CN208517168U - Tall building life sewage treatment electric generator - Google Patents

Tall building life sewage treatment electric generator Download PDF

Info

Publication number
CN208517168U
CN208517168U CN201820820682.4U CN201820820682U CN208517168U CN 208517168 U CN208517168 U CN 208517168U CN 201820820682 U CN201820820682 U CN 201820820682U CN 208517168 U CN208517168 U CN 208517168U
Authority
CN
China
Prior art keywords
water
level detecting
detecting device
electric valve
connect
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820820682.4U
Other languages
Chinese (zh)
Inventor
李娟�
李超超
吴星
徐敏
董启兴
杨佳豪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ningxia University
Original Assignee
Ningxia University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ningxia University filed Critical Ningxia University
Priority to CN201820820682.4U priority Critical patent/CN208517168U/en
Application granted granted Critical
Publication of CN208517168U publication Critical patent/CN208517168U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Physical Water Treatments (AREA)
  • Water Treatment By Electricity Or Magnetism (AREA)

Abstract

A kind of tall building life sewage treatment electric generator, including sewage-treatment plant, hydroelectric installation, electrical storage device, control device, sewage-treatment plant includes process chamber, the first reservoir chamber, it is provided in process chamber except diamicton, it prevents from scratching power generator to remove solid impurity, first water-level detecting device, pH value detection device, pH value adjustment device, third solenoid electric valve in first reservoir chamber, pH value is neutrality when guaranteeing that water enters hydroelectric installation to cooperate;Hydroelectric installation includes the second reservoir chamber, power compartment, second reservoir chamber is provided with the second water-level detecting device, second water-level detecting device is connect with control device, the second solenoid electric valve is closed when water level is lower than the position of lower layer's water-level detecting device, it is higher than in water level or when position in upper layer detection device opens the second solenoid electric valve, generated energy is stablized in the unit time when guaranteeing power compartment inner impeller electrical power generators.

Description

Tall building life sewage treatment electric generator
Technical field
The utility model relates to tall building life technical field of sewage treatment and utilization, and in particular to a kind of skyscraper is raw Sewage treatment electric generator living.
Background technique
Modern society's skyscraper is more and more, the kinetic energy impact arranged when using skyscraper sewerage from high-storey Fixed wheel rotation, stator winding coil cutting magnetic line produce electricl energy on driven generator axis.But it is built currently with high level It builds sewage to carry out in hydroelectric technology, the problems such as cannot be guaranteed because of sewage treatment rear impact, be used after first generating electricity substantially The mode of processing thereby results in sundries, acidic materials, alkaline matter in sewage etc. and scratches, corrodes generating equipment, in addition, high The discharge of sewage in layer building is uncertain, small when big when causing generated energy, too small electric current can be lost in conducting wire and can not be into Enter in electrical storage device, this is also required in skyscraper sewage generating technology solves the problems, such as.
Summary of the invention
In view of this, not will cause it is necessary to provide generated energy stabilization in a kind of unit time and generating equipment scuffing, corruption The tall building life sewage treatment electric generator of erosion.
A kind of tall building life sewage treatment electric generator, including sewage-treatment plant, hydroelectric installation, electric power storage dress It sets, control device, sewage-treatment plant is connect with building blow-off line, and sewage-treatment plant also passes through water with hydroelectric installation Pipe connection, by treated, sewage is used to generate electricity, and hydroelectric installation is connect with electrical storage device, to store hydroelectric installation The electric energy of generation, control device are connect with sewage-treatment plant, hydroelectric installation respectively, to control its working condition, sewage Processing unit includes process chamber, the first reservoir chamber, and process chamber is connect with building blow-off line, and process chamber passes through with the first reservoir chamber The connection of first solenoid electric valve, the first reservoir chamber are connect by water pipe with hydroelectric installation;Hydroelectric installation includes second Reservoir chamber, power compartment, the second reservoir chamber are located at the top of power compartment, are connected by the second solenoid electric valve and are connect with power compartment, Second reservoir chamber also passes through water pipe and connect with the first reservoir chamber, and hydroelectric generation component is provided in power compartment, using under water flow When impact force complete power generation, water outlet, the first solenoid electric valve, the second solenoid electric valve difference are provided with below power compartment It is connect with control device.
It preferably, include removing solid impurity in sewage-treatment plant, in process chamber except diamicton, multiple pairs of water carry out essence The drainage layer of close filtering is located at the top of drainage layer except diamicton, is provided in the first reservoir chamber including upper layer water-level detecting device With the first water-level detecting device, pH value detection device, the pH value adjustment device of lower layer water-level detecting device, under the first reservoir chamber End is additionally provided with the first solenoid electric valve, third solenoid electric valve, the first water-level detecting device, pH value detection with water pipe junction Device, pH value adjustment device, third solenoid electric valve are connect with control device respectively, and control device is filled according to the first water level detecting The opening and closing of testing result control the first solenoid electric valve, third solenoid electric valve set, fills in water level lower than lower layer's water level detecting Behind the position set, third solenoid electric valve is closed, the first solenoid electric valve is then turned on, is in upper layer detection device in water level The first solenoid electric valve is closed behind position, is later acid or alkalinity according to the testing result of PH detection device, control PH is adjusted The testing result that device launches alkaline matter or acidic materials to PH detection device is neutrality, is then turned on third Electromagnetic Control Valve.
Preferably, in hydroelectric installation, the second reservoir chamber is provided with including upper layer water-level detecting device and lower layer's water level Second water-level detecting device of detection device, the second water-level detecting device are connect with control device, and control device is according to the second water The testing result of level detecting apparatus controls the opening and closing of the second solenoid electric valve, is lower than the position of lower layer's water-level detecting device in water level After close the second solenoid electric valve, be higher than in water level or the position in upper layer detection device after open the second solenoid electric valve; Turbo dynamo is provided in power compartment.
Preferably, water outlet includes the first connector, the second connector, is set respectively at the first connector, the second connector It is equipped with electric-controlled switch, the first connector is connect with resident living water pipeline, and the second connector is connect with resident's blow-off line, the One connector uses transparent setting, and transparent place is provided with ultraviolet emission device, is killed so that ultraviolet light maps in water Poison sterilizing, water outlet are additionally provided with water quality detecting device.
Preferably, in sewage-treatment plant, the upper end of process chamber is set as the lid being threadedly coupled with process chamber, on lid It is provided with handle, lid is rotated by handle to facilitate, and then open process chamber and cleared up or closed process chamber.
Tall building life sewage treatment electric generator provided by the utility model, including sewage-treatment plant, waterpower hair Electric installation, electrical storage device, control device, sewage-treatment plant include process chamber, the first reservoir chamber, are provided with removal of impurities in process chamber Layer is prevented from scratching power generator, is provided in the first reservoir chamber including upper layer water-level detecting device under to remove solid impurity The first water-level detecting device, pH value detection device, pH value adjustment device, the third solenoid electric valve of layer water-level detecting device, the One water-level detecting device, pH value detection device, pH value adjustment device, third solenoid electric valve are connect with control device respectively, control Device processed controls the opening and closing of the first solenoid electric valve, third solenoid electric valve according to the testing result of the first water-level detecting device, Behind position of the water level lower than lower layer's water-level detecting device, third solenoid electric valve is closed, the first solenoid electric valve is then turned on, The first solenoid electric valve is closed behind the position that water level is in upper layer detection device, later according to the testing result of PH detection device It is acid or alkalinity, the testing result that control PH regulating device launches alkaline matter or acidic materials to PH detection device is Property, it is then turned on third solenoid electric valve, prevents power generator from sour corrosion or alkalinity alkalinity occurs to neutralize the acid-base property of water Corrosion;Hydroelectric installation includes the second reservoir chamber, power compartment, the second reservoir chamber be provided with including upper layer water-level detecting device and Second water-level detecting device of lower layer's water-level detecting device, the second water-level detecting device are connect with control device, are lower than in water level The second solenoid electric valve is closed when the position of lower layer's water-level detecting device, is higher than in water level or the position in upper layer detection device The second solenoid electric valve of Shi Kaiqi is begun by difference in height existing for the second reservoir chamber and power compartment and the indoor water of the second water storage There is certain height i.e. hydraulic pressure eventually, generated energy is stablized in the unit time when guaranteeing power compartment inner impeller electrical power generators.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of tall building life sewage treatment electric generator.
In figure: tall building life sewage treatment electric generator 1, sewage-treatment plant 2, process chamber 21, except diamicton 211, Drainage layer 212, the first reservoir chamber 22, the first water-level detecting device 221, pH value detection device 222, pH value adjustment device 223, Three solenoid electric valves 224, the first solenoid electric valve 23, lid 24, handle 241, hydroelectric installation 33, the second reservoir chamber 31, Second water-level detecting device 311, power compartment 32, the second solenoid electric valve 33, water outlet 34, the connection of the first connector 341, second Mouth 342, electric-controlled switch 342, ultraviolet emission device 344, water quality detecting device 345, electrical storage device 4, control device 5.
Specific embodiment
Below in conjunction with specific embodiment, the utility model is elaborated, so that those skilled in the art can be more The advantages of understanding the utility model got well.
Please refer to Fig. 1, a kind of tall building life sewage treatment electric generator 1, including sewage-treatment plant 2, waterpower hair Electric installation 33, electrical storage device 4, control device 5, sewage-treatment plant 2 are connect with building blow-off line, and sewage-treatment plant 2 is also It is connect with hydroelectric installation 3 by water pipe, by treated, sewage is used to generate electricity, hydroelectric installation 3 and electrical storage device 4 Connection, with store hydroelectric installation 3 generation electric energy, control device 5 respectively with sewage-treatment plant 2, hydroelectric installation 3 Connection, to control its working condition, sewage-treatment plant 2 includes process chamber 21, the first reservoir chamber 22, and process chamber 21 and building are arranged Dirty pipeline connection, process chamber 21 are connect with the first reservoir chamber 22 by the first solenoid electric valve 23, and the first reservoir chamber 22 passes through water Pipe is connect with hydroelectric installation 3;Hydroelectric installation 3 includes the second reservoir chamber 31, power compartment 32, and the second reservoir chamber 31 is located at The top of power compartment 32 is connected by the second solenoid electric valve 33, and the second reservoir chamber 31 also passes through water pipe and the first reservoir chamber 22 It connects, is provided with turbo dynamo in power compartment 32, impact force when with using under water flow completes power generation, the lower section of power compartment 32 It is provided with water outlet 34, the first solenoid electric valve 23, the second solenoid electric valve 33 are connect with control device 5 respectively.
Further, include except diamicton 211 in sewage-treatment plant 2, in process chamber 21, multiple drainage layers 212, remove diamicton 211 are located at the top of drainage layer 212, are provided in the first reservoir chamber 22 including upper layer water-level detecting device and lower layer's water level detecting The first water-level detecting device 221, pH value detection device 222, the pH value adjustment device 223 of device, the lower end of the first reservoir chamber 22 Third solenoid electric valve 224, the first water-level detecting device 221, pH value detection device 222, PH are additionally provided with water pipe junction Value adjusting device 223, third solenoid electric valve 224 are connect with control device 5 respectively, and control device 5 is according to the first water level detecting The testing result of device 221 controls the opening and closing of the first solenoid electric valve 23, third solenoid electric valve 224, is lower than lower layer in water level Behind the position of water-level detecting device, third solenoid electric valve 224 is closed, the first solenoid electric valve 23 is then turned on, at water level The first solenoid electric valve 23 is closed behind the position of upper layer detection device, is according to the testing result of PH detection device 222 later Acid or alkalinity, control PH regulating device 223 launches alkaline matter or the testing result of acidic materials to PH detection device 222 is Neutrality is then turned on third solenoid electric valve 224;In hydroelectric installation 3, the second reservoir chamber 31 is provided with including upper layer water level Second water-level detecting device 311 of detection device and lower layer's water-level detecting device, the second water-level detecting device 311 and control device 5 connections, control device 5 control the opening and closing of the second solenoid electric valve 33 according to the testing result of the second water-level detecting device 311;Hair Turbo dynamo is provided in electric room 32;Water outlet 34 includes the first connector 341, the second connector 342, the first connector 341, electric-controlled switch 343 is respectively arranged at the second connector 342, the first connector 341 is connect with resident living water pipeline, Second connector 342 is connect with resident's blow-off line, and the first connector 341 uses transparent setting, and transparent place is provided with ultraviolet light Emitter 344 is additionally provided with water quality detecting device at water outlet 34 so that ultraviolet light, which maps to, carries out exterminating bacterium in water 345;In sewage-treatment plant 2, the upper end of process chamber 21 is set as the lid 24 being threadedly coupled with process chamber 21, is arranged on lid 24 There is handle 241, to facilitate by the way that 241 hands are rotated lid 24, and then opens process chamber 21 and cleared up or closed process chamber 21.
The tall building life sewage treatment electric generator handle when in use, in sewage treatment it is indoor except diamicton, with Removing solid impurity prevents from scratching power generator, and drainage layer carries out purified treatment to sewage, be provided in the first reservoir chamber including First water-level detecting device of upper layer water-level detecting device and lower layer's water-level detecting device, pH value detection device 222, pH value adjustment Device, third solenoid electric valve, the first water-level detecting device, pH value detection device 222, pH value adjustment device, third electromagnetism control Valve processed is connect with control device respectively, is controlled PH regulating device according to the testing result of PH detection device and is launched acidic materials or alkali Property substance to adjust the pH value of water, prevent power generator from sour corrosion or alkaline alkaline corrosion occurs, be in upper layer inspection in water level The first solenoid electric valve is closed when surveying the position of device, and third electromagnetism is opened after launching acidic materials or alkaline matter Control valve closes third solenoid electric valve when water level is lower than the position of lower layer's water-level detecting device, is then turned on the first electromagnetism Control valve;Hydroelectric installation 3 includes the second reservoir chamber, power compartment, and the second reservoir chamber is provided with to be filled including upper layer water level detecting The second water-level detecting device with lower layer water-level detecting device is set, the second water-level detecting device is connect with control device, in water level Lower than lower layer's water-level detecting device position when close the second solenoid electric valve, be higher than in water level or in upper layer detection device The second solenoid electric valve is opened when position, generated energy is stablized in the unit time when guaranteeing power compartment inner impeller electrical power generators. When draining, after water quality detecting device detects, when water quality qualification, the electric-controlled switch at the first connector is opened, treated water Resident living water pipeline, electric-controlled switch when water quality detection is unqualified, at the second connector are flowed into after ultraviolet sterilization It opens, water flows into resident's blow-off line.

Claims (5)

1. a kind of tall building life sewage treatment electric generator, it is characterised in that: filled including sewage-treatment plant, hydroelectric generation Set, electrical storage device, control device, sewage-treatment plant with building blow-off line connect, sewage-treatment plant also with hydroelectric generation Device is connected by water pipe, and by treated, sewage is used to generate electricity, and hydroelectric installation is connect with electrical storage device, to store water The electric energy that power generation device generates, control device is connect with sewage-treatment plant, hydroelectric installation respectively, to control its work State, the sewage-treatment plant include process chamber, the first reservoir chamber, and process chamber connect with building blow-off line, process chamber and First reservoir chamber is connected by the first solenoid electric valve, and the first reservoir chamber is connect by water pipe with the hydroelectric installation;Institute Stating hydroelectric installation includes the second reservoir chamber, power compartment, and the second reservoir chamber is located at the top of power compartment, passes through the second electromagnetism control Valve connection processed is connect with power compartment, and the second reservoir chamber also passes through water pipe and connect with first reservoir chamber, is provided in power compartment Hydroelectric generation component, impact force when with using under water flow complete power generation, are provided with water outlet, the first electromagnetism below power compartment Control valve, the second solenoid electric valve are connect with the control device respectively.
2. tall building life sewage treatment electric generator as described in claim 1, it is characterised in that: the sewage treatment dress In setting, the interior process chamber includes removing solid impurity except diamicton, multiple pairs of water carry out the drainage layer of secondary filter, except diamicton Positioned at the top of drainage layer, it is provided in first reservoir chamber including upper layer water-level detecting device and lower layer's water-level detecting device The first water-level detecting device, pH value detection device, pH value regulating device, lower end and the water pipe junction of the first reservoir chamber are also set It is equipped with third solenoid electric valve, the first water-level detecting device, pH value detection device, pH value regulating device, third solenoid electric valve It is connect respectively with the control device, control device controls the first Electromagnetic Control according to the testing result of the first water-level detecting device The opening and closing of valve, third solenoid electric valve closes third Electromagnetic Control behind position of the water level lower than lower layer's water-level detecting device Valve is then turned on the first solenoid electric valve, closes the first solenoid electric valve behind the position that water level is in upper layer detection device, it It is afterwards acid or alkalinity according to the testing result of pH detection device, control PH regulating device launches alkaline matter or acidic materials extremely The testing result of pH detection device is neutrality, is then turned on third solenoid electric valve.
3. tall building life sewage treatment electric generator as claimed in claim 1 or 2, it is characterised in that: the waterpower hair In electric installation, second reservoir chamber is provided with the second water level including upper layer water-level detecting device and lower layer's water-level detecting device Detection device, the second water-level detecting device are connect with the control device, and control device is according to the inspection of the second water-level detecting device The opening and closing that result controls second solenoid electric valve is surveyed, closes second behind position of the water level lower than lower layer's water-level detecting device Solenoid electric valve, be higher than in water level or the position in upper layer detection device after open the second solenoid electric valve;The power compartment Inside it is provided with turbo dynamo.
4. tall building life sewage treatment electric generator as claimed in claim 3, it is characterised in that: the water outlet includes First connector, the second connector are respectively arranged with electric-controlled switch, the first connection at first connector, the second connector Mouth is connect with resident living water pipeline, and the second connector is connect with resident's blow-off line, and the first connector uses transparent setting, Transparent place is provided with ultraviolet emission device, so that ultraviolet light, which maps to, carries out exterminating bacterium in water, water outlet is also set up There is water quality detecting device.
5. tall building life sewage treatment electric generator as claimed in claim 4, it is characterised in that: the sewage treatment dress In setting, the upper end of the process chamber is set as the lid being threadedly coupled with process chamber, is provided with handle on lid, is passed through with facilitating Handle rotates lid, and then opens process chamber and cleared up or closed process chamber.
CN201820820682.4U 2018-05-26 2018-05-26 Tall building life sewage treatment electric generator Expired - Fee Related CN208517168U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820820682.4U CN208517168U (en) 2018-05-26 2018-05-26 Tall building life sewage treatment electric generator

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820820682.4U CN208517168U (en) 2018-05-26 2018-05-26 Tall building life sewage treatment electric generator

Publications (1)

Publication Number Publication Date
CN208517168U true CN208517168U (en) 2019-02-19

Family

ID=65340738

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820820682.4U Expired - Fee Related CN208517168U (en) 2018-05-26 2018-05-26 Tall building life sewage treatment electric generator

Country Status (1)

Country Link
CN (1) CN208517168U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2022233242A1 (en) * 2021-05-06 2022-11-10 江苏科技大学 Adaptive seawater hydraulic system applied to pendulum-type wave energy power generation device

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2022233242A1 (en) * 2021-05-06 2022-11-10 江苏科技大学 Adaptive seawater hydraulic system applied to pendulum-type wave energy power generation device

Similar Documents

Publication Publication Date Title
CN208517168U (en) Tall building life sewage treatment electric generator
KR101046317B1 (en) Tidal power generation method and apparatus
CN108558091A (en) Tall building life sewage treatment electric generator
CN102536602A (en) Power generating device using sewage treatment plant tail water
CN204981459U (en) Waste water treatment adds in alkali and automatic control device
CN207512899U (en) A kind of vacuum sewage case apparatus
KR100914883B1 (en) System for eliminating radon in small-scale water supply establishments
CN217972891U (en) Frequency conversion electromagnetic descaling device for water purification and circulation pipeline
CN109095637A (en) A kind of sea water desalination and power-generating control system
CN209468250U (en) GEOTHERMAL WATER purification apparatus
CN205740625U (en) A kind of ocean fresh water processing system
CN106145261A (en) A kind of seawater desalination system
KR101503709B1 (en) Oxygen supply apparatus for restoration of tidal flat
RU2019141523A (en) ELECTRIC POWER PRODUCTION METHOD
RU2019138867A (en) ELECTRIC POWER PRODUCTION METHOD
RU2019140141A (en) ELECTRIC POWER PRODUCTION METHOD
RU2019138858A (en) ELECTRIC POWER PRODUCTION METHOD
RU2019138833A (en) ELECTRIC POWER PRODUCTION METHOD
RU2019141524A (en) ELECTRIC POWER PRODUCTION METHOD
RU2097598C1 (en) Power plant with energy carrier in closed cycle
RU2020106423A (en) ELECTRIC POWER PRODUCTION METHOD
RU2020108843A (en) ELECTRICITY PRODUCTION METHOD
RU2020102099A (en) ELECTRICITY PRODUCTION METHOD
RU2020106450A (en) ELECTRIC POWER PRODUCTION METHOD
RU2020106425A (en) ELECTRIC POWER PRODUCTION METHOD

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190219

Termination date: 20210526