CN208415063U - A kind of road and bridge crack ruggedized construction - Google Patents

A kind of road and bridge crack ruggedized construction Download PDF

Info

Publication number
CN208415063U
CN208415063U CN201820879832.9U CN201820879832U CN208415063U CN 208415063 U CN208415063 U CN 208415063U CN 201820879832 U CN201820879832 U CN 201820879832U CN 208415063 U CN208415063 U CN 208415063U
Authority
CN
China
Prior art keywords
road
groove
horizontal steel
reinforcing bar
crack
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820879832.9U
Other languages
Chinese (zh)
Inventor
李莉
邝青云
叶晓勇
杨勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201820879832.9U priority Critical patent/CN208415063U/en
Application granted granted Critical
Publication of CN208415063U publication Critical patent/CN208415063U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Road Paving Structures (AREA)
  • Road Repair (AREA)

Abstract

The utility model discloses a kind of road and bridge crack ruggedized constructions, including road surface, the road surface is internally provided with crack body, and the first groove is provided with outside the body of crack, and first inside grooves are filled with asphalt road table body, and asphalt road table body lower part is fixedly connected with supporting block, the supporting block lower part is fixedly connected with the second groove, and the second inside grooves are provided with reinforcing bar, and the reinforcing bar lower part is provided with horizontal steel, and hole is set, and steel tank is provided with outside hole on the left of horizontal steel.The road and bridge crack ruggedized construction is dug in crack at V-shaped structure using crusher, then by the way that horizontal steel to be threadedly coupled with the steel tank being embedded in hole, to make horizontal steel and the first groove form inverted triangular structure, the first inside grooves structure can be enabled more stable, then reinforcing bar both ends are connected respectively on horizontal steel and supporting block, then concrete is poured into, so that the crack on road structure of repairing is more stable.

Description

A kind of road and bridge crack ruggedized construction
Technical field
The utility model relates to crack on road reinforcement technique field, specially a kind of road and bridge crack ruggedized construction.
Background technique
Development occurred for China's road swift and violent in recent years, but can satisfy the need in present traffic, natural cause and other reasons Face generates crack, so that the mechanism on road surface is made to be damaged, and so-called road and bridge ruggedized construction, refer to reliability deficiency Or owner requires the load-carrying members, component and its relevant portion that improve reliability to take enhancing, local replacing or adjust its internal force Equal measures, make it have safety required by current designs specification and owner, durability and applicability.
Road surface is destroyed usually using crusher in the road surface repaired in municipal administration now, then by ready concrete Floating is poured into, and this way cannot reinforce the structure on road surface, can only play a supporting role, to not be able to satisfy municipal road now The demand of road maintenance.
Utility model content
The purpose of this utility model is to provide a kind of road and bridge crack ruggedized constructions, to solve in above-mentioned background technique Road surface is destroyed usually using crusher in the road surface repaired in the present municipal administration proposed, then falls ready concrete Enter to smooth out, and this way cannot reinforce the structure on road surface, can only play a supporting role, to not be able to satisfy present town road The problem of demand of maintenance.
To achieve the above object, the utility model provides the following technical solutions: a kind of road and bridge crack ruggedized construction, packet Road surface is included, the road surface is internally provided with crack body, and the first groove is provided with outside the body of crack, and first inside grooves are filled out Filled with asphalt road table body, and asphalt road table body lower part is fixedly connected with supporting block, and the supporting block lower part is fixedly connected with second Groove, and the second inside grooves are provided with reinforcing bar, the reinforcing bar lower part is provided with horizontal steel, and hole is arranged on the left of horizontal steel, and And steel tank is provided with outside hole.
Preferably, first groove is V-shaped structure, and the first slot opening area is equal to the face of asphalt road table body Product.
Preferably, the supporting block and horizontal steel are symmetrical about reinforcing bar transverse axis, and reinforcing bar is vertical with horizontal steel composition Structure.
Preferably, the reinforcing bar and the second groove constitute screw connection structure, and reinforcing bar vertical distribution is in supporting block lower part.
Preferably, the horizontal steel and the first groove may make up an inverted triangular structure, and horizontal steel and steel tank constitute screw thread Connection structure.
Compared with prior art, the utility model has the beneficial effects that the road and bridge crack ruggedized construction is using broken Machine digs in crack at V-shaped structure, then by the way that horizontal steel to be threadedly coupled with the steel tank being embedded in hole, to make Horizontal steel and the first groove form inverted triangular structure, and the first inside grooves structure can be enabled more stable, then by reinforcing bar both ends point It is not connected in horizontal steel and supporting block, then pours into concrete, so that the crack on road structure of repairing is more stable.It should First groove of device is V-shaped structure, and the first slot opening area is equal to the area of asphalt road table body, this structure makes When carrying out crack on road repairing, crack can be dug into V-shaped structure by crusher, and will can be ready to again after laying Asphalt road table body be laid on the first groove upper surface, thus road surface repair is got well, supporting block and horizontal steel are about reinforcing bar cross It is distributed to axisymmetrical, and reinforcing bar and horizontal steel constitute vertical structure, this structure makes when placing under repair pavement crack, can be by steel Muscle passes through rotation respectively and is fixed with the groove in supporting block on the second groove and horizontal steel, then by concreting to support In the structure of block, horizontal steel and reinforcing bar composition, can thus be supported fissured structure fixation, and reinforcing bar and the second groove constitute spiral shell Line connection structure, and reinforcing bar vertical distribution, in supporting block lower part, this structure makes when carrying out pavement crack repair, it need to be by reinforcing bar It is connected respectively to one I-shape construction of formation on supporting block and horizontal steel, concrete can be enabled to be formed with the mutual structure of I-shape construction Rock-steady structure, horizontal steel and the first groove may make up an inverted triangular structure, and horizontal steel and steel tank constitute screw connection structure, this It, can one up-side down triangle knot of another horizontal steel and the formation of the first groove lower part when structure to dig crack body at the first groove structure Structure, to keep the bottom structure of the first groove more stable, to keep the fissured structure of repairing more stable.
Detailed description of the invention
Fig. 1 is the utility model schematic view of the front view;
Fig. 2 is the utility model overlooking structure diagram;
Fig. 3 is enlarged structure schematic diagram at A in the utility model Fig. 1.
In figure: 1, road surface, 2, asphalt road table body, the 3, first groove, 4, crack body, 5, supporting block, the 6, second groove, 7, steel Muscle, 8, horizontal steel, 9, hole, 10, steel tank.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work Every other embodiment obtained, fall within the protection scope of the utility model.
Fig. 1-3 is please referred to, the utility model provides a kind of technical solution: a kind of road and bridge crack ruggedized construction, including Road surface 1, road surface 1 are internally provided with crack body 4, and the first groove 3 is provided with outside crack body 4, and the first groove 3 is V-shaped knot Structure, and 3 opening area of the first groove is equal to the area of asphalt road table body 2, this structure makes when carrying out crack on road repairing, can Crack is dug into V-shaped structure by crusher, and ready asphalt road table body 2 can be laid on the again after laying One groove, 3 upper surface, thus gets well road surface repair, and asphalt road table body 2, and asphalt road table are filled with inside the first groove 3 2 lower part of body is fixedly connected with supporting block 5, and supporting block 5 is symmetrical about 7 transverse axis of reinforcing bar with horizontal steel 8, and reinforcing bar 7 and cross Steel 8 constitutes vertical structure, this structure makes when placing under repair pavement crack, reinforcing bar 7 can be passed through rotation and supporting block 5 respectively Groove on upper second groove 6 and horizontal steel 8 is fixed, and then forms concreting to supporting block 5, horizontal steel 8 and reinforcing bar 7 Structure in, can thus be supported fissured structure fixation, and 5 lower part of supporting block is fixedly connected with the second groove 6, and second Groove 6 is internally provided with reinforcing bar 7, and reinforcing bar 7 and the second groove 6 constitute screw connection structure, and 7 vertical distribution of reinforcing bar is in supporting block 5 lower parts, this structure make when carrying out pavement crack repair, need to be connected respectively to reinforcing bar 7 on supporting block 5 and horizontal steel 8 and be formed One I-shape construction can enable concrete and the mutual structure of I-shape construction form rock-steady structure, and 7 lower part of reinforcing bar is provided with horizontal steel 8, and hole 9 is set on the left of horizontal steel 8, and steel tank 10 is provided with outside hole 9, horizontal steel 8 and the first groove 3 may make up one Inverted triangular structure, and horizontal steel 8 and steel tank 10 constitute screw connection structure, this structure to dig crack body 4 at the first groove 3 When structure, separately an inverted triangular structure can be formed in horizontal steel 8 and 3 lower part of the first groove, to make the bottom structure of the first groove 3 It is more stable, to keep the fissured structure of repairing more stable.
Working principle: when using the road and bridge crack ruggedized construction, first check that the device is damaged with the presence or absence of part Or the case where being not connected firmly, check it is errorless after carry out again using, then with hand hold crusher alignment crack road surface dig at V word First groove 3 of shape structure then will be dug out 2 holes 9 on 3 two sides inner wall of the first groove with chisel, will be then ready to again Steel tank 10 be embedded into hole 9, then by horizontal steel 8 alignment steel tank 10 rotate, then horizontal 8 another side of steel is also inserted into again To in pre-buried good steel tank 10, horizontal steel 8 is rotated in the steel tank 10 of right side from left side steel tank 10, when two sides, all fixations can stop Rotation stop is dynamic, and then 7 lower thread of reinforcing bar is connected on horizontal steel 8, then 7 threaded upper ends of reinforcing bar are connected in supporting block 5 again, Then it is left 2 reinforcing bars 7 also to be installed according to above-mentioned, such first groove, 3 inner supporting structure is formed, then will be quasi- In the concreting got ready to the support construction formed, until concrete is flushed with supporting block 5, then equal concrete are solidifying After Gu, then ready asphalt road table body 2 is routed to above, then flattened asphalt road table body 2, such pavement crack Good with regard to constructing, here it is the working principles of the road and bridge crack ruggedized construction.
Although the utility model is described in detail with reference to the foregoing embodiments, come for those skilled in the art Say, it is still possible to modify the technical solutions described in the foregoing embodiments, or to part of technical characteristic into Row equivalent replacement, within the spirit and principle of the utility model, any modification, equivalent replacement, improvement and so on should all It is included within the scope of protection of this utility model.

Claims (5)

1. a kind of road and bridge crack ruggedized construction, including road surface (1), it is characterised in that: the road surface (1), which is internally provided with, to be split It stitches body (4), and is provided with the first groove (3) outside crack body (4), asphalt road table body is filled with inside first groove (3) (2), and asphalt road table body (2) lower part is fixedly connected with supporting block (5), and it is recessed that supporting block (5) lower part is fixedly connected with second Slot (6), and the second groove (6) is internally provided with reinforcing bar (7), reinforcing bar (7) lower part is provided with horizontal steel (8), and horizontal steel (8) is left Hole (9) are arranged in side, and are provided with steel tank (10) outside hole (9).
2. a kind of road and bridge crack ruggedized construction according to claim 1, it is characterised in that: first groove (3) For V-shaped structure, and the first groove (3) opening area is equal to the area of asphalt road table body (2).
3. a kind of road and bridge crack ruggedized construction according to claim 1, it is characterised in that: the supporting block (5) with Horizontal steel (8) is symmetrical about reinforcing bar (7) transverse axis, and reinforcing bar (7) and horizontal steel (8) constitute vertical structure.
4. a kind of road and bridge crack ruggedized construction according to claim 1, it is characterised in that: the reinforcing bar (7) and the Two grooves (6) constitute screw connection structure, and reinforcing bar (7) vertical distribution is in supporting block (5) lower part.
5. a kind of road and bridge crack ruggedized construction according to claim 1, it is characterised in that: the horizontal steel (8) and the One groove (3) may make up an inverted triangular structure, and horizontal steel (8) and steel tank (10) constitute screw connection structure.
CN201820879832.9U 2018-06-05 2018-06-05 A kind of road and bridge crack ruggedized construction Expired - Fee Related CN208415063U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820879832.9U CN208415063U (en) 2018-06-05 2018-06-05 A kind of road and bridge crack ruggedized construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820879832.9U CN208415063U (en) 2018-06-05 2018-06-05 A kind of road and bridge crack ruggedized construction

Publications (1)

Publication Number Publication Date
CN208415063U true CN208415063U (en) 2019-01-22

Family

ID=65110533

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820879832.9U Expired - Fee Related CN208415063U (en) 2018-06-05 2018-06-05 A kind of road and bridge crack ruggedized construction

Country Status (1)

Country Link
CN (1) CN208415063U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110952509A (en) * 2019-12-23 2020-04-03 中国地质大学(北京) Earth and rockfill dam crack repairing structure and repairing method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110952509A (en) * 2019-12-23 2020-04-03 中国地质大学(北京) Earth and rockfill dam crack repairing structure and repairing method thereof

Similar Documents

Publication Publication Date Title
CN206553864U (en) A kind of road and bridge crack bracing means
CN104947603B (en) A kind of rc beam bridge girder reinforcing construction and reinforcement means
CN102995572B (en) The method of attachment of Thin-wall Hollow Pier and former pier stud and device thereof after bridge jacking
CN104674660B (en) A kind of cored slab hinge crack structure and construction method thereof
CN103726613B (en) A kind of novel fabricated concrete column
CN205444968U (en) Bar planting anchor structure
CN109537929A (en) Demolishing columns bracing means and reinforcement means
CN208415063U (en) A kind of road and bridge crack ruggedized construction
CN108708452A (en) The U-shaped integral prefabricated window member that floats, assembled float window joint structure and its construction method
CN105672144A (en) Medium-small span old bridge reinforcement and jointing-widening structure and construction method thereof
CN208266912U (en) A kind of roadbed section retaining wall
CN103061357A (en) Connection joint between basement base plate and underground diaphragm wall
CN204491412U (en) A kind of hollow sheet hinge crack structure
CN106759563A (en) A kind of device for pile foundation repairing and reinforcing and the construction method using the device
CN207176482U (en) A kind of municipal bridge-collision-avoidance wall
CN206545159U (en) A kind of road deck concrete construction formwork
CN206266980U (en) A kind of road and bridge crack bracing means
CN204589831U (en) A kind of rc beam bridge girder reinforcing construction
CN208649865U (en) A kind of road and bridge crack ruggedized construction
CN208167566U (en) Spelling width bridge based on overhanging simply supported slab structure
CN208266667U (en) A kind of bridge pier structure
CN105951987A (en) Sub-frame post-cast joint with external permanent aluminum plate outer mold
CN207376488U (en) A kind of road and bridge crack bracing means
CN211665599U (en) Road and bridge crack repairing and fixing structure
CN209975293U (en) Road bridge road bed reinforced structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190122

CF01 Termination of patent right due to non-payment of annual fee