CN208563128U - One kind being used for bridge prefabrication segment concatenation construction daub device - Google Patents
One kind being used for bridge prefabrication segment concatenation construction daub device Download PDFInfo
- Publication number
- CN208563128U CN208563128U CN201821119895.0U CN201821119895U CN208563128U CN 208563128 U CN208563128 U CN 208563128U CN 201821119895 U CN201821119895 U CN 201821119895U CN 208563128 U CN208563128 U CN 208563128U
- Authority
- CN
- China
- Prior art keywords
- staving
- capping
- movable plate
- construction
- ptfe
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Abstract
One kind being used for bridge prefabrication segment concatenation construction daub device, includes the staving in cavity structure, and staving bottom outside is fixed with gum outlet guide wheel, and gum outlet guide wheel and the perforation of staving bottom connect;Corresponding two sides are provided with handle in the middle part of staving, and staving is lifted carrying by handle;Polytetrafluoroethylene (PTFE) movable plate is equipped at the top of staving, polytetrafluoroethylene (PTFE) movable plate is connected in capping by spring;The top outer of staving is equipped with buckle, is connected staving with lidstock by buckling;Tracheae fast interface is installed for connecting external air pump in the capping.The utility model has the beneficial effects that light easy to operate, installed capacity and daub thickness can adjust according to demand, and construction efficiency is higher, and construct thickness and flatness high reliablity reduce waste of material.It can reach save the cost and improve the effect of construction efficiency.
Description
Technical field
The utility model relates to large area daub constructing device fields, specially a kind of to apply for the splicing of bridge prefabrication segment
Work daub device, bridge prefabrication segment can be concrete material, Steel material etc..
Background technique
Precast Concrete Segmental Bridges technology is industrialized architecture production mode, and precast segment spliced girder is opened from the 1950s
Beginning is recognized and is applied, at the end of the 20th century, precast assembly technology be widely used in industry and civil buildings, bridge road,
The engineering structures fields such as flowering structure, municipal basis, wherein most commonly used application is in bridge construction field, currently, on bridge
It is all using Precast Concrete Segmental Bridges technology, currently, substantially process is such as between the beam sections in portion, between bridge deck and girder unit
Under: precast bridge segment is simultaneously conserved → is transported to scene and try assembly → interim prestressing force → prestressing force of Mosaic face daub → application
Tensioning.Wherein, when daub is constructed, it is substantially all made of artificial daub mode, bondline thickness, uniformity are more difficult to control, simultaneously
Construction efficiency is low.
Utility model content
In order to solve above-mentioned problems of the prior art, the utility model provides a kind of for the spelling of bridge prefabrication segment
Connect construction daub device.
The technical scheme adopted by the utility model to solve the technical problem is as follows: a kind of apply for the splicing of bridge prefabrication segment
Work daub device, includes the staving in cavity structure, and staving bottom outside is fixed with gum outlet guide wheel, gum outlet guide wheel and bucket
The perforation connection of body bottom;Corresponding two sides are provided with handle in the middle part of staving, and staving is lifted carrying by handle;It is equipped at the top of staving
Polytetrafluoroethylene (PTFE) movable plate, polytetrafluoroethylene (PTFE) movable plate are connected in capping by spring;The top outer of staving is equipped with buckle,
Staving is connected with lidstock by buckling;Tracheae fast interface is installed for connecting external air pump in the capping.
The utility model also has following additional technical feature:
Optimization: the material of the staving is polyfluortetraethylene plate;The outer diameter and staving of the polytetrafluoroethylene (PTFE) movable plate
Internal diameter match, and the outer profile of polytetrafluoroethylene (PTFE) movable plate is cased with sealing joint strip.
Optimization: the inside of capping and the junction of staving have rubber ring.
Optimization: the capping is the stainless steel material of high-strength light.
Optimization: the fast interface of tracheae is pressure vent, and aperture is matched with air compressor pipe.
The utility model compared to the prior art, the advantage is that:
1, device is light, easily operated, using flexible, and installed capacity and daub thickness can adjust according to demand, construction effect
Rate is higher;
2, staving capacity customizes, can be according to actual needs to staving Capacity design;
3, daub thickness is adjustable, and the requirement according to design to colloid thickness can adjust gum outlet guide wheel size, realizes design
Thickness;
4, plastic emitting rate is adjustable, applies pressure to polytetrafluoroethylene (PTFE) movable plate by air pump and bridge subsection is spliced glue extruding
It is applied to beam sections face, according to factors such as construction personnel, basal plane situation, construction environments, is controlled out by adjusting air pressure size
Glue rate, it is more flexible practical.
5, save the cost preferably controls the thickness and flatness of colloid, and construct thickness and flatness high reliablity are reduced
Waste of material, reduction colloid smearing is too thick to cause waste of material, can reach save the cost and improves the effect of construction efficiency.
The additional aspect and advantage of the utility model will be set forth in part in the description, partially will be from following description
In become obvious, or recognized by the practice of the utility model.
Detailed description of the invention
In order to illustrate the embodiment of the utility model or the technical proposal in the existing technology more clearly, below will be to embodiment
Or attached drawing needed to be used in the description of the prior art is briefly described, it should be apparent that, the accompanying drawings in the following description is only
It is some embodiments of the utility model, for those of ordinary skill in the art, in the premise not made the creative labor
Under, it is also possible to obtain other drawings based on these drawings.
Fig. 1 is the capping and movable plate downlink connection schematic diagram of the utility model;
Fig. 2 is the utility model agent structure schematic diagram;
Fig. 3 is the utility model gum outlet guide wheel schematic diagram.
In figure: 1, gum outlet guide wheel;2, staving;3, polytetrafluoroethylene (PTFE) movable plate;4, spring;5, handle;6, it covers;7, gas
Manage fast interface;8, it buckles.
Specific embodiment
Exemplary embodiments of the present disclosure are described in more detail below with reference to accompanying drawings.Although showing the disclosure in attached drawing
Exemplary embodiment, it being understood, however, that may be realized in various forms the disclosure without should be by embodiments set forth here
It is limited.On the contrary, these embodiments are provided to facilitate a more thoroughly understanding of the present invention, and can be by the scope of the present disclosure
It is fully disclosed to those skilled in the art.
In the description of the present invention, it should be understood that term " longitudinal direction ", " transverse direction ", "upper", "lower", " preceding ",
The orientation or positional relationship of the instructions such as " rear ", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outside" be based on
Orientation or positional relationship shown in the drawings is merely for convenience of description the utility model, rather than the dress of indication or suggestion meaning
It sets or element must have a particular orientation, be constructed and operated in a specific orientation, therefore should not be understood as to the utility model
Limitation.
One kind being used for bridge prefabrication segment concatenation construction daub device, includes the staving 2 in cavity structure, 2 bottom of staving
Gum outlet guide wheel 1 is fixed on the outside of portion, gum outlet guide wheel 1 and the perforation of 2 bottom of staving connect;Two sides setting is corresponded in the middle part of staving 2
There is handle 5, staving 2 is lifted by carrying by handle 5;Polytetrafluoroethylene (PTFE) movable plate 3 is equipped at the top of staving 2, polytetrafluoroethylene (PTFE) is living
Movable plate 3 is connected in capping 6 by spring 4;The top outer of staving 2 is equipped with buckle 8, by buckling 8 for staving 2 and capping 6
It is tightly connected;The installation fast interface 7 of tracheae is for connecting external air pump in the capping 6.
The material of the staving 2 is polyfluortetraethylene plate;The outer diameter of the polytetrafluoroethylene (PTFE) movable plate 3 is interior with staving 2
Diameter matches, and the outer profile of polytetrafluoroethylene (PTFE) movable plate 3 is cased with sealing joint strip.
The capping 6 is the stainless steel material of high-strength light, and the inside of the capping 6 and the junction of staving 2 have rubber
Cushion rubber.
The fast interface 7 of tracheae is pressure vent, and aperture is matched with air compressor pipe.
Embodiment 1
One kind being used for bridge prefabrication segment concatenation construction daub device, including staving, gum outlet guide wheel, staving, polytetrafluoro
The capping lower part of ethylene movable plate, spring, handle, capping, the fast interface of tracheae and buckle, the construction daub device connects bullet
Spring reserves the fast interface of tracheae, and tracheae external tapping connects air pump, will be covered using buckle and staving is tightly connected.Outside the staving
There is handle, polytetrafluoroethylene (PTFE) movable plate and gum outlet guide wheel are arranged at staving bottom.The utility model, will be deployed according to quality proportioning
Bridge subsection splicing mucilage binding enter staving, with buckle lidstock is good, the fast interface of tracheae and air pump are connected, air pump is passed through
Pressure will push away under capping makes bridge subsection splicing glue uniformly squeeze out and be applied on beam sections face from gum outlet, and construction is convenient.
In the utility model, the material of the daub device staving is polyfluortetraethylene plate, high-strength light.
In the utility model, the capping is the stainless steel material of high-strength light, and edge is embedded with rubber ring, guarantees envelope
Cover the airtightness connecting with staving.
In the utility model, the fast interface of tracheae is pressure vent, and grafting universal air compressor is convenient in aperture
Pipe, convenient for quickly connection.
Embodiment 2
Application method for bridge prefabrication segment concatenation construction daub device:, should be according to the face in construction section before construction
Each factor such as product, colloid design thickness, construction environment determines that engineering uses the staving capacity and gum outlet of construction daub device
Guide wheel.Segment concatenation construction daub device is assembled, and carries out no-load test, whether check device system has abnormal phenomenon.Construction
When, it should be stirred evenly according to colloid dosage is calculated, according to the proportion of colloid by the splicing mucilage binding stirred evenly in device staving
It is interior, buckle is compressed after covering capping, the gum outlet guide wheel of size needed for installing connects the fast interface of tracheae, starts daub construction.Root
Plastic emitting rate is determined according to factors such as construction area, worker operation qualification, construction environments, determines that air pressure is big by plastic emitting rate
Small, air pressure can also be adjusted at any time according to practice of construction situation.After the completion of construction, the colloid inside staving is cleaned out,
And it is cleaned in time with absolute alcohol or other solvents.
Although the various embodiments described above are described, once a person skilled in the art knows basic wounds
The property made concept, then additional changes and modifications can be made to these embodiments, so the foregoing is merely the realities of the utility model
Example is applied, the scope of patent protection of the utility model is not intended to limit, it is all to utilize the utility model specification and accompanying drawing content
Made equivalent structure or equivalent flow shift, is applied directly or indirectly in other relevant technical fields, and similarly includes
Within the scope of patent protection of the utility model.
Claims (5)
1. one kind is used for bridge prefabrication segment concatenation construction daub device, which is characterized in that include the staving in cavity structure
(2), staving (2) bottom outside is fixed with gum outlet guide wheel (1), and gum outlet guide wheel (1) and the perforation of staving (2) bottom connect;Bucket
Corresponding two sides are provided with handle (5) in the middle part of body (2), and staving (2) is lifted carrying by handle (5);It is equipped at the top of staving (2) poly-
Tetrafluoroethene movable plate (3), polytetrafluoroethylene (PTFE) movable plate (3) are connected on capping (6) by spring (4);The top of staving (2)
Outside is equipped with buckle (8), is tightly connected staving (2) and capping (6) by buckle (8);Tracheae is installed fast on the capping (6)
Interface (7) is for connecting external air pump.
2. according to claim 1 be used for bridge prefabrication segment concatenation construction daub device, it is characterized in that: the staving
(2) material is polyfluortetraethylene plate;The outer diameter of the polytetrafluoroethylene (PTFE) movable plate (3) matches with the internal diameter of staving (2), and
The outer profile of polytetrafluoroethylene (PTFE) movable plate (3) is cased with sealing joint strip.
3. according to claim 1 be used for bridge prefabrication segment concatenation construction daub device, it is characterized in that: the capping
(6) junction of inside and staving (2) has rubber ring.
4. according to claim 1 be used for bridge prefabrication segment concatenation construction daub device, it is characterized in that: the capping
It (6) is the stainless steel material of high-strength light.
5. according to claim 1 be used for bridge prefabrication segment concatenation construction daub device, it is characterized in that: the tracheae is fast
Interface (7) is pressure vent, and aperture is matched with air compressor pipe.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821119895.0U CN208563128U (en) | 2018-07-16 | 2018-07-16 | One kind being used for bridge prefabrication segment concatenation construction daub device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821119895.0U CN208563128U (en) | 2018-07-16 | 2018-07-16 | One kind being used for bridge prefabrication segment concatenation construction daub device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208563128U true CN208563128U (en) | 2019-03-01 |
Family
ID=65492434
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201821119895.0U Active CN208563128U (en) | 2018-07-16 | 2018-07-16 | One kind being used for bridge prefabrication segment concatenation construction daub device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208563128U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109898424A (en) * | 2019-03-28 | 2019-06-18 | 刘良国 | A kind of bridge construction of tube head flow resistance reduction glue configuration equipment |
-
2018
- 2018-07-16 CN CN201821119895.0U patent/CN208563128U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109898424A (en) * | 2019-03-28 | 2019-06-18 | 刘良国 | A kind of bridge construction of tube head flow resistance reduction glue configuration equipment |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP3188895B1 (en) | Improvements relating to wind turbine blade manufacture | |
CN100447350C (en) | GRP examine and repair hole structure and manufacturing method of GRP examine and repair hole and connection tube | |
CN208563128U (en) | One kind being used for bridge prefabrication segment concatenation construction daub device | |
CN1900465A (en) | Prestress hole path pressure grouting construction process by post-tensioning method | |
CN105350445A (en) | Novel efficient assembly-type reinforced concrete composite beam | |
CN108177240A (en) | Autoclaved aerated concrete slab with built-in pipe and preparation method thereof | |
CN209538743U (en) | A kind of high-pressure slip-casting leakage maintaining device | |
CN110126367A (en) | A kind of be wrapped band and its manufacture and winding construction method containing flexible fluorocarbon material | |
CN207742066U (en) | A kind of concrete impervious testing mold | |
CN202266018U (en) | Template sealing structure for grouting of connecting sleeve | |
CN103278379B (en) | The special short tube of pressure testing and the using method in long-distance pipe pipe section pressure test thereof | |
CN210995059U (en) | Intelligent control system is glued to bi-component structure | |
US7828496B1 (en) | Watertight joint seal for concrete structures | |
CN211446554U (en) | Bridge joint structure is assembled in prefabricated of festival section | |
CN208668645U (en) | A kind of assembled architecture sealed waterproof device | |
CN208060300U (en) | A kind of pneumatic pressure testing device of vehicle mounted electric | |
JP2006068698A (en) | Mixed coating method and mixed coater for two liquid type adhesive and its adhesion structure body | |
CN207469290U (en) | Underground pipe gallery mould plate supporting device and underground pipe gallery template construction structure | |
CN217896234U (en) | Automatic glue of box girder is assembled in prefabrication and is pieced together device | |
CN208497279U (en) | A kind of aerated capsule core model | |
CN109955504A (en) | A kind of three-dimensional porous thermal protection struc ture prepares mold and preparation method with the shape | |
CN219343571U (en) | Prefabricated window seam antiseep structure that wafts of assembled building | |
US11697249B2 (en) | Load introduction device and method for adhesive bonding of a load introduction device | |
CN105625714A (en) | Concrete post-cast strip air mold | |
CN113530286B (en) | Hotel reinforcement robot and use method thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right | ||
TR01 | Transfer of patent right |
Effective date of registration: 20200525 Address after: 300 380 C1, C2 Workshops, No. 1 Shengda Road, Xiqing Economic and Technological Development Zone, Tianjin Patentee after: Carbo Technology Group Co.,Ltd. Address before: 301700 Tianjin District of Wuqing City Heng Yuan Road No. 1 Keihin Industrial Zone Patentee before: CARBON COMPOSITES (TIANJIN) Co.,Ltd. |