CN208517969U - The full assembling structure of outer wall of basement - Google Patents

The full assembling structure of outer wall of basement Download PDF

Info

Publication number
CN208517969U
CN208517969U CN201820818465.1U CN201820818465U CN208517969U CN 208517969 U CN208517969 U CN 208517969U CN 201820818465 U CN201820818465 U CN 201820818465U CN 208517969 U CN208517969 U CN 208517969U
Authority
CN
China
Prior art keywords
plate
support plate
wall
prefabricated
basement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820818465.1U
Other languages
Chinese (zh)
Inventor
王立明
陈培良
张赛
李忠
赵文虎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANGHAI CITI-RAISE CONSTRUCTION (GROUP) Co Ltd
Shanghai Urban Construction And Construction Industry Group New Building Material Jiaxing Co Ltd
Original Assignee
SHANGHAI CITI-RAISE CONSTRUCTION (GROUP) Co Ltd
Shanghai Urban Construction And Construction Industry Group New Building Material Jiaxing Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANGHAI CITI-RAISE CONSTRUCTION (GROUP) Co Ltd, Shanghai Urban Construction And Construction Industry Group New Building Material Jiaxing Co Ltd filed Critical SHANGHAI CITI-RAISE CONSTRUCTION (GROUP) Co Ltd
Priority to CN201820818465.1U priority Critical patent/CN208517969U/en
Application granted granted Critical
Publication of CN208517969U publication Critical patent/CN208517969U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model relates to a kind of full assembling structures of outer wall of basement, are made of prefabricated panel, prefabricated post, precast beam;Prefabricated panel is located at the outside of prefabricated post, is made of span centre plate, support plate, and is linked to be entirety with prefabricated post, precast beam, and span centre plate upper end is connected with basement roof, and lower end is connected with basement bottom board, and left side plate end is connect with support plate respectively;Support plate is one block of plate, or is made of two boards, two boards or so distribution, or two boards are distributed up and down, the left side plate end of support plate is connect with the span centre plate respectively, and support plate and the wing plate at the left side plate end of span centre plate fasten respectively, and grouting is tamped in the cavity between wing plate.It is constructed with the full assembling structure of the outer wall of basement, external wall waterproof performance is more preferable, and speed of application is faster, more environmentally protective, has a extensive future.

Description

The full assembling structure of outer wall of basement
Technical field
The utility model relates to the full assembling structure of outer wall of basement in civil engineering in concrete structure technique field, tools Body refers to a kind of structure technology that outer wall of basement is completed using concrete prefabricated element assembled in situ.
Background technique
Currently, assembled architecture replaces cast-in-place concrete structure to have become as national development strategy, precast concrete For the inexorable trend of building trade development.In high water level area, concrete basement structure exterior wall, due to fearing infiltration, at present It is all cast-in-place concrete structure, not only live scaffold is close and numerous for cast-in-place structural, but also construction site is tacky, and assembles Formula concrete structure site operation is clean and tidy orderly to make people fresh and new, more importantly fabricated construction speed of application is fast, It is also advantageous for reducing deep pit monitor risk and reducing foundation pit enclosure cost.Therefore, outside Study of The Underground room wall full assembly Structure technology is more conducive to assembled architecture in the popularization of the underground space.
Utility model content
The purpose of the utility model is to overcome it is above-mentioned in the prior art the shortcomings that, a kind of underground structure of can be improved is provided Construction speed, the full assembling structure of outer wall of basement for reducing engineering cost.
In order to achieve the above objectives, the full assembling structure of outer wall of basement provided by the utility model uses following technical scheme:
The full assembling structure of the outer wall of basement is made of prefabricated panel, prefabricated post, precast beam, the prefabricated panel (i.e. vertically arranged concrete walls) are located at the outside of prefabricated post, and the prefabricated panel is made of span centre plate, support plate, described Support plate, prefabricated post, precast beam be linked to be entirety.Span centre plate refers to the prefabricated panel among two exterior wall pillar spans, Support plate refers to the prefabricated panel against pillar.
For routinely frame structures under action, Side fascia is most of close to one-way slabs, the moment of flexure and shearing ratio of horizontal direction Vertical relatively small, prefabricated panel is divided into span centre plate and support plate, the vertical splicing seams of span centre plate and support plate in the horizontal direction Position is near 1/3 horizontal span (i.e. three branches between two exterior wall pillars) of plate, herein close to zero moment of flexure position, plate stitch It is smaller to locate bending force, Side fascia splits the most advantageous.Vertical splicing seams are arranged to be also beneficial to the waterproof of Side fascia, dredge Water.
Support plate is located at the outside of prefabricated post, refers to for basement indoor location, close to the position of basement Be it is interior, the position far from basement is outer.Support plate is located at the outside of prefabricated post, is more advantageous to the soil pressure of outside passing through branch Seat board passes in prefabricated post, and the joining method relative to support plate and prefabricated post on one wire, and not only stress is more closed Reason, and lacked one of splicing seams, the risk of structure safety and infiltration is reduced, also reduces construction cost simultaneously.
The support plate, prefabricated post, precast beam are linked to be entirety by cast-in-place node, are conducive to the prefabricated outer wall panel With prefabricated post, precast beam cooperative bearing.The column plate ring of setting connection prefabricated outer wall panel and prefabricated post, precast beam in cast-in-place node It binds round (i.e. horizontally disposed closed stirrup).
The span centre plate upper end is connected (for multi-storey basement also wallboard phase with upper one layer simultaneously with basement roof Even), lower end is connected with basement bottom board, and left side plate end is connect with the support plate respectively, the left side plate end shape Shape is L shape jaggy, and notch is located inside, and wing plate is located at outside.
The left side plate end, refers to the plate end on two vertical sides of one piece of prefabricated outer wall panel, the plate end perpendicular to Basement roof and bottom plate.The wing plate is that thickness of the fingerboard in end is thinning, plate face linear extension on a face of plate, And be mutated on the other surface, plate end section configuration is L shape, and the part of the thinner thickness of plate is known as wing plate, and wing plate is than outer The part of wallboard missing, referred to as notch.The wing plate of span centre plate on the outside, it is logical to be conducive to the soil pressure that will act on span centre plate Support plate is crossed to pass in prefabricated post.
The support plate can be one block of plate, can also be made of two boards.Consider it is prefabricated and transport facilitate it is feasible, It is one block of plate when support board size is smaller;It is two boards when support board size is larger;When support plate uses two boards, two pieces Plate horizontal distribution or two boards are distributed up and down, and the left side plate end of the support plate is connect with the span centre plate respectively, The left side plate end of the support plate is L shape jaggy, and notch is located at outside, and wing plate is located inside, the support Plate and the wing plate at the left side plate end of the span centre plate fasten respectively, and plate stitch cavity is formed between wing plate, and grouting is filled out in cavity It is real.The horizontal distribution refers to that two boards are distributed in the horizontal direction, and plate stitch is vertical.Corner post support plate in corner post position, By three pieces of board groups at, for component standardization, using the support plate of two pieces of horizontal distributions, between connect a corner post plate, it is described Corner post plate be L shape, the same support plate of plate thickness.
The junction of span centre plate and support plate, moment of flexure are sheared and are not so, therefore support plate wing plate exists close to zero Interior, span centre plate wing plate is conducive to Transfer of Shear outside, from the reliability that structurally ensure that Shear transfer.
In the plate stitch cavity of the junction of support plate and span centre plate, support plate and support plate and support plate and prefabricated post, It pours into or injects cementation of fissures slurries and form cementation of fissures slurry.Cementation of fissures slurries are micro-expansion cement base binding material, or are other types Slurry.In the plate stitch cavity of everywhere, at least one sealing rod (the hydro-expansive rubber item of that side to banket close to outdoor Deng) it is vertically communicated, close to indoor side, ecto-entad, at least one vertically communicated sealing rod, a drain pipe and One of sealing strip (rubber bar or closing glue or closing mortar).
In terms of waterproof, precast facade is relative to the advantages of cast-in-place exterior wall: although cast-in-place exterior wall good integrity, by In the reasons such as temperature change, structure stress and concrete shrinkage generate crack location can not, it is expected that therefore waterproof measure without Method is shot the arrow at the target;And prefabricated outer wall panel this weight is an advantage over cast-in-place exterior wall, it is not easy to crack will not leak, and its splicing seams Position be it is known, can artificially determine, therefore can targetedly handle the seepage problem of splicing seams.Plate stitch cavity it is interior Outer two sides are respectively set sealing rod (materials such as hydro-expansive rubber item can be used), are microdilatancy cementation of fissures slurries between sealing rod, Three is formed together water blockoff mechanism and forms effective " stifled ", i.e. first defence line.And even if once local splicing prefabricated wallboard stitches The intracorporal infiltration of wall can also be drained into the indoor gutter in underground and ponding by vertically arranged drain pipe by water blockoff failure In hole, i.e. the Article 2 defence line of waterproof, drain pipe i.e. drainage tube, effect be will seep water in wall it is directive controllable Carrying-off.The waterproof type in " policy follow, twice defence line " in this way is very suitable to the full assembling structure of wall outside the room of underground, so that full assembly The outer wall of basement waterproof performance of structure is simultaneously not less than cast-in-place structural.
The precast beam, prefabricated post, support plate have exposure reinforcing bar in capital respectively, and the exposure reinforcing bar is cast-in-place one In a cast-in-place node.Exposure reinforcing bar refers to that reinforcing bar a part is embedded in precast concrete, and another part stays in outside component Face, the reinforcing bar outside component are known as exposure reinforcing bar.
It is connected between the prefabricated panel by battle pin connection structure.
The battle pin connection structure, is made of ring and pin, the ring be ring muscle or ring set, two of pre-connection After ring overlapping, pin is placed in the ring of overlapping.The ring muscle be by steel bar meter at ring, can be the ring muscle of opening, It can be closed-loop muscle;The ring set is the closed-loop (usually steel loop) connected in the end of reinforcing bar.Pre-connection Two pieces of prefabricated outer wall panels, reserved when prefabricated it is handy the groove of ring muscle or ring set is arranged and for the reserved pin hole of bayonet lock, Prefabricated part hanging in place after, ring muscle and ring set are inserted into reserved groove, pin is inserted into reserved pin hole, then reserve it is recessed It is in the milk and fills in slot and reserved pin hole.
The support plate and another connection method of span centre plate, prefabricated post are: by pair perpendicular to prefabricated panel Drawing is bolted support plate and span centre plate, prefabricated post, i.e. split bolt connection structure.The split bolt connection structure is by spiral shell Bolt, nut, waterstop pad (rubber pad etc.) and seal body composition.When Side fascia is prefabricated, nut, bolt are reserved in Side fascia in advance Hole, nut space (for installing the reserved space of nut) can be wrapped with the material of water-swellable when bolt is installed on bolt (such as hydro-expansive rubber, unsintered tape material).Bolt, nut are closed with seal body, and the seal body is mortar, closing glue Equal materials.
The invention also discloses a kind of construction methods of the full assembling structure of outer wall of basement, which is characterized in that described Construction method the following steps are included:
(1) prefabricated components are made respectively;
(2) lifting and split prefabricated components;
(3) sealing rod, drain pipe and sealing strip are installed in splicing seams;
(4) component is connected by battle pin connection structure or split bolt, be in the milk filleting.
The utility model has the beneficial effects that compared with cast-in-place concrete structure outer wall of basement, outside the basement The full assembling structure of wall has the advantage that
1, speed of application is fast, saves the duration, is conducive to the safety of foundation pit enclosure;
2, cost is reduced, the cost of fabricated construction can be reduced using battle pin connection structure technology, and duration reduction has It is reduced conducive to the selection of foundation pit enclosure stake and cost, and prefabricated components precision is high, can exempt to paint, to reduce cost;
3, environmentally protective, construction site is neatly orderly, reduces execute-in-place worker number, is conducive to building industrialization;
4, waterproof performance is more preferable.
Detailed description of the invention
Fig. 1 is the plane relation figure of the full assembling structure of outer wall of basement of the utility model.
Fig. 2 is the horizontal sectional view of the span centre plate of the prefabricated outer wall panel of the utility model.
Fig. 3 is the horizontal sectional view of (two pieces of level) support plate of the prefabricated outer wall panel of the utility model.
Fig. 4 is the outer side elevational view of (vertical two pieces) support plate of the prefabricated outer wall panel of the utility model.
Fig. 5 is the horizontal sectional view of (corner post) support plate of the prefabricated outer wall panel of the utility model.
Fig. 6 is the horizontal sectional view that (split bolt connection) support plate of the utility model is connect with span centre plate.
Fig. 7 is the vertical cross-section diagram that (split bolt connection) support plate of the utility model is connect with span centre plate.
Fig. 8 is the horizontal sectional view that (battle pin connection) support plate of the utility model is connect with span centre plate.
Fig. 9 is the vertical cross-section diagram that (battle pin connection) support plate of the utility model is connect with span centre plate.
Figure 10 is the front elevation view of (vertical two pieces of the battle pin connection before assembly) support plate of the utility model.
Figure 11 is the vertical cross-section diagram of (vertical two pieces of the battle pin connection before assembly) support plate of the utility model.
Figure 12 is the vertical cross-section diagram of (vertical two pieces of the battle pin connection after assembly) support plate of the utility model.
Figure 13 is that the support plate of the utility model is disconnected with the level of prefabricated post (battle pin in conjunction with ring muscle, ring set) connecting node Face figure.
Figure 14 is that the support plate of the utility model breaks with the vertical of prefabricated post (battle pin in conjunction with ring muscle, ring set) connecting node Face figure.
Figure 15 is the support plate of the utility model and the horizontal sectional view of prefabricated post (ring muscle battle pin) connecting node.
Figure 16 is the support plate of the utility model and the vertical cross-section diagram of prefabricated post (unilateral ring muscle battle pin) connecting node.
Figure 17 is the support plate and the water of prefabricated (angle) column (battle pin in conjunction with ring muscle ring set) connecting node of the utility model Plane cross section.
Figure 18 be the prefabricated outer wall panel of the utility model, precast beam, Bars In Poured Concrete Slab correlation vertical cross-section diagram.
Figure 19 be the prefabricated outer wall panel of the utility model, precast beam, superimposed sheet correlation vertical cross-section diagram.
Figure 20 be the prefabricated outer wall panel of the utility model, precast beam, prefabricated post correlation vertical cross-section diagram.
Figure 21 be the prefabricated outer wall panel of the utility model, precast beam, prefabricated post correlation horizontal sectional view.
Appended drawing reference
1 support plate
10 backfills
11 horizontal distribution support plates
111 horizontal distribution support plate wing plates
About 12 distribution support plate upper plates
About 13 distribution support plate lower plates
14 closed-loop muscle
15 reserved grooves
16 reserved pin holes
17 pins
2 span centre plates
21 span centre plate wing plates
3 corner post support plates
31 corner post plates
4 prefabricated posts
40 U-loop muscle
41 ring sets
45 cast-in-place nodes
5 Vierendeel girders
51 column plate hoops
52 exposure reinforcing bars
60 plate stitch cavitys
61 sealing rods
62 drain pipes
63 sealing strips
64 seal bodies
71 bolts
72 nuts
73 waterstop pads
8 precast beams
91 Bars In Poured Concrete Slabs
92 prefabricated boards
Specific embodiment
In order to be more clearly understood that the technology contents of the utility model, spy lifts following embodiment and is described in detail.
It please refers to shown in Fig. 1~21, the full assembling structure of the outer wall of basement is by prefabricated panel, prefabricated post, precast beam Composition, the prefabricated panel (i.e. vertically arranged concrete walls) are located at the outside of prefabricated post, the prefabricated panel by across Middle plate, support plate composition, the support plate, prefabricated post, precast beam are linked to be entirety.Span centre plate refers to positioned at two exterior wall pillars Prefabricated panel among span, support plate refer to the prefabricated panel against pillar.
For routinely frame structures under action, Side fascia is most of close to one-way slabs, the moment of flexure and shearing ratio of horizontal direction Vertical relatively small, prefabricated panel is divided into span centre plate and support plate, the vertical splicing seams of span centre plate and support plate in the horizontal direction Position is near 1/3 horizontal span (i.e. three branches between two exterior wall pillars) of plate, herein close to zero moment of flexure position, plate stitch It is smaller to locate bending force, Side fascia splits the most advantageous.Vertical splicing seams are arranged to be also beneficial to the waterproof of Side fascia, dredge Water.
Support plate is located at the outside of prefabricated post, refers to for basement indoor location, close to the position of basement Be it is interior, the position far from basement is outer.Support plate is located at the outside of prefabricated post, is more advantageous to the soil pressure of outside passing through branch Seat board passes in prefabricated post, and the joining method relative to support plate and prefabricated post on one wire, and not only stress is more closed Reason, and lacked one of splicing seams, the risk of structure safety and infiltration is reduced, also reduces construction cost simultaneously.
The support plate, prefabricated post, precast beam are linked to be entirety by cast-in-place node, are conducive to the prefabricated outer wall panel With prefabricated post, precast beam cooperative bearing.The column plate ring of setting connection prefabricated outer wall panel and prefabricated post, precast beam in cast-in-place node It binds round (i.e. horizontally disposed closed stirrup).
The span centre plate upper end is connected (for multi-storey basement also wallboard phase with upper one layer simultaneously with basement roof Even), lower end is connected with basement bottom board, and left side plate end is connect with the support plate respectively, the left side plate end shape Shape is L shape jaggy, and notch is located inside, and wing plate is located at outside.
The left side plate end, refers to the plate end on two vertical sides of one piece of prefabricated outer wall panel, the plate end perpendicular to Basement roof and bottom plate.The wing plate is that thickness of the fingerboard in end is thinning, plate face linear extension on a face of plate, And be mutated on the other surface, plate end section configuration is L shape, and the part of the thinner thickness of plate is known as wing plate, and wing plate is than outer The part of wallboard missing, referred to as notch.The wing plate of span centre plate on the outside, it is logical to be conducive to the soil pressure that will act on span centre plate Support plate is crossed to pass in prefabricated post.
The support plate can be one block of plate, can also be made of two boards.Consider it is prefabricated and transport facilitate it is feasible, It is one block of plate when support board size is smaller;It is two boards when support board size is larger;When support plate uses two boards, two pieces Plate horizontal distribution or two boards are distributed up and down, and the left side plate end of the support plate is connect with the span centre plate respectively, The left side plate end of the support plate is L shape jaggy, and notch is located at outside, and wing plate is located inside, the support Plate and the wing plate at the left side plate end of the span centre plate fasten respectively, and plate stitch cavity is formed between wing plate, and grouting is filled out in cavity It is real.The horizontal distribution refers to that two boards are distributed in the horizontal direction, and plate stitch is vertical.Corner post support plate in corner post position, By three pieces of board groups at, for component standardization, using the support plate of two pieces of horizontal distributions, between connect a corner post plate, it is described Corner post plate be L shape, the same support plate of plate thickness.
The junction of span centre plate and support plate, moment of flexure are sheared and are not so, therefore support plate wing plate exists close to zero Interior, span centre plate wing plate is conducive to Transfer of Shear outside, from the reliability that structurally ensure that Shear transfer.
In the plate stitch cavity of the junction of support plate and span centre plate, support plate and support plate and support plate and prefabricated post, It pours into or injects cementation of fissures slurries and form cementation of fissures slurry.Cementation of fissures slurries are micro-expansion cement base binding material, or are other types Slurry.In the plate stitch cavity of everywhere, at least one sealing rod (the hydro-expansive rubber item of that side to banket close to outdoor Deng) it is vertically communicated, close to indoor side, ecto-entad, at least one vertically communicated sealing rod, a drain pipe and One of sealing strip (rubber bar or closing glue or closing mortar).
In terms of waterproof, precast facade is relative to the advantages of cast-in-place exterior wall: although cast-in-place exterior wall good integrity, by In the reasons such as temperature change, structure stress and concrete shrinkage generate crack location can not, it is expected that therefore waterproof measure without Method is shot the arrow at the target;And prefabricated outer wall panel this weight is an advantage over cast-in-place exterior wall, it is not easy to crack will not leak, and its splicing seams Position be it is known, can artificially determine, therefore can targetedly handle the seepage problem of splicing seams.Plate stitch cavity it is interior Outer two sides are respectively set sealing rod (materials such as hydro-expansive rubber item can be used), are microdilatancy cementation of fissures slurries between sealing rod, Three is formed together water blockoff mechanism and forms effective " stifled ", i.e. first defence line.And even if once local splicing prefabricated wallboard stitches The intracorporal infiltration of wall can also be drained into the indoor gutter in underground and ponding by vertically arranged drain pipe by water blockoff failure In hole, i.e. the Article 2 defence line of waterproof, drain pipe i.e. drainage tube, effect be will seep water in wall it is directive controllable Carrying-off.The waterproof type in " policy follow, twice defence line " in this way is very suitable to the full assembling structure of wall outside the room of underground, so that full assembly The outer wall of basement waterproof performance of structure is simultaneously not less than cast-in-place structural.
The precast beam, prefabricated post, support plate have exposure reinforcing bar in capital respectively, and the exposure reinforcing bar is cast-in-place one In a cast-in-place node.Exposure reinforcing bar refers to that reinforcing bar a part is embedded in precast concrete, and another part stays in outside component Face, the reinforcing bar outside component are known as exposure reinforcing bar.
It is connected between the prefabricated panel by battle pin connection structure.
The battle pin connection structure, is made of ring and pin, the ring be ring muscle or ring set, two of pre-connection After ring overlapping, pin is placed in the ring of overlapping.The ring muscle be by steel bar meter at ring, can be the ring muscle of opening, It can be closed-loop muscle;The ring set is the closed-loop (usually steel loop) connected in the end of reinforcing bar.Pre-connection Two pieces of prefabricated outer wall panels, reserved when prefabricated it is handy the groove of ring muscle or ring set is arranged and for the reserved pin hole of bayonet lock, Prefabricated part hanging in place after, ring muscle and ring set are inserted into reserved groove, pin is inserted into reserved pin hole, then reserve it is recessed It is in the milk and fills in slot and reserved pin hole.
The support plate and another connection method of span centre plate, prefabricated post are: by pair perpendicular to prefabricated panel Drawing is bolted support plate and span centre plate, prefabricated post, i.e. split bolt connection structure.The split bolt connection structure is by spiral shell Bolt, nut, waterstop pad (rubber pad etc.) and seal body composition.When Side fascia is prefabricated, nut, bolt are reserved in Side fascia in advance Hole, nut space (for installing the reserved space of nut) can be wrapped with the material of water-swellable when bolt is installed on bolt (such as hydro-expansive rubber, unsintered tape material).Bolt, nut are closed with seal body, and the seal body is mortar, closing glue Equal materials.
For realizing the construction method of the full assembling structure of outer wall of basement of the utility model, wherein the construction method The following steps are included:
(1) prefabricated components are made respectively;
(2) lifting and split prefabricated components;
(3) sealing rod, drain pipe and sealing strip are installed in splicing seams;
(4) component is connected by battle pin connection structure or split bolt, be in the milk filleting.
Embodiment 1
Step 1: making prefabricated components support plate 1, span centre plate 2, prefabricated post 4, precast beam 8, corner post support plate 3, angle respectively Column plate 31;
Step 2: hoisting prefabricated component assembles horizontal distribution support plate 11, prefabricated post 4, span centre plate 2, angle to predetermined position Column plate 31;
Step 3: clogging sealing rod 61, drain pipe 62, sealing strip 63 respectively in 60 internal heads of plate stitch cavity;
Step 4: connecting the wing plate 111 of horizontal seat plate 11 and the wing of span centre plate 2 with bolt 71, nut 72, waterstop pad 73 Plate 21 (or connected with closed-loop muscle 14 or U-loop muscle 40 and ring set 41, pin 17 by reserved groove 15 and reserved pin hole 16 The wing plate 111 of water receiving flat bearing plate 11 and the wing plate 21 of span centre plate 2), with U-loop muscle 40 or closed-loop muscle 14 or ring set 41, pin Bolt 17 connects horizontal distribution support plate 11 and prefabricated post 4, connects horizontal distribution support with U-loop muscle 40 or ring set 41, pin 17 Plate 11, prefabricated post 4 and corner post plate 31;
Step 5: live the plate stitch and reserved groove 15 of prefabricated outer wall panel with engineering template clamp, plate stitch cavity 60, reserve it is recessed Bonding slurries (micro-expansion cement base binding material etc. can be used) is poured into slot 15 and reserved pin hole 16, completes grouting filleting, it is full After sufficient curing period requires, engineering template is removed.Seal body 64 (cement mortar, closing glue etc. are filled in bolt hole end portion cavity Material).
Step 6: lifting, assembly precast beam 8, prefabricated board 92, mounting post plate hoop 51, construction Bars In Poured Concrete Slab 91, Vierendeel girder 5, Casting concrete forms cast-in-place node 45.
Embodiment 2
Step 1: making prefabricated components support plate 1, span centre plate 2, prefabricated post 4, precast beam 8, corner post plate 31 respectively;
Step 2: hoisting prefabricated component assembles prefabricated post 4 to predetermined position, support plate lower plate is then distributed under fit on 13, it is distributed support plate upper plate 12 up and down, assembles span centre plate 2;
Step 3: with 1 third step of embodiment;
Step 4: with the 4th step of embodiment 1;
Step 5: with the 5th step of embodiment 1;
Step 6: with the 6th step of embodiment 1.
The utility model proposes the full assembling structure of outer wall of basement and construction method, in environmentally protective, speed of application, build It is set as this and waterproof effect etc., all there is significant innovative and helpfulness than traditional outer wall of basement cast-in-place structural, it will Huge positive effect and motive force can be brought to the extension of the application field of assembled architecture.
In this description, the utility model is described with reference to its specific embodiment.But it is clear that still can be with The spirit and scope that various modification can be adapted and converts without departing from the utility model.Therefore, the description and the appended drawings should be considered as It is illustrative and not restrictive.

Claims (7)

1. a kind of full assembling structure of outer wall of basement, which is characterized in that the full assembling structure of the outer wall of basement is by dry wall Plate, prefabricated post, precast beam composition, the prefabricated panel are located at the outside of prefabricated post, and the prefabricated panel is by span centre plate, branch Seat board composition, the support plate, prefabricated post, precast beam are linked to be entirety.
2. the full assembling structure of outer wall of basement according to claim 1, which is characterized in that the upper end of the span centre plate with Basement roof is connected, and the lower end of the span centre plate is connected with basement bottom board, left side plate end respectively with the support plate It is connected, the left side plate end is L shape jaggy, and notch is located inside, and wing plate is located at outside.
3. the full assembling structure of outer wall of basement according to claim 1, which is characterized in that the support plate is by two boards Composition, two boards or so distribution or two boards up and down be distributed, the support plate left side plate end respectively with the span centre The left side plate end of plate connection, the support plate is L shape jaggy, and notch is located at outside, and wing plate is located inside, described Support plate and the wing plate at the left side plate end of the span centre plate fasten respectively, cavity, grouting in cavity are formed between wing plate It tamps.
4. the full assembling structure of outer wall of basement according to claim 1, which is characterized in that the support plate is one piece whole Body plate.
5. the full assembling structure of outer wall of basement according to claim 1, which is characterized in that the precast beam, prefabricated post, Support plate has exposure reinforcing bar in capital respectively, and the exposure reinforcing bar is cast-in-place in a cast-in-place node.
6. the full assembling structure of outer wall of basement according to claim 1, which is characterized in that lead between the prefabricated panel The connection of battle pin connection structure is crossed, the battle pin connection structure is made of ring and pin, and the ring is ring muscle or ring set, The ring of pre-connection is locally overlapped, and the pin is placed in the ring of overlapping.
7. the full assembling structure of outer wall of basement according to claim 1, which is characterized in that the support plate and span centre Plate, prefabricated post are connected by split bolt.
CN201820818465.1U 2018-05-30 2018-05-30 The full assembling structure of outer wall of basement Active CN208517969U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820818465.1U CN208517969U (en) 2018-05-30 2018-05-30 The full assembling structure of outer wall of basement

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820818465.1U CN208517969U (en) 2018-05-30 2018-05-30 The full assembling structure of outer wall of basement

Publications (1)

Publication Number Publication Date
CN208517969U true CN208517969U (en) 2019-02-19

Family

ID=65339506

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820818465.1U Active CN208517969U (en) 2018-05-30 2018-05-30 The full assembling structure of outer wall of basement

Country Status (1)

Country Link
CN (1) CN208517969U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108560585A (en) * 2018-05-30 2018-09-21 上海城建建设实业集团新型建筑材料嘉兴有限公司 The full assembling structure of outer wall of basement and its construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108560585A (en) * 2018-05-30 2018-09-21 上海城建建设实业集团新型建筑材料嘉兴有限公司 The full assembling structure of outer wall of basement and its construction method
CN108560585B (en) * 2018-05-30 2023-12-19 上海城建建设实业集团新型建筑材料嘉兴有限公司 Basement outer wall full assembly structure and construction method thereof

Similar Documents

Publication Publication Date Title
CN108678258B (en) Large-span hemispherical reinforced concrete dome structure and construction method thereof
CN106013811B (en) A kind of installation method of assembled architecture
CN105781125B (en) A kind of installation method of assembled architecture
CN102116061B (en) Masonry construction method for filling wall core pillar, core girder and building blocks into framework structure
CN106436893A (en) Fully-prefabricated structure and construction method thereof
CN105696817A (en) Multilayer cold-formed steel integrally prefabricated house and splicing method thereof
CN106836479A (en) A kind of prefabricated PC concrete frame structure
CN206562836U (en) Fully-prefabricated assembled enclosure wall
CN108661221A (en) A kind of precast floor slab and its connection structure and its construction method
CN103510723A (en) Integrally assembled type frame structure housing system
CN110565797B (en) Hidden corbel type beam-column joint connection method for shock absorption
CN108005265A (en) A kind of prefabricated steel reinforced concrete shear wall structure of multilayer and its preparation and construction method
CN110258640A (en) A kind of construction method of the overlapping wall system of covered back-digging
CN106088657A (en) The ruggedized construction of a kind of rowlock wall body and construction method thereof
CN107587605A (en) A kind of complete precast prestressed fabricated construction and its construction method
CN108560585A (en) The full assembling structure of outer wall of basement and its construction method
CN108005264A (en) A kind of steel framework constraint precast reinforced concrete shear wall structure and preparation and installation method
CN208517969U (en) The full assembling structure of outer wall of basement
CN106284742A (en) Half column frame antidetonation faced wall and manufacture method
CN105297956A (en) Cast-in-situ composite thermal insulation concrete shear wall and manufacturing method thereof
CN105040855B (en) Prefabricated shear wall welded end plate and horizontal section steel combined connection apparatus
CN204781443U (en) Device for connecting precast shear wall concatenation about being used for
CN208618627U (en) A kind of precast floor slab and its connection structure
CN208202224U (en) A kind of prefabricated steel reinforced concrete shear wall structure of multilayer
CN207739439U (en) A kind of steel framework constraint precast reinforced concrete shear wall structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant