping device for pipe fitting machining | |
CN214838851U (en) | Pipeline strutting arrangement for hydraulic engineering | |
CN208503945U (en) | A kind of air cleaning air accumulator | |
CN212056129U (en) | Fixed device that holds that adds of hydraulic engineering construction pipeline | |
CN219402571U (en) | Water pipe cutting machine | |
CN220749246U (en) | Municipal pipeline embeds pipeline support fixed bolster | |
CN213945356U (en) | Steel pipe weldment work platform for building | |
CN219909317U (en) | Frame supporting device | |
CN214418733U (en) | Auxiliary rotating device for machining steel pipe | |
CN208614090U (en) | A kind of metal drum production boring soldering equipment | |
CN211588106U (en) | Adjustable manual bending device | |
CN210618230U (en) | Metal pipe conveying device with fixing function | |
CN220666509U (en) | Steel pipe connecting device | |
CN215546395U (en) | Clamping mechanism for welding angle steel flange for pipeline engineering |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20190319 Termination date: 20190602 |
|
CF01 | Termination of patent right due to non-payment of annual fee |