CN208444466U - A kind of civil engineering account valuation practice device - Google Patents

A kind of civil engineering account valuation practice device Download PDF

Info

Publication number
CN208444466U
CN208444466U CN201820045467.1U CN201820045467U CN208444466U CN 208444466 U CN208444466 U CN 208444466U CN 201820045467 U CN201820045467 U CN 201820045467U CN 208444466 U CN208444466 U CN 208444466U
Authority
CN
China
Prior art keywords
label
box
fixed
civil engineering
box body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820045467.1U
Other languages
Chinese (zh)
Inventor
张晓芳
李健
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201820045467.1U priority Critical patent/CN208444466U/en
Application granted granted Critical
Publication of CN208444466U publication Critical patent/CN208444466U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Packaging Of Annular Or Rod-Shaped Articles, Wearing Apparel, Cassettes, Or The Like (AREA)

Abstract

A kind of civil engineering account valuation practice device, including box body and drawer box, shaft insertion tube is respectively fixed at four, the surface angle of box body, tag board and the upper and lower ends shaft for drilling clipboard are respectively inserted in ipsilateral upper lower rotary shaft insertion tube, the a plurality of label mounting groove being parallel to each other is had in tag board, the magnet perforation of hollow out is also respectively provided in every strip label mounting groove, label fixed magnet piece is embedded in box surface immediately below at magnet perforation respectively, the back side of label box is embedded with label fixed iron piece, label box is correspondingly placed in each label mounting groove, and the label fixed iron piece at the back side is close to corresponding label fixed magnet piece, multiple label box storage chambers are separated by partition respectively inside drawer box, one pen tool storage chamber and paper storage chamber.The utility model is conducive to sufficient time more efficiently carrying out civil engineering account valuation rehearsal in the rehearsal for calculating, arranging, classifying in cost.

Description

A kind of civil engineering account valuation practice device
Technical field
The utility model relates to a kind of civil engineering articles, specifically a kind of civil engineering account valuation rehearsal dress It sets.
Background technique
Civil engineering is a kind of natural subject of university.The basic reason of all kinds of civil engineering subjects is grasped in special culture By and basic knowledge, can building construction, hypogee, road, tunnel, bridge construction, power station, harbour and offshore structure with Facility.Civil engineering cost, that is, civil engineering for example building construction, hypogee, road, tunnel construction price.Civil engineering meter The three elements of valence: amount, is taken valence.Civil engineering cost, which refers to, carries out the full payment that a certain engineering construction is spent, in core Appearance is investment estimate, estimation per design, amendment budgetary estimate, working drawing budget, Engineering Settlement, budget needed for the completion of projects etc..The master of project cost It wants task: according to drawing, quota and bill code, calculating cost included in engineering such as artificial, material and equipment, applies The use of work equipment, enterprise administration expense, measure expense, set-fee, profit and tax etc..
Construction engineering cost needs to carry out according to the budget process of regulation, needs to study hard and practice repeatedly could slap It holds, if account valuation inaccuracy will lead to waste man power and money, and existing civil engineering account valuation practice device volume ratio It is huger, it is not readily portable to use at any time generally by structure compositions such as complicated computer, bodies, it is used for the ease of carrying Dedicated cost calculus book, using cost calculus book, the content for needing to write is more, such as more commonly used some materials, equipment, The title of tool is also required to fill in, and will occupy a large amount of rehearsal time in this way, and more times is unfavorable for be used in cost It calculates in rehearsal.Come therefore, it is necessary to design device that is a kind of portable and being more suitable for civil engineering account valuation rehearsal Improve the professional skill of civil engineering cost person.
Utility model content
To solve the above problems, the purpose of the utility model is to provide a kind of civil engineering account valuation practice devices.
The utility model to achieve the above object, open by a kind of civil engineering account valuation practice device, including one end setting Mouthful box body and be inserted in drawable drawer box in box body, multiple label boxes storages are separated by partition respectively inside drawer box Chamber, a pen tool storage chamber and paper storage chamber, pen tool storage chamber can be used for storing the pen tool for writing, convenient for the receipts of pen tool It receives, paper storage is intracavitary, can be used for storing the paper that rehearsal uses, and can store more paper, meets and drill a large amount of books Write use, the intracavitary drawing that can be also used for storage Construction of Civil Engineering of paper storage, the bill of materials, calculating calculator Deng being preferably adapted to carry and use at any time, the two sides up and down of box body are screwed with respectively through box side wall and drawer is close in inner end The drawer box fixing bolt of box lateral wall, when carrying, which tightens drawer box fixing bolt, to prevent drawer box from extracting out, drawer box It is fixed with knob on lateral wall, when needing to pull out drawer box, unscrews drawer box fixing bolt, drawer can be pulled out by pulling knob Box;
Shaft insertion tube is respectively fixed at four, the surface angle of box body, tag board and the upper and lower ends for drilling clipboard turn Axis is respectively inserted in ipsilateral upper lower rotary shaft insertion tube, can make in this way tag board and drill clipboard box body surface pivots, The a plurality of label mounting groove being parallel to each other is had in tag board, and the magnetic of hollow out is also respectively provided in every strip label mounting groove Iron perforation, at magnet perforation immediately below box surface in be embedded with label fixed magnet piece respectively, the back side of label box is embedded with mark Fixed iron piece is signed, label box is correspondingly placed in each label mounting groove, and the label fixed iron piece at the back side and corresponding label Fixed magnet piece is close to, and the writing slot that be then respectively set hollow out on clipboard and item number is greater than label mounting groove, label are drilled Box front transparent;
With the above arrangement, can write common civil engineering material, equipment, reference book on label, and label is inserted Enter into label box, when carrying out cost rehearsal every time, without writing these civil engineering materials, equipment, tool etc. again Title directly uses and is placed in corresponding label mounting groove, greatly reduces the number of words write needed for rehearsal in this way, Be conducive to sufficient time more efficiently carrying out civil engineering account valuation in the rehearsal for calculating, arranging, classifying in cost Rehearsal.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the utility model;
Fig. 2 is the perspective view of the utility model label box.
Specific embodiment
As shown in Fig. 1 Fig. 2, a kind of civil engineering account valuation practice device is arranged the box body 1 of opening including one end and inserts The drawable drawer box 2 in box body 1, the two sides up and down of box body 1 are screwed with respectively through 1 side wall of box body and drawer box is close in inner end The drawer box fixing bolt 3 of 2 lateral walls is fixed with knob 4 on the lateral wall of drawer box 2, distinguishes at four, the surface angle of box body 1 It is fixed with shaft insertion tube 5, tag board 6 and the upper and lower ends shaft 8 for drilling clipboard 7 are respectively inserted in ipsilateral upper lower rotary shaft and insert In cylinder 5, a plurality of label mounting groove 9 being parallel to each other is had in tag board 6, is also respectively set in every strip label mounting groove 9 Have hollow out magnet perforation 10, magnet perforation 10 at immediately below 1 surface of box body in respectively be embedded with label fixed magnet piece 11, mark The back side for signing box 25 is embedded with label fixed iron piece 12, and label box 25 is correspondingly placed in each label mounting groove 9, and the mark at the back side Label fixed iron piece 12 is close to corresponding label fixed magnet piece 11, be then respectively set hollow out on rehearsal clipboard 7 and item number Greater than the writing slot 13 of label mounting groove 9, the horizontal length for drilling clipboard 7 is greater than the horizontal length of tag board 6, equally, book The horizontal length for writing slot 13 is greater than the horizontal length of label mounting groove 9, is separated into respectively by partition 14 inside drawer box 2 multiple 15, pen tool storage chambers 16 of label box storage chamber and paper storage chamber 17.
For preferably fixed and opening tag board 6, rehearsal clipboard 7, the upper and lower ends of tag board 6 are respectively fixed with mark Plate fixed magnet 18 is signed, every piece of tag board fixed magnet 18 is tightly attached to the tag board fixed iron piece 19 that 1 surface of box body is embedded with respectively On, the upper and lower ends of rehearsal clipboard 7 are then respectively fixed with the clipboard fixed magnet 20 of strip, the fixed magnetic of every piece of clipboard Iron 20 is tightly attached to respectively on the strip clipboard fixed iron piece 21 that 1 surface of box body is embedded with.
In order to preferably clamp the label box 25 being placed in label box storage chamber 15, the left and right of each label box storage chamber 15 It is posted respectively on the side wall of two sides and clamps sponge block 22, place multiple label boxes closely vertically in label box storage chamber 15 25, and the clamping sponge block 22 of the left and right sides is made to be in compressive state, clamping sponge block 22 in this way can play buffer function Meanwhile and being capable of clamping label box 25.
For the ease of the label insertion and taking-up of strip, the front of label box 25 is covered with transparent plastic sheet 23, and marks 23 edge of transparent plastic sheet at the label place open at one end of box 25 is provided with the arc notch 24 being recessed inwardly.
Utility model works principle: in use, drawer box 2 is pulled out, taking out paper, and Unscrew drills clipboard 7, Paper is placed on 1 surface of box body at rehearsal clipboard 7, paper size requires the size for being less than rehearsal clipboard 7, then closes Experienced clipboard 7 is costared to push down paper, according to engineering drawing, inventory etc., selection needs to carry out cost calculating and writing material, The label box 25 of equipment, tool, and label box 25 is put into corresponding label mounting groove 9, eliminate write engineering material, The time of equipment, tool, and these labels can according to need arbitrary arrangement, and can reuse, for better area Point a variety of materials, equipment, tool can also paste the photograph of the material of scaled down version, equipment, tool on the label in label box 25 Piece, or be distinguish using the font of different colours, it more can effectively prevent the generation for wrong row occur.
Certainly, the above description is not intended to limit the present invention, and the utility model is also not limited to the example above, this The those of ordinary skill of technical field, in the essential scope of the utility model, variation, change, addition or the replacement made, all It should belong to the protection scope of the utility model.

Claims (5)

1. a kind of civil engineering account valuation practice device, it is characterised in that: the box body (1) of opening is arranged including one end and is inserted in Drawable drawer box (2) in box body (1), the two sides up and down of box body (1) are screwed with respectively through box body (1) side wall and inner end abutting The drawer box fixing bolt (3) of drawer box (2) lateral wall is fixed with knob (4) on the lateral wall of drawer box (2), box body (1) Four, surface is respectively fixed with shaft insertion tube (5) at angle, tag board (6) and the upper and lower ends shaft (8) for drilling clipboard (7) It is respectively inserted in ipsilateral upper lower rotary shaft insertion tube (5), has a plurality of label mounting groove being parallel to each other in tag board (6) (9), it is also respectively provided with the magnet perforation (10) of hollow out in every strip label mounting groove (9), magnet is perforated immediately below at (10) Label fixed magnet piece (11) is embedded in box body (1) surface respectively, the back side of label box (25) is embedded with label fixed iron piece (12), Label box (25) is correspondingly placed in each label mounting groove (9), and the label fixed iron piece (12) at the back side and corresponding label Fixed magnet piece (11) is close to, and be then respectively set hollow out in rehearsal clipboard (7) and item number is greater than the book of label mounting groove (9) It writes slot (13), drawer box (2) is internal to be separated into multiple label box storage chambers (15), a pen tool storage by partition (14) respectively Chamber (16) and paper storage chamber (17).
2. a kind of civil engineering account valuation practice device according to claim 1, it is characterised in that: rehearsal clipboard (7) horizontal length is greater than the horizontal length of tag board (6), and equally, the horizontal length for writing slot (13) is greater than label mounting groove (9) horizontal length.
3. a kind of civil engineering account valuation practice device according to claim 1, it is characterised in that: tag board (6) Upper and lower ends are respectively fixed with tag board fixed magnet (18), and every piece of tag board fixed magnet (18) is tightly attached to box body (1) respectively On the tag board fixed iron piece (19) that surface is embedded with, the upper and lower ends of rehearsal clipboard (7) are then respectively fixed with the book of strip It writes plate fixed magnet (20), every piece of clipboard fixed magnet (20) is tightly attached to the strip that box body (1) surface is embedded with respectively and writes On plate fixed iron piece (21).
4. a kind of civil engineering account valuation practice device according to claim 1, it is characterised in that: each label box is deposited It puts to post respectively on the left and right sides side wall of chamber (15) and clamps sponge block (22).
5. a kind of civil engineering account valuation practice device according to claim 1, it is characterised in that: label box (25) Front is covered with transparent plastic sheet (23), and transparent plastic sheet (23) edge at label box (25) place open at one end is provided with and concaves Sunken arc notch (24).
CN201820045467.1U 2018-01-11 2018-01-11 A kind of civil engineering account valuation practice device Expired - Fee Related CN208444466U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820045467.1U CN208444466U (en) 2018-01-11 2018-01-11 A kind of civil engineering account valuation practice device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820045467.1U CN208444466U (en) 2018-01-11 2018-01-11 A kind of civil engineering account valuation practice device

Publications (1)

Publication Number Publication Date
CN208444466U true CN208444466U (en) 2019-01-29

Family

ID=65096022

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820045467.1U Expired - Fee Related CN208444466U (en) 2018-01-11 2018-01-11 A kind of civil engineering account valuation practice device

Country Status (1)

Country Link
CN (1) CN208444466U (en)

Similar Documents

Publication Publication Date Title
CN203828407U (en) File cabinet used for financial book management
CN208444466U (en) A kind of civil engineering account valuation practice device
CN208335550U (en) A kind of novel Financial Management Teaching data line chart displaying device
CN203776422U (en) Office filing cabinet
CN207561493U (en) A kind of project cost toolbox for budget
CN207100827U (en) A kind of construction engineering cost tool box
CN201948205U (en) Special tool box for accounting
CN212778932U (en) Detachable soil profile ruler storage device
US2653038A (en) Container
CN209449995U (en) A kind of civil engineering Cost Management budget tool box
CN211910786U (en) Multifunctional stationery box
CN207733869U (en) A kind of project cost budget platform
CN201357674Y (en) Special office appliance for finance
CN215552092U (en) Financial accounting is with tax-declaring table storage box
CN201468305U (en) Multi-functional financial storage box
CN210271682U (en) Link plate structure of investment financing flow chart
CN210190925U (en) Voucher document finishing device for financial accounting
CN215340910U (en) Data estimation drilling device for construction cost
CN205923257U (en) Accounting is with multi -functional account book box
CN208101495U (en) A kind of dedicated bill fold of finance
CN207925004U (en) A kind of agricultural greenhouse sightseeing instruction device
CN208573215U (en) Project cost Special office table
CN203575823U (en) Toolbox used for construction project budget
CN208875569U (en) A kind of project cost desk convenient for reading drawing
CN206185845U (en) Engineering project management toolbox

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190129

Termination date: 20200111

CF01 Termination of patent right due to non-payment of annual fee