CN208441449U CN201820817803.XU CN201820817803U CN208441449U CN 208441449 U CN208441449 U CN 208441449U CN 201820817803 U CN201820817803 U CN 201820817803U CN 208441449 U CN208441449 U CN 208441449U
Authority
CN
China
Prior art keywords
stabilizer blade
high stability
gauge
snap
scaffold according
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820817803.XU
Other languages
Chinese (zh)
Inventor
王萍
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Shangdu Construction Co Ltd
Original Assignee
Zhejiang Shangdu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Shangdu Construction Co Ltd filed Critical Zhejiang Shangdu Construction Co Ltd
Priority to CN201820817803.XU priority Critical patent/CN208441449U/en
Application granted granted Critical
Publication of CN208441449U publication Critical patent/CN208441449U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses a kind of high stability scaffolds, it is related to technical field of building construction, aim to solve the problem that scaffold is placed on uneven or there is a problem of unstable when the ground of barrier in the prior art, its key points of the technical solution are that, in support rod bottom end, two one group of stabilizer blade is hingedly set, it places scaffold time-division spending foot and is fixed by position of the locked assembly to stabilizer blade, to achieve the purpose that avoid ground relief position or barrier.The utility model has the advantage that stability is high, is adapted for placement in uneven bottom surface.

Description

A kind of high stability scaffold
Technical field
The utility model relates to the realm of building construction, more specifically, it relates to a kind of high stability scaffold.
Background technique
Scaffold is one of common equipment in building trade construction, in exterior wall or the higher place of interior decoration, people Generally use scaffold as support equipment.
Existing Authorization Notice No. is that the Chinese patent of CN206737384U discloses a kind of scaffold, by supporting leg Bottom end be provided with the sleeve of idler wheel.By adjusting the relative position of sleeve and supporting leg, in supporting leg ground connection and idler wheel Switch between ground connection two states, to achieve the purpose that facilitate transfer scaffold position.
But either idler wheel ground connection or supporting leg ground connection, contact area is smaller, and ground environment bumps not It is flat or even totally unfavorable there are being placed to the stabilization of scaffold in the case where barrier, it is easily placed using when above-mentioned scaffold Shakiness, safety are low.Thus, it would be desirable to a kind of shelf-stability is high, can be suitably used for using on various uneven ground Scaffold.
Utility model content
In view of the deficienciess of the prior art, the purpose of this utility model is to provide a kind of high stability scaffold, Advantage high with stability, being adapted for placement in uneven ground.
To achieve the above object, the utility model provides following technical solution:
A kind of high stability scaffold, support rod and more horizontal directions including more vertical directions are solid for connecting Determine the connecting rod of support rod, the bottom end of the support rod is coaxially inserted with inserted link, and is threadedly coupled between inserted link and support rod;Institute It states inserted link and one end of support rod is provided with mounting blocks, two stabilizer blades are hingedly provided on the bottom surface of the same mounting blocks; Position is fixed tight when be provided between two stabilizer blades being arranged on the same mounting blocks for being bonded to two stabilizer blades Firmware, and the locked assembly for two stabilizer blade deployed positions to be fixed.
By using above-mentioned technical proposal, when normal use scaffold, without releasing fastener to the fixed function of stabilizer blade, The use and common scaffold of scaffold are no different.In the presence of the bottom surface for placing scaffold is uneven or has barrier, After the fixed function for releasing fastener, the stabilizer blade of the support rod bottom end of rotating opening corresponding position, while rotating inserted link and adjusting branch Support height.Separated stabilizer blade can avoid position uneven or there are barrier, can be formed to scaffold surely Fixed support.The setting of locked assembly, for separated stabilizer blade to be fixed, so that being able to maintain between stabilizer blade relatively fixed.
Further, the fastener is the fastening bolt being plugged between two stabilizer blades jointly.
By using above-mentioned technical proposal, screw that fastening bolt makes it while being inserted into two stabilizer blades can be such that two stabilizer blades keep Fit-state, at this time scaffold can as common scaffold normal use.When needing to separate stabilizer blade, fastening bolt is unscrewed i.e. It can.
Further, the fastening bolt is goat's horn bolt.
By using above-mentioned technical proposal, has and conveniently unscrew or screw fastening bolt with fixed or two branch of release The effect of foot, without tool.
Further, the locked assembly includes the snap-gauge and be arranged in another branch that one end is hinged on a stabilizer blade Card column on foot;The card slot being caught in for card column is provided on the snap-gauge.
By using above-mentioned technical proposal, after two stabilizer blades are separated, rotation snap-gauge makes the card slot inlay card on snap-gauge another In card column on a piece stabilizer blade, two stabilizer blades can be kept in separated state, fixed property easy to use and to stabilizer blade It is good.
Further, equal spacing in length direction of the card slot on snap-gauge along snap-gauge is provided with several places.
By using above-mentioned technical proposal, make card column inlay card on snap-gauge at the card slot of different location, adjustable stabilizer blade Degree of separation, increase Different Ground place scaffold when the controllability to stabilizer blade opening degree, improve foot hand Adaptability of the frame to use environment.
Further, pin shaft is provided on the stabilizer blade, the snap-gauge is rotated by pin shaft to be arranged;The pin shaft is plugged in On stabilizer blade, and it is threadedly coupled between stabilizer blade;The pin shaft is provided with convex block away from one end of stabilizer blade.
By using above-mentioned technical proposal, snap-gauge can be fixed, be further increased to branch using convex block rotary pin shaft The fixed effect of foot relative position so that scaffold place stability, safety it is higher.
Further, the side of the convex block is provided with lug.
By using above-mentioned technical proposal, it may be convenient to rotating pin, to unclamp or fasten snap-gauge.
Further, the inserted link rotation is plugged in the top surface of mounting blocks.
By using above-mentioned technical proposal, mounting blocks can be freely rotated in the end of inserted link, further increase adjusting The flexibility of location footprint improves scaffold to the adaptability of placement location.
Further, the stabilizer blade is provided with non-slip mat far from one end of mounting blocks.
By using above-mentioned technical proposal, the confficient of static friction of leg end portions is increased, so that scaffold is difficult to slide, puts It sets more stable.
Further, the reinforcing bar intersected in X-type is provided between the connecting rod.
By using above-mentioned technical proposal, the overall structure stability of scaffold is increased, improves its safety in utilization.
In conclusion the utility model has the following beneficial effects:
1, the stabilizer blade being hingedly arranged, can avoid that bottom surface is uneven or position there are barrier after separating, adapt to Property is good, stability is high;
2, the snap-gauge with several card slots is matched with card column, allows to adjust the opening degree of stabilizer blade as needed, Adaptability is high;
3, inserted link one end is plugged in support rod and is threadedly coupled between support rod, and other end activity is plugged in mounting blocks It is interior, inserted link can be rotated and adjust the bearing height of respective support bar or the placement location of rotational installation block adjusting stabilizer blade, into one Step increases scaffold to the adaptability of placement location.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of high stability scaffold in embodiment;
Fig. 2 is the enlarged drawing of part A in Fig. 1;
Fig. 3 is the enlarged drawing of part B in Fig. 1.
In figure: 1, support rod;2, connecting rod;21, reinforcing bar;22, workbench;3, inserted link;4, mounting blocks;5, stabilizer blade; 51, non-slip mat;6, fastening bolt;7, locked assembly;71, snap-gauge;711, card slot;72, card column;8, pin shaft;81, convex block;82, convex Ear.
Specific embodiment
The utility model is described in further detail below in conjunction with attached drawing.
Embodiment:
A kind of high stability scaffold, referring to Fig.1 comprising four support rods 1 being arranged along the vertical direction, support rod 1 Between be provided with horizontal connecting rod 2 to be attached fixation to support rod 1.Be provided at the top of scaffold by wire mesh or The workbench 22 that the metallic rod that person's transverse and longitudinal is staggered is constituted.It is set between connecting rod 2 on vertical direction in different height It is equipped with reinforcing bar 21, reinforcing bar 21 is arranged in X-type cross, so that the whole stability with higher of scaffold.
Referring to Figures 1 and 2, the bottom end of every support rod 1 is inserted with inserted link 3, and screw thread connects between inserted link 3 and support rod 1 It connects.The length that the adjustable inserted link 3 of inserted link 3 stretches out 1 part of support rod is rotated, to adjust the bearing height of support rod 1.Inserted link 3 The other end be provided with mounting blocks 4, and the end of inserted link 3 is plugged in mounting blocks 4, allows mounting blocks 4 at the end of inserted link 3 Portion's rotation.
Referring to Fig. 2 and Fig. 3, two stabilizer blades 5 are hingedly provided on the bottom surface of same mounting blocks 4, rotation stabilizer blade 5 can make two Root stabilizer blade 5 is in fitting or separated state.Fastening bolt 6 is inserted on two stabilizer blades 5 jointly, two stabilizer blades 5 can when being bonded With fixed by fastening bolt 6.It before separating stabilizer blade 5, needs first to unscrew fastening bolt 6, releases and two the fixed of stabilizer blade 5 are made With.
Referring to Fig. 2 and Fig. 3, it is additionally provided with locked assembly 7 between two stabilizer blades 5 being arranged on same mounting blocks 4, is locked Component 7 includes the snap-gauge 71 and be fixed on another stabilizer blade 5 that one end is hingedly arranged on a stabilizer blade 5 by pin shaft 8 Card column 72.Length direction on snap-gauge 71 along snap-gauge 71 is equidistantly provided with several card slots 711, in the present embodiment on snap-gauge 71 It is provided with card slot 711 at two.State as shown in Figure 2, after separating stabilizer blade 5, rotation snap-gauge 71 makes 711 inlay card of card slot in another stabilizer blade At card column 72 on 5, the position of two stabilizer blades 5 can be made to keep relatively fixed.At this point, be supported by separated stabilizer blade 5, It can avoid at ground relief or barrier, increase the stationarity of scaffold placement.In order to increase stabilizer blade 5 and ground Between frictional force, stabilizer blade 5 is provided with the non-slip mat 51 of rubber material far from one end of mounting blocks 4.
Referring to Fig. 2, the pin shaft 8 for installing snap-gauge 71 is plugged on stabilizer blade 5 and is threadedly coupled between stabilizer blade 5, pin shaft 8 End be provided with convex block 81,81 side of convex block is provided with lug 82.Rotation has the convex block 81 of lug 82, can make pin shaft 8 Rotation, to unclamp or fasten snap-gauge 71.For 711 inlay card of card slot on snap-gauge 71 when in card column 72, screwing pin shaft 8 can be into one Step increases fastening effect, avoids that snap-gauge 71 during scaffold is used to loosen disengaging.
Working principle is as follows:
Fixed by fastening bolt 6 when two stabilizer blades 5 on same mounting blocks 4 are bonded to each other, scaffold can be at this time Common scaffold equally uses.When needing in uneven position or having the ground placement scaffold of barrier, fastening is unscrewed Bolt 6 releases the fixed function to stabilizer blade 5.It rotates and separates stabilizer blade 5, rotation snap-gauge 71 makes 711 inlay card of card slot on another stabilizer blade 5 Card column 72 at.According to the actual situation, at the card slot 711 that 72 inlay card of card column can be made different on snap-gauge 71, to control stabilizer blade 5 Between separated angle.Pin shaft 8 is screwed, to further fixing for snap-gauge 71.Then, the adjustable branch of mounting blocks 4 is rotated Foot 5 supports in place;It rotates inserted link 3 and adjusts the length that inserted link 3 stretches out 1 bottom part of support rod, so that respective support The bearing height of the bearing height of bar 1 and other support rods 1 is adapted.The scaffold of the utility model can be placed on recessed Bottom surface that is convex uneven or having barrier, adaptable, shelf-stability and safe to use.
Above-mentioned specific embodiment is only the explanation to the utility model, is not limitations of the present invention, this Field technical staff can according to need the modification that not creative contribution is made to the present embodiment after reading this specification, But as long as all by the protection of Patent Law in the scope of the claims of the utility model.

Claims (10)

1. a kind of high stability scaffold, support rod (1) and more horizontal directions including more vertical directions are solid for connecting Determine the connecting rod (2) of support rod (1), it is characterised in that: the bottom end of the support rod (1) is coaxially inserted with inserted link (3), and inserted link (3) it is threadedly coupled between support rod (1);The inserted link (3) is provided with mounting blocks (4) far from the one end of support rod (1), same Two stabilizer blades (5) are hingedly provided on the bottom surface of the mounting blocks (4);Two branch on the same mounting blocks (4) are set The fastener that position is fixed when be provided between foot (5) for being bonded to two stabilizer blades (5), and for two stabilizer blades (5) The locked assembly (7) that open position is fixed.
2. a kind of high stability scaffold according to claim 1, it is characterised in that: the fastener is to be plugged in jointly Fastening bolt (6) between two stabilizer blades (5).
3. a kind of high stability scaffold according to claim 2, it is characterised in that: the fastening bolt (6) is goat's horn Bolt.
4. a kind of high stability scaffold according to claim 1, it is characterised in that: the locked assembly (7) includes one The card column (72) holding the snap-gauge (71) being hinged on a stabilizer blade (5) and being arranged on another stabilizer blade (5);The snap-gauge (71) card slot (711) being caught in for card column (72) is provided on.
5. a kind of high stability scaffold according to claim 4, it is characterised in that: the card slot (711) is in snap-gauge (71) equal spacing in length direction on along snap-gauge (71) is provided with several places.
6. a kind of high stability scaffold according to claim 5, it is characterised in that: be provided with pin on the stabilizer blade (5) Axis (8), the snap-gauge (71) pass through pin shaft (8) rotation setting;The pin shaft (8) is plugged on stabilizer blade (5), and with stabilizer blade (5) Between be threadedly coupled;The pin shaft (8) is provided with convex block (81) away from the one end of stabilizer blade (5).
7. a kind of high stability scaffold according to claim 6, it is characterised in that: the side of the convex block (81) is arranged There are lug (82).
8. a kind of high stability scaffold according to claim 1-7, it is characterised in that: the inserted link (3) turns The dynamic top surface for being plugged in mounting blocks (4).
9. a kind of high stability scaffold according to claim 1-7, it is characterised in that: the stabilizer blade (5) is remote One end from mounting blocks (4) is provided with non-slip mat (51).
10. a kind of high stability scaffold according to claim 1-7, it is characterised in that: the connecting rod (2) Between be provided with intersect be in X-type reinforcing bar (21).
CN201820817803.XU 2018-05-29 2018-05-29 A kind of high stability scaffold Active CN208441449U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820817803.XU CN208441449U (en) 2018-05-29 2018-05-29 A kind of high stability scaffold

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820817803.XU CN208441449U (en) 2018-05-29 2018-05-29 A kind of high stability scaffold

Publications (1)

Publication Number Publication Date
CN208441449U true CN208441449U (en) 2019-01-29

Family

ID=65091399

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820817803.XU Active CN208441449U (en) 2018-05-29 2018-05-29 A kind of high stability scaffold

Country Status (1)

Country Link
CN (1) CN208441449U (en)

Similar Documents

Publication Publication Date Title
US2195579A (en) Scaffold bracket
CN205935623U (en) Adjustable footboard angle stair
CN208441449U (en) A kind of high stability scaffold
CN206899142U (en) Wind bird scaring device installation tool
CN205901665U (en) Support device of photovoltaic board
CN202170750U (en) Turnover escape rack
CN208533990U (en) A kind of support device for building structure construction
CN208251589U (en) A kind of architectural engineering scaffold bracing means
CN109898827A (en) A kind of protective device for building scaffold
CN210007270U (en) cable fixing support
CN206801197U (en) Tent bracket
CN210901660U (en) Shoe supporting device for repairing shoes
CN209099807U (en) A kind of architectural stair temporary guard rail
CN207714723U (en) A kind of alien invasion lines that bear down on one intersperse coating application supporting rack
CN208080076U (en) A kind of shiny-leaved yellowhorn plantation support device
CN205990780U (en) One kind is safe, easy-to-dismount to face frontier defense protection unit
CN211499728U (en) Steel construction installation scaffold
CN108412416A (en) A kind of ladder for construction and decoration
CN203547508U (en) Ladder with safety protection structure
CN220228431U (en) Adjustable mounting bracket for display screen
CN208625529U (en) A kind of shower disc mounting device
CN208986877U (en) Mountainous region photovoltaic flexible support
CN204743997U (en) Multi -functional regulation support
CN220487273U (en) Protective fence for house building construction
CN106247488A (en) A kind of air-conditioner mounting rack regulating height

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of utility model: A high stability scaffold

Effective date of registration: 20221016

Granted publication date: 20190129

Pledgee: Zhejiang Tailong Commercial Bank Co.,Ltd. Jiaxing Branch

Pledgor: ZHEJIANG SHANGDU CONSTRUCTION Co.,Ltd.

Registration number: Y2022330002617

PE01 Entry into force of the registration of the contract for pledge of patent right