CN208520945U CN201820328221.5U CN201820328221U CN208520945U CN 208520945 U CN208520945 U CN 208520945U CN 201820328221 U CN201820328221 U CN 201820328221U CN 208520945 U CN208520945 U CN 208520945U
Authority
CN
China
Prior art keywords
line
background server
line fault
field device
fault
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820328221.5U
Other languages
Chinese (zh)
Inventor
王震
赵健
吴征
陈豹
崔福星
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hangzhou Colin Electric Ltd By Share Ltd
Original Assignee
Hangzhou Colin Electric Ltd By Share Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hangzhou Colin Electric Ltd By Share Ltd filed Critical Hangzhou Colin Electric Ltd By Share Ltd
Priority to CN201820328221.5U priority Critical patent/CN208520945U/en
Application granted granted Critical
Publication of CN208520945U publication Critical patent/CN208520945U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Locating Faults (AREA)
  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)

Abstract

The utility model discloses a kind of mixed line fault deciding field devices, including main control module, background server and multiple acquisition modules, and when route breaks down, each acquisition module three-phase synchronous acquires high speed recording, and is uploaded to the main control module;The recording waveform received is uploaded to the background server by the main control module;The background server carries out fault section positioning according to the recording waveform received, judges that line fault occurs in power transmission cable side or overhead line trackside.The utility model quickly positions line fault section, analyzed and is prevented, judge that failure occurs in power transmission cable side or overhead line trackside, when cable overhead line mixed power transmission line breaks down, fault location can accurately be carried out, on the one hand it can reduce line walking burden, on the other hand it can accelerate route again to restore electricity, reduce because of economic loss caused by having a power failure.

Description

A kind of mixed line fault deciding field device
Technical field
The utility model relates to Relay Protection Technology in Power System fields, and in particular to a kind of mixed line fault section is fixed Position device.
Background technique
With the rapid development of electric system, transmission line of electricity develops on the basis of original cable, overhead transmission line Cable overhead line mixed power transmission line, and application is more and more extensive.Extra-high-tension cable overhead line mixed power transmission line can be across greatly Water channel, straits, can be directly to big city and industrial area center feed.Meanwhile being limited by city space and planning, cable is aerial Line mixed power transmission line is in city using more and more extensive.It is not straight that cable overhead line mixed power transmission line is also applied to neutral point In the low current transmission system of ground connection, such as railway signal power supply power supply system.
But due to the flaw in the manufacture of cable overhead line mixed power transmission line or through use after a period of time, cable it is exhausted Edge level can decline, to can cause cable that ground fault occurs, equally, similar failure can also occur for overhead line.
Utility model content
Technical problem to be solved in the utility model is cable overhead line mixed power transmission line due to the flaw in manufacture Or through use after a period of time, cable insulation level is caused to decline, so as to cause cable, overhead line ground fault occurs.
In order to solve the above-mentioned technical problem, technical solution used by the utility model is to provide a kind of mixed line fault Deciding field device, including main control module, background server and multiple acquisition modules, it is each described when route breaks down Acquisition module three-phase synchronous acquires high speed recording, and is uploaded to the main control module;The recording that the main control module will receive Waveform is uploaded to the background server;The background server carries out fault section positioning according to the recording waveform received, Judge that line fault occurs in power transmission cable side or overhead line trackside.
Preferably, the traveling wave generated when the background server occurs according to failure reach the time of the acquisition module with And the spread speed of traveling wave in the line carries out abort situation positioning.
Preferably, each acquisition module is mounted on distribution line and insulating sheath ground line, each acquisition module Adaptable line load current size, and three-phase synchronous acquisition cable run load current and transmission of electricity electricity when line fault occurs Earth current, Fault feature of single phase earthing data and the profile information of cable insulating sheath, are combined by wide frequency domain current sensor FPGA high speed acquisition captures fault traveling wave and partial discharge in time.
Preferably, the acquisition information of the acquisition module passes through 101 agreements with the remote signalling information upload background service Device, and do SOE record.
Preferably, the acquisition module and background server support internal communication protocol, and the background server can be long-range Check and modify the relevant parameter and remote upgrade program of the acquisition module.
Preferably, the acquisition module using 5A low current automatic electricity getting and is aided with super capacitor as master control power supply, simultaneously Integrated energy collection system is extracted nanoscale energy from daylight, thermoelectricity, electromagnetism and the various sources of vibrational energy and is carried out to it Management is using as backup power source.
Preferably, the main control module is communicated with distribution main website, supports solar panels or the power supply of TA way to take power, and It is aided with rechargeable battery as backup power supply.
Preferably, the background server supports wireless communication, by mobile client or debugging software to the backstage Server carries out parameter reading and writing, telemetry reading and remote control.
Preferably, the background server sends alarm message to specified mobile client automatically.
Preferably, user sends ad hoc inquiry short message to the background server by mobile client, monitors model in real time Enclose whether interior route breaks down.
The utility model proposes a kind of mixed line fault deciding field devices, quickly determine line fault section Position, analysis and prevention judge that failure occurs in power transmission cable side or overhead line trackside, when cable overhead line mixed power transmission line When breaking down, fault location can be accurately carried out, line walking burden is on the one hand can reduce, on the other hand can accelerate route again It restores electricity, reduces because of economic loss caused by having a power failure.
Detailed description of the invention
Fig. 1 is a kind of block diagram of mixed line fault deciding field device in the utility model;
Fig. 2 is a kind of topological diagram of mixed line fault deciding field device in the utility model.
Specific embodiment
In order to solve existing cable overhead line mixed power transmission line due to the flaw in manufacture or through after a period of time Use, cause cable insulation level decline, so as to cause cable, overhead line occur ground fault the problem of.The utility model A kind of mixed line fault deciding field device is proposed, is mounted at the high-pressure tower pole that power transmission cable and overhead transmission line combine, It is supervised in real time for the ground state to cable overhead line mixed power transmission line state and high voltage power cable insulating sheath It surveys, and uploads monitoring information and fault-detection data to remote server, line fault section is quickly positioned, is analyzed With prevention, judge that failure occurs in power transmission cable side or overhead line trackside.When event occurs for cable overhead line mixed power transmission line When barrier, fault location can be accurately carried out, on the one hand can reduce line walking burden, on the other hand can accelerate route again and restore to supply Electricity is reduced because of economic loss caused by having a power failure.
The utility model is described in detail with specific embodiment with reference to the accompanying drawings of the specification.
The utility model embodiment provides a kind of mixed line fault deciding field device, as depicted in figs. 1 and 2, tool Body includes main control module 20, background server 30 and multiple acquisition modules 10, when route breaks down, each acquisition module 10 Three-phase synchronous acquires high speed recording, and is uploaded to main control module 20;After the recording waveform received is uploaded to by main control module 20 Platform server 30;Background server 30 carries out fault section positioning according to the recording waveform received, is mainly calculated using experts database The methods of method, current curve, traveling wave location algorithm and partial discharge location algorithm judge that line fault occurs in power transmission cable Side or overhead line trackside.
Meanwhile the traveling wave that generates when being occurred according to failure of background server 30 reach the acquisition module 10 time and The spread speed of traveling wave in the line carries out abort situation positioning.
Each acquisition module 10 is mounted on distribution line and insulating sheath ground line, the adaptive line of each acquisition module 10 Road load current size, and three-phase synchronous acquisition cable run load current and power transmission cable insulation shield when line fault occurs Earth current, Fault feature of single phase earthing data and the profile information of set pass through wide frequency domain current sensor combination FPGA high speed Acquisition captures fault traveling wave and partial discharge in time, and fault traveling wave is uploaded to main control module 20 using wirelessly or non-wirelessly communication mode. Wherein, the short circuit of acquisition module 10, ground connection, high temperature and the cell voltage acquisition information such as low are passed through 101 agreements and are believed with remote signalling Breath uploads background server 30, and does SOE record, supports failure wave-recording.Other than 101 agreements, acquisition module 10 and backstage are taken Business device 30 also supports internal communication protocol, background server 30 remotely can check and modify acquisition module 10 relevant parameter and Remote upgrade program, is convenient for remote maintenance.
Above-mentioned acquisition module 10 is using low current (5A) automatic electricity getting and is aided with super capacitor as master control power supply, integrates simultaneously Energy collecting system, can be extracted from the various sources such as daylight, thermoelectricity, electromagnetism and vibrational energy nanoscale energy and to its into Row management is using as backup power source.
Main control module 20 to the acquisition information labeling time parameter that the acquisition module 10 received uploads, and passes through GPRS Communication is uploaded to background server 30.
Main control module 20 is communicated with distribution main website, supports solar panels or the power supply of TA way to take power, and be aided with and can fill Battery is as backup power supply.
Background server 30 supports wireless communication, is joined by mobile client or debugging software to background server 30 Number read-write, telemetry is read and remote control.
The also included hardware clock module of the device, and being powered by independent battery, can also by telecommunication to terminal into When row school.
When short circuit, ground connection, the failures such as high temperature occur for route, background server can send alarm message to specifying automatically Mobile client.Also there is the function by message search route operating status, user can be by sending specific short message enquiry To background server 30, monitor whether route in range occurs the failures such as short circuit, ground connection, high temperature and battery undervoltage in real time.
Mobile client is carried out telecommunication using GPRS communication mode with background server 30, and communication pattern is TCP association The server/customer end mode of view, mobile client and background server 30 are mainly using DL/T634.5101-2002 communication rule About, it supports equilibrium and non-equilibrium transmission mode, supports a variety of transmission reason length, public address length and link address long Degree.
Mixed line fault deciding field device cable-type main power source takes electricity using open C T, and backup power supply uses super electricity Hold (optional ferric phosphate lithium cell) and nanoscale energy collecting system, and overhead type uses solar energy electricity getting device, backup power supply Using 1 section 12V7AH lead-acid accumulator.When main power source has electricity, power management module automatically controls backup power supply and does not supply to terminal Electricity automatically carries out it charging and fills function with tiny stream if backup power supply voltage is low.If mixed line fault deciding field fills It sets and has worked normally, when main power source power loss, it is fixed to mixed line fault section that power management module automatically controls backup power supply Position device power supply.
Mixed line fault deciding field device provided by the utility model, rely on innovation low current power taking technology, LORA is wireless, 4G communication, collection of energy, Rogowski coil sampling technique, wide frequency domain current transformer and FPGA high-speed sampling etc., When cable overhead line mixed power transmission line breaks down, start high speed recording, it is negative that each acquisition module 10 monitors route three-phase The operation informations such as charged current, fault current, partial discharge and traveling wave and main power supply, backup power supply etc., by wirelessly or non-wirelessly etc. For mode by recording waveform transfer to main control module 20, main control module 20 is communicated by GPRS uploads recording waveform to background server 30, background server 30 carries out fault section positioning to cable overhead line mixed power transmission line according to the recording waveform received, To realize all kinds of failures precisely detect, subregion and positioning.
Wherein, synchronous acquisition is threephase cable line current and cable cover(ing) earth current, according to the same moment electric current Variation, if the line current of certain two-phase becomes larger simultaneously, and earth current does not change, then confirms certain line to line fault and short dot is Occur in overhead transmission line side.The utility model directly measures the traveling wave generated when failure occurs, reaches acquisition mould according to traveling wave The time of block 10, the spread speed of traveling wave in the line, to calculate abort situation.
Meanwhile mixed line fault deciding field device is under cable overhead line mixed power transmission line normal operation, Monitor load variations, send line current to background work personnel, provide line load reference information for staff, when When ground fault, short trouble occur for cable overhead line mixed power transmission line, abort situation is shown, in time with guide maintenance personnel Rapidly removing faults restore electricity.
The utility model has the advantage that
1, the low current (5A) innovated accesses power technology
Acquisition module built-in large capacity, long-life lithium Asia battery and super capacitor, pass through and apply new material and innovation Power technology, can continuously take electricity within the scope of line current 0-600A, route 5A electric current can meet confession operation and deposit electricity Minimum requirements, without battery, thus effectively extend life of product.
2, it precisely identifies route operating condition, supports current recording
By the precision current measurement of innovation and current detection technology over the ground, can line current 0-1000A range, it is electric The measurement accuracy for flowing acquisition ± 1% within the scope of 0-100A, can accurately identify route operating condition.
3, real-time monitoring line status
Using short-distance wireless communication and GPRS mixed networking technology, various complicated line topologicals are supported;And actively timing Report line status.With communications two-way confirmation and functions of retransmission, it is ensured that the reliability of data transmission, to control line at any time Road real-time running state.
4, high frequency partial discharge information collection
By wide frequency domain CT combination FPGA high speed acquisition, the partial discharge information generated when acquiring failure.
5, traveling wave positions
By wide frequency domain CT combination bandpass filtering, while high speed and real time sampling, the traveling wave generated when capturing failure in time are believed Breath, passes through background server experts database algorithm combination current information, fault point.
6, the high-precision clock synchronization of GPS, time service
Main control module GPS high-precision (1us) time service, obtains accurate absolute time mark.Main control module with every 30 points of acquisition module Clock wireless synchronization once can guarantee three-phase synchronous precision (± 100us), realize three-phase current, over the ground electric field waveform acquisition.
7, non-maintaining design, can remote radio upgrade
Autonomous operation after hanging wire, complete non-maintaining design can update event by long distance wireless maintenance operation parameter when necessary Hinder criterion or upgrading software program, promotes working efficiency.
The utility model is not limited to above-mentioned preferred forms, anyone knot made under the enlightenment of the utility model Structure variation, it is all that there is with the utility model same or similar technical solution, each fall within the protection scope of the utility model it It is interior.

Claims (9)

1. a kind of mixed line fault deciding field device characterized by comprising
Main control module, background server and multiple acquisition modules, when route breaks down, each acquisition module three is identical Step acquisition high speed recording, and it is uploaded to the main control module;The recording waveform received is uploaded to described by the main control module Background server;The background server carries out fault section positioning according to the recording waveform received, judges that line fault is sent out Life is in power transmission cable side or overhead line trackside;
Each acquisition module is mounted on distribution line and insulating sheath ground line, and each acquisition module adaptable line is negative Charged current size, and three-phase synchronous acquisition cable run load current and power transmission cable insulating sheath when line fault occurs Earth current, Fault feature of single phase earthing data and profile information pass through wide frequency domain current sensor combination FPGA high speed acquisition Capture fault traveling wave and partial discharge in time.
2. mixed line fault deciding field device as described in claim 1, which is characterized in that the background server according to The traveling wave that failure generates when occurring reaches the spread speed of the time and traveling wave of the acquisition module in the line and carries out failure Position positioning.
3. mixed line fault deciding field device as described in claim 1, which is characterized in that the acquisition of the acquisition module Information passes through 101 agreements and uploads the background server with remote signalling information, and does SOE record.
4. mixed line fault deciding field device as claimed in claim 3, which is characterized in that the acquisition module and backstage Server support internal communication protocol, the background server remotely can check and modify the relevant parameter of the acquisition module with And remote upgrade program.
5. mixed line fault deciding field device as described in claim 1, which is characterized in that the acquisition module uses 5A Low current automatic electricity getting is simultaneously aided with super capacitor as master control power supply, while integrated energy collection system, from daylight, thermoelectricity, electromagnetism With extract nanoscale energy in the various sources of vibrational energy and it be managed using as backup power source.
6. mixed line fault deciding field device as described in claim 1, which is characterized in that the main control module and distribution Main website is communicated, and supports solar panels or the power supply of TA way to take power, and be aided with rechargeable battery as backup power supply.
7. mixed line fault deciding field device as described in claim 1, which is characterized in that the background server is supported Wireless communication, parameter reading and writing is carried out to the background server by mobile client or debugging software, telemetry read with And remote control.
8. mixed line fault deciding field device as described in claim 1, which is characterized in that the background server is automatic Alarm message is sent to specified mobile client.
9. mixed line fault deciding field device as described in claim 1, which is characterized in that user passes through mobile client Ad hoc inquiry short message is sent to the background server, monitors whether route in range breaks down in real time.
CN201820328221.5U 2018-03-09 2018-03-09 A kind of mixed line fault deciding field device Active CN208520945U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820328221.5U CN208520945U (en) 2018-03-09 2018-03-09 A kind of mixed line fault deciding field device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820328221.5U CN208520945U (en) 2018-03-09 2018-03-09 A kind of mixed line fault deciding field device

Publications (1)

Publication Number Publication Date
CN208520945U true CN208520945U (en) 2019-02-19

Family

ID=65340946

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820328221.5U Active CN208520945U (en) 2018-03-09 2018-03-09 A kind of mixed line fault deciding field device

Country Status (1)

Country Link
CN (1) CN208520945U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110441649A (en) * 2019-06-27 2019-11-12 国网福建省电力有限公司福州供电公司 One kind is aerial-cable hybrid line fault fast positioning dress and localization method
CN112147457A (en) * 2019-06-26 2020-12-29 国网江苏省电力有限公司南京供电分公司 Underground comprehensive pipe gallery cable fault detection and positioning system and method based on Hilbert-Huang transform
CN112147457B (en) * 2019-06-26 2024-06-11 国网江苏省电力有限公司南京供电分公司 Underground comprehensive pipe rack cable fault detection and positioning system and method based on Hilbert-Huang transformation

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112147457A (en) * 2019-06-26 2020-12-29 国网江苏省电力有限公司南京供电分公司 Underground comprehensive pipe gallery cable fault detection and positioning system and method based on Hilbert-Huang transform
CN112147457B (en) * 2019-06-26 2024-06-11 国网江苏省电力有限公司南京供电分公司 Underground comprehensive pipe rack cable fault detection and positioning system and method based on Hilbert-Huang transformation
CN110441649A (en) * 2019-06-27 2019-11-12 国网福建省电力有限公司福州供电公司 One kind is aerial-cable hybrid line fault fast positioning dress and localization method

Similar Documents

Publication Publication Date Title
CN108051708A (en) A kind of transient state recording type fault detector
CN108254655A (en) A kind of mixed line fault deciding field device
CN102590700B (en) Based on pole line fast fault locating method and the device of time synchronized
CN106501656A (en) A kind of on-line acquisition system of distribution line failure waveform
CN203350392U (en) Fault locating system for high tension transmission line
CN102043115B (en) Network on-line live line measurement method for line parameter of power system
CN101446618B (en) Real-time monitoring system of faults of overhead lines of distribution network
CN111650478B (en) Power distribution network fault diagnosis and positioning method and gateway
CN103852744A (en) Distributed online monitoring system and method for electric energy metering device
CN106556754A (en) A kind of online acquisition method of distribution line failure waveform
CN106249073A (en) Distribution network failure based on LoRa communication technology instruction system
CN103592566A (en) Wireless communication based power distribution network distributed online monitoring and fault positioning system
CN207882374U (en) A kind of transient state recording type fault detector
CN110244190A (en) A kind of feeder line fault on-line monitoring and positioning system
CN102928741A (en) Satellite time synchronization based electric power line fault location system and method
CN102435871A (en) On-line monitoring system for data collection of electric arresters based on GPS (Global Positioning System) synchronization
CN208421129U (en) Line fault on-line monitoring system
CN104865489A (en) System and method for overhead line fault location and monitoring
CN106501671A (en) A kind of monitoring method of electric distribution network overhead wire failure
CN208432682U (en) A kind of fore device and system of transmission line malfunction diagnosis
CN201314942Y (en) Monitoring system for detecting the fault of distribution network trolly wires
CN102193050A (en) Positioning system for fault of direct-current transmission line
CN103995214A (en) Overhead line intelligent fault positioning processing system and method thereof
CN103529360B (en) Power failure indication device supporting geological information
CN106501657A (en) A kind of monitoring system of electric distribution network overhead wire failure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP02 Change in the address of a patent holder

Address after: 310000 6 storeys, 7 blocks, No. 1418-41, Moganshan Road, Hangzhou City, Zhejiang Province

Patentee after: Hangzhou Colin electric Limited by Share Ltd

Address before: 310000 No. 1418-15, Moganshan Road, Hangzhou City, Zhejiang Province

Patentee before: Hangzhou Colin electric Limited by Share Ltd