CN208502313U - A kind of new steel plate covering increasing floor beam strength - Google Patents
A kind of new steel plate covering increasing floor beam strength Download PDFInfo
- Publication number
- CN208502313U CN208502313U CN201821146505.9U CN201821146505U CN208502313U CN 208502313 U CN208502313 U CN 208502313U CN 201821146505 U CN201821146505 U CN 201821146505U CN 208502313 U CN208502313 U CN 208502313U
- Authority
- CN
- China
- Prior art keywords
- floor beam
- installation frame
- steel plate
- ribs
- plate covering
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Floor Finish (AREA)
- Building Environments (AREA)
Abstract
The utility model discloses the new steel plate coverings that one kind can increase floor beam strength, including installation frame, mounting hole is offered on the installation frame, installation frame is day font structure, bindiny mechanism is connected with by ribs in the square groove of the installation frame, originally it can increase the new steel plate covering of floor beam strength, polytetrafluoroethylene film is equipped in the outside of skin panel, polytetrafluoroethylene film has the function of waterproof and breathable, to which to prevent, moisture immersion floor beam is interior and reduces the intensity of floor beam, substantially increase the service performance of the steel plate covering, ribs in installation frame square groove has two groups, two groups of ribs are arranged in a crossed manner, to to progress diagonal strut on the inside of installation frame, the integral strength of installation frame is improved using the stability of triangle, floor beam is carried out stablize support with this, thus to increase floor beam Intensity.
Description
Technical field
The utility model relates to mobile house technical field, specially a kind of new steel plate that can increase floor beam strength is covered
Skin.
Background technique
In the prior art: the patent of 106541994 A of application publication number CN discloses a kind of new structural car top side
Covering and preparation method thereof, the top side covering include on reinforcing rib, arc skin, gutter channel and window along seam allowance, the arc
Covering is the laminated structure of arc, is located at side edge at the top of car, and the reinforcing rib is located at top side covering upper surface and levels off to directly
The position of line is connected with the upper edge of the arc skin, the gutter channel using double sheets constitute, be located at car at the top of with
The intersection of vehicle window, and be connected with the lower edge of the arc skin, it is located at the lower section of the gutter channel on the window along seam allowance,
One steel plate is constituted by roll-in along seam allowance on the reinforcing rib, arc skin, gutter channel and window, however, there is presently no one
Kind can increase the new steel plate covering of floor beam strength, and it is impossible to meet use demands.
Utility model content
The technical problems to be solved in the utility model is to overcome existing defect, and floor beam strength can be increased by providing one kind
New steel plate covering, performance is high, and intensity is high, easy to assembly, and construction efficiency is high, can effectively solve the problems in background technique.
To achieve the above object, the utility model provides the following technical solutions: one kind can increase the novel of floor beam strength
Steel plate covering, including installation frame, mounting hole is offered on the installation frame, and installation frame is day font structure, the peace
Frame up frame square groove in bindiny mechanism is connected with by ribs, installation frame has skin panel, the illiteracy by rivet
Dermatotome is anticorrosion steel plate, and the outside of skin panel is equipped with polytetrafluoroethylene film, between adjacent installation frame by clamping mechanism into
Row clamping, clamping mechanism are fixed by retaining mechanism.
As a kind of optimal technical scheme of the utility model, the ribs in the installation frame square groove has two groups,
Two groups of ribs are arranged in a crossed manner.
As a kind of optimal technical scheme of the utility model, the bindiny mechanism includes anchor block, and anchor block is fixed on
On ribs, the anchor block is connect by joist anchor with floor beam.
As a kind of optimal technical scheme of the utility model, the clamping mechanism includes locating slot and fastener, fastening
Part is fixed on one end of installation frame, and the locating slot is provided with the other end of locating slot, and fastener and locating slot are clamped.
As a kind of optimal technical scheme of the utility model, the retaining mechanism includes locker and lockhole, and lockhole is opened
It is located on fastener, the locker is mounted on installation frame, locker and lockhole grafting.
Compared with prior art, the utility model has the beneficial effects that the new steel plate that floor beam strength originally can be increased covers
Skin is equipped with polytetrafluoroethylene film in the outside of skin panel, and polytetrafluoroethylene film has the function of waterproof and breathable, thus to prevent moisture
The intensity that floor beam is reduced in immersion floor beam, substantially increases the service performance of the steel plate covering, installation frame square groove
Interior ribs has two groups, and two groups of ribs are arranged in a crossed manner, to utilize triangle to diagonal strut is carried out on the inside of installation frame
Stability improve the integral strength of installation frame, floor beam is carried out to stablize support with this, thus to increase floor beam
Intensity, floor beam and anchor block are attached by bindiny mechanism, thus to increase the company of floor beam Yu the steel plate covering
Intensity is connect, two groups of installation frames are assembled by clamping mechanism, it is easy to assembly, substantially increase mobile house construction
Efficiency.
Detailed description of the invention
FIG. 1 is a schematic structural view of the utility model;
Fig. 2 is the utility model side structure schematic diagram.
In figure: 1 installation frame, 2 mounting holes, 3 rivets, 4 clamping mechanisms, 5 locating slots, 6 lockers, 7 retaining mechanisms, 8 are gathered
Tetrafluoroethylene, 9 skin panels, 10 ribs, 11 joist anchors, 12 anchor blocks, 13 lockholes, 14 fasteners, 15 bindiny mechanisms.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model
Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole
Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work
Every other embodiment obtained, fall within the protection scope of the utility model.
The utility model provides a kind of technical solution referring to FIG. 1-2: one kind can increase the new steel plate of floor beam strength
Covering, including installation frame 1 offer mounting hole 2 on installation frame 1, and installation frame 1 is day font structure, installation frame 1
Bindiny mechanism 15 is connected with by ribs 10 in square groove, installation frame 1 has skin panel 9, skin panel 9 by the riveting of rivet 3
Outside for anticorrosion steel plate, skin panel 9 is equipped with polytetrafluoroethylene film 8, and polytetrafluoroethylene film 8 has the function of waterproof and breathable, from
And the intensity of floor beam is reduced preventing moisture from immersing in floor beam, the service performance of the steel plate covering is substantially increased, phase
It is clamped between adjacent installation frame 1 by clamping mechanism 4, clamping mechanism 4 is fixed by retaining mechanism 7.
Ribs 10 in 1 square groove of installation frame has two groups, and two groups of ribs 10 are arranged in a crossed manner, thus to installation frame
1 inside carries out diagonal strut, and the integral strength of installation frame 1 is improved using the stability of triangle, is come with this to floor beam
It carries out stablizing support, thus to increase the intensity of floor beam.
Bindiny mechanism 15 includes anchor block 12, and anchor block 12 is fixed on ribs 10, anchor block 12 by joist anchor 11 with
Floor beam connection, joist anchor 11 is protruded into floor beam, to be attached to floor beam and anchor block 12, thus to increase floor
The bonding strength of beam and the steel plate covering.
Clamping mechanism 4 includes locating slot 5 and fastener 14, and fastener 14 is fixed on one end of installation frame 1, locating slot 5
It is provided with the other end of locating slot 5, fastener 14 and locating slot 5 are clamped, are clamped by fastener 14 and locating slot 5 to two groups of peaces
The frame 1 that frames up is assembled, easy to assembly, substantially increases the efficiency of mobile house construction.
Retaining mechanism 7 includes locker 6 and lockhole 13, and lockhole 13 is provided on fastener 14, and locker 6 is mounted on installation
On frame 1, locker 6 and 13 grafting of lockhole are fixed two groups of installation frames 1 with 13 grafting of lockhole by locker 6,
It is fixed, it ensure that the bonding strength between two groups of installation frames 1.
When in use: ribs 10 is arranged in a crossed manner, to utilize triangle to diagonal strut is carried out on the inside of installation frame 1
Stability improve the integral strength of installation frame 1.
Joist anchor 11 is protruded into floor beam, to be attached to floor beam and anchor block 12.
Two groups of installation frames 1 are assembled by fastener 14 and the clamping of locating slot 5.
Two groups of installation frames 1 are fixed with 13 grafting of lockhole by locker 6.
The utility model is equipped with polytetrafluoroethylene film 8 in the outside of skin panel 9, and polytetrafluoroethylene film 8 has waterproof and breathable
Function substantially increases the use of the steel plate covering to reduce the intensity of floor beam preventing moisture from immersing in floor beam
Performance, the ribs 10 in 1 square groove of installation frame have two groups, and two groups of ribs 10 are arranged in a crossed manner, thus in installation frame 1
Side carries out diagonal strut, and the integral strength of installation frame 1 is improved using the stability of triangle, to carry out floor beam with this
Stablize support, so that floor beam and anchor block 12 are attached by bindiny mechanism 15 to increase the intensity of floor beam, thus
Increase the bonding strength of floor beam Yu the steel plate covering, two groups of installation frames 1 is assembled by clamping mechanism 4, group
Dress is convenient, substantially increases the efficiency of mobile house construction.
While there has been shown and described that the embodiments of the present invention, for the ordinary skill in the art,
It is understood that these embodiments can be carried out with a variety of variations in the case where not departing from the principles of the present invention and spirit, repaired
Change, replacement and variant, the scope of the utility model is defined by the appended claims and the equivalents thereof.
Claims (5)
1. one kind can increase the new steel plate covering of floor beam strength, including installation frame (1), it is characterised in that: the installation
It is offered on frame (1) mounting hole (2), installation frame (1) is day font structure, is led in the square groove of the installation frame (1)
It crosses ribs (10) to be connected with bindiny mechanism (15), installation frame (1) has skin panel (9), the covering by rivet (3) riveting
Plate (9) is anticorrosion steel plate, and the outside of skin panel (9) is equipped with polytetrafluoroethylene film (8), passes through between adjacent installation frame (1)
Clamping mechanism (4) is clamped, and clamping mechanism (4) is fixed by retaining mechanism (7).
2. the new steel plate covering that one kind according to claim 1 can increase floor beam strength, it is characterised in that: the peace
The ribs (10) in frame (1) square groove that frames up has two groups, and two groups of ribs (10) are arranged in a crossed manner.
3. the new steel plate covering that one kind according to claim 1 can increase floor beam strength, it is characterised in that: the company
Connection mechanism (15) includes anchor block (12), and anchor block (12) is fixed on ribs (10), and the anchor block (12) passes through joist anchor
(11) it is connect with floor beam.
4. the new steel plate covering that one kind according to claim 1 can increase floor beam strength, it is characterised in that: the card
Connection mechanism (4) includes locating slot (5) and fastener (14), and fastener (14) is fixed on one end of installation frame (1), the positioning
Slot (5) is provided with the other end of locating slot (5), and fastener (14) and locating slot (5) are clamped.
5. the new steel plate covering that one kind according to claim 1 can increase floor beam strength, it is characterised in that: the lock
Tight mechanism (7) includes locker (6) and lockhole (13), and lockhole (13) is provided on fastener (14), locker (6) installation
On installation frame (1), locker (6) and lockhole (13) grafting.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821146505.9U CN208502313U (en) | 2018-07-19 | 2018-07-19 | A kind of new steel plate covering increasing floor beam strength |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821146505.9U CN208502313U (en) | 2018-07-19 | 2018-07-19 | A kind of new steel plate covering increasing floor beam strength |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208502313U true CN208502313U (en) | 2019-02-15 |
Family
ID=65289705
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201821146505.9U Expired - Fee Related CN208502313U (en) | 2018-07-19 | 2018-07-19 | A kind of new steel plate covering increasing floor beam strength |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208502313U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110409860A (en) * | 2019-07-26 | 2019-11-05 | 中城科泽工程设计有限责任公司 | A kind of reconstruction structure and its remodeling method in old house |
-
2018
- 2018-07-19 CN CN201821146505.9U patent/CN208502313U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110409860A (en) * | 2019-07-26 | 2019-11-05 | 中城科泽工程设计有限责任公司 | A kind of reconstruction structure and its remodeling method in old house |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP4015294B2 (en) | Solar panel installation equipment | |
CN208502313U (en) | A kind of new steel plate covering increasing floor beam strength | |
CN209082844U (en) | A kind of roof lighting plate location structure for interior decoration | |
CN208899760U (en) | A kind of connection system of metal Roof decorative panel | |
CN208748981U (en) | A kind of wind resistance roofing reinforcement system | |
CN207045684U (en) | Plane airfoil combines rib | |
CN208202275U (en) | A kind of photovoltaic bracket top structure suitable for steel construction | |
CN217116610U (en) | Cabinet body, cabinet body with hoisting function and cabinet body with cabinet combining function | |
CN215563661U (en) | Building curtain wall waterproof construction | |
CN210789673U (en) | Laser welding room wallboard section bar | |
CN208563572U (en) | Construction steel structure | |
CN209454878U (en) | A kind of lightweight passenger carriage aluminum alloy roof frame structure | |
CN208486448U (en) | A kind of autoclaved aerated concrete slab reinforced bar fastener | |
CN212386424U (en) | Wingspan compartment door waterproof top structure | |
CN205591439U (en) | Metal roofing the annular clamped structure | |
CN215168337U (en) | Detachable roof glass maintenance purlin | |
CN108842969A (en) | A kind of the connection system and its operating method of metal Roof decorative panel | |
CN220666704U (en) | Novel triggering type reinforced wind-resistant fixing seat | |
CN214834158U (en) | High-grade aluminum alloy gutter roof assembly structure | |
CN204847697U (en) | Toeguard at bottom of sedan -chair of car | |
CN213741827U (en) | Edge sealing beam structure | |
CN217711328U (en) | Steel truss auxiliary ceiling device | |
CN219732485U (en) | Novel frame is hung to structure collection | |
CN218814758U (en) | Combined top rib | |
CN216196119U (en) | Photovoltaic building integrated roof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20190215 Termination date: 20190719 |
|
CF01 | Termination of patent right due to non-payment of annual fee |