CN208520972U - Bilateral grounding type Online Transaction Processing for switching devices - Google Patents

Bilateral grounding type Online Transaction Processing for switching devices Download PDF

Info

Publication number
CN208520972U
CN208520972U CN201821301916.0U CN201821301916U CN208520972U CN 208520972 U CN208520972 U CN 208520972U CN 201821301916 U CN201821301916 U CN 201821301916U CN 208520972 U CN208520972 U CN 208520972U
Authority
CN
China
Prior art keywords
switchgear
host
stake
tested
bilateral
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821301916.0U
Other languages
Chinese (zh)
Inventor
彭紫楠
王淇锋
林长海
杨博
王赫男
郭鑫
王泽霖
宋杨
韩楠
薄彦斌
何云峰
王玮民
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Hebei Electric Power Co Ltd
Shijiazhuang Power Supply Co of State Grid Hebei Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Hebei Electric Power Co Ltd
Shijiazhuang Power Supply Co of State Grid Hebei Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Hebei Electric Power Co Ltd, Shijiazhuang Power Supply Co of State Grid Hebei Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201821301916.0U priority Critical patent/CN208520972U/en
Application granted granted Critical
Publication of CN208520972U publication Critical patent/CN208520972U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Testing Of Short-Circuits, Discontinuities, Leakage, Or Incorrect Line Connections (AREA)

Abstract

The utility model discloses a kind of bilateral grounding type Online Transaction Processings for switching devices, it is related to power equipment the field of test technology, and in particular to a kind of bilateral grounding type on-line testing equipment and test method that compbined test is carried out to defeated, change, distribution line switchgear.Technical solutions of the utility model include tested switchgear and the action drives device for controlling tested switchgear divide-shut brake, further includes: host, connecting cable, ground line, current sensor;Wherein, the ground line for connecting tested switchgear the same side binding post is electrically connected with the weldering stake of same ground connection, and the ground connection weldering stake is electrically connected by the connecting cable with the constant current source output terminal in host respectively.The utility model is intended to provide a kind of Online Transaction Processing for improving switchgear power failure test efficiency, Optimum Experiment process, reduction operational risk.

Description

Bilateral grounding type Online Transaction Processing for switching devices
Technical field
The utility model relates to power equipment the field of test technology, and in particular to a kind of to set to defeated, change, distribution line switch The standby bilateral grounding type on-line testing equipment and test method for carrying out compbined test.
Background technique
Switchgear includes the routes division brake apparatus such as breaker, disconnecting link, switchgear, air-break circuit-breaker, low tension switch, is Important equipment in defeated, change, distribution system, and usage amount is very big.By taking breaker as an example, a general 220kV substation Interior breaker is about in 20-30 platform.According to requiring, power supply company answers regular switching devices to be tested, to judge to switch Status of equipment, removal system hidden danger.The test of switchgear mainly includes mechanical characteristic test and loop circuit test etc..It is existing When carrying out power failure test to online switchgear, it is primarily present following problems: needing when a) switchgear has a power failure in its bilateral Suspension ground line, i.e. bilateral are grounded, but have a power failure when testing and generally required to remove unilateral ground line again, and process is more;B) it removes It connects wires and needs frequently to lift insulating bar, be easy to happen down bar to adjacent electrification and be spaced, lead to electric shock accidents, risk is high;C) it removes Needs of connecting wires are not easy to improve by regulation, O&M and the agreement of three departments of maintenance, the efficiency of management, and the preparatory period is long;D) to online The power failure of equipment is tested, because its installation site is high, when test generally requires several staff on ground or operating platform It lifts 3 to 5 meters long of insulating bar to carry out tearing extension work open, tears extension work open and have to comply with regulation, the once-through operation time is longer, test efficiency It is low;E) test apparatus with cable of different tests are different, and the mode of connection is generally also different, so scene holds when having a power failure test Easily disorderly, standardized management is difficult for wiring.
In the prior art to the loop resistance testing equipment of the switchgear of two sides earth, all think that earth mat resistance is much larger than The loop resistance of switchgear, therefore be insignificant, but in practical operation, there are missing inspection defects for this measurement form.Very More varieties in saline-alkali areas and copper ground web area (especially at substation's low tension switch), earth mat resistance very little, only switchgear returns Several times, Ji Shibei of road resistance, when a flow of electric current is passed through it, it is very big that network part is through-flow, this portion of electrical current be can not ignore, if Algorithm or wiring before also using there is very big error, lead to the erroneous judgement to equipment.
Utility model content
The utility model is intended to provide a kind of raising switchgear power failure test efficiency, Optimum Experiment process, reduces operation The Online Transaction Processing of risk.
Specific technical solution used by the utility model is:
A kind of bilateral grounding type Online Transaction Processing for switching devices, including tested switchgear and control are tested and open Close the action drives device of equipment divide-shut brake, further includes:
Host, the host are internally provided with central processing unit and the constant-current source connecting respectively with central processing unit, lead to Module, display module, operation panel and grafting panel are interrogated, the host is connect with action drives device and control action driver Drive tested switchgear divide-shut brake;
Connecting cable, described connecting cable one end are detachably connected by grafting panel with host, the other end be fixed with The clamping joint that ground connection weldering stake connects and fixes;
Ground line, described ground line one end are electrically connected with the binding post of tested switchgear, the other end and ground connection weldering stake electricity Connection;
Current sensor, the current sensor are connect by grafting panel with host, are set to tested switchgear and are returned Road, for detecting the electric current for flowing through tested switchgear;The tested switchgear circuit refers to circuit where its each phase contact, Or circuit of each phase contact by grounding point after in parallel;
Wherein, the ground line for connecting tested switchgear the same side binding post is electrically connected with the weldering stake of same ground connection, described to connect Ground weldering stake is electrically connected by the connecting cable with the constant current source output terminal in host respectively.
The technical solution further improvement lies in that: constant-current source be ac/dc constant-current source.
The technical solution further improvement lies in that: be additionally provided with voltage sensor in machine, the voltage sensor input Stake is welded with the ground connection by the connecting cable respectively and is connect in end.
The technical solution further improvement lies in that: in central processing unit be equipped with storage measurement record storage unit.
In one embodiment in technical solutions of the utility model, the tested switchgear is threephase switch equipment, When ground connection, every survey three-phase binding post is connected to the same grounding point.
In one embodiment in technical solutions of the utility model, the constant-current source is industrial frequency AC constant-current source.
To illustrate in the utility model embodiment, the utility model can be had the benefit that
1) after tested switchgear completes power failure movement, ground line can be retained and carry out subsequent mechanical characteristic test, return Road resistance test, loop voltage test while the earth-continuity for detecting live grounding point;2) technical solutions of the utility model can be with Aforementioned four test assignment is completed during same test;3) reduce the divide-shut brake number of switchgear periodic test, Extend the service life of switchgear;4) reduce pull rod operation, reduce the risk of falling bar, shorten test period.
Technical solutions of the utility model have the working method of innovation, have abandoned testable work side of the tradition side of taking out stitches Method;Test philosophy is improved, the monitoring current that is changed to exempt to take out stitches is changed by monitoring voltage of taking out stitches and is become;It ensure that work safety, no longer It tears hanging earthing conductor open, evades induced electricity and hurt sb.'s feelings, the work risk for the electric shock of falling bar;Working efficiency is promoted, 3/4 is saved and tears extension work open, Working time, testing crew reduced half by shortening 70%, and test apparatus reduces half.
Detailed description of the invention
With reference to embodiments and attached drawing makes specific descriptions to the utility model:
Fig. 1 is the working principle diagram of Tthe utility model system embodiment;
Fig. 2 is the wiring schematic diagram of Fig. 1 system;
Fig. 3 is the local circuit schematic diagram of interface section in host in Fig. 2;
Fig. 4 is the flow diagram that the utility model method is realized using system in Fig. 1;
Wherein, 101, tested switchgear, 102, action drives device, 103, ground connection weldering stake, 104, host, 105, ground connection Line, 201, constant-current source, 202, connecting cable, 203, central processing unit, 204, current sensor, 205, voltage sensor.
Specific embodiment
Further description is made to the technical solution of the utility model with attached drawing combined with specific embodiments below.
As shown in Figure 1 and Figure 2, the present embodiment is a kind of bilateral grounding type Online Transaction Processing for switching devices, packet Include: tested switchgear, the action drives device for controlling tested switchgear divide-shut brake, test host, connection cables, ground line with And current sensor.
In the present embodiment, host be internally provided with central processing unit and the constant-current source being connect respectively with central processing unit, Communication module, display module, voltage sensor and operation panel.When specific implementation, central processing unit, which is selected, has high-precision AD acquires 32 monolithic processors of port and DA output port, and constant-current source uses the AC and DC adjustable current based on IGBT Source, when constant-current source works in exchange status, output frequency is 50Hz power frequency, and central processing unit passes through modulation pulse control constant current Source exports size of current and waveform;Display module is the LCD Panel controlled by central processing unit, and operation module is A/D volume Code key disk;Communication module is WIFI chip or zigbee communication chip, has what is connect with drive control device to connect on grafting panel Mouthful, for sending divide-shut brake signal to drive control device, make drive control device control switch equipment divide-shut brake.
In another embodiment of the utility model, central processing unit is built-in with wireless communication module, by with wireless telecommunications The radio-frequency antenna of module connection communicates wirelessly.
In the present embodiment, being tested switchgear is threephase switch equipment, and one end of ground line connects with tested switchgear Terminal electrical connection, the other end are electrically connected with ground connection weldering stake 103.When it is implemented, ground line is the six roots of sensation, it is divided into two groups, every group three Root, wherein first group three piece-root grafting electric wire one end, which are connected to, to be connect with tested the first side of switchgear three-phase binding post On cable, that is, do not remove the wiring of original the first side of tested switchgear, the other end of first group of three piece-root grafting electric wires is total Stake is welded with the first ground connection is connected to;Second group three piece-root grafting electric wire one end are connected to and tested switchgear second side three-phase On cable of binding post connection, that is, do not remove the wiring of original tested switchgear second side, second group of three piece-root graftings electricity The other end of line is commonly connected to the weldering stake of the second ground connection.
In the present embodiment, current sensor is connect by grafting panel with host, is set to tested switchgear circuit, is used The electric current of tested switchgear is flowed through in detection;In specific implementation, current sensor is the non-contact current sensor of open type, because Using the fixed form of above-mentioned first cable, so having current sensor line when using the clamping ground connection weldering stake of the first clamp Circle side is covered in the circuit side close to tested switchgear.
In the present embodiment, connecting cable one end is detachably connected by grafting panel with host, and the other end is fixed with can be with The clamping joint that ground connection weldering stake connects and fixes.When it is implemented, tested switchgear is threephase switch equipment;The card street corner can be Electric power often uses three-phase clamp, which can be used for current measurement by electric current, it may have voltage measurement contact is to three-phase electricity Pressure measures;Connecting cable includes: the first cable, and first cable one end is fixed with closely to be connect with the first ground connection weldering stake The first clamp, the other end is fixed with the connector with jack grafting mating on grafting panel, this is fixed on first clamp Current sensor described in embodiment, current sensor are three and are fixed on ground connection weldering stake in the first clamp while entangling respectively Circuit where threephase switch contact, the non-contact current sensor are connect with central processing unit;Second cable, described Two cable one end, which are fixed with, closely connect the second clamp with the second ground connection weldering stake, and the other end is fixed with and matches inserting on grafting panel The connector of hole grafting.The connector of first cable and the second cable is connect with the output end of constant-current source respectively.
In another embodiment of the utility model, the three piece-root grafting ground wires and ground connection for being set to threephase switch equipment the same side are welded Bifurcation before stake tie point, three current sensors are separately provided, and are wired to grafting panel respectively, and with center Processor connection.
In another embodiment of the utility model, being tested switchgear is single-phase switch equipment, is arranged on the first cable Current sensor is one.
In the present embodiment, be additionally provided with voltage sensor in host, the clamp of the first cable and the second cable respectively with institute The measurement end connection of voltage sensor is stated, voltage sensor is for measuring constant-current source both end voltage;Voltage sensor acquisition interval Less than 0.1ms, it is poor with the operating frequency phase of constant current source output current to be calculated by central processing unit.
In the present embodiment, there is power down nonvolatile storage in central processing unit, wherein part memory space is for storing Application program, part control is used to store the storage unit of measurement record, when the measurement record of storage can be run by application program It is sent to the PC connecting with host communication or tablet device by communication module, by the application program run on PC or tablet device It handles and shows.
As shown in figure 3, host described in the utility model embodiment is equipped with A/D keyboard as operation module, it is equipped with liquid crystal As display module, operation module and display module are connect with central processing unit (CPU) respectively;CTC is on main machine transplanting of rice junction plate Current sensor interface, KC, KN be main machine transplanting of rice junction plate on drive control device interface, for the input with drive control device End connection, wherein KC connects drive control device input signal end, and KN connects drive control device common end.
The present embodiment further includes a kind of bilateral grounding type on-line testing method for switching devices, which uses Above system is completed, and the tested switch of the test of mechanical characteristic test and loop resistance and connection of achievable tested switchgear is set Earth-continuity at standby ground connection weldering stake, while assessing earth mat index.The test method, which specifically includes that, will be connected with action drives The tested switchgear two sides binding post of device is linked with the weldering stake of more than two ground connection respectively, makes tested switchgear two sides difference Ground connection;It is separately connected constant current source output terminal in tested switchgear two sides, keeps tested switchgear in parallel with constant-current source, centre Manage device control constant-current source export specified size, direction, waveform and frequency electric current, and switched using above-mentioned current sensor measurement First electric current in equipment circuit;The second electricity of switchgear two sides earth-continuity is calculated by the electric current of constant-current source and the first electric current Stream;The end time that making process in tested switchgear mechanical characteristic test is judged by the appearance of the first electric current, pass through The disappearance of first electric current judges the end time of separating brake process in tested switchgear mechanical characteristic test;Pass through the first galvanometer Calculate the loop resistance of equipment under test;The earth-continuity for the grounding point connecting with tested switchgear is calculated by the second electric current.
Specifically to use the present embodiment above system to being that tested switchgear carries out experimental test and is with three-phase breaker Example, as shown in figure 4, steps are as follows:
S01: before experimental test, the power down of three-phase breaker is completed according to conventional steps, by the binding post of its two sides Stake is welded with two ground connection by ground line respectively to connect.Specifically, retaining the original primary connection of three-phase breaker, by first group three One end of piece-root grafting ground wire is connected with first three primary connections for flanking terminal for connecting three-phase breaker respectively, and first group three The other end of ground line is commonly connected to the weldering stake of the first ground connection;By one end of second group of three piece-root grafting ground wire respectively with connect three-phase and break Three primary connections of second side binding post of road device connect, and the other end of second group of three piece-root grafting ground wire is commonly connected to second and connects Weld stake in ground.Three groups of contacts between first side of three-phase breaker and second side form parallel relationship, the first side in its combined floodgate The Z in equivalent resistance, that is, Fig. 1 between second side1
S02: the clamp of the first cable and the second cable is connect with ground connection weldering stake respectively.Specifically, the first cable The one end and the first ground connection weldering stake for being fixed with the first clamp are reliably clamped, and the other end is inserted into host grafting panel and central processing unit Connection;Second cable is fixed with one end of the second clamp and the second ground connection weldering stake is reliably clamped, and the other end is inserted into host plug surface Plate is connect with central processing unit;Constant-current source 201 in Fig. 1 is formed after the completion of connection, any road contact is equivalent in three-phase breaker Resistance Z1, voltage sensor and earth mat equivalent resistance Z2Parallel circuit, the current sensor on the first clamp are covered in Z1Place is returned Lu Zhong operates additionally by the pull rod of insulating bar, drive control device is fixed on three-phase breaker, drive control device can pass through machine Tool structure drives three-phase breaker divide-shut brake.
S03: enabling tested switchgear separating brake, enables host control constant-current source stablize the first electric current of output, and obtain tested open Equipment two sides first voltage is closed, the earth-continuity of tested switchgear two sides is obtained using the first electric current and first voltage.Specifically , central processing unit issues separating brake instruction to drive control device, and drive control device is complete by mechanical structure control three-phase breaker After separating brake, central processing unit controls constant-current source and exports power frequency 50Hz sinusoidal current, and current effective value 300A is passed by voltage Sensor measures current first voltage, measures earth mat impedance, the i.e. exchange of earth mat equivalent resistance by the first electric current and first voltage Impedance Z2, Z2It is that the weldering stake of the first ground connection is connected indirectly with earth mat, the second ground connection welds stake and earth mat is connected indirectly and earth mat hinders Anti- sum, Z2The earth-continuity of the weldering stake of the first ground connection and the second ground connection weldering stake and the size of earth mat stray capacitance are embodied, such as Fruit Z2Qualification, then related ground conducting and earth mat evaluation index are up to standard.
S04: it enables the tested switch of drive control device control close a floodgate, it is judged according to the time that tested switchgear electric current occurs Mechanical property closing time index, while the second electric current and second that record passes through tested switchgear circuit after the completion of combined floodgate Voltage obtains the loop resistance of tested switch using the second electric current and second voltage.Specifically, central processing unit first controls constant current Source exports 300A direct current output, then issues order of closing a floodgate to drive control device, starts simultaneously at timing, when passing through current sensor When detecting the second electric current by three-phase contactor, stop timing, which is that three groups of contacts of three-phase breaker are closed The lock time obtains earth mat by the stationary value of constant current source output current size and the second electric current when the second electric current stablizes constant Electric current calculates breaker impedance loop, algorithm are as follows: impedance loop=earth mat by earth mat electric current, earth mat impedance and the second electric current Impedance (the second electric current/earth mat electric current).In another embodiment, host obtains the second electric current by current sensor and stablizes not Change when value, while the second voltage of three-phase breaker both ends at this time has been obtained by voltage sensor, has passed through the second electric current Impedance loop, algorithm are as follows: impedance loop=second voltage/the second electric current are obtained with second voltage;Switch is tested in the present embodiment to set Standby is three-phase equipment, and the current sensor is respectively arranged in the circuit of tested switchgear three-phase contact, therefore, in this step Second electric current of the middle available three-phase of reality to obtain the loop resistance of three-phase contact, while also obtaining the second electricity of three-phase The respective stable time of stream.
S05: the tested switch separating brake of drive control device control is enabled, it is judged according to the time of tested switchgear current vanishes Mechanical property opening time index.Specifically, central processing unit first controls constant-current source output 300A direct current output, then to driving Controller issues separating brake order, starts simultaneously at timing, detects when by current sensor through the second electric of three-phase contactor When stream is zero, stop timing, which is three groups of contact opening times of three-phase breaker.
Working principle
In above-described embodiment, when there are ground line in breaker two sides, the independent constant-current source of three-phase is added at both ends, Form circuit closed circuit.The division of breaker acts, and can cause the variation of electric current in circuit.Current sensor is introduced, it can also It to be clamp on amperemeter, is directly stuck on unilateral ground line, is judged by the variation of current signal in monitoring clamp on amperemeter disconnected Road device equipment division state, actuation time complete breaker operating characteristic experiment work.
In above-described embodiment, pass through the ground line of breaker two sides, the constant-current source of test apparatus output, the closure electricity of formation Road is flowed back to, voltage signal is directly taken, resistance value can be obtained.Clamp on amperemeter can measure the division state of breaker, movement again Time, therefore breaker loop resistor and acting characteristic pilot project can be tested simultaneously.
In above-described embodiment, host store to all test datas and connect by communication module with database, PMS system and equipment factory information are docked, automatically extracts breaker producer testing standard, historical test data and with factory's homotype The relevant informations such as number equipment test data, by significant difference scheduling algorithm, by test data carry out laterally, it is longitudinal compare, can To provide breaker apparatus state evaluation score, real-time judge equipment state.
Practical application compares
Technical solutions of the utility model started to be widely popularized in 2018, and the innovation achievement is answered by more ground Utilities Electric Co. It is effective in terms of safety, economy, management, social benefit for (including combined electrical apparatus) in real work.
Safety benefit: saved about 15 times act bars tear open, hanging wire operation, evaded the induced electricity electric shock risk and electric shock of falling bar Problem ensure that the person and equipment safety.
Economic benefit: test period was foreshortened to 1 hour by 3 hours, and testing crew foreshortens to 2 people, labour production by 4 people Rate is promoted to (1 hour * 2 people)/1=2 hour/part by (3 hours * 4 people)/1=12 hour/part.
* 200 times=4.8 ten thousand yuan of recruitment cost=(3-1) hour * (4-2) 60 yuan/people of people * hour is saved, sale of electricity is increased Measuring income is about 19.5 ten thousand yuan.The accumulative first half of the year in 2018 is 24.3 ten thousand yuan of enterprise's additional income.
Management and social benefit: tripartite's connection of regulation, O&M, maintenance is avoided, breaker experiment work has been saved Power off time promotes the management efficiency of enterprises, guarantees the reliable supply of society's electricity consumption, establishes company's favorable image.
The innovation achievement can carry out circuit-breaker testing work without removing ground line, can also equally apply in combination electricity Device field.The achievement is worth promoting in terms of safety, management, social performance.In economic aspect, on 6 ground of Southern Hebei Network After the application of company of city, recruitment cost will be saved about: 4.8 ten thousand yuan * 6 * 2=57.6 ten thousand yuan, increasing electricity sales amount income about: 19.5 ten thousand First * 6 * 2=2,340,000 yuan.
Technical solution provided by the utility model is easy to operate, and reproducibility is strong, can be mass, and answers conducive to being widely popularized With.
Referring to Guo Wang company electrical test equipment configurations principle, power supply company of districts and cities need at least be equipped with 2, the device, electric power Internal system market at least needs to be equipped with instrument number of units to be about 600.According to investigation, National Power System maintenance model is similar, should Device is also applied for all units popularization and application that railway, power generation, steel mill etc. possess breaker, and demand is about network system 30%, about 180, through price accounting, calculated with every 20,000 yuan of profit (cosxts involved in determining price by core technology research and development, hardware device, The composition such as technical support, after-sale service, product promotion, about 40,000 yuan, ten thousand yuan of selling price 6-8), profit margin is about 780 * 2 Ten thousand yuan=15,600,000, promotion prospect is wide.

Claims (4)

1. a kind of bilateral grounding type Online Transaction Processing for switching devices, including tested switchgear (101) and control quilt Survey the action drives device (102) of switchgear divide-shut brake, which is characterized in that further include:
Host (104), the constant current that the host (104) is internally provided with central processing unit and connect respectively with central processing unit Source (201), communication module, display module, operation panel and grafting panel, the host (104) and action drives device (102) It connects and control action driver (102) drives tested switchgear (101) divide-shut brake;
Connecting cable (202), described connecting cable one end are detachably connected by grafting panel with host (104), and the other end is solid Surely there is the clamping joint connected and fixed with ground connection weldering stake (103);
It is grounded (105), described ground line one end is electrically connected with the binding post of tested switchgear, the other end and ground connection weldering stake (103) it is electrically connected;
Current sensor (204), the current sensor are connect by grafting panel with host, are set to tested switchgear and are returned Road, for detecting the electric current for flowing through tested switchgear;
Wherein, the ground line for connecting tested switchgear the same side binding post is electrically connected with same ground connection weldering stake (103), described to connect Ground weldering stake (103) is electrically connected by the connecting cable (202) with constant-current source (201) output end in host respectively.
2. bilateral grounding type Online Transaction Processing for switching devices according to claim 1, it is characterised in that: described Constant-current source is AC or DC constant-current source.
3. bilateral grounding type Online Transaction Processing for switching devices according to claim 2, it is characterised in that: host It is inside additionally provided with voltage sensor, the voltage sense input welds stake by the connecting cable and the ground connection respectively and connects It connects.
4. bilateral grounding type Online Transaction Processing for switching devices according to claim 3, it is characterised in that: center The storage unit of storage measurement record is equipped in processor.
CN201821301916.0U 2018-08-14 2018-08-14 Bilateral grounding type Online Transaction Processing for switching devices Active CN208520972U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821301916.0U CN208520972U (en) 2018-08-14 2018-08-14 Bilateral grounding type Online Transaction Processing for switching devices

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821301916.0U CN208520972U (en) 2018-08-14 2018-08-14 Bilateral grounding type Online Transaction Processing for switching devices

Publications (1)

Publication Number Publication Date
CN208520972U true CN208520972U (en) 2019-02-19

Family

ID=65334154

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821301916.0U Active CN208520972U (en) 2018-08-14 2018-08-14 Bilateral grounding type Online Transaction Processing for switching devices

Country Status (1)

Country Link
CN (1) CN208520972U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109143051A (en) * 2018-08-14 2019-01-04 国家电网有限公司 Bilateral grounding type Online Transaction Processing for switching devices and test method
CN112630634A (en) * 2020-11-13 2021-04-09 深圳供电局有限公司 Switching operation characteristic measuring device and method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109143051A (en) * 2018-08-14 2019-01-04 国家电网有限公司 Bilateral grounding type Online Transaction Processing for switching devices and test method
CN112630634A (en) * 2020-11-13 2021-04-09 深圳供电局有限公司 Switching operation characteristic measuring device and method
CN112630634B (en) * 2020-11-13 2023-03-03 深圳供电局有限公司 Switching operation characteristic measuring device and method

Similar Documents

Publication Publication Date Title
CN102435886B (en) Test bed and test system for inverter of rail transit vehicle
CN208520972U (en) Bilateral grounding type Online Transaction Processing for switching devices
CN102508057A (en) Test bed and system for testing charger for rail transit vehicle
CN107024641A (en) A kind of platform area line loss per unit exception monitoring system
CN101581752A (en) Power transmission line parameter online measurement method based on fault wave recording
CN107728006A (en) Traction substation traction current is monitored on-line with ground state and fault diagnosis system
CN107436420A (en) A kind of electric energy metrical remote verification monitoring system and its method of work
CN110208652A (en) A kind of Small Electric Current Earthing And Routing Device and selection method
CN206684228U (en) A kind of high-voltage circuit-breaker switching on-off coil resistance universal test device
CN105259488A (en) 500kV high-voltage parallel electric reactor turn-to-turn insulation performance testing platform
CN109143051A (en) Bilateral grounding type Online Transaction Processing for switching devices and test method
CN105182156B (en) Based on waveform visualization synchronous loop device for detecting polarity and detection method
CN109116119A (en) A kind of loop resistance test macro under double ground states
CN112505610A (en) Voltage transformer insulation and metering performance integrated test device and method for metering of 35kV and below
CN103176048B (en) A kind of method of quick measuring transformer delta connection mode winding D.C. resistance
CN215219111U (en) Online real-time monitoring and warning device of voltage transformer multipoint earthing
Huang et al. A short circuit current study for the power supply system of Taiwan railway
CN209070019U (en) A kind of loop resistance test macro under double ground states
CN205015427U (en) Neutral point multipoint earthing detection device based on high accuracy testing electric current
CN112816818A (en) Portable direct current test box
CN209496133U (en) Detection device of electric energy meter, system and power grid maintenance equipment
CN113866526A (en) One-time simulation live test system and method for intelligent substation
CN107219418B (en) A kind of power distribution network monitoring running state terminal
CN205642673U (en) A temperature check gauge for main transformer
CN114252674B (en) Secondary wiring detection device and method