CN208526130U - A kind of construction dust-extraction unit - Google Patents

A kind of construction dust-extraction unit Download PDF

Info

Publication number
CN208526130U
CN208526130U CN201820709889.4U CN201820709889U CN208526130U CN 208526130 U CN208526130 U CN 208526130U CN 201820709889 U CN201820709889 U CN 201820709889U CN 208526130 U CN208526130 U CN 208526130U
Authority
CN
China
Prior art keywords
rectangular cylinder
pipe
collecting box
baffle
plugged
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820709889.4U
Other languages
Chinese (zh)
Inventor
温全
刘利伟
杨象光
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhangjiakou Third Construction Engineering Co
Original Assignee
Zhangjiakou Third Construction Engineering Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhangjiakou Third Construction Engineering Co filed Critical Zhangjiakou Third Construction Engineering Co
Priority to CN201820709889.4U priority Critical patent/CN208526130U/en
Application granted granted Critical
Publication of CN208526130U publication Critical patent/CN208526130U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Filtering Of Dispersed Particles In Gases (AREA)

Abstract

The utility model discloses a kind of construction dust-extraction units, including pedestal and collecting box, collecting box is welded on the right side of the upper surface of the pedestal, the upper surface left screw of the pedestal is connected with water pump, the right side clamp connection of the water pump has one end of the first water inlet pipe, the other end of first water inlet pipe and the left side inner bottom of collecting box are interference fitted and connect, clamp connection has one end of the second outlet pipe on the right side of the top of the water pump, and upper and lower ends are interference fitted respectively inside the right side of the collecting box is connected with the second water inlet pipe and the first outlet pipe.The construction dust-extraction unit, when use, by starting blower and water pump, so that large area clears up dust, the dust after processing is avoided to blow out, influence dedusting quality, by the grafting of slideway and the second fixture block, filter screen is cleaned or is replaced, so that the water energy for clearing up dust be made to be recycled, the utilization rate of water is got higher, and meets the theory of modern water conservation.

Description

A kind of construction dust-extraction unit
Technical field
The utility model relates to technical field of buildings, specially a kind of construction dust-extraction unit.
Background technique
Currently, construction site is difficult to avoid that the generation of dust, the generation of a large amount of dust generate the body of worker when constructing Very big influence, since dust is small in size, light weight, it is easy to large area raises, once it is sucked by mouth, nose by construction worker In vivo, worker's throat, lung can be caused uncomfortable, be difficult to be discharged after dust sucking, lung is deposited in and is easy to cause pulmonary disease, it is right The health harm of worker is very big, and construction worker is in for a long time in the environment of the construction of construction site, and eyes directly contact largely Dust causes ophthalmic uncomfortable, and raising due to dust, and construction site low visibility increases the difficulty of worker's construction, reduces Construction quality can only also be done although the problem of many companies are directed to dust from flying is equipped with safeguard for construction worker Some simple protection, present simplest protective approach be prevent dust from being sucked by human body by way of wearing masks, but Mask makes worker's unsmooth breath, has a great impact for construction quality, and construction site dust quantity is huge, even if wearing mouth Cover carries out the construction working in construction site, and dust can also be assembled on mask quickly, it is difficult to play protection effect, existing building site Used dust-extraction unit when in use can not large area dust is cleared up, and it is processed after dust be easy to blow out, shadow
Dedusting quality is rung, and the water for clearing up dust cannot be recycled, the utilization rate of water is lower, and does not meet the modern times The theory of water conservation.
Utility model content
The purpose of this utility model is to provide a kind of construction dust-extraction units, to solve to propose in above-mentioned background technique The problem of.
To achieve the above object, the utility model provides the following technical solutions: a kind of construction dust-extraction unit, including bottom The upper surface right side of seat and collecting box, the pedestal is welded with collecting box, and the upper surface left screw of the pedestal is connected with water Pump, the right side clamp connection of the water pump have one end of the first water inlet pipe, the other end of first water inlet pipe and collecting box The interference fit connection of left side inner bottom, the top right side clamp connection of the water pump have one end of the second outlet pipe, the receipts Upper and lower ends are interference fitted respectively inside the right side of header is connected with the second water inlet pipe and the first outlet pipe, first outlet pipe Upper surface on the right side of be threaded with valve, the top inner hub location interference fit of the collecting box is connected with third rectangle Cylinder, the top of the third rectangular cylinder are welded with the second rectangular cylinder, and the inner cavity left-hand face of second rectangular cylinder offers the One groove, the inner cavity front and rear sides surface of second rectangular cylinder offer the second groove, and the inside of second groove is inserted It is connected to filter screen, and extends to the inside of the first groove on the left of filter screen, the outer right wall of second rectangular cylinder offers Third groove, the inner tip of the third groove offer blind hole, and the inside of the third groove is plugged with first baffle, institute The outer right wall center for stating first baffle offers slideway, and the inner bottom of the first baffle is plugged with spring, described The top of spring is connected with the second fixture block, and extends the inside of slideway on the right side of the second fixture block, the top of second fixture block Left side is welded with the first fixture block, and the top of the first fixture block extends to the inside of blind hole, the top welding of second rectangular cylinder There is trapezoidal cylinder, the top of the trapezoidal cylinder is welded with the first rectangular cylinder, and the top of first rectangular cylinder is welded with second baffle, Bottom end is plugged with one end of spray line on the right side of the inner cavity of first rectangular cylinder, and the other end of spray line extends the first rectangle The left side outer wall of cylinder is connected with the other end of the second outlet pipe, and gap arrangement has the second spray to the outer wall of the spray line from left to right Head, the inner cavity top of first rectangular cylinder are plugged with the second discharge pipe, the outer wall of second discharge pipe gap from left to right It is arranged with first spray head, the outer wall center interference fit of second discharge pipe is connected with one end of the first discharge pipe, institute The other end for stating the first discharge pipe is plugged with blower through the inside of second baffle, and blower is located at the top right side of second baffle Side is socketed with one end of the first blast pipe on the right side of the blower, is welded with square at left and right sides of the top of the second baffle Shape plate, the inner tip of the rectangular slab is plugged with the second blast pipe, and rectangular slab is extended in the left and right ends of the second blast pipe Outer wall, the other end grafting of the inner right side of second blast pipe and the first blast pipe, the outer wall of second blast pipe Center is plugged with third blast pipe, and the equal grafting in top of the left and right ends and third blast pipe of second blast pipe is free Gas hood.
Preferably, the bottom end screw of the blower is connected with bottom plate, and the bottom plate is connect with second baffle screw.
Preferably, the inside of the airhood is embedded with gauze.
Preferably, the right side inner hub location of the collecting box is embedded with glass plate.
Preferably, it is 5cm that second fixture block, which extends the distance of the inside of slideway,.
Compared with prior art, the utility model has the beneficial effects that the construction dust-extraction unit, in use, passing through Start blower and water pump, extraneous dust is sucked from airhood under the suction of blower, passes sequentially through third blast pipe, the Two blast pipes and the first blast pipe are passed to blower, and dust passes sequentially through the first discharge pipe, the second discharge pipe by the air outlet of blower Dust is sprayed into the first rectangular cylinder with first spray head, at the same time under the suction of water pump, the water in collecting box is led to It crosses the first water inlet pipe to be passed in water pump, then so that water is sequentially passed through the second outlet pipe and spray line from the second spray by the water outlet of water pump Head sprays, and waterwall lateral together is formed in the first rectangular cylinder, and the dust sucked in the first rectangular cylinder passes through waterwall and removed Dirt, the sewage after dedusting successively flow on filter screen along the inner wall of the first rectangular cylinder and trapezoidal cylinder, and filter screen is to sewage at this time It is filtered, filtered sewage flows into collecting box along third rectangular cylinder, so that clearing up dust for large area, keeps away Exempt from it is processed after dust blow out, influence dedusting quality, by the grafting of slideway and the second fixture block, when filter screen need cleaning or When damage, the second fixture block is pressed downwards, the second fixture block squeezes spring along the inside slide downward of slideway, after spring is squeezed Elastic deformation is generated, the second fixture block drives the first fixture block along the inside slide downward of blind hole at the same time, until the first fixture block Separated with blind hole, pull first baffle to the right, first baffle along third groove inside Slideslip to the right, until first gear Plate is separated with third groove, and filter screen is pulled out out of the first groove and the second groove, is cleaned or is replaced to filter screen, from And the water energy for clearing up dust is recycled, the utilization rate of water is got higher, and meets the theory of modern water conservation.
Detailed description of the invention
FIG. 1 is a schematic structural view of the utility model;
Fig. 2 is the first baffle cross-sectional view of the utility model.
In figure: 1, pedestal, 2, collecting box, 3, water pump, the 4, first water inlet pipe, the 5, first outlet pipe, 6, valve, 7, second into Water pipe, the 8, second outlet pipe, 9, spray line, the 10, first rectangular cylinder, the 11, second discharge pipe, 12, airhood, the 13, second air inlet Pipe, the 14, first discharge pipe, 15, third blast pipe, the 16, first blast pipe, 17, rectangular slab, 18, blower, 19, second baffle, 20, first spray head, 21, second spray head, 22, trapezoidal cylinder, 23, filter screen, the 24, second rectangular cylinder, 25, third rectangular cylinder, 26, One groove, the 27, second groove, 28, third groove, 29, blind hole, 30, first baffle, 31, slideway, the 32, first fixture block, 33, Two fixture blocks, 34, spring, 35, bottom plate.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work Every other embodiment obtained, fall within the protection scope of the utility model.
The utility model provides a kind of technical solution referring to FIG. 1-2: a kind of construction dust-extraction unit, including pedestal 1 It is welded with collecting box 2 with the upper surface right side of collecting box 2, pedestal 1, the upper surface left screw of pedestal 1 is connected with water pump 3, leads to Crossing water pump 3 is transported to the water in collecting box 2 in first rectangular cylinder 10, and the right side clamp connection of water pump 3 has the first water inlet pipe 4 One end, the other end of the first water inlet pipe 4 and the left side inner bottom of collecting box 2 are interference fitted and connect, card on the right side of the top of water pump 3 Hoop is connected with one end of the second outlet pipe 8, and upper and lower ends are interference fitted respectively inside the right side of collecting box 2 is connected with the second water inlet Pipe 7 and the first outlet pipe 5, are injected water into collecting box 2 by the second water inlet pipe 7, spiral shell on the right side of the upper surface of the first outlet pipe 5 Line is connected with valve 6, and by the cooperation of the first outlet pipe 5 and valve 6, the sewage after making dedusting is flowed out out of collecting box 2, collects The top inner hub location interference fit of case 2 is connected with third rectangular cylinder 25, and the top of third rectangular cylinder 25 is welded with second Rectangular cylinder 24, the inner cavity left-hand face of the second rectangular cylinder 24 offer the first groove 26, the inner cavity front and back two of the second rectangular cylinder 24 Side surface offers the second groove 27, filter screen 23 is fixed by the first groove 26 and the second groove 27, second is recessed The inside of slot 27 is plugged with filter screen 23, and the left side of filter screen 23 extends to the inside of the first groove 26, the second rectangular cylinder 24 Outer right wall offer third groove 28, the inner tip of third groove 28 offers blind hole 29, passes through blind hole 29 and first The grafting of fixture block 32 is fixed on first baffle 30 in third groove 28, and the inside of third groove 28 is plugged with first baffle 30, The outer right wall center of first baffle 30 offers slideway 31, and the inner bottom of first baffle 30 is plugged with spring 34, bullet Spring 34 is helical spring, and coefficient of elasticity 30N/CM, spring 34 is stretched or generates after squeezing elastic deformation, after removing external force Restore to original state, the top of spring 34 is connected with the second fixture block 33, and slideway 31 is extended on the right side of the second fixture block 33 Inside moves downward the second fixture block 33 along the inside of slideway 31 by pressing the second fixture block 33 downwards, the second fixture block 33 Top left hand is welded with the first fixture block 32, and the top of the first fixture block 32 extends to the inside of blind hole 29, the second rectangular cylinder 24 Top is welded with trapezoidal cylinder 22, and the top of trapezoidal cylinder 22 is welded with the first rectangular cylinder 10, and the top of the first rectangular cylinder 10 is welded with Second baffle 19, the inner cavity right side bottom end of the first rectangular cylinder 10 is plugged with one end of spray line 9, and the other end of spray line 9 prolongs The left side outer wall for stretching out the first rectangular cylinder 10 is connected with the other end of the second outlet pipe 8, the outer wall of spray line 9 gap from left to right It is arranged with second spray head 21, the inner cavity top of the first rectangular cylinder 10 is plugged with the second discharge pipe 11, the outer wall of the second discharge pipe 11 Gap arrangement has first spray head 20 from left to right, and the outer wall center interference fit of the second discharge pipe 11 is connected with the first outlet air The other end of one end of pipe 14, the first discharge pipe 14 is plugged with blower 18 through the inside of second baffle 19, will by blower 18 The dust in the device external world sucks in the first rectangular cylinder 10, and blower 18 is located on the right side of the top of second baffle 19, blower 18 Right side is socketed with one end of the first blast pipe 16, is welded with rectangular slab 17, rectangular slab at left and right sides of the top of second baffle 19 17 inner tip is plugged with the second blast pipe 13, and the outer wall of rectangular slab 17 is extended in the left and right ends of the second blast pipe 13, It inserts the outer wall center of the other end grafting of the inner right side of second blast pipe 13 and the first blast pipe 16, the second blast pipe 13 It is connected to third blast pipe 15, the left and right ends of the second blast pipe 13 and the top of third blast pipe 15 are plugged with airhood 12, The bottom end screw of blower 18 is connected with bottom plate 35, and bottom plate 35 is connect with 19 screw of second baffle, and the inside of airhood 12 is embedded with Gauze is filtered dust by gauze, and the right side inner hub location of collecting box 2 is embedded with glass plate, passes through glass plate Convenient for the dirty degree of the water in observation collecting box 2, the distance that the second fixture block 33 extends the inside of slideway 31 is 5cm, is needed When cleaning or replacement filter screen, convenient for pressing the second fixture block 33 downwards.
The construction dust-extraction unit, in use, being injected in collecting box 2 from the second water inlet pipe 7 by clear water, peripheral control unit By power initiation blower 18 and water pump 3, extraneous dust is sucked from airhood 12 under the suction of blower 18, is successively led to Cross third blast pipe 15, the second blast pipe 13 and the first blast pipe 16 and be passed to blower 18, dust by blower 18 air outlet successively Dust is sprayed into the first rectangular cylinder 10 by the first discharge pipe 14, the second discharge pipe 11 and first spray head 20, is existed at the same time Under the suction of water pump 3, the water in collecting box 2 is passed in water pump 3 by the first water inlet pipe 4, then by the water outlet of water pump 3 Make water sequentially pass through the second outlet pipe 8 and spray line 9 to spray from second spray head 21, be formed in the first rectangular cylinder 10 together laterally Waterwall, suck the first rectangular cylinder 10 in dust in impurity be integrated with water, the sewage after dedusting is successively along the first rectangle The inner wall of cylinder 10 and trapezoidal cylinder 20 flows on filter screen 23, and filter screen 23 is filtered sewage at this time, and the impurity of filtering stays in On filter screen 23, filtered sewage flows into collecting box 2 along third rectangular cylinder 25, so that carrying out to dust for large area is clear Reason, avoid it is processed after dust blow out, influence dedusting quality, when filter screen 23 needs to clean or damage, press the downwards Two fixture blocks 33, the second fixture block 33 squeeze spring 34 along the inside slide downward of slideway 31, and spring 34 generates bullet after being squeezed Property deformation, the second fixture block 33 drives the first fixture block 32 along the inside slide downward of blind hole 29, until the first fixture block at the same time 32 separate with blind hole 29, pull first baffle 30 to the right, first baffle 30 along third groove 28 inside Slideslip to the right, Until first baffle 30 is separated with third groove 28, filter screen 23 is pulled out out of the first groove 26 and the second groove 27, to mistake Strainer 23 is cleaned or is replaced, so that the water energy for clearing up dust be made to be recycled, the utilization rate of water is got higher, and meets the modern times The theory of water conservation.

Claims (5)

1. a kind of construction dust-extraction unit, including pedestal (1) and collecting box (2), the upper surface right side welding of the pedestal (1) There are collecting box (2), it is characterised in that: the upper surface left screw of the pedestal (1) is connected with water pump (3), the water pump (3) Right side clamp connection has one end of the first water inlet pipe (4), the other end of first water inlet pipe (4) and the left side of collecting box (2) Inner bottom interference fit connection, the top right side clamp connection of the water pump (3) has one end of the second outlet pipe (8), described Upper and lower ends are interference fitted respectively inside the right side of collecting box (2) is connected with the second water inlet pipe (7) and the first outlet pipe (5), institute It states and is threaded with valve (6) on the right side of the upper surface of the first outlet pipe (5), the top inner hub location of the collecting box (2) Interference fit is connected with third rectangular cylinder (25), and the top of the third rectangular cylinder (25) is welded with the second rectangular cylinder (24), institute The inner cavity left-hand face for stating the second rectangular cylinder (24) offers the first groove (26), before and after the inner cavity of second rectangular cylinder (24) Both side surface offers the second groove (27), and the inside of second groove (27) is plugged with filter screen (23), and filter screen (23) inside of the first groove (26) is extended on the left of, the outer right wall of second rectangular cylinder (24) offers third groove (28), the inner tip of the third groove (28) offers blind hole (29), and the inside of the third groove (28) is plugged with The outer right wall center of one baffle (30), the first baffle (30) offers slideway (31), the first baffle (30) Inner bottom be plugged with spring (34), the top of the spring (34) is connected with the second fixture block (33), and the second fixture block (33) Right side extend the inside of slideway (31), the top left hand of second fixture block (33) is welded with the first fixture block (32), and The top of one fixture block (32) extends to the inside of blind hole (29), and the top of second rectangular cylinder (24) is welded with trapezoidal cylinder (22), the top of the trapezoidal cylinder (22) is welded with the first rectangular cylinder (10), and the top of first rectangular cylinder (10) is welded with Second baffle (19), the inner cavity right side bottom end of first rectangular cylinder (10) are plugged with one end of spray line (9), and spray line (9) the left side outer wall that the other end extends the first rectangular cylinder (10) is connected with the other end of the second outlet pipe (8), the sprinkling Gap arrangement has second spray head (21) outer wall of pipe (9) from left to right, and the inner cavity top of first rectangular cylinder (10) is plugged with Second discharge pipe (11), gap arrangement has first spray head (20) outer wall of second discharge pipe (11) from left to right, and described The outer wall center interference fit of two discharge pipes (11) is connected with one end of the first discharge pipe (14), first discharge pipe (14) the other end is plugged with blower (18) through the inside of second baffle (19), and blower (18) is located at second baffle (19) On the right side of top, one end of the first blast pipe (16), the top of the second baffle (19) are socketed on the right side of the blower (18) The left and right sides is welded with rectangular slab (17), and the inner tip of the rectangular slab (17) is plugged with the second blast pipe (13), and the The outer wall of rectangular slab (17) is extended in the left and right ends of two blast pipes (13), the inner right side of second blast pipe (13) and the The outer wall center of the other end grafting of one blast pipe (16), second blast pipe (13) is plugged with third blast pipe (15), the left and right ends of second blast pipe (13) and the top of third blast pipe (15) are plugged with airhood (12).
2. a kind of construction dust-extraction unit according to claim 1, it is characterised in that: the bottom end spiral shell of the blower (18) Nail is connected with bottom plate (35), and the bottom plate (35) connect with second baffle (19) screw.
3. a kind of construction dust-extraction unit according to claim 1, it is characterised in that: the inside of the airhood (12) It is embedded with gauze.
4. a kind of construction dust-extraction unit according to claim 1, it is characterised in that: the right side of the collecting box (2) Inner hub location is embedded with glass plate.
5. a kind of construction dust-extraction unit according to claim 1, it is characterised in that: second fixture block (33) extends The distance of the inside of slideway (31) is 5cm out.
CN201820709889.4U 2018-05-12 2018-05-12 A kind of construction dust-extraction unit Expired - Fee Related CN208526130U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820709889.4U CN208526130U (en) 2018-05-12 2018-05-12 A kind of construction dust-extraction unit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820709889.4U CN208526130U (en) 2018-05-12 2018-05-12 A kind of construction dust-extraction unit

Publications (1)

Publication Number Publication Date
CN208526130U true CN208526130U (en) 2019-02-22

Family

ID=65393508

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820709889.4U Expired - Fee Related CN208526130U (en) 2018-05-12 2018-05-12 A kind of construction dust-extraction unit

Country Status (1)

Country Link
CN (1) CN208526130U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110448975A (en) * 2019-07-05 2019-11-15 高邮市永发机械有限公司 A kind of CNC milling machine high effect dust cleaner
CN111228938A (en) * 2020-03-03 2020-06-05 河海大学 Dust removal environmental protection equipment for building site
CN111451239A (en) * 2020-05-12 2020-07-28 山西省工业设备安装集团有限公司 Building site excavation device
CN113798270A (en) * 2021-09-18 2021-12-17 河南同心传动股份有限公司 Environment-friendly transmission shaft processing dust collector
CN114768431A (en) * 2022-04-25 2022-07-22 宁夏新创艺实业有限公司 Multistage fountain dust suppression water saving fixtures that green building construction used

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110448975A (en) * 2019-07-05 2019-11-15 高邮市永发机械有限公司 A kind of CNC milling machine high effect dust cleaner
CN111228938A (en) * 2020-03-03 2020-06-05 河海大学 Dust removal environmental protection equipment for building site
CN111451239A (en) * 2020-05-12 2020-07-28 山西省工业设备安装集团有限公司 Building site excavation device
CN113798270A (en) * 2021-09-18 2021-12-17 河南同心传动股份有限公司 Environment-friendly transmission shaft processing dust collector
CN114768431A (en) * 2022-04-25 2022-07-22 宁夏新创艺实业有限公司 Multistage fountain dust suppression water saving fixtures that green building construction used
CN114768431B (en) * 2022-04-25 2023-08-15 宁夏新创艺实业有限公司 Multistage spray dust suppression water saving fixtures that green construction used

Similar Documents

Publication Publication Date Title
CN208526130U (en) A kind of construction dust-extraction unit
CN109011964A (en) A kind of textile manufacturing weaving loom dust collecting installation
CN209696581U (en) A kind of textile garment dust-extraction unit
CN109127138A (en) A kind of Wet-type electric dust removal system for capacitor production
CN208555011U (en) A kind of wheat processing cleaner
CN207680273U (en) A kind of weaving dirt collection device for spinning and weaving workshop
CN203694802U (en) Oil fume purifying device with movable brush
CN107537197A (en) Rapid sewage filtering equipment
CN206643030U (en) A kind of historical relic dust arrester
CN214782344U (en) Cleaning device is used in weaving
CN208678693U (en) Willow catkins flying in the air automatic clearing apparatus
CN210907127U (en) Spray cleaning machine water smoke filter
CN208943731U (en) A kind of raising-dust purifier
CN207494187U (en) A kind of dust-extraction unit for down-filling machine
CN211073077U (en) Wet-type polishing dust removal all-in-one
CN207806098U (en) A kind of dust exhaust apparatus
CN209195472U (en) A kind of sprinkling dust-removing device for development machine underground construction
CN207813182U (en) A kind of air improvement health tent
CN208383660U (en) A kind of dust in mine on-line monitoring data processor
CN208448943U (en) A kind of textile machinery dust-extraction unit
CN208694475U (en) A kind of air cleaning unit being convenient for changing filter
CN209529019U (en) A kind of health food production powder collecting dust-removing device
CN210544113U (en) Weaving is with weaving quick-witted weaving dirt collection device
CN217725036U (en) Integrated wet-type electric dust collector
CN208003652U (en) A kind of water curtain cleaning type air cleaning facility

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190222

Termination date: 20190512

CF01 Termination of patent right due to non-payment of annual fee