CN208494721U - A kind of double-edged sword manufacture color painting equipment - Google Patents

A kind of double-edged sword manufacture color painting equipment Download PDF

Info

Publication number
CN208494721U
CN208494721U CN201821025355.6U CN201821025355U CN208494721U CN 208494721 U CN208494721 U CN 208494721U CN 201821025355 U CN201821025355 U CN 201821025355U CN 208494721 U CN208494721 U CN 208494721U
Authority
CN
China
Prior art keywords
double
edged sword
air brushing
brushing room
room
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201821025355.6U
Other languages
Chinese (zh)
Inventor
梅景霞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Longquan Jingying Technology Co Ltd
Original Assignee
Longquan Jingying Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Longquan Jingying Technology Co Ltd filed Critical Longquan Jingying Technology Co Ltd
Priority to CN201821025355.6U priority Critical patent/CN208494721U/en
Application granted granted Critical
Publication of CN208494721U publication Critical patent/CN208494721U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Spray Control Apparatus (AREA)

Abstract

The utility model discloses a kind of double-edged sword to manufacture color painting equipment, including pedestal, paint box and air brushing room, the left side of air brushing chamber interior is equipped with infrared ray calibrator, infrared ray calibrator is fixedly connected with air brushing room, the right side of air brushing chamber interior is equipped with baking lamp, baking lamp is fixedly connected with air brushing room, the bottom of paint pipeline is sent to be equipped with spray head, spray head is connected with paint pipeline insertion is sent, infrared ray calibrator can calibrate the double-edged sword position in double-edged sword placement plate, and by control driving motor and hydraulic press double-edged sword placement plate is displaced, after being moved to designated position to double-edged sword, spray painting can be used to carry out air brushing to double-edged sword, so that being sprayed to double-edged sword more accurate, a fairly large number of spray head is additionally provided in air brushing room, it can more quickly paint to spraying position, after the completion of painting to double-edged sword, baking lamp can be to the portion of spraying Position carries out heated baking, accelerates the setting rate of spray painting, effectively raises the working efficiency of paint spraying apparatus.

Description

A kind of double-edged sword manufacture color painting equipment
Technical field
The utility model relates to the technical field of spray drawing apparatus, specially a kind of double-edged sword manufactures color painting equipment.
Background technique
Spraying equipment is after reform and opening-up, is the production in the more and more common environment of the development automation of industrial technology Object.As the degree of automation is higher and higher, the application of spray-painting production line is also more and more extensive, and is deep into the more of national economy A field.Now spraying equipment in the market can be divided into according to the degree of automation: manual spray equipment, semi-automatic spraying equipment and complete Three kinds of automatic spraying equipment, with the development of industrial technology, simple craft can no longer meet the demand in market, spraying by Develop by hand to industrial automation direction, and the degree automated is higher and higher, so the application of spray-painting production line is also more next It is more extensive, and it is deep into the multiple fields of national economy.After China especially reforms and opens up to the outside world, spraying equipment achieves considerable Development.
Existing double-edged sword manufacture color painting equipment leakproofness is poor, is easy so that the dust in outside air makes lacquer painting At large effect, and existing double-edged sword manufacture color painting equipment, after painting to double-edged sword, heating is slower, and lacquer painting solidification is slow, Cause process time longer, the working efficiency of equipment is lower, cannot bring biggish help, existing spray-painting plant pair When double-edged sword is painted, can not to spray painting position calibrate, be easy to cause spray painting error, cause the final product quality produced compared with Difference is not able to satisfy the demand of people.
So how to design a kind of double-edged sword manufacture color painting equipment, becoming us will currently be solved the problems, such as.
Utility model content
The purpose of this utility model is to provide a kind of double-edged sword to manufacture color painting equipment, to solve in above-mentioned background technique The problems such as leakproofness of proposition is poor, working efficiency is lower and spray painting error is larger.
To achieve the above object, the utility model provides the following technical solutions: a kind of double-edged sword manufacture color painting equipment, packet Pedestal, paint box and air brushing room are included, the left side of the base top is equipped with paint box, the paint box and the fixed company of the pedestal It connects, the right side of the base top is equipped with air brushing room, and the air brushing room is fixedly connected with the base, the right side of the paint box Equipped with paint pipeline is sent, described send paints pipeline and paint box insertion connection, and described send paints pipeline and air brushing room insertion Connection, the bottom for sending paint pipeline are equipped with spray head, and the spray head send paint pipeline insertion to connect with described, the right side of the air brushing room Side is equipped with isolating door, and the isolating door is flexibly connected with the air brushing room, and the bottom of the air brushing chamber interior is provided with double-edged sword and puts Plate is set, the double-edged sword placement plate and air brushing room insertion connect, and the top of the double-edged sword placement plate is equipped with double-edged sword fixed frame, institute It states double-edged sword fixed frame to be fixedly connected with the double-edged sword placement plate, the inside of the double-edged sword placement plate is equipped with driving motor, the drive Dynamic motor and double-edged sword placement plate insertion connect, and the bottom of the double-edged sword placement plate is equipped with pulley, the pulley and the treasured Sword placement plate is flexibly connected, and the top of the chassis interior is equipped with sliding rail, and the sliding rail is fixedly connected with the base, the bottom Intermediate position inside seat is equipped with hydraulic press, and the hydraulic press and pedestal insertion connect, and the top of the hydraulic press is equipped with Lifting column, the lifting column are flexibly connected with the hydraulic press.
Further, the front of the air brushing room is equipped with exhaust fan, the exhaust fan and the air brushing room through connection.
Further, the right side of the air brushing chamber interior is equipped with baking lamp, the fixed company of the baking lamp and the air brushing room It connects.
Further, the left side of the air brushing chamber interior be equipped with infrared ray calibrator, the infrared ray calibrator with it is described Air brushing room is fixedly connected.
Further, the top of the air brushing chamber interior is equipped with heat-insulated top layer, and the heat-insulated top layer and the air brushing room are embedding Enter connection.
Further, the air brushing room is used is made with the good dark glass of shading performance.
Further, there are five the spray head settings.
Compared with prior art, the utility model has the beneficial effects that this kind of double-edged sword manufacture color painting equipment improves The disadvantage that existing product leakproofness is poor, working efficiency is lower and spray painting error is larger, compared to existing product, the utility model double-edged sword Manufacture color painting equipment is provided with isolating door and air brushing room, and when carrying out air brushing to double-edged sword, double-edged sword is passed through isolating door first It being sent in air brushing room, then isolating door is closed, isolating door has preferable leakproofness, and air brushing room is isolated from the outside and is come, Double-edged sword would not be interfered in air brushing room by the fugitive dust in outside air, improve the quality of converted products, put double-edged sword Enter to after air brushing room, infrared ray calibrator, the double-edged sword position in double-edged sword placement plate can be calibrated, and passes through control driving electricity Machine and hydraulic press are displaced double-edged sword placement plate, after being moved to designated position to double-edged sword, that is, can be used spray painting to double-edged sword into Row air brushing, so that it is more accurate to double-edged sword spraying, it is additionally provided with a fairly large number of spray head in air brushing room, is sprayed to double-edged sword When paint, can more quickly it paint to spraying position, after the completion of painting to double-edged sword, baking lamp can be to the position of spraying Heated baking is carried out, accelerates the setting rate of spray painting, effectively raises the working efficiency of paint spraying apparatus, bring larger Help.
Detailed description of the invention
Fig. 1 is the overall structure diagram of the utility model;
Fig. 2 is the paint box diagrammatic cross-section of the utility model;
Fig. 3 is the air brushing room diagrammatic cross-section of the utility model.
1, pedestal in figure, 2, paint box, 201, send paint pipeline, 202, spray head, 3, air brushing room, 301, exhaust fan, 302, every From door, 303, infrared ray calibrator, 304, baking lamp, 305, heat-insulated top layer, 306, hydraulic press, 307, lifting column, 4, double-edged sword puts Set plate, 401, driving motor, 402, double-edged sword fixed frame, 403, pulley, 404, sliding rail.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work Every other embodiment obtained, fall within the protection scope of the utility model.
Fig. 1-3 is please referred to, the utility model provides a kind of technical solution: a kind of double-edged sword manufacture color painting equipment, including The left side of pedestal 1, paint box 2 and air brushing room 3,1 top of pedestal is equipped with paint box 2, and paint box 2 is fixedly connected with pedestal 1, pedestal The right side at 1 top is equipped with air brushing room 3, and air brushing room 3 is fixedly connected with pedestal 1, and the right side of paint box 2, which is equipped with, send paint pipeline 201, send It paints pipeline 201 and the insertion of paint box 2 connects, and paint pipeline 201 and the insertion of air brushing room 3 is sent to connect, the bottom of paint pipeline 201 is sent to set Have a spray head 202, spray head 202 and the paint insertion of pipeline 201 sent to connect, the right side of air brushing room 3 is equipped with isolating door 302, isolating door 302 with Air brushing room 3 is flexibly connected, and the bottom inside air brushing room 3 is provided with double-edged sword placement plate 4, and double-edged sword placement plate 4 and the insertion of air brushing room 3 connect It connects, the top of double-edged sword placement plate 4 is equipped with double-edged sword fixed frame 402, and double-edged sword fixed frame 402 is fixedly connected with double-edged sword placement plate 4, double-edged sword The inside of placement plate 4 is equipped with driving motor 401, and driving motor 401 and the insertion of double-edged sword placement plate 4 connect, the bottom of double-edged sword placement plate 4 Portion is equipped with pulley 403, and pulley 403 is flexibly connected with double-edged sword placement plate 4, and the top inside pedestal 1 is equipped with sliding rail 404, sliding rail 404 It is fixedly connected with pedestal 1, the intermediate position inside pedestal 1 is equipped with hydraulic press 306, and hydraulic press 306 and the insertion of pedestal 1 connect, liquid The top of depressor 306 is equipped with lifting column 307, and lifting column 307 is flexibly connected with hydraulic press 306.
Further, the front of air brushing room 3 is equipped with exhaust fan 301, exhaust fan 301 and air brushing room 3 through connection, exhaust fan 301 can give out heat extra in air brushing room 3, prevent the excessively high damage internal structure of heat, and improve equipment uses the longevity Life.
Further, the right side inside air brushing room 3 is equipped with baking lamp 304, and baking lamp 304 is fixedly connected with air brushing room 3, bakes Heated baking can be carried out to the position of spraying by painting lamp 304, accelerated the setting rate of spray painting, effectively raised the work of this product Efficiency.
Further, the left side inside air brushing room 3 is equipped with infrared ray calibrator 303, infrared ray calibrator 303 and air brushing room 3 are fixedly connected, and infrared ray calibrator 303 can carry out school to double-edged sword position by control driving motor 401 and hydraulic press 306 Standard, so that being sprayed to double-edged sword more accurate.
Further, the top inside air brushing room 3 is equipped with heat-insulated top layer 305, and heat-insulated top layer 305 connects with the insertion of air brushing room 3 It connects, heat-insulated top layer 305, which can separate the temperature inside air brushing room 3 with the external world, prevents high temperature from damaging to staff, rises It is acted on to safeguard protection.
Further, using having shading performance, good dark glass is made for air brushing room 3, prevents extraneous light to spray painting It causes light reaction to influence, reduces unnecessary influence, and staff can also improve dark glass and observe internal spray painting Situation brings biggish help.
Further, spray head 202 setting there are five, more spray head work at the same time can simultaneously to each position of double-edged sword into Row spray head effectively raises the working efficiency of this product.
Working principle: staff overhauls this kind of double-edged sword manufacture color painting equipment first, prevents equipment from occurring Color painting equipment is moved to designated place by damaged or failure, the personnel that proceed with one's work, and Spraying-drawing apparatus is even being connected with the mains, When carrying out air brushing to double-edged sword, people first open isolating door 302, and double-edged sword is placed on double-edged sword fixed frame 402, then will be every It is closed from door 302, guarantees to be isolated from the outside inside air brushing room 3, the infrared ray calibrator 303 inside air brushing room 3 can pass through control Driving motor 401 and hydraulic press 306 calibrate double-edged sword position, so that double-edged sword placement plate 4 is by pulley 403 in sliding rail 404 In move left and right, hydraulic press 306 control lifting column 307 double-edged sword placement plate 4 is moved to suitable height, then people are in paint Room 2 will need the paint vehicle sprayed to carry out toning processing, and then spray painting passes through spray by sending paint pipeline 301 to be transported at spray head 202 The position that first 202 pairs of double-edged sword need to spray carries out color spray, and after the completion of color spray, the baking lamp 304 being equipped with can dry spray painting Dry, so that spray painting solidification faster, the heat that it is extra in air brushing room 3 that the exhaust fan 301 being equipped with can also shed prevents heat excessively high Internal structure is damaged, here it is kind of a working principles for double-edged sword manufacture color painting equipment.
While there has been shown and described that the embodiments of the present invention, for the ordinary skill in the art, It is understood that these embodiments can be carried out with a variety of variations in the case where not departing from the principles of the present invention and spirit, repaired Change, replacement and variant, the scope of the utility model is defined by the appended claims and the equivalents thereof.

Claims (7)

1. a kind of double-edged sword manufactures color painting equipment, including pedestal (1), paint box (2) and air brushing room (3), it is characterised in that: institute It states the left side at the top of pedestal (1) and is equipped with paint box (2), the paint box (2) is fixedly connected with the pedestal (1), the pedestal (1) right side at the top of is equipped with air brushing room (3), and the air brushing room (3) is fixedly connected with the pedestal (1), the paint box (2) Right side, which is equipped with, send paint pipeline (201), described that paint pipeline (201) and the paint box (2) insertion is sent to connect, and described send paint pipeline (201) it is connected with the air brushing room (3) insertion, the bottom for sending paint pipeline (201) is equipped with spray head (202), the spray head (202) paint pipeline (201) insertion is sent to connect with described, the right side of the air brushing room (3) is equipped with isolating door (302), the isolation Door (302) is flexibly connected with the air brushing room (3), and the internal bottom of the air brushing room (3) is provided with double-edged sword placement plate (4), institute It states double-edged sword placement plate (4) and the air brushing room (3) insertion connects, the top of the double-edged sword placement plate (4) is equipped with double-edged sword fixed frame (402), the double-edged sword fixed frame (402) is fixedly connected with the double-edged sword placement plate (4), the inside of the double-edged sword placement plate (4) Equipped with driving motor (401), the driving motor (401) and the double-edged sword placement plate (4) insertion are connected, the double-edged sword placement plate (4) bottom is equipped with pulley (403), and the pulley (403) is flexibly connected with the double-edged sword placement plate (4), in the pedestal (1) The top in portion is equipped with sliding rail (404), and the sliding rail (404) is fixedly connected with the pedestal (1), in pedestal (1) inside Between position be equipped with hydraulic press (306), the hydraulic press (306) and the pedestal (1) insertion connect, the hydraulic press (306) Top is equipped with lifting column (307), and the lifting column (307) is flexibly connected with the hydraulic press (306).
2. a kind of double-edged sword according to claim 1 manufactures color painting equipment, it is characterised in that: the air brushing room (3) Front is equipped with exhaust fan (301), and the exhaust fan (301) and the air brushing room (3) are through connection.
3. a kind of double-edged sword according to claim 1 manufactures color painting equipment, it is characterised in that: in the air brushing room (3) The right side in portion is equipped with baking lamp (304), and the baking lamp (304) is fixedly connected with the air brushing room (3).
4. a kind of double-edged sword according to claim 1 manufactures color painting equipment, it is characterised in that: in the air brushing room (3) The left side in portion is equipped with infrared ray calibrator (303), and the infrared ray calibrator (303) is fixedly connected with the air brushing room (3).
5. a kind of double-edged sword according to claim 1 manufactures color painting equipment, it is characterised in that: in the air brushing room (3) The top in portion is equipped with heat-insulated top layer (305), and the heat-insulated top layer (305) and the air brushing room (3) insertion connect.
6. a kind of double-edged sword according to claim 1 manufactures color painting equipment, it is characterised in that: the air brushing room (3) is adopted It is made of with the good dark glass of shading performance.
7. a kind of double-edged sword according to claim 1 manufactures color painting equipment, it is characterised in that: the spray head (202) sets There are five setting.
CN201821025355.6U 2018-06-30 2018-06-30 A kind of double-edged sword manufacture color painting equipment Expired - Fee Related CN208494721U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821025355.6U CN208494721U (en) 2018-06-30 2018-06-30 A kind of double-edged sword manufacture color painting equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821025355.6U CN208494721U (en) 2018-06-30 2018-06-30 A kind of double-edged sword manufacture color painting equipment

Publications (1)

Publication Number Publication Date
CN208494721U true CN208494721U (en) 2019-02-15

Family

ID=65281957

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821025355.6U Expired - Fee Related CN208494721U (en) 2018-06-30 2018-06-30 A kind of double-edged sword manufacture color painting equipment

Country Status (1)

Country Link
CN (1) CN208494721U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110962467A (en) * 2019-11-30 2020-04-07 江苏旭正信息科技有限公司 Equipment suitable for rubber pipeline surface marking printing

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110962467A (en) * 2019-11-30 2020-04-07 江苏旭正信息科技有限公司 Equipment suitable for rubber pipeline surface marking printing

Similar Documents

Publication Publication Date Title
CN208494721U (en) A kind of double-edged sword manufacture color painting equipment
CN104358494A (en) Automatic sealing door
CN111648167A (en) Full-automatic rotary paper pulp molding hot-pressing and shaping integrated production equipment
CN204751494U (en) Glass substrate carries special elevating gear
CN203610254U (en) Automatic cleaning device of powder spraying gun
CN203100365U (en) Catalyst drying device
CN204009281U (en) A kind of on-line automatic defoamer of production line that connects
CN204602506U (en) Enamel cooking utensil automatic spray-paint device
CN218003590U (en) Pressure sensor chip test fixture
CN206787202U (en) A kind of multilayer electrical heating type Snakegourd Fruit drying plant
CN206763246U (en) A kind of automatic application product line of chain saw guide plate
CN205928144U (en) Glass anti -slip treatment machine
CN212759346U (en) Spraying device for paint baking process
CN108993814A (en) A kind of optical-fiber laser lamp pattern spray-painting plant
CN114226093A (en) Spray painting drying device for processing resin artware and processing method thereof
CN211726322U (en) Pot inner container spraying system
CN204100711U (en) A kind of follow-on sheet material baking room
CN207521262U (en) Continuous workpiece applies glue solidifying equipment
CN111807041A (en) Automatic go up hypoplastron and paint spraying flow production line
CN106216158A (en) A kind of environmental-protecting and high-efficient type paint spraying apparatus
CN208032965U (en) A kind of vehicle body profiling ion wind purge system
CN208332880U (en) Grinding wheel hardening cabinet device for pilling
CN220258560U (en) Coloring device for robot processing
CN205988845U (en) Changeable full-automatic cleaning powder spraying chamber
CN205887368U (en) Be applied to jewelry processing's baking finish device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190215

Termination date: 20200630

CF01 Termination of patent right due to non-payment of annual fee