A kind of bilayer building curtain wall
Technical field
The utility model relates to building curtain wall technical field, specially a kind of double-deck building curtain wall.
Background technique
Building curtain wall refers to the exterior wall encirclement of building not load-bearing, usually by panel (glass, metal plate, slabstone and pottery
Porcelain plate etc.) and subsequent supporting structure (aluminium cross beam and upright post, steel construction and Glass Rib etc.) composition, building curtain wall be by bearing tie
What structure system and panel formed, there can be certain displacement ability with respect to main structure, not share main structure institute building affected
Peripheral structure or decorative structure, curtain wall are the exterior wall encirclements of building, and not load-bearing is hung up as curtain, therefore also known as
It is the lightweight wall that modern large-scale and skyscraper commonly has decorative effect, by structural framing and elbow-board to hang wall
Material composition, does not undertake the architectural exterior-protecting construction of main structure load and effect.
With the continuous aggravation of building curtain wall industry competition, M&A integration and capital operation day between heavy construction curtain wall enterprise
Become frequently, domestic outstanding building curtain wall manufacturing enterprise more and more payes attention to the research to industry market, especially to enterprise development
The further investigation of environment and customer demand Long-term change trend, Just because of this, the outstanding building curtain wall brand in large quantities of country are rapid
It emerges, the outstanding figure being increasingly becoming in building curtain wall industry, but the building curtain wall knot that building higher for some load-bearing is present
Structure load-bearing may not enough will form collapsing, so propose a kind of double-deck building curtain wall solve the problems, such as it is above-mentioned proposed in.
Utility model content
(1) the technical issues of solving
In view of the deficiencies of the prior art, the utility model provides a kind of double-deck building curtain wall, has the advantages of load-bearing, solves
The problem of present Building Curtain Wall Structures load-bearing of building higher for some load-bearing of having determined may not enough will form collapsing.
(2) technical solution
For the purpose for realizing above-mentioned load-bearing, the utility model is provided the following technical solutions: a kind of bilayer building curtain wall, including
Top plate, there are four support columns for the bottom fixed installation of the top plate, and the bottom of the support column is fixedly installed with bottom plate, the top
The back side of plate and bottom plate is fixedly installed with bright deckle board, fixed between two support columns in left side and two support columns on right side
Baffle is installed, the junction of the baffle and support column is movably installed with limit plate, between two opposite limit plates
It is fixedly installed with side lever, the bolt being threadedly coupled with support column, the support column of two centres are installed on the limit plate
Between opposite side be fixedly installed with fixing seat, half arc block of left side is fixedly installed on the right side of the fixing seat in left side,
Half arc block of right side is fixedly installed on the left of the fixing seat on right side, half arc block intersection of the half arc block of left side and right side
Front, which is movably installed with, agrees with plate, and the front for agreeing with plate, which is equipped with, to be threadedly coupled with half arc block of left side and half arc block of right side
Screw is mounted on the fixed block fixed with top plate and bottom plate at the top and bottom of the half arc block of left side and half arc block of right side,
The half arc block of left side and the opposite side of half arc block of right side are fixedly installed with connecting rod, fixed between two connecting rods
Adjustment spring is installed, in the connecting rod in left side and is located at the outside of adjustment spring and is fixedly installed with interior retaining ring, right side
The outer retaining ring being fixedly installed in the connecting rod outside interior retaining ring.
Preferably, the limit buckle being mutually clamped is fixedly installed on the interior retaining ring and outer retaining ring.
Preferably, movable span corresponding with bolt is offered on the limit plate, and is fixedly installed in movable span wear-resisting
Piece, the material of wear plate can be steel or copper.
Preferably, the material of the support column can be concrete, and the inside of concrete is fixedly installed with reinforced frame.
Preferably, described agree with offers rotation hole corresponding with screw on plate, and the material for agreeing with plate can be butyronitrile rubber
Glue.
Preferably, stated clearly deckle board is composed of multiple pieces of glass plate, and fixed frame is fixedly installed between glass plate.
(3) beneficial effect
Compared with prior art, the utility model provides a kind of double-deck building curtain wall, have it is following the utility model has the advantages that
1, the bilayer building curtain wall agrees with plate by having on setting screw, screw can be made by agreeing with plate and left side half
Fixed stronger of arc block and half arc block of right side, by having limit plate on setting side lever, can be such that side lever contacts with support rod
Area is bigger to which stress is more, by having bolt on setting limit plate, limit plate can be fixed on support column by bolt
On, achieve the effect that load-bearing.
2, there are interior retaining ring and outer retaining ring in the bilayer building curtain wall, the outside by the way that adjustment spring is arranged, can pass through interior shield
Ring and outer retaining ring protect adjustment spring, can be to avoid interior retaining ring by having limit buckle on retaining ring in being arranged and outer retaining ring
It is in the presence of falling off with outer retaining ring, thus the building curtain wall knot that effective solution building higher for some load-bearing is present
Structure load-bearing may not enough will form the problem of collapsing.
Detailed description of the invention
FIG. 1 is a schematic structural view of the utility model;
Fig. 2 is the structure enlargement diagram of A in the utility model Fig. 1;
Fig. 3 is the structure enlargement diagram of B in the utility model Fig. 1.
In figure: 1 top plate, 2 support columns, 3 bottom plates, 4 bright deckle boards, 5 side levers, 6 fixing seats, 7 left side half arc blocks, 8 screws, 9 contracts
Plywood, 10 half arc blocks of right side, 11 connecting rods, 12 fixed blocks, 13 limit plates, 14 bolts, retaining ring, 16 outer retaining rings, 17 adjustings in 15
Spring, 18 baffles.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model
Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole
Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work
Every other embodiment obtained, fall within the protection scope of the utility model.
Fig. 1-3, a kind of bilayer building curtain wall, including top plate 1 are please referred to, there are four supports for the bottom fixed installation of top plate 1
The material of column 2, support column 2 can be concrete, and the inside of concrete is fixedly installed with reinforced frame, and the bottom of support column 2 is fixed
Bottom plate 3 is installed, the back side of top plate 1 and bottom plate 3 is fixedly installed with bright deckle board 4, and bright deckle board 4 is composed of multiple pieces of glass plate,
And fixed frame is fixedly installed between glass plate, fixed peace between two support columns 2 in left side and two support columns 2 on right side
Equipped with baffle 18, the junction of baffle 18 and support column 2 is movably installed with limit plate 13, consolidates between two opposite limit plates 13
Dingan County is equipped with side lever 5, is equipped with the bolt 14 being threadedly coupled with support column 2 on limit plate 13, offers on limit plate 13 and spiral shell
The corresponding movable span of bolt 14, and wear plate is fixedly installed in movable span, the material of wear plate can be steel or copper, two centres
Opposite side is fixedly installed with fixing seat 6 between support column 2, and the right side of the fixing seat 6 in left side is fixedly installed with left side half
Arc block 7, the left side of the fixing seat 6 on right side are fixedly installed with half arc block 10 of right side, half arc block 7 of left side and the intersection of half arc block 10 of right side
The front at place, which is movably installed with, agrees with plate 9, agrees with and offers rotation hole corresponding with screw 8 on plate 9, and agrees with the material of plate 9
It can be nitrile rubber, the front for agreeing with plate 9 is equipped with the screw 8 being threadedly coupled with half arc block 7 of left side and half arc block 10 of right side, left
The top and bottom of half arc block 10 of half arc block 7 of side and right side are mounted on the fixed block 12 fixed with top plate 1 and bottom plate 3, left side
Half arc block 7 and the opposite side of half arc block 10 of right side are fixedly installed with connecting rod 11, are fixedly mounted between two connecting rods 11
There is an adjustment spring 17, in the connecting rod 11 in left side and is located at the outside of adjustment spring 17 and is fixedly installed with interior retaining ring 15, right side
The outer retaining ring 16 being fixedly installed with outside interior retaining ring 15 in connecting rod 11 is fixedly mounted on interior retaining ring 15 and outer retaining ring 16
There is the limit buckle being mutually clamped, which agrees with plate 9 by having on setting screw 8, screw 8 can be made to pass through contract
Plywood 9 and half arc block 7 of left side and fixed stronger of half arc block 10 of right side, by having limit plate 13 on setting side lever 5, can make
The area that side lever 5 is contacted with support rod 2 is bigger to which stress is more, by having bolt 14 on setting limit plate 13, can pass through
Limit plate 13 is fixed on support column 2 by bolt 14, has achieved the effect that load-bearing, and the bilayer building curtain wall, is adjusted by setting
There are interior retaining ring 15 and outer retaining ring 16 in the outside of section spring 17, can be carried out by interior retaining ring 15 and outer retaining ring 16 to adjustment spring 17
Protection can be fallen off by having limit buckle on retaining ring 15 in being arranged and outer retaining ring 16 to avoid interior retaining ring 15 and outer retaining ring 16
Situation, so that the present Building Curtain Wall Structures load-bearing of effective solution building higher for some load-bearing not enough may
Form the problem of collapsing.
In conclusion the bilayer building curtain wall, agrees with plate 9 by having on setting screw 8, screw 8 can be made by agreeing with
Plate 9 and half arc block 7 of left side and fixed stronger of half arc block 10 of right side, by having limit plate 13 on setting side lever 5, can make side
The area that bar 5 is contacted with support rod 2 is bigger to which stress is more, by having bolt 14 on setting limit plate 13, can pass through spiral shell
Limit plate 13 is fixed on support column 2 by bolt 14, has achieved the effect that load-bearing.
Also, there are interior retaining ring 15 and outer retaining ring 16 in the bilayer building curtain wall, the outside by the way that adjustment spring 17 is arranged, can be with
Adjustment spring 17 is protected by interior retaining ring 15 and outer retaining ring 16, by having limit on retaining ring 15 in being arranged and outer retaining ring 16
Button, can be in the presence of falling off to avoid interior retaining ring 15 and outer retaining ring 16, so that effective solution is higher for some load-bearing
The present Building Curtain Wall Structures load-bearing of building the problem of may not enough will form collapsing.
It should be noted that the terms "include", "comprise" or its any other variant are intended to the packet of nonexcludability
Contain, so that the process, method, article or equipment for including a series of elements not only includes those elements, but also including
Other elements that are not explicitly listed, or further include for elements inherent to such a process, method, article, or device.
In the absence of more restrictions, the element limited by sentence "including a ...", it is not excluded that including the element
Process, method, article or equipment in there is also other identical elements.
While there has been shown and described that the embodiments of the present invention, for the ordinary skill in the art,
It is understood that these embodiments can be carried out with a variety of variations in the case where not departing from the principles of the present invention and spirit, repaired
Change, replacement and variant, the scope of the utility model is defined by the appended claims and the equivalents thereof.