CN208421565U - building monitoring system based on BIM - Google Patents

building monitoring system based on BIM Download PDF

Info

Publication number
CN208421565U
CN208421565U CN201820004182.3U CN201820004182U CN208421565U CN 208421565 U CN208421565 U CN 208421565U CN 201820004182 U CN201820004182 U CN 201820004182U CN 208421565 U CN208421565 U CN 208421565U
Authority
CN
China
Prior art keywords
bim
fire
subsystem
building
information
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820004182.3U
Other languages
Chinese (zh)
Inventor
王代虎
朱加鹏
史常州
王代林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Suzhou Andardo Technical Engineering Co Ltd
Original Assignee
Suzhou Andardo Technical Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Suzhou Andardo Technical Engineering Co Ltd filed Critical Suzhou Andardo Technical Engineering Co Ltd
Priority to CN201820004182.3U priority Critical patent/CN208421565U/en
Application granted granted Critical
Publication of CN208421565U publication Critical patent/CN208421565U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Fire Alarms (AREA)
  • Alarm Systems (AREA)

Abstract

The utility model provides a kind of building monitoring system based on BIM, including sequentially connected BIM operation management platform, BIM model component, central processing unit and coordinated control system;Coordinated control system includes that building automation subsystem, automatic fire alarm subsystem, smoke controlling control subsystem, fire-extinguishing apparatus control subsystem and personnel simulate evacuation subsystem;The facility information of coordinated control system is sent to BIM model component by central processing unit;BIM model component adds the facility information in BIM threedimensional model, and is sent to BIM operation management platform;BIM operation management platform stores and shows BIM threedimensional model.In this way user can it is intuitive by BIM threedimensional model, it is detailed obtain coordinated control system facility information, supervision difficulty is reduced, the transparence degree of items of equipment information is improved, keeps fire-fighting and rescue work more intuitive, more efficiently, to guarantee the safe and reasonable operation of Architectural Equipment.

Description

Building monitoring system based on BIM
Technical field
The utility model relates to monitoring device technical fields, more particularly, to a kind of building monitoring system based on BIM.
Background technique
Building Information Model (BIM, Building Information Modeling) is the items with construction-engineering project Based on relevant information data, by real information possessed by digital information analogue simulation building, pass through three-dimensional building Model realizes the functions such as project supervision, estate management, equipment management, Digital manufacturing, engineering management.BIM has information complete For property, information relevance, consistency on messaging, visualization, harmony, simulation, optimization property and the big feature of figure eight can be gone out, extensively Applied to architectural design field.Position and the parameter letter of the equipment installed in building can be understood intuitively, in detail by BIM Breath.
With the development of population increased with city, various high-rise, middle layer buildings are seen everywhere, the mechanical electric in building The Architectural Equipments such as equipment and fire warning device, as increasing for floor is more and more.In order to guarantee the peace of Architectural Equipment Row for the national games, it is higher and higher to the monitoring requirement of Architectural Equipment.Since the Architectural Equipment in building is more, so corresponding monitoring number According to more, cause when fire occurs for building, monitoring personnel can not be rapidly and accurately determined according to a large amount of monitoring data to building The control strategy for building equipment is unfavorable for the timely development of fire-fighting and rescue work in this way.In addition, the daily maintenance and inspection of Architectural Equipment The inadequate transparence of the items of equipment information such as job information is repaired, the normal operation of various functions is unfavorable for.
In summary, existing building monitoring system is asked there are difficult to regulate, items of equipment Information Visibility degree are low Topic causes fire-fighting and rescue work not carry out in time, low efficiency, not can guarantee the safe and reasonable operation of Architectural Equipment.
Utility model content
In view of this, the purpose of this utility model is to provide a kind of building monitoring system based on BIM, to reduce supervision Difficulty improves the transparence degree of items of equipment information, keeps fire-fighting and rescue work more intuitive, more efficiently, guarantees Architectural Equipment Safe and reasonable operation.
In a first aspect, the utility model embodiment provides a kind of building monitoring system based on BIM, including it is sequentially connected with BIM operation management platform, BIM model component, central processing unit and coordinated control system;
The coordinated control system includes building automation subsystem, automatic fire alarm subsystem, smoke controlling control subsystem System, fire-extinguishing apparatus control subsystem and personnel simulate evacuation subsystem;
The facility information of the coordinated control system is sent to the BIM model component by the central processing unit, described Facility information includes daily maintenance information, service work information and monitoring information;The BIM model component is by the facility information Addition is sent to the BIM operation management platform in BIM threedimensional model, and by the BIM threedimensional model after addition;The BIM Operation management platform stores and shows the BIM threedimensional model.
With reference to first aspect, the utility model embodiment provides the first possible embodiment of first aspect, In, the building automation subsystem includes: one of lift facility, heating and ventilating equipment and plumbing equipment or a variety of.
With reference to first aspect, the utility model embodiment provides second of possible embodiment of first aspect, In, the automatic fire alarm subsystem includes: fire detector, fire broadcast and fire-alarm.
The possible embodiment of second with reference to first aspect, the utility model embodiment provide the of first aspect Three kinds of possible embodiments, wherein the fire detector includes temperature sensor, smoke sensor device, combustible gas detecting One of device, carbon monoxide detector are a variety of.
With reference to first aspect, the utility model embodiment provides the 4th kind of possible embodiment of first aspect, In, the smoke controlling control subsystem includes one of induced-draft fan, fire resistant doorsets, fire resisting shutter or a variety of.
With reference to first aspect, the utility model embodiment provides the 5th kind of possible embodiment of first aspect, In, the fire-extinguishing apparatus control subsystem includes sprinkling fire-distinguishing equipment and/or fire hydrant fire-extinguishing apparatus.
With reference to first aspect, the utility model embodiment provides the 6th kind of possible embodiment of first aspect, In, it includes one of emergency power supply, elevator control device and emergency lamp signal telegraph or a variety of that the personnel, which simulate evacuation subsystem,.
With reference to first aspect, the utility model embodiment provides the 7th kind of possible embodiment of first aspect, In, the building monitoring system based on BIM further includes stream of people's counter and wagon flow counter, stream of people's counter and described Wagon flow counter is connect with the central processing unit;
The central processing unit obtains the personnel amount of disengaging building from stream of people's counter, from the wagon flow counter The vehicle fleet size of disengaging building is obtained, and the personnel amount and the vehicle fleet size are sent to the BIM model component.
Second aspect, the utility model embodiment also provides a kind of building monitoring system based on BIM, including is sequentially connected with BIM operation management platform, BIM model component, central processing unit and coordinated control system, further include and the BIM O&M pipe The terminal of platform connection;
The coordinated control system includes building automation subsystem, automatic fire alarm subsystem, smoke controlling control subsystem System, fire-extinguishing apparatus control subsystem and personnel simulate evacuation subsystem;
The facility information of the coordinated control system is sent to the BIM model component by the central processing unit, described Facility information includes daily maintenance information, service work information and monitoring information;The BIM model component is by the facility information Addition is sent to the BIM operation management platform in BIM threedimensional model, and by the BIM threedimensional model after addition;The BIM Operation management platform stores the BIM threedimensional model, and is believed by BIM threedimensional model described in the terminal display and the equipment Breath.
In conjunction with second aspect, the utility model embodiment provides the first possible embodiment of second aspect, In, the terminal includes individual client end, property client, maintenance client, fire-fighting supervision client, automatic rescue client One of or it is a variety of.
The utility model embodiment bring it is following the utility model has the advantages that
In the utility model embodiment, the building monitoring system based on BIM includes that sequentially connected BIM operation management is flat Platform, BIM model component, central processing unit and coordinated control system;Coordinated control system include building automation subsystem, fire from Dynamic alert sub-system, smoke controlling control subsystem, fire-extinguishing apparatus control subsystem and personnel simulate evacuation subsystem;Central processing The facility information of coordinated control system is sent to BIM model component by device, and facility information includes daily maintenance information, service work Information and monitoring information;BIM model component adds the facility information in BIM threedimensional model, and the BIM after addition is three-dimensional Model is sent to BIM operation management platform;BIM operation management platform stores and shows the BIM threedimensional model.Such monitoring personnel Equal users can be believed by the equipment of intuitive, the detailed acquisition coordinated control system of BIM threedimensional model of BIM operation management platform Breath, reduces supervision difficulty, improves the transparence degree of items of equipment information, keeps fire-fighting and rescue work more intuitive, more effectively Rate, to guarantee the safe and reasonable operation of Architectural Equipment.
Other feature and advantage of the utility model will illustrate in the following description, also, partly from specification In become apparent, or understood and implementing the utility model.The purpose of this utility model and other advantages are illustrating Specifically noted structure is achieved and obtained in book, claims and attached drawing.
To enable the above objects, features, and advantages of the utility model to be clearer and more comprehensible, preferred embodiment is cited below particularly, and Cooperate appended attached drawing, is described in detail below.
Detailed description of the invention
It, below will be right in order to illustrate more clearly of specific embodiment of the present invention or technical solution in the prior art Specific embodiment or attached drawing needed to be used in the description of the prior art are briefly described, it should be apparent that, it is described below In attached drawing be that some embodiments of the utility model are not paying creativeness for those of ordinary skill in the art Under the premise of labour, it is also possible to obtain other drawings based on these drawings.
Fig. 1 is a kind of building monitoring system based on BIM provided by the embodiment of the utility model;
Fig. 2 is another building monitoring system based on BIM provided by the embodiment of the utility model;
Fig. 3 is another building monitoring system based on BIM provided by the embodiment of the utility model;
Fig. 4 is another building monitoring system based on BIM provided by the embodiment of the utility model.
Icon:
100-BIM operation management platform;200-BIM model component;300- central processing unit;400- coordinated control system; 410- building automation subsystem;411- lift facility;412- heating and ventilating equipment;413- plumbing equipment;420- automatic fire alarm Subsystem;421- fire detector;The broadcast of 422- fire;423- fire-alarm;430- smoke controlling control subsystem;431- row Smoke machine;432- fire resistant doorsets;433- fire resisting shutter;440- fire-extinguishing apparatus control subsystem;441- sprinkling fire-distinguishing equipment;442- disappears fire Bolt fire-extinguishing apparatus;450- personnel simulate evacuation subsystem;451- emergency power supply;452- elevator control device;453- emergency parachute Lamp;500- terminal;510- individual client end;520- property client;530- maintenance client;Client is supervised in 540- fire-fighting; 550- automatic rescue client.
Specific embodiment
To keep the objectives, technical solutions, and advantages of the embodiments of the present invention clearer, below in conjunction with attached drawing to this The technical solution of utility model is clearly and completely described, it is clear that described embodiment is that the utility model a part is real Example is applied, instead of all the embodiments.Based on the embodiments of the present invention, those of ordinary skill in the art are not making Every other embodiment obtained, fall within the protection scope of the utility model under the premise of creative work.
Current existing building monitoring system has that difficult to regulate, items of equipment Information Visibility degree is low, leads Cause fire-fighting and rescue, which works, to be carried out in time, low efficiency, not can guarantee the safe and reasonable operation of Architectural Equipment.Based on this, this reality A kind of building monitoring system based on BIM provided with new embodiment can be to various equipment by introducing BIM model component Information carries out communicating and having the information processing function, and joint-monitoring builds interior mechanical electric equipment and fire warning device, It can coordinate the work between each subsystem, realize linkage control between architectural electricity and each subsystem of fire alarm;So as to Supervision difficulty is reduced, the transparence degree of items of equipment information is improved, keeps fire-fighting and rescue work more intuitive, more efficiently, is guaranteed The safe and reasonable of Architectural Equipment is run.
For convenient for understanding the present embodiment, below to a kind of based on BIM's disclosed in the utility model embodiment Building monitoring system describes in detail.
Embodiment one:
BIM Building Information Model includes information exchange layer, core layer and resource layer, and resource layer is by the spy of architecture information resource Sign storage is into corresponding resource module, and by core technologies such as network, computers, information, which is aggregated into, to be used interchangeably ShareBuilder element guarantees in information exchanging process without missing or omission.BIM operation management platform simultaneously, by building BA Each smart machine systems such as (Building Automation, automatic control) control, fire alarm, smoke controlling equipment, fire-extinguishing apparatus Control management is integrated on a unified administration interface, can store the daily maintenance and service work information of equipment.
Fig. 1 is a kind of building monitoring system based on BIM provided by the embodiment of the utility model, as shown in Figure 1, this is based on The building monitoring system of BIM includes sequentially connected BIM operation management platform 100, BIM model component 200, central processing unit (CPU, Central Processing Unit) 300 and coordinated control system 400;Coordinated control system 400 includes building automation Subsystem 410, automatic fire alarm subsystem 420, smoke controlling control subsystem 430, fire-extinguishing apparatus control subsystem 440 and people Member's simulation evacuation subsystem 450.
A kind of course of work of the building monitoring system based on BIM is as follows:
The facility information of coordinated control system 400 is sent to BIM model component 200, facility information by central processing unit 300 Including daily maintenance information, service work information and monitoring information;BIM model component 200 adds the facility information in BIM tri- In dimension module, and the BIM threedimensional model after addition is sent to BIM operation management platform 100;BIM operation management platform 100 is deposited It stores up and shows the BIM threedimensional model.BIM operation management platform 100 can be server, and user passes through access BIM operation management Platform 100 checks the BIM threedimensional model.The users such as monitoring personnel pass through the monitoring information shown on BIM threedimensional model in this way The working condition etc. that intuitive, detailed can obtain installation fire-fighting equipment in the position and building that fire behavior occurs, reduces prison Pipe difficulty keeps fire-fighting and rescue work more intuitive, more efficiently;Daily maintenance can also be obtained by BIM operation management platform 100 Information and service work information, improve the transparence degree of items of equipment information, to guarantee the safe and reasonable of Architectural Equipment Operation.
Another course of work of the building monitoring system based on BIM is as follows:
BIM operation management platform 100 melts every Architectural Equipment such as building automation subsystem and fire controlling alarm Close into BIM Building Information Model, items of equipment information counted by analysis, inside integrated management building every building facility be System carries out communication management to various facility informations, guarantees the operation of Architectural Equipment safe and reasonable.
Fig. 2 is another building monitoring system based on BIM provided by the embodiment of the utility model, as shown in Fig. 2, scheming On the basis of 1, building automation subsystem 410 includes: one in lift facility 411, heating and ventilating equipment 412 and plumbing equipment 413 Kind is a variety of.Corresponding, the monitoring information of building automation subsystem 410 includes: elevator operation, and heating, ventilation state supply Water, hull-borne etc..
As shown in Fig. 2, automatic fire alarm subsystem 420 includes: fire detector 421, fire broadcast 422 and fire report Alert device 423, wherein fire detector 421 includes temperature sensor, smoke sensor device, combustible gas probe, carbon monoxide spy Survey one of device or a variety of.It is corresponding, the monitoring information of automatic fire alarm subsystem 420 include: temperature, smokescope, Fuel gas content, carbon monoxide content etc., starting, the halted state etc. of fire broadcast 422.Fire-alarm 423 can with but It is not limited to combined aural and visual alarm.After fire detector 421 detects fire dangerous situation, broadcast-ing personnel is carried out by fire broadcast 422 Information and real-time the condition of a disaster information etc. are evacuated, fire alarm is carried out by fire-alarm 423.
As shown in Fig. 2, smoke controlling control subsystem 430 is including in induced-draft fan 431, fire resistant doorsets 432, fire resisting shutter 433 It is one or more.Corresponding, the monitoring information of smoke controlling control subsystem 430 includes: the hand of smoke controlling control subsystem 430 Dynamic, automatic mode, the working condition of smoke exhaust fan power supply, blower, electronic smoke exhaust fire damper, normally closed are sent electric fire-damper The action state of air port, smoke outlet, electronic vent window etc., fire resistant doorsets 432, open state of fire resisting shutter 433 etc..
As shown in Fig. 2, fire-extinguishing apparatus control subsystem 440 includes sprinkling fire-distinguishing equipment 441 and/or fire hydrant fire-extinguishing apparatus 442.It is corresponding, the monitoring information of fire-extinguishing apparatus control subsystem 440 include: spray pump power work state, the opening of spray pump, Stop state and malfunction, the action state of water flow indicator, the action state etc. of fire pump.
As shown in Fig. 2, it includes emergency power supply 451, elevator control device 452 and emergency that personnel, which simulate evacuation subsystem 450, One of signal lamp 453 is a variety of.Corresponding, the monitoring information that personnel simulate evacuation subsystem 450 includes: emergency power supply 451 working condition, the deactivated and working condition of elevator, the switch state etc. of emergency lamp signal telegraph 453.
A kind of building monitoring system based on BIM provided by the embodiment of the utility model, so that the money of building structure information Source is shared, cooperates with, and can make the information lossless transmitting in BIM Building Information Model (BIM threedimensional model) for building various aspects;Solution The daily maintenance for equipment of having determined and the transparence problem of service work information, can make staff understand the dimension of items of equipment at any time Shield and emm message, guarantee the normal operation of various functions.
It is above-mentioned to be based on BIM in order to realize the monitoring statisticss to personnel and vehicle in building in some possible embodiments Building monitoring system further include stream of people's counter and wagon flow counter, stream of people's counter and wagon flow counter are and central processing Device 300 connects;Central processing unit 300 from stream of people's counter obtain disengaging building personnel amount, from wagon flow counter obtain into The vehicle fleet size built out, and personnel amount and vehicle fleet size are sent to BIM model component 200, pass through BIM model component 200 are uploaded to BIM operation management platform 100.In this way, user can be checked in building currently by BIM operation management platform 100 Personnel amount and vehicle fleet size, for fire-fighting and rescue work provide strong support.
Embodiment two:
Fig. 3 is another building monitoring system based on BIM provided by the embodiment of the utility model, as shown in figure 3, upper On the basis of stating Fig. 1, being somebody's turn to do the building monitoring system based on BIM further includes the terminal 500 connecting with BIM operation management platform 100.
Specifically, terminal 500 be with display screen, and can with BIM operation management platform 100 communicate to connect electronics set It is standby, such as mobile phone, computer, monitoring room etc..User by terminal 500 access BIM operation management platform 100, terminal 500 show on BIM threedimensional model and facility information are stated, is checked for user.User can also issue control instruction to BIM O&M by terminal 500 Platform 100 is managed, the working condition of coordinated control system 400 is controlled.
Fig. 4 is another building monitoring system based on BIM provided by the embodiment of the utility model as shown in figure 4, in Fig. 3 On the basis of, terminal 500 includes individual client end 510, property client 520, maintenance client 530, fire-fighting supervision client 540, one of automatic rescue client 550 or a variety of.Correspondence can be notified in time when the dangerous situations such as fire occur in this way Personnel.
In addition, BIM operation management platform 100 is additionally provided with Inspection and maintenance reminding module, the Inspection and maintenance reminding module energy It is enough periodically the relevant personnel to be reminded to carry out overhaul of the equipments and maintenance work, and then preferably guarantee the building monitoring system based on BIM The safe and reasonable operation of each Architectural Equipment in uniting.
In the present embodiment, user can check BIM threedimensional model by terminal 500, intuitive, detailed to obtain fire behavior Position and building in the working condition etc. of installation fire-fighting equipment make fire-fighting and rescue work more to reduce supervision difficulty Intuitively, more efficiently;The daily maintenance information and service work information of Architectural Equipment can also be checked by terminal 500, improved The transparence degree of items of equipment information, to guarantee the safe and reasonable operation of Architectural Equipment.
It is apparent to those skilled in the art that for convenience and simplicity of description, above-described embodiment two is retouched The specific work process for the building monitoring system based on BIM stated, can be with reference to the corresponding process in previous embodiment one, herein It repeats no more.
In addition, in the description of the utility model embodiment unless specifically defined or limited otherwise, term " connected ", " connection " shall be understood in a broad sense, for example, it may be being connected directly, can also can be two indirectly connected through an intermediary Connection inside element.For the ordinary skill in the art, it can understand that above-mentioned term is practical at this with concrete condition Concrete meaning in novel.
Block diagram in attached drawing shows the architectural framework in the cards of multiple embodiments according to the present utility model.At this On point, each box in block diagram can represent a part of a module, section or code, the module, program segment or A part of code includes one or more executable instructions for implementing the specified logical function.It should also be noted that having In a little realizations as replacement, function marked in the box can also occur in a different order than that indicated in the drawings.Example Such as, two continuous boxes can actually be basically executed in parallel, they can also be executed in the opposite order sometimes, this according to Depending on related function.It is also noted that the combination of each box in block diagram and the box in block diagram, Ke Yiyong The dedicated hardware based system of defined function or movement is executed to realize, or can be referred to specialized hardware and computer The combination of order is realized.
In several embodiments provided herein, it should be understood that the disclosed building based on BIM monitors system System, may be implemented in other ways.Embodiments described above is only schematical, for example, the unit is drawn Point, only a kind of logical function partition, there may be another division manner in actual implementation, in another example, multiple units or group Part can be combined or can be integrated into another system, or some features can be ignored or not executed.Another point, it is shown Or the mutual coupling, direct-coupling or communication connection discussed can be through some communication interfaces, device or unit Indirect coupling or communication connection can be electrical property, mechanical or other forms.
The unit as illustrated by the separation member may or may not be physically separated, aobvious as unit The component shown may or may not be physical unit, it can and it is in one place, or may be distributed over multiple In network unit.It can select some or all of unit therein according to the actual needs to realize the mesh of this embodiment scheme 's.
In addition, each functional unit in each embodiment of the utility model can integrate in one processing unit, It can be each unit to physically exist alone, can also be integrated in one unit with two or more units.
Finally, it should be noted that embodiment described above, only specific embodiment of the present utility model, to illustrate this The technical solution of utility model, rather than its limitations, the protection scope of the utility model is not limited thereto, although referring to aforementioned The utility model is described in detail in embodiment, those skilled in the art should understand that: it is any to be familiar with this skill The technical staff in art field within the technical scope disclosed by the utility model, still can be to skill documented by previous embodiment Art scheme modify or can readily occur in variation or equivalent replacement of some of the technical features;And these modifications, Variation or replacement, the spirit and model of the utility model embodiment technical solution that it does not separate the essence of the corresponding technical solution It encloses, should be covered within the scope of the utility model.Therefore, the protection scope of the utility model is answered described is wanted with right Subject to the protection scope asked.

Claims (10)

1. a kind of building monitoring system based on BIM, which is characterized in that including sequentially connected BIM operation management platform, BIM Model component, central processing unit and coordinated control system;
The coordinated control system includes building automation subsystem, automatic fire alarm subsystem, smoke controlling control subsystem, goes out Fiery equipment control subsystem and personnel simulate evacuation subsystem;
The facility information of the coordinated control system is sent to the BIM model component, the equipment by the central processing unit Information includes daily maintenance information, service work information and monitoring information;The BIM model component adds the facility information The BIM operation management platform is sent in BIM threedimensional model, and by the BIM threedimensional model after addition;The BIM O&M Management platform stores and shows the BIM threedimensional model.
2. the building monitoring system according to claim 1 based on BIM, which is characterized in that the building automation subsystem It include: one of lift facility, heating and ventilating equipment and plumbing equipment or a variety of.
3. the building monitoring system according to claim 1 based on BIM, which is characterized in that automatic fire alarm System includes: fire detector, fire broadcast and fire-alarm.
4. the building monitoring system according to claim 3 based on BIM, which is characterized in that the fire detector includes One of temperature sensor, smoke sensor device, combustible gas probe, carbon monoxide detector are a variety of.
5. the building monitoring system according to claim 1 based on BIM, which is characterized in that the smoke controlling controls subsystem System includes one of induced-draft fan, fire resistant doorsets, fire resisting shutter or a variety of.
6. the building monitoring system according to claim 1 based on BIM, which is characterized in that fire-extinguishing apparatus control System includes sprinkling fire-distinguishing equipment and/or fire hydrant fire-extinguishing apparatus.
7. the building monitoring system according to claim 1 based on BIM, which is characterized in that the personnel simulate evacuation System includes one of emergency power supply, elevator control device and emergency lamp signal telegraph or a variety of.
8. the building monitoring system according to claim 1 based on BIM, which is characterized in that the building prison based on BIM Control system further includes stream of people's counter and wagon flow counter, stream of people's counter and the wagon flow counter with the center Processor connection;
The central processing unit obtains the personnel amount of disengaging building from stream of people's counter, obtains from the wagon flow counter The vehicle fleet size of building is passed in and out, and the personnel amount and the vehicle fleet size are sent to the BIM model component.
9. a kind of building monitoring system based on BIM, which is characterized in that including sequentially connected BIM operation management platform, BIM Model component, central processing unit and coordinated control system further include the terminal connecting with the BIM operation management platform;
The coordinated control system includes building automation subsystem, automatic fire alarm subsystem, smoke controlling control subsystem, goes out Fiery equipment control subsystem and personnel simulate evacuation subsystem;
The facility information of the coordinated control system is sent to the BIM model component, the equipment by the central processing unit Information includes daily maintenance information, service work information and monitoring information;The BIM model component adds the facility information The BIM operation management platform is sent in BIM threedimensional model, and by the BIM threedimensional model after addition;The BIM O&M It manages platform and stores the BIM threedimensional model, and pass through BIM threedimensional model and the facility information described in the terminal display.
10. the building monitoring system according to claim 9 based on BIM, which is characterized in that the terminal includes personal visitor One of family end, property client, maintenance client, fire-fighting supervision client, automatic rescue client are a variety of.
CN201820004182.3U 2018-01-02 2018-01-02 building monitoring system based on BIM Active CN208421565U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820004182.3U CN208421565U (en) 2018-01-02 2018-01-02 building monitoring system based on BIM

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820004182.3U CN208421565U (en) 2018-01-02 2018-01-02 building monitoring system based on BIM

Publications (1)

Publication Number Publication Date
CN208421565U true CN208421565U (en) 2019-01-22

Family

ID=65121373

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820004182.3U Active CN208421565U (en) 2018-01-02 2018-01-02 building monitoring system based on BIM

Country Status (1)

Country Link
CN (1) CN208421565U (en)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110124227A (en) * 2019-05-22 2019-08-16 成张佳宁 A kind of fire prevention to high buildings control system and its working method
CN110138825A (en) * 2019-04-02 2019-08-16 广州正为明昱信息科技有限公司 A kind of dynamic building mark guidance system based on Internet of Things
CN110363865A (en) * 2019-05-31 2019-10-22 成都科旭电子有限责任公司 Wisdom bank monitoring system based on BIM and Internet of Things
CN110925696A (en) * 2019-12-09 2020-03-27 湖北文华系统工程有限公司 BIM-based fire escape system and route calculation factor confirmation method
CN111179143A (en) * 2020-01-06 2020-05-19 紫光云技术有限公司 Intelligent fire fighting system based on BIM
CN111260086A (en) * 2020-01-13 2020-06-09 五邑大学 BIM-based central air conditioner operation and maintenance method, system and device
CN111563285A (en) * 2019-01-28 2020-08-21 开利公司 Building 3D visual monitoring method, system and storage medium
CN112130478A (en) * 2019-12-27 2020-12-25 国网中兴有限公司 Building integrated comprehensive management and control platform system based on BIM and management and control method thereof
CN112541704A (en) * 2020-12-23 2021-03-23 浙江杭州赛诺捷节能科技有限公司 Intelligent building operation and maintenance management system based on BIM platform
CN115186352A (en) * 2022-07-20 2022-10-14 中国建筑西南设计研究院有限公司 BIM technology-based fire damper compliance inspection method and related device
CN117085272A (en) * 2023-08-07 2023-11-21 营口天成消防设备有限公司 Fire-fighting linkage control system for high-rise building fire and escape and rescue method

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111563285A (en) * 2019-01-28 2020-08-21 开利公司 Building 3D visual monitoring method, system and storage medium
CN110138825A (en) * 2019-04-02 2019-08-16 广州正为明昱信息科技有限公司 A kind of dynamic building mark guidance system based on Internet of Things
CN110124227A (en) * 2019-05-22 2019-08-16 成张佳宁 A kind of fire prevention to high buildings control system and its working method
CN110124227B (en) * 2019-05-22 2020-09-01 南通居者安建筑科学研究院有限公司 High-rise building fire prevention control system and working method thereof
CN110363865A (en) * 2019-05-31 2019-10-22 成都科旭电子有限责任公司 Wisdom bank monitoring system based on BIM and Internet of Things
CN110925696A (en) * 2019-12-09 2020-03-27 湖北文华系统工程有限公司 BIM-based fire escape system and route calculation factor confirmation method
CN112130478A (en) * 2019-12-27 2020-12-25 国网中兴有限公司 Building integrated comprehensive management and control platform system based on BIM and management and control method thereof
CN111179143A (en) * 2020-01-06 2020-05-19 紫光云技术有限公司 Intelligent fire fighting system based on BIM
CN111260086A (en) * 2020-01-13 2020-06-09 五邑大学 BIM-based central air conditioner operation and maintenance method, system and device
CN112541704A (en) * 2020-12-23 2021-03-23 浙江杭州赛诺捷节能科技有限公司 Intelligent building operation and maintenance management system based on BIM platform
CN115186352A (en) * 2022-07-20 2022-10-14 中国建筑西南设计研究院有限公司 BIM technology-based fire damper compliance inspection method and related device
CN115186352B (en) * 2022-07-20 2023-09-05 中国建筑西南设计研究院有限公司 Fire-proof valve compliance checking method based on BIM technology and related device
CN117085272A (en) * 2023-08-07 2023-11-21 营口天成消防设备有限公司 Fire-fighting linkage control system for high-rise building fire and escape and rescue method

Similar Documents

Publication Publication Date Title
CN208421565U (en) building monitoring system based on BIM
KR100880211B1 (en) Integrated management system and method
CN104615112B (en) Resource and environmental monitoring early warning system under network environment
CN110158648A (en) A kind of Urban Underground pipe gallery O&M monitoring management system
CN109525668A (en) Fire-fighting Internet of Things remote monitoring system based on cloud platform
CN110069387A (en) The data processing method and system of calculator room equipment
CN111585875B (en) Fire-fighting and security-protection integrated edge computing gateway and application thereof
CN111523277B (en) Fire prediction method, storage device and processor
CN106656664A (en) Smart city power consumption safety monitoring and management system
CN104918274A (en) Environment monitoring system and method for machine room cluster based on wireless sensor network
CN108898255A (en) One kind is based on the twinborn intelligence community O&M supervisory control simulation cloud platform of digitlization
CN108154663A (en) A kind of safety detection early warning system
JP3293020B2 (en) Disaster prevention information processing device
CN105320093A (en) Intelligent building monitoring system and method
CN104111632A (en) Power environment centralized monitoring system
CN106774120A (en) A kind of easy equipment running monitoring fault alarm and transmission method
CN114972657A (en) Intelligent machine room management system and method based on three-dimensional model
CN202127289U (en) Electric control device of intelligent environment detection system of substation
CN102769339A (en) Intelligent security auxiliary system based on IEC 61850
CN204360200U (en) A kind of real-time monitoring system
CN211959265U (en) Monitoring device of intelligent cabinet and intelligent cabinet
CN202840684U (en) Intelligent security assistance system based on IEC 61850
CN203217337U (en) Multifunctional intelligent-building information comprehensively monitoring and managing system
CN115733880A (en) Wisdom fire control management system
CN113205598A (en) Laboratory management system based on three-dimensional visualization

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant