CN208534070U - The vertical underthrust constructing device of steel column high-precision - Google Patents
The vertical underthrust constructing device of steel column high-precision Download PDFInfo
- Publication number
- CN208534070U CN208534070U CN201820929754.9U CN201820929754U CN208534070U CN 208534070 U CN208534070 U CN 208534070U CN 201820929754 U CN201820929754 U CN 201820929754U CN 208534070 U CN208534070 U CN 208534070U
- Authority
- CN
- China
- Prior art keywords
- steel column
- clamp assemblies
- precision
- straight
- constructing device
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The utility model relates to be related to the vertical underthrust constructing device of steel column high-precision, including for clamping steel column, lower clamp assemblies, and for adjusting, the adjusting component of lower clamp assemblies relative position, there is the first through hole for allowing steel column to pass through on upper clamp assemblies, and the first clamping element for clamp or release steel column, there is the second through-hole for allowing steel column to pass through on lower clamp assemblies, and the second clamping element for clamp or release steel column, the adjusting component includes multiple straight-line motion mechanisms and rotating mechanism, the straight-line motion mechanism by rotating mechanism with it is upper, lower clamp assemblies connection, upper and lower clamp assemblies in the direction of motion where straight-line motion mechanism close to or far from, on, lower clamp assemblies adjust the angle between straight-line motion mechanism by rotating mechanism.The constructing device and method of the utility model can multiple degrees of freedom adjustment steel column verticality, improve underthrust construction precision.
Description
Technical field
The utility model relates to steel column constructing devices, and in particular to the vertical underthrust constructing device of steel column high-precision.
Background technique
In one column construction of underground steel column, steel column is more demanding to vertical precision, conventional installation of steel columns
It is to use manually to descend to after bottom hole installation positioner, then the construction method of steel column is installed, long construction period, complex procedures, and
In work progress worker to descend bottom hole carry out concrete cut and locator installation, it is single there are many insecurity factors
Steel column construction period is up to 10~20 days, and construction cost is also higher, has some limitations.It is main existing for other methods
Problem is that the verticality precision of steel column relies primarily on air bag, hydraulic system is rectified a deviation, the displacement essence of the deviation correction mechanism system
Spend low, feedback is slow, and stability is poor, for thin tail sheep trace regulation, it is difficult to realize, and people and equipment is needed to merge ability repeatedly
Play optimal regulating power, it is difficult to meet duration of a project and required precision.Cannot according to other construction methods in the industry
Meet construction precision and construction period.
Summary of the invention
The steel column height that the main purpose of the utility model is to provide a kind of multiple degrees of freedom adjustment steel column verticality hangs down
Straight precision underthrust constructing device.
To achieve the goals above, the utility model provides a kind of steel column high-precision vertical underthrust constructing device, including
For clamping the upper and lower clamp assemblies of steel column, and the adjusting component for adjusting upper and lower clamp assemblies relative position,
There is the first through hole for allowing steel column to pass through, and for the first of clamp or release steel column on upper clamp assemblies
Clamping element,
There is the second through-hole for allowing steel column to pass through, and for the second of clamp or release steel column on lower clamp assemblies
Clamping element,
The adjusting component includes multiple straight-line motion mechanisms and rotating mechanism, and the straight-line motion mechanism passes through
Rotating mechanism is connect with upper and lower clamp assemblies, upper and lower clamp assemblies it is close in the direction of motion where straight-line motion mechanism or
Separate, upper and lower clamp assemblies adjust the angle between straight-line motion mechanism by rotating mechanism.
Above-mentioned constructing device further includes following optimization structure:
Including laser guidance device, obliquity sensor.
The rotating mechanism is using universal spherical joint, cross universal hinge or hinge.
The straight-line motion mechanism includes hydraulic cylinder, electric cylinder, electric pushrod or ball-screw.
Distribution is provided with 3 straight-line motion mechanisms between upper clamp assemblies and lower clamp assemblies.
Multiple anti-torque arm are connected between upper and lower clamp assemblies.
The advantages of the utility model:
1, mechanism is simple, and required power is small;
2, system stiffness is high, and response is fast, and the adjustment period is short, it can be achieved that precise fine-adjustment.
The beneficial effects of the utility model include:
1. the scope of application of the construction method is wider, easy construction, high reliablity;
2. it is safe and reliable, bottom hole, which is carried out, without artificial tripping in abolishes pile crown;
3. speed of application is fast, duration effect is obvious and loss is few, at low cost.
Detailed description of the invention
The front view of Fig. 1 the utility model.
Fig. 2 is the utility model side view.
In figure: 1- steel column, the upper clamp assemblies of 2-, the anti-torque arm of 3-, 4- universal spherical joint, 5- hydraulic cylinder, clamping group under 6-
Part.
Specific embodiment
Hereinafter, be described further with attached drawing for the utility model in conjunction with the embodiments, embodiment and attached drawing are only used for solving
It releases explanation rather than limits the protection scope of the utility model.
The vertical underthrust constructing device structure of steel column high-precision in embodiment as shown in the figures 1 and 2, including is used to clamp steel
The upper and lower clamp assemblies of column, and the adjusting component for adjusting upper and lower clamp assemblies relative position, in order to increase adjustment
Precision can also be equipped with laser guidance device, obliquity sensor.In order to increase stability, pedestal can also be set.
Upper and lower clamp assemblies main body is a platform member in this embodiment, has in platform hook and steel column is allowed to wear
The first, second through-hole crossed, and for the first, second clamping element of clamp or release steel column, clamping element can use liquid
Clamping device is pressed, set-up mode, which can be, to be directly anchored in upper and lower two platform members,
Adjusting component includes multiple straight-line motion mechanisms and rotating mechanism, straight-line motion mechanism can be hydraulic cylinder,
Electric cylinder, electric pushrod or ball-screw etc..Rotating mechanism can be using universal spherical joint, cross universal hinge or hinge etc..It has
The set-up mode of body is, upper and lower clamp assemblies pass through respectively to be rotatably connected in the push rod of the oil cylinder of hydraulic cylinder and solid
On fixed end, it is hydraulic have sympathetic clamp assemblies or lower clamp assemblies can be pushed to move in a straight line.Electric cylinder, electric pushrod are set
Set that mode is similar, the set-up mode of ball-screw is that upper and lower clamp assemblies are separately positioned on the traveling nut on screw rod and screw rod
On, it moves along a straight line.The movable both ends of universal spherical joint, cross universal hinge or hinge are separately positioned on corresponding upper and lower clamping
On component and straight-line motion mechanism, there are two the freedom degrees relatively rotated for two components that rotating device allows to connect.Straight line fortune
Motivation structure is connect by rotating mechanism with upper and lower clamp assemblies, and upper and lower clamp assemblies are in the movement side where straight-line motion mechanism
It abuts up close or remote from upper and lower clamp assemblies adjust the angle between straight-line motion mechanism by rotating mechanism.Preferably, exist
In the present embodiment, distribution is provided with 3 straight-line motion mechanisms between upper clamp assemblies and lower clamp assemblies.Upper and lower clamp assemblies
Between be connected with multiple anti-torque arm.Its set-up mode can be taken into account in this way as shown in Figure 1, in approximate equilateral triangle in figure
To the adjustment of all angles, and it is further, it can be set to 2,4,5 are even more.
It is constructed using the above-mentioned vertical underthrust constructing device of steel column high-precision, Specific construction principle are as follows: using super
Retarded concrete construction lower support stake, to ensure that steel column has certain adjusting leeway and construction after reaching design buried depth
Space, later utilize above-mentioned apparatus, using on steel column laser guidance device and above-mentioned apparatus as fulcrum, pass through Three Degree Of Freedom
The internal hydraulic pressure clamper of underthrust construction machinery carries out the adjusting of depth, center and verticality, wants to reach design
It asks.
Construction procedure includes:
A) preparation of construction;
B) drilling machine is removed in pour stake body by concrete completion, clears up aperture;
C) installation of Three Degree Of Freedom underthrust machinery tune, positioning, leveling;
D) steel column is hung in;
E) upper mounting plate clamps steel column, and lower platform releasing orientation is pushed by linear motion device and carried out vertical
Degree adjustment;
F) lower platform clamps steel column, upper mounting plate releasing orientation;
G) upper mounting plate return repeats e, f step;
H) after projected depth being inserted under steel column, steel column is fixed;
I) stake holes backfills slip casting;
One pile for one column proposes high requirement to verticality as permanent structural column.One pile for one column top steel column
Verticality require to reach 1/2000, in order to ensure the insertion depth of steel column in one pile for one column construction, center and vertical
Degree meets design requirement, need to accomplish claimed below:
1) fixation of laser guidance device and steel column must be close, secured.
2) present apparatus decomposes lifting, accomplishes that base center, the Clamping Center of upper and lower clamp assemblies and pile center's deviation are little
In 1 cm, and ensure the stability of straightening frame.
3) after steel column is inserted under guide hydraulic clamping device under, different location installs sensing with steel column
Device, sensor must not be placed on same section or same straight line, more accurately to reflect the verticality of steel column.
4) after steel column lifts up into the present apparatus, start the underthrust construction that steel column is carried out with upper mounting plate internal clampers.It is logical
It crosses after setting basic parameter, equipment can carry out insertion automatically and verticality adjusts work.
5) verticality for the obliquity sensor monitoring steel column that the monitoring of equipment overall process is mounted on steel column, if hung down
Straight degree is maintained within coarse adjustment range, and equipment only repeats circulation and is downwardly into work, if the verticality reading read
More than the coarse adjustment range limiting value of setting, after the insertion circulation currently carried out terminates, equipment automatically switches to vertical adjustment mode,
The closed-loop automatic control of verticality is realized by the progressive error of three electric cylinders of process control.
6) control for carrying out insertion depth in steel column down process by the scale on shaft, is adjusted subsequent in place
It is continuous that projected depth in lower support stake will be inserted under steel column, and after inspection center position, verticality are qualified to steel column into
Row is fixed.
7) lower platform and lower gripper can remove after lower support stake reaches some strength, be connected later by reinforcing bar
Tap into the fixation work of row steel column.
Claims (6)
1. a kind of vertical underthrust constructing device of steel column high-precision, it is characterised in that including the upper and lower folder for clamping steel column
Component, and the adjusting component for adjusting upper and lower clamp assemblies relative position are held,
There is the first through hole for allowing steel column to pass through on upper clamp assemblies, and clamped for the first of clamp or release steel column
Part,
There is the second through-hole for allowing steel column to pass through on lower clamp assemblies, and clamped for the second of clamp or release steel column
Part,
The adjusting component includes multiple straight-line motion mechanisms and rotating mechanism, and the straight-line motion mechanism passes through rotation
Mechanism is connect with upper and lower clamp assemblies, upper and lower clamping part in the direction of motion where straight-line motion mechanism close to or far from,
Upper and lower clamping part adjusts the angle between straight-line motion mechanism by rotating mechanism.
2. the vertical underthrust constructing device of steel column as described in claim 1 high-precision, it is characterised in that filled including laser guide
It sets, obliquity sensor.
3. the vertical underthrust constructing device of steel column as described in claim 1 high-precision, it is characterised in that the rotating mechanism
Using universal spherical joint, cross universal hinge or hinge.
4. the vertical underthrust constructing device of steel column as described in claim 1 high-precision, it is characterised in that the linear motion
Mechanism includes hydraulic cylinder, electric cylinder, electric pushrod or ball-screw.
5. the vertical underthrust constructing device of steel column as described in claim 1 high-precision, it is characterised in that upper clamp assemblies are under
Distribution is provided with 3 straight-line motion mechanisms between clamp assemblies.
6. the vertical underthrust constructing device of steel column as described in claim 1 high-precision, it is characterised in that upper and lower clamp assemblies it
Between be connected with multiple anti-torque arm.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820929754.9U CN208534070U (en) | 2018-06-15 | 2018-06-15 | The vertical underthrust constructing device of steel column high-precision |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820929754.9U CN208534070U (en) | 2018-06-15 | 2018-06-15 | The vertical underthrust constructing device of steel column high-precision |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208534070U true CN208534070U (en) | 2019-02-22 |
Family
ID=65392704
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820929754.9U Active CN208534070U (en) | 2018-06-15 | 2018-06-15 | The vertical underthrust constructing device of steel column high-precision |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208534070U (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108691421A (en) * | 2018-06-15 | 2018-10-23 | 中铁上海工程局集团有限公司 | The vertical underthrust constructing device of steel column high-precision and method |
CN110130662A (en) * | 2019-07-09 | 2019-08-16 | 上海建工集团股份有限公司 | The fine plumbing device of one pile for one column, system and method |
CN114808807A (en) * | 2022-04-22 | 2022-07-29 | 湖南省通和工程有限公司 | Visual adjusting system for guaranteeing construction quality control of waveform guardrail stand column |
-
2018
- 2018-06-15 CN CN201820929754.9U patent/CN208534070U/en active Active
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108691421A (en) * | 2018-06-15 | 2018-10-23 | 中铁上海工程局集团有限公司 | The vertical underthrust constructing device of steel column high-precision and method |
CN110130662A (en) * | 2019-07-09 | 2019-08-16 | 上海建工集团股份有限公司 | The fine plumbing device of one pile for one column, system and method |
CN110130662B (en) * | 2019-07-09 | 2019-09-27 | 上海建工集团股份有限公司 | The fine plumbing device of one pile for one column, system and method |
CN114808807A (en) * | 2022-04-22 | 2022-07-29 | 湖南省通和工程有限公司 | Visual adjusting system for guaranteeing construction quality control of waveform guardrail stand column |
CN114808807B (en) * | 2022-04-22 | 2023-08-22 | 湖南省通和工程有限公司 | Visual governing system of guarantee wave form guardrail stand construction quality control |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108691421A (en) | The vertical underthrust constructing device of steel column high-precision and method | |
CN208534070U (en) | The vertical underthrust constructing device of steel column high-precision | |
CN110962695B (en) | Automatic installation equipment and installation method for high-speed rail contact network cantilever | |
CN207077092U (en) | A kind of mash welder welding bench | |
CN208054811U (en) | A kind of portable hinge connecting rod lifting device | |
CN207047712U (en) | A kind of precast beam is traversing and vertical fall girder apparatus | |
CN105971539A (en) | Coring drilling machine mast adjusting mechanism | |
CN112265133B (en) | Support leveling steel plate position adjusting device and method for manufacturing precast beam | |
CN108691277A (en) | The three-dimensional adjustment tooling positioned in erection process for precast segment spliced girder | |
CN104594143A (en) | Inner supporting type screw adjuster and track skeleton positioning method | |
CN208023578U (en) | Stake machine | |
CN116480108A (en) | Equipment and method for installing prefabricated bare concrete exterior wall cladding | |
CN208762878U (en) | A kind of mobile formwork for building | |
CN212742614U (en) | Foundation inner stand column positioning and mounting structure | |
CN110962696B (en) | Contact net cantilever mounting template | |
CN110593261A (en) | Vertical supporting pile verticality adjusting platform and construction method | |
JP2005023719A (en) | Rail holding device and rail installation method by use of rail holding device | |
CN113882692A (en) | Steel column positioning device and positioning method thereof | |
CN210395423U (en) | Tower machine basis installation positioner | |
CN210597309U (en) | Vertical supporting pile verticality adjusting platform | |
CN220434271U (en) | Steel-pipe column positioning and mounting device | |
CN112049029A (en) | Deviation-rectifying and resetting device for pier stud of bridge | |
CN110821190A (en) | Installing and verticality adjusting machine for steel pipe column and installing and verticality adjusting method for steel pipe column | |
WO2016073982A9 (en) | Apparatus and method for a pipe handling system | |
CN220644638U (en) | Novel steel column connection structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CP01 | Change in the name or title of a patent holder |
Address after: 200436, No. three, 278 Road, Jingan District, Shanghai Patentee after: SHANGHAI CIVIL ENGINEERING Co.,Ltd. OF CREC Patentee after: China Railway Municipal Environmental Construction Co.,Ltd. Address before: 200436, No. three, 278 Road, Jingan District, Shanghai Patentee before: SHANGHAI CIVIL ENGINEERING Co.,Ltd. OF CREC Patentee before: China Railway Shanghai Engineering Bureau Group Municipal Engineering Co.,Ltd. |
|
CP01 | Change in the name or title of a patent holder |