- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Sewage (AREA)
Abstract
The utility model discloses a kind of construction of hydro project pipeline fixing devices, including fixing seat, two the first fixed blocks are welded at the top of the fixing seat, the side that two the first fixed blocks are located remotely from each other is fixedly installed with driving motor, the side that two the first fixed blocks are located remotely from each other offers rotation hole, placed cavity is offered on two the first fixed blocks, placed cavity is connected with rotation hole, the output shaft of driving motor is through rotation hole and is welded with the first angular wheel, the second angular wheel is engaged on first angular wheel, screw rod is welded on second angular wheel, the top of first fixed block offers through-hole, through-hole is corresponding with placed cavity, the second fixed block is equipped with above two the first fixed blocks, the bottom of second fixed block offers thread groove.The utility model keeps pipeline solid and reliable in the laying operation of pipeline, and it is convenient to operate, and the pipeline for being adapted to different size is laid with, and adaptable, structure is simple, easy to use.
Description
Technical field
The utility model relates to hydraulic engineering technical field more particularly to a kind of construction of hydro project pipeline fixing devices.
Background technique
In construction of hydro project, it is often necessary to be laid with pipeline, in order to prevent pipe shifted, folder is set usually on pipeline
Circle, this clamping ring are easy to displacement in the construction surface of hydraulic engineering, influence the laying effect of pipeline, are not easy to construction personnel behaviour
Make, there are biggish difficulty of construction when construction, and there are problems that being difficult to continue to construct to the laying of the pipeline of different size.
Utility model content
Purpose of the utility model is to solve disadvantages existing in the prior art, and a kind of hydraulic engineering proposed is applied
Work pipeline fixing device.
To achieve the goals above, the utility model adopts the technical scheme that
A kind of construction of hydro project pipeline fixing device, including fixing seat are welded with two at the top of the fixing seat
One fixed block, the side that two the first fixed blocks are located remotely from each other are fixedly installed with driving motor, and two the first fixed blocks are mutual
Separate side offers rotation hole, offers placed cavity on two the first fixed blocks, and placed cavity is connected with rotation hole,
The output shaft of driving motor is through rotation hole and is welded with the first angular wheel, and the second conical tooth is engaged on the first angular wheel
It takes turns, is welded with screw rod on the second angular wheel, the top of the first fixed block offers through-hole, and through-hole is corresponding with placed cavity;
The second fixed block is equipped with above two the first fixed blocks, the bottom of the second fixed block offers thread groove, spiral shell
The top of bar extends in thread groove through through-hole, and screw rod is threadedly coupled with thread groove, and two the first fixed blocks are close to each other
Side and two the second fixed block sides close to each other be welded with fixture block, the side that two fixture blocks are located remotely from each other opens up
There is sliding eye, slide bar is slidably fitted in sliding eye, the side that two slide bars are located remotely from each other is fixedly installed with pull rod, two fixture blocks
It is respectively positioned between two pull rods, the side that two fixture blocks are located remotely from each other is fixedly mounted there are two the first spring, the first spring
One end is fixedly connected with corresponding pull rod.
Preferably, two fixture block sides close to each other offer arc groove, and two arc grooves are adapted.
Preferably, one end of the slide bar all extends in arc groove and is welded with block arc, two block arc phases
Cooperation.
Preferably, the top of two the first fixed blocks is welded with third fixed block, and two the second fixed blocks are located remotely from each other
Side be welded with sliding block, sliding block is slidably connected with corresponding third fixed block.
Preferably, placing groove is offered on the two sides inner wall of the sliding eye, the two sides of slide bar are uniformly provided with multiple
Limiting slot is slidably fitted with limited block on the inner wall of placing groove, and the side that limited block is located remote from slot notch is welded with the second bullet
The other end of one end of spring, second spring is welded on the inner wall of limiting slot, and limited block is adapted with limiting slot.
Preferably, annular spacing groove is offered on the inner wall of the through-hole, and ring limit block, annular limit are welded on screw rod
Position slot is adapted with ring limit block.
Compared with prior art, the utility model has the beneficial effects that
Pass through driving motor, the first angular wheel, the second angular wheel, screw rod, the second fixed block, thread groove and fixture block knot
The fixation of construction pipeline is realized in the cooperation of structure, starts driving motor, and the output shaft rotation of driving motor drives the first angular wheel
Rotation, the first angular wheel drive the rotation of the second angular wheel, and the second angular wheel drives screw rod rotation, and one end of screw rod is in spiral shell
Rotation drives the second fixed block to move up and down in groove, is connected by the drive that moves up and down of the second fixed block with the second fixed block
Fixture block it is mobile, to realize the fixation of construction pipeline,
Fastening pipeline specifications are realized by the cooperation of arc groove, sliding eye, slide bar, pull rod, the first spring and block arc
Adjusting pull pull rod, pull rod band moving slide-bar slides in sliding eye, while in sliding eye when needing to adjust pipeline specifications
Limited block release limit to slide bar, sliding bar drives block arc sliding, to realize the adjusting to pipeline specifications.
The utility model keeps pipeline solid and reliable in the laying operation of pipeline, and it is convenient to operate, and is adapted to different size
Pipeline is laid with, and adaptable, structure is simple, easy to use.
Detailed description of the invention
Fig. 1 be the utility model proposes a kind of construction of hydro project pipeline fixing device structural schematic diagram;
Fig. 2 be the utility model proposes a kind of construction of hydro project pipeline fixing device part A structural schematic diagram;
Fig. 3 be the utility model proposes a kind of construction of hydro project pipeline fixing device part B structural schematic diagram.
In figure: 1 fixing seat, 2 first fixed blocks, 3 driving motors, 4 rotation holes, 5 placed cavities, 6 first angular wheels, 7,
Two angular wheels, 8 screw rods, 9 through-holes, 10 second fixed blocks, 11 thread grooves, 12 fixture blocks, 13 arc grooves, 14 sliding eyes, 15 slide bars,
16 pull rods, 17 first springs, 18 block arcs, 19 third fixed blocks.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model
Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole
Embodiment.
Referring to Fig.1-3, a kind of construction of hydro project pipeline fixing device, including fixing seat 1, the top welding of fixing seat 1
There are two the first fixed block 2, the side that two the first fixed blocks 2 are located remotely from each other is fixedly installed with driving motor 3, and two first
The side that fixed block 2 is located remotely from each other offers rotation hole 4, offers placed cavity 5, placed cavity 5 on two the first fixed blocks 2
It is connected with rotation hole 4, the output shaft of driving motor 3 through rotation hole 4 and is welded with the first angular wheel 6, the first conical tooth
It is engaged with the second angular wheel 7 on wheel 6, screw rod 8 is welded on the second angular wheel 7, the top of the first fixed block 2 offers
Through-hole 9, through-hole 9 is corresponding with placed cavity 5, and the top of two the first fixed blocks 2 is equipped with the second fixed block 10, the second fixed block
10 bottom offers thread groove 11, and the top of screw rod 8 extends in thread groove 11 through through-hole 9, and screw rod 8 and thread groove 11
It is threadedly coupled, two the first fixed blocks 2 side close to each other and two the second fixed block 10 sides close to each other are welded
There is fixture block 12, the side that two fixture blocks 12 are located remotely from each other offers sliding eye 14, slide bar 15 is slidably fitted in sliding eye 14,
The side that two slide bars 15 are located remotely from each other is fixedly installed with pull rod 16, and two fixture blocks 12 are respectively positioned between two pull rods 16, and two
The side that fixture block 12 is located remotely from each other is fixedly mounted there are two the first spring 17, one end of the first spring 17 and corresponding pull rod 16
It is fixedly connected, passes through driving motor 3, the first angular wheel 6, the second angular wheel 7, screw rod 8, the second fixed block 10, thread groove
11 and 12 structure of fixture block cooperation, realize the fixation of construction pipeline, start driving motor 3, the output shaft of driving motor 3 rotates band
Dynamic first angular wheel 6 rotation, the first angular wheel 6 drive the rotation of the second angular wheel 7, and the second angular wheel 7 drives screw rod 8
Rotation, one end of screw rod 8 rotates in thread groove 11 drives the second fixed block 10 to move up and down, and passes through the upper of the second fixed block 10
It is lower it is mobile drive the fixture block 12 being connected with the second fixed block 10 to move, to realize the fixation for pipeline of constructing, by arc groove 13,
The adjusting for fastening pipeline specifications is realized in the cooperation of sliding eye 14, slide bar 15, pull rod 16, the first spring 17 and block arc 18,
When needing to adjust pipeline specifications, pull rod 16 is pulled, pull rod 16 slides in sliding eye 14 with moving slide-bar 15, while in sliding eye 14
Limited block release limit to slide bar 15, the sliding of slide bar 15 drives block arc 18 to slide, to realize to pipeline specifications
It adjusts, the utility model keeps pipeline solid and reliable in the laying operation of pipeline, and it is convenient to operate, and is adapted to the pipe of different size
Road is laid with, and adaptable, structure is simple, easy to use.
In the utility model, two fixture blocks 12 side close to each other offers arc groove 13, two 13 phases of arc groove
Adaptation, one end of slide bar 15 all extend in arc groove 13 and are welded with block arc 18, and two block arcs 18 match, and two
The top of a first fixed block 2 is welded with third fixed block 19, and the side that two the second fixed blocks 10 are located remotely from each other is welded
There is sliding block, sliding block is slidably connected with corresponding third fixed block 19, offers placing groove on the two sides inner wall of sliding eye 14, sliding
The two sides of bar 15 are uniformly provided with multiple limiting slots, and limited block is slidably fitted on the inner wall of placing groove, and limited block is located remote from
The side of slot notch is welded with one end of second spring, and the other end of second spring is welded on the inner wall of limiting slot, and limits
Block is adapted with limiting slot, and annular spacing groove is offered on the inner wall of through-hole 9, and ring limit block, annular limit are welded on screw rod 8
Position slot is adapted with ring limit block, solid by driving motor 3, the first angular wheel 6, the second angular wheel 7, screw rod 8, second
Determine the cooperation of 12 structure of block 10, thread groove 11 and fixture block, realize the fixation of construction pipeline, starts driving motor 3, driving motor 3
Output shaft rotation drive the first angular wheel 6 rotation, the first angular wheel 6 drive the second angular wheel 7 rotation, the second taper
Gear 7 drives screw rod 8 to rotate, and one end of screw rod 8 rotate the second fixed block 10 of drive in thread groove 11 and moves up and down, by the
Moving up and down for two fixed blocks 10 drives the fixture block 12 being connected with the second fixed block 10 mobile, to realize consolidating for construction pipeline
It is fixed, fastener tube is realized by the cooperation of arc groove 13, sliding eye 14, slide bar 15, pull rod 16, the first spring 17 and block arc 18
The adjusting of road specification pulls pull rod 16 when needing to adjust pipeline specifications, and pull rod 16 is sliding in sliding eye 14 with moving slide-bar 15
It is dynamic, while the limited block in sliding eye 14 releases the limit to slide bar 15, the sliding of slide bar 15 drives block arc 18 to slide, thus
Realize adjusting to pipeline specifications, the utility model keeps pipeline solid and reliable in the laying operation of pipeline, and it is convenient to operate, can be with
The pipeline for adapting to different size is laid with, and adaptable, structure is simple, easy to use.
Working principle: when needing fixed construction pipeline, start driving motor 3, the output shaft of driving motor 3, which rotates, to be driven
The rotation of first angular wheel 6, the first angular wheel 6 drive the rotation of the second angular wheel 7, and the second angular wheel 7 drives 8 turns of screw rod
Dynamic, one end of screw rod 8 rotates in thread groove 11 drives the second fixed block 10 to move up and down, above and below the second fixed block 10
It is mobile to drive the fixture block being connected with the second fixed block 10 mobile, to realize the fixation of construction pipeline, needing to adjust pipeline rule
When lattice, pull rod 16 is pulled, pull rod 16 slides in sliding eye 14 with moving slide-bar 15, while the limited block releasing pair in sliding eye 14
The limit of slide bar 15, the sliding of slide bar 15 drive block arc 18 to slide, when reaching required specification, stop drag pull rod
16, by 17 reaction force of the first spring, keep two slide bars 15 mobile to side close to each other, while passing through second spring
Reaction force slides into limited block in limiting slot, realizes limit to slide bar 15, thus realize adjusting to pipeline specifications and
It is fixed.
The preferable specific embodiment of the above, only the utility model, but the protection scope of the utility model is not
It is confined to this, anyone skilled in the art is within the technical scope disclosed by the utility model, practical according to this
Novel technical solution and its utility model design are subject to equivalent substitution or change, should all cover the protection model in the utility model
Within enclosing.
Claims (6)
1. a kind of construction of hydro project pipeline fixing device, including fixing seat (1), which is characterized in that the top of the fixing seat (1)
Portion is welded with two the first fixed blocks (2), and the side that two the first fixed blocks (2) are located remotely from each other is fixedly installed with driving motor
(3), the side that two the first fixed blocks (2) are located remotely from each other offers rotation hole (4), opens on two the first fixed blocks (2)
Equipped with placed cavity (5), placed cavity (5) is connected with rotation hole (4), and the output shaft of driving motor (3) through rotation hole (4) and welds
It is connected to the first angular wheel (6), is engaged on the first angular wheel (6) the second angular wheel (7), on the second angular wheel (7)
It is welded with screw rod (8), the top of the first fixed block (2) offers through-hole (9), and through-hole (9) is corresponding with placed cavity (5);
It is equipped with the second fixed block (10) above two the first fixed blocks (2), the bottom of the second fixed block (10) offers spiral shell
The top of groove (11), screw rod (8) extends in thread groove (11) through through-hole (9), and screw rod (8) and thread groove (11) screw thread
Connection, two the first fixed blocks (2) side close to each other and two the second fixed block (10) sides close to each other are welded
Have fixture block (12), the side that two fixture blocks (12) are located remotely from each other offers sliding eye (14), is slidably installed in sliding eye (14)
Have slide bar (15), the side that two slide bars (15) are located remotely from each other is fixedly installed with pull rod (16), and two fixture blocks (12) are respectively positioned on two
Between a pull rod (16), the side that two fixture blocks (12) are located remotely from each other is fixedly mounted there are two the first spring (17), the first bullet
One end of spring (17) is fixedly connected with corresponding pull rod (16).
2. a kind of construction of hydro project pipeline fixing device according to claim 1, which is characterized in that two fixture blocks (12)
Side close to each other offers arc groove (13), and two arc grooves (13) are adapted.
3. a kind of construction of hydro project pipeline fixing device according to claim 1, which is characterized in that the slide bar (15)
One end all extend in arc groove (13) and be welded with block arc (18), two block arcs (18) match.
4. a kind of construction of hydro project pipeline fixing device according to claim 1, which is characterized in that two first fixations
The top of block (2) is welded with third fixed block (19), and the side that two the second fixed blocks (10) are located remotely from each other is welded with cunning
Block, sliding block are slidably connected with corresponding third fixed block (19).
5. a kind of construction of hydro project pipeline fixing device according to claim 1, which is characterized in that the sliding eye
(14) offer placing groove on two sides inner wall, the two sides of slide bar (15) are uniformly provided with multiple limiting slots, placing groove it is interior
Limited block is slidably fitted on wall, the side that limited block is located remote from slot notch is welded with one end of second spring, second spring
The other end be welded on the inner wall of limiting slot, and limited block is adapted with limiting slot.
6. a kind of construction of hydro project pipeline fixing device according to claim 1, which is characterized in that the through-hole (9)
Inner wall on offer annular spacing groove, ring limit block is welded on screw rod (8), annular spacing groove is mutually fitted with ring limit block
Match.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820603821.8U CN208417756U (en) | 2018-04-26 | 2018-04-26 | A kind of construction of hydro project pipeline fixing device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820603821.8U CN208417756U (en) | 2018-04-26 | 2018-04-26 | A kind of construction of hydro project pipeline fixing device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208417756U true CN208417756U (en) | 2019-01-22 |
Family
ID=65117386
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820603821.8U Expired - Fee Related CN208417756U (en) | 2018-04-26 | 2018-04-26 | A kind of construction of hydro project pipeline fixing device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208417756U (en) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110454617A (en) * | 2019-09-04 | 2019-11-15 | 温州续影贸易有限公司 | A kind of anti-loosening pvc pipe channel fixing device |
CN111421295A (en) * | 2020-05-14 | 2020-07-17 | 周口易圣热力供应有限公司 | Welding fixture convenient for position adjustment for welding heat supply pipeline |
CN112013707A (en) * | 2020-09-08 | 2020-12-01 | 谢娟 | Waste heat recovery device for gas steam boiler |
CN113063035A (en) * | 2021-03-13 | 2021-07-02 | 江阴市众达建设有限公司 | Clamping claw for pipeline fixing device for municipal water supply and drainage construction |
CN113078586A (en) * | 2021-04-01 | 2021-07-06 | 金华永威机械设备有限公司 | Plum blossom pipe laying system |
CN113586806A (en) * | 2021-07-14 | 2021-11-02 | 张瑞 | Ocean engineering submarine pipeline erection device of two-way clamp formula |
CN114382951A (en) * | 2021-12-13 | 2022-04-22 | 中建五局安装工程有限公司 | Modularized pipeline installation method |
-
2018
- 2018-04-26 CN CN201820603821.8U patent/CN208417756U/en not_active Expired - Fee Related
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110454617A (en) * | 2019-09-04 | 2019-11-15 | 温州续影贸易有限公司 | A kind of anti-loosening pvc pipe channel fixing device |
CN111421295A (en) * | 2020-05-14 | 2020-07-17 | 周口易圣热力供应有限公司 | Welding fixture convenient for position adjustment for welding heat supply pipeline |
CN112013707A (en) * | 2020-09-08 | 2020-12-01 | 谢娟 | Waste heat recovery device for gas steam boiler |
CN113063035A (en) * | 2021-03-13 | 2021-07-02 | 江阴市众达建设有限公司 | Clamping claw for pipeline fixing device for municipal water supply and drainage construction |
CN113078586A (en) * | 2021-04-01 | 2021-07-06 | 金华永威机械设备有限公司 | Plum blossom pipe laying system |
CN113078586B (en) * | 2021-04-01 | 2022-12-13 | 山西双龙电力建设有限公司 | Plum blossom pipe laying system |
CN113586806A (en) * | 2021-07-14 | 2021-11-02 | 张瑞 | Ocean engineering submarine pipeline erection device of two-way clamp formula |
CN113586806B (en) * | 2021-07-14 | 2022-11-01 | 福建华航建设集团有限公司 | Ocean engineering submarine pipeline erection device of two-way clamp formula |
CN114382951A (en) * | 2021-12-13 | 2022-04-22 | 中建五局安装工程有限公司 | Modularized pipeline installation method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN208417756U (en) | A kind of construction of hydro project pipeline fixing device | |
CN105466662B (en) | A kind of wind-tunnel angle of attack adjusting apparatus | |
CN206446377U (en) | The variable flexible vehicle bridge of wheelspan | |
CN101954528B (en) | Arc swinging device for welding gun | |
CN106017853A (en) | Attack angle adjusting device | |
CN202491944U (en) | Lifting mechanism | |
CN103624472A (en) | Chuck clamping device | |
CN105293332B (en) | A kind of loaded self-adaptive type transmission mechanism of variable gear ratio | |
CN104913010A (en) | Double clutch structure reducer | |
CN202726043U (en) | Three-section telescopic boom type cantilever ginpole telescopic mechanism | |
CN204592194U (en) | A kind of linear actuators and quick release device thereof | |
CN203998384U (en) | A kind of construction steel cable wind2 | |
CN108915339A (en) | Electric pole repairing device | |
CN205979059U (en) | Automatic it is flexible from rapping bar and automatic telescopic link | |
CN206156480U (en) | A automatic winding and unwinding devices of chain for automatic mechanical float | |
CN204566798U (en) | Automatic paper bag handle rope knot tying machine | |
CN203614894U (en) | Hand-operated direction valve | |
CN104848751A (en) | Full-automatic arrow pulling device | |
CN203471028U (en) | Hydraulic cutting machine | |
CN208221574U (en) | A kind of magnetic material slice machine positioning device | |
CN208415247U (en) | A kind of municipal works piling equipment | |
CN208474435U (en) | A kind of hydraulic power station flow manual switching device | |
CN203176282U (en) | Device capable of converting between linear and rotary motions | |
CN106150328A (en) | The retracting decelerator of curtain | |
CN206439014U (en) | A kind of magnetic force rotation oil well pipe wrench and its control system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20190122 Termination date: 20200426 |