CN208382429U - A kind of new blower of included hot and cold water circulation-supplied - Google Patents

A kind of new blower of included hot and cold water circulation-supplied Download PDF

Info

Publication number
CN208382429U
CN208382429U CN201820628433.5U CN201820628433U CN208382429U CN 208382429 U CN208382429 U CN 208382429U CN 201820628433 U CN201820628433 U CN 201820628433U CN 208382429 U CN208382429 U CN 208382429U
Authority
CN
China
Prior art keywords
way valve
coil
hot
air
port
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820628433.5U
Other languages
Chinese (zh)
Inventor
许曼
彭强强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu 365 Indoor Environment Technology Co Ltd
Original Assignee
Jiangsu 365 Indoor Environment Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu 365 Indoor Environment Technology Co Ltd filed Critical Jiangsu 365 Indoor Environment Technology Co Ltd
Priority to CN201820628433.5U priority Critical patent/CN208382429U/en
Application granted granted Critical
Publication of CN208382429U publication Critical patent/CN208382429U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Other Air-Conditioning Systems (AREA)

Abstract

The utility model discloses a kind of new blowers of included hot and cold water circulation-supplied, including indoor blower and outdoor host computer, and wherein indoor blower is mainly the processing to fresh air, and main includes again hot coil, the second evaporator coil, the first evaporator coil;Outdoor unit undertakes the function of condenser and cold and hot water process, mainly includes compressor, four-way valve, condenser coil, plate heat exchanger.By being combined new blower and cold and hot wetting system to form an independent system, not only realize constant temperature, constant humidity, permanent oxygen, permanent net target, and it is easy to control, cost is lower, safe and reliable, installation simplifies, energy saving, low noise.

Description

A kind of new blower of included hot and cold water circulation-supplied
Technical field
The utility model relates to a kind of new blowers, more particularly, to a kind of new blower of included hot and cold water circulation-supplied.
Background technique
In current HVAC system design field, in order to allow interior to reach constant temperature, constant humidity, permanent oxygen, permanent net state, generally use The mode of new Fan Equipment collocation hot and cold water host equipment, wherein new Fan Equipment main purpose is by outdoor fresh air air-treatment To the temperature and humidity of human comfort, the PM2.5 in outdoor air is filtered, while continuous to indoor supply fresh air, guarantees room Interior oxygen is sufficient.And on the one hand hot and cold water host gives new blower supply hot and cold water to carry out cold cycling, meet new fan operation need It asks;On the other hand hot and cold water is supplied to indoor radiating system or fan coil, to undertake indoor cooling and heating load.
However there are problems in actual use in existing this collocation, such as:
New Fan Equipment and hot and cold water host equipment are usually different equipment manufacturer and carry out development & production, and client is made Type selecting collocation has relatively high requirement, if mismatch, effect that may be final can be very unsatisfactory.
Two sets of equipment are each accounted for bigger space, larger for the requirements of installation space of client, for small apartment Client, the space not used at all.
The cost price of two sets of equipment superposition is very high, is only applicable to high-end user crowd at present, ordinary consumer is difficult to hold By.
For the centralized control of equipment, two sets of equipment often have respectively different communications protocol and baud rate, to intelligence Household centralized control system brings inconvenience.
There is higher requirement for integrated and controlled software developer, it is necessary to assure two sets of equipment harmony collocation operations, ability Guarantee that whole system is stablized.
System stability needs by two sets of equipment while guaranteeing, if one of them goes wrong, then whole system will It is difficult to maintain.
HVAC installation is complicated, and the water lines of water chiller-heater unit not only need to supply new blower, it is also necessary to radiation in supply room System or fan coil, water piping system are complicated.
The water flow assignment problem of hot and cold water host leans on heat pump main frame if new blower does not have individual water pump to supply water entirely Water pump supplies water, then the water flow for being likely to result in new blower is unstable, and then leads to new blower fluctuation of service, or even therefore Barrier or damage, if there is independent water pump supplies water to new blower, then can additionally increase cost and water lines installation space.
Energy consumption is high, since the cooling and warming of water chiller-heater unit needs to belong to secondary heat exchange, system pipeline by transmitting in fact In there are various losses, power consumption is also not what common customer can be born.
Anti-freeze design, for the new wind devices with water coil, it is necessary to additionally consider anti-freeze design, otherwise winter temperature compared with Low operating condition, water coil are very easy to bursting by freezing, this all occurred in many Engineering Projects.
In double-cold source fresh air handling unit, there are compressor and blower in inside while running, and noise not can avoid.
Therefore, how to realize that new blower has been combined with cold and hot wetting system into this field urgent problem to be solved.
Utility model content
The purpose of the utility model is to overcome the defects of background technique, a kind of included hot and cold water circulation-supplied is provided New blower is combined new blower and cold and hot wetting system to form an independent system, not only realizes constant temperature, constant humidity, perseverance Oxygen, permanent net target, and it is easy to control, cost is lower, safe and reliable, installation simplifies, energy saving, low noise.
To achieve the above object, the utility model provides the following technical solutions: a kind of included hot and cold water circulation-supplied it is new Blower, including indoor blower and outdoor host computer, the indoor blower include air supply duct connection indoor and outdoors, air-supply The first evaporator coil, the second evaporator coil are sequentially arranged with by outdoor end to indoor end in pipeline;
The outdoor host computer includes duplex cylinder compressor, the first four-way valve, the second four-way valve, condenser coil and plate-type heat-exchange Device, the first port that wherein gas outlet of duplex cylinder compressor divides two-way to be separately connected the first four-way valve and the second four-way valve, and the The second port of one four-way valve and the second four-way valve connects one end of condenser coil, and the of the first four-way valve and the second four-way valve Three ports are separately connected the air entry of two cavitys of duplex cylinder compressor, the 4th port difference of the first four-way valve and the second four-way valve Connect one end of the first evaporator coil and the second evaporator coil, the first evaporator coil and the second evaporator coil it is another End connects the other end of condenser coil, the plate heat exchanger by the first electric expansion valve and the second electric expansion valve respectively The both ends in left side are separately connected the 4th port of condenser coil and the first four-way valve, and fill on the pipeline of connection condenser coil There is plate to change electric expansion valve, the plate heat exchanger other side is passed through recirculated water.
It is additionally provided with again hot coil in the air supply duct and is located at indoor end, one end connects the second four-way valve by pipeline Second port, the other end connects the other end of condenser coil by reheating electric expansion valve, to the sky to freeze in air supply duct Gas carries out reheating.
For the duplex cylinder compressor tool there are two air entry and a gas outlet, inside has two cavitys of high pressure and low pressure, And two cavitys respectively correspond two air entries, the third port of the first four-way valve connects the air entry of high pressure chest by gas point, The air entry that the third port of second four-way valve passes through gas point connection low pressure chamber.
The gas outlet of the duplex cylinder compressor is connected with oil.
The indoor blower further includes that air filter is mounted on one end that air supply duct is located outside, to the new of feeding Wind is filtered.
The indoor blower further includes that wet-membrane humidifier is mounted on air supply duct and is located at indoor one end, in winter when pair Fresh air is humidified.
Compared with prior art, the revealed a kind of new blower of included hot and cold water circulation-supplied of the utility model, has It is following the utility model has the advantages that
New blower and hot and cold water host equipment are combined, using a compressor loop simultaneously realize Fresh air handing and Hot and cold water circulation provides, and using duplex cylinder compressor high-low pressure cavity is separated, and implements spatial scalable compression improves system entirety COP, saves The problem of energy consumption, the new blower in conjunction with after greatly reduce overall volume and cost, and there is no equipment collocation conflicts, can be with Ensure entire blower stable operation;
Various heat exchange processing may be implemented by multi-circuit evaporator coil pipe combination plate heat exchanger in total, it is entire to pacify Assembling structure is simplified, and realizes quick installation, securely and reliably;
Compressor is arranged in outdoor, noise can be greatly reduced, promote indoor comfort level.
Detailed description of the invention
Fig. 1 is the systematic schematic diagram of the utility model;
Fig. 2 is the utility model refrigeration cycle schematic diagram;
Fig. 3 is that the utility model heats circulation theory figure.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work Every other embodiment obtained, fall within the protection scope of the utility model.
As shown in Figure 1, a kind of revealed new blower of included hot and cold water circulation-supplied of the utility model, new blower is set It is standby to be combined with hot and cold water host equipment, realize that the air-treatment of new blower and hot and cold water circulation supply using a compressor It answers.
Specific structure includes indoor fan and outdoor host computer, and the indoor fan includes air supply duct 1, air filter 2, wet-membrane humidifier 3, the first evaporator coil 4, the second evaporator coil 5 and reheating coil pipe 6, wherein 1 communication chamber of air supply duct It is interior and outdoor, outdoor fresh air is sent into interior, the air filter 2 is mounted on one end that air supply duct 1 is located outside, right The air of sucking carries out PM2.5 and the filtering of other particulate matters, it is ensured that is sent into the cleanliness of fresh air, the wet-membrane humidifier 3 is pacified It is located at indoor one end mounted in air supply duct 2, the fresh air of feeding is humidified when being sent into warm wind in winter, it is ensured that indoor control Humidity is comfortable, and first evaporator coil 4, the second evaporator coil 5 and reheating coil pipe 6 are sequentially arranged in air supply duct, And first evaporator coil 4 close to outdoor end, the fresh air of outdoor feeding be filtered after by the first evaporator coil and second Evaporator coil carries out secondary cooling (summer) or heating (winter) twice is sent into after forming preference temperature afterwards and is sent into interior, described Hot coil is positioned close to indoor end again, and in summer, two evaporator coils reduce temperature, but the temperature is relaxed lower than human body Thermophilic angle value, therefore air is carried out by hot rise by a reheating coil pipe, reach human comfort's temperature value.
The outdoor host computer includes duplex cylinder compressor 7, the first four-way valve 8, the second four-way valve 9, condenser coil 10 and plate Formula heat exchanger 11, wherein there are two air entry and a gas outlets for the tool of duplex cylinder compressor 1, and inside is divided into two chambers of high pressure and low pressure Body, and two cavitys respectively correspond two air entries, and the pipeline of gas outlet connection is by being divided into two-way after oil 12, respectively The first port of the first four-way valve 8 and the second four-way valve 9 is connected, the second port connection of the first four-way valve and the second four-way valve is cold The third port of one end of condenser coils 9, the first four-way valve and the second four-way valve passes through connection twin-tub compression after gas point 13 respectively 4th port of the air entry of machine high pressure chest and low pressure chamber, the first four-way valve and the second four-way valve is separately connected the first evaporator plate The other end of one end of pipe and the second evaporator coil, first evaporator coil 4 and the second evaporator coil 5 passes through respectively The other end of first electric expansion valve 14 and the second electric expansion valve 15 connection condenser coil, reheating disk one end passes through pipe Road connects the second port of the second four-way valve, and the other end connects the other end of condenser coil by reheating electric expansion valve 16, The both ends in 11 left side of plate heat exchanger are separately connected the 4th port of condenser coil and the first four-way valve, and connect condensation Electric expansion valve 17 is changed equipped with plate on the pipeline of device coil pipe, is passed through recirculated water on the right side of plate heat exchanger, which is to work as front ring The water of border temperature, the normal-temperature water that will be fed into summer are cooled to cold feed to radiating system or fan coil to indoor system It is cold, and radiating system or fan coil are supplied to indoor heating after the normal-temperature water heating that winter time is sent into.
A kind of revealed new blower of included hot and cold water circulation-supplied of the utility model specifically freezes and heats and follows Ring principle are as follows:
Refrigeration cycle
As shown in Fig. 2, cooling down by the new blower to the fresh air of feeding in summer, while cold water is provided, the mode The first port of lower first four-way valve and the second four-way valve is connected to second port, and third port is connected to the 4th port, twin-tub The high temperature and high pressure gas of compressor output is divided into the first port that two-way is sent into two four-way valves, the gas come out from second port It is divided into two-way after collecting, feeding condenser coil carries out cooling and forms liquid refrigerants all the way, and another way is sent directly into hot coil again, The liquid refrigerants that condenser coil comes out is divided into three tunnels, is changed after electric expansion valve carries out reducing pressure by regulating flow by plate form gas-liquid all the way Two-phase refrigerant, carries out heat exchange to the normal-temperature water for being sent into plate heat exchanger, and normal-temperature water is become cold water, and gas-liquid two-phase refrigerant is logical Completely gaseous low temperature refrigerant (temperature is higher than temperature before heat exchange) is formed after crossing heat exchange, the second tunnel that condenser coil comes out is logical It is sent into the first evaporator coil after crossing the first electric expansion valve reducing pressure by regulating flow, the high humidity high fever fresh air of feeding is once dropped Temperature, so that air themperature decreases, third road liquid refrigerants is sent into the second steaming after passing through the second electric expansion valve reducing pressure by regulating flow Device coil pipe is sent out, the fresh air after primary cooling is cooled down twice, the temperature value after reducing temperature twice is relatively low, therefore passes through reheating Coil pipe carries out hot rise, because what is be sent into hot coil again is initial high temperature and high pressure gas, it is achieved that lower to temperature Fresh air carries out hot rise, complies with human comfort's temperature value, then the refrigerant that hot coil comes out passes through after reheating electric expansion valve The refrigerant come out with condenser coil is collected, and the gaseous coolant and plate heat exchanger that first evaporator coil comes out go out The complete gaseous low temperature refrigerant come is sent into the 4th port of the first four-way valve after collecting, and it is corresponding to be sent into compressor high pressure chest Air entry, formation circulation loop, and the low-pressure gaseous refrigerant that the second evaporator coil comes out, it is sent into the 4th end of the second four-way valve Mouthful, and it is sent into the corresponding air entry of compressor low pressure chamber, form another circulation loop.
In entire cyclic process, plate heat exchanger is for reducing water temperature, by cold feed to radiating system or wind Machine coil pipe gives indoor refrigeration, and two evaporator coils are used to reduce and dehumidify to new air temperature, wherein the first evaporator plate is effective In preliminary cooling, the second evaporator coil dehumidifies for deep temperature reduction, and fresh air is by after cool-down dehumidification, then passes through reheating coil pipe liter Temperature processing is sent into the temperature and humidity that indoor fresh air reaches human comfort to allow.
Heating circulation
As shown in figure 3, heating up in winter by the new blower to the fresh air of feeding, while hot water is provided, the mode The first port of lower first four-way valve and the second four-way valve is connected to the 4th port, and second port is connected to third port, twin-tub Compressor sends out high temperature and high pressure gas and is divided into two-way two four-way valves of feeding, wherein the high temperature and high pressure gas that the first four-way valve comes out It is divided into two-way, wherein being sent into the first evaporator coil all the way, primary heating is carried out to the low temperature fresh air of entrance, another way is sent into plate Formula heat exchanger heats the water at low temperature being passed through, and forms hot water and sends out, and the high temperature and high pressure gas that the second four-way valve comes out is sent Enter the second evaporator coil and reheating, the first evaporation gas coil pipe and the second evaporator coil are carried out to the fresh air after primary heating It is cold that room temperature liquid refrigerants out forms gas-liquid two-phase after the first electric expansion valve and the second electric expansion valve reducing pressure by regulating flow Matchmaker, and the gas-liquid two-phase refrigerant come out with electric expansion valve after plate heat exchanger collect being sent into condenser coil and be inhaled Thermal evaporation forms gaseous coolant, the second port for dividing two-way to be respectively fed to the first four-way valve and the second four-way valve, and from third end Mouth is sent to the air entry of duplex cylinder compressor, and a circulation loop is integrally formed.
In entire cyclic process, plate heat exchanger supplies radiating system or fan coil to interior for water to heat up Heating, two evaporator coils, which are used to heat up to fresh air, guarantees that supply air temperature is suitable for, and wet-membrane humidifier is used to humidify to fresh air, protects It is comfortable to demonstrate,prove blasting humidity.
Finally it should be noted that: above embodiments are only to illustrate the technical solution of the utility model rather than limit it System;Although the utility model has been described in detail with reference to the preferred embodiment, those of ordinary skill in the art are still Specific implementation of the utility model can be modified or some technical features can be equivalently replaced, but as long as not It is detached from the spirit of technical solutions of the utility model, should all cover and work as in the claimed technical proposal scope of the utility model In.

Claims (6)

1. a kind of new blower of included hot and cold water circulation-supplied, including indoor blower and outdoor host computer, it is characterised in that:
The indoor blower includes air supply duct connection indoor and outdoors, is successively filled in air supply duct by outdoor end to indoor end There are the first evaporator coil, the second evaporator coil;
The outdoor host computer includes duplex cylinder compressor, the first four-way valve, the second four-way valve, condenser coil and plate heat exchanger, The wherein first port that the gas outlet of duplex cylinder compressor divides two-way to be separately connected the first four-way valve and the second four-way valve, and the one or four Port valve connects one end of condenser coil, the third end of the first four-way valve and the second four-way valve with the second port of the second four-way valve Mouth is separately connected the air entries of two cavitys of duplex cylinder compressor, and the 4th port of the first four-way valve and the second four-way valve is separately connected The other end of one end of first evaporator coil and the second evaporator coil, the first evaporator coil and the second evaporator coil point Not Tong Guo the first electric expansion valve and the second electric expansion valve connect the other end of condenser coil, on the left of the plate heat exchanger Both ends be separately connected the 4th port of condenser coil and the first four-way valve, and connect and plate be housed on the pipeline of condenser coil Electric expansion valve is changed, the plate heat exchanger other side is passed through recirculated water.
2. a kind of new blower of included hot and cold water circulation-supplied according to claim 1, it is characterised in that: the air supply tube It is additionally provided with again hot coil in road and is located at indoor end, one end connects the second port of the second four-way valve by pipeline, and the other end is logical The other end for crossing reheating electric expansion valve connection condenser coil carries out reheating to the air to freeze in air supply duct.
3. a kind of new blower of included hot and cold water circulation-supplied according to claim 1, it is characterised in that: the twin-tub pressure There are two air entry and a gas outlets for contracting equipment, and inside has two cavitys of high pressure and low pressure, and two cavitys respectively correspond Two air entries, air entry of the third port of the first four-way valve by gas point connection high pressure chest, the third end of the second four-way valve The air entry that mouth passes through gas point connection low pressure chamber.
4. a kind of new blower of included hot and cold water circulation-supplied according to claim 1, it is characterised in that: the twin-tub pressure The gas outlet of contracting machine is connected with oil.
5. a kind of new blower of included hot and cold water circulation-supplied according to claim 1, it is characterised in that: send the interior Blower further includes that air filter is mounted on one end that air supply duct is located outside, and is filtered to the fresh air of feeding.
6. a kind of new blower of included hot and cold water circulation-supplied according to claim 1, it is characterised in that: send the interior Blower further includes that wet-membrane humidifier is mounted on air supply duct and is located at indoor one end, in winter when fresh air is humidified.
CN201820628433.5U 2018-04-28 2018-04-28 A kind of new blower of included hot and cold water circulation-supplied Expired - Fee Related CN208382429U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820628433.5U CN208382429U (en) 2018-04-28 2018-04-28 A kind of new blower of included hot and cold water circulation-supplied

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820628433.5U CN208382429U (en) 2018-04-28 2018-04-28 A kind of new blower of included hot and cold water circulation-supplied

Publications (1)

Publication Number Publication Date
CN208382429U true CN208382429U (en) 2019-01-15

Family

ID=64973522

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820628433.5U Expired - Fee Related CN208382429U (en) 2018-04-28 2018-04-28 A kind of new blower of included hot and cold water circulation-supplied

Country Status (1)

Country Link
CN (1) CN208382429U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108548256A (en) * 2018-04-28 2018-09-18 江苏三六五室内环境科技有限公司 A kind of new wind turbine of included hot and cold water circulation-supplied
CN111795427A (en) * 2019-04-09 2020-10-20 恒泽节能有限公司 Regulating system for regulating air temperature, humidity and water temperature by using outdoor air heat exchanger

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108548256A (en) * 2018-04-28 2018-09-18 江苏三六五室内环境科技有限公司 A kind of new wind turbine of included hot and cold water circulation-supplied
CN111795427A (en) * 2019-04-09 2020-10-20 恒泽节能有限公司 Regulating system for regulating air temperature, humidity and water temperature by using outdoor air heat exchanger

Similar Documents

Publication Publication Date Title
WO2016179884A1 (en) Variable-refrigerant-flow radiant air-conditioning system
CN103615788B (en) A kind of control method of air conditioner
CN108679870A (en) A kind of warm and humid sub-control air-conditioning system with Fresh air handing function
CN204128094U (en) A kind of small and exquisite lustration type fresh air dehumidifier
CN205717538U (en) Mixed ventilation heating air conditioning equipment
CN107270447A (en) A kind of capillary radiation special air conditioner heat pump fresh air group and its control method
CN215951606U (en) Residential fifth-constant system based on centralized cooling and heating
CN108548256A (en) A kind of new wind turbine of included hot and cold water circulation-supplied
CN208382429U (en) A kind of new blower of included hot and cold water circulation-supplied
CN101806473A (en) Fresh air processor with split twin-stage surface coolers and method for processing air by same
CN106705298A (en) Multi-connection type fresh air conditioner unit with exhaust air heat pump heat recovery function and heat exchange method
CN205561111U (en) Constant temperature dehumidification system
CN103453691A (en) Three-in-one air conditioner and hot water supply device
CN207881275U (en) It is a kind of using dual-condition heat pump as the capillary radiation system of Cooling and Heat Source
CN102840634B (en) A kind of air-conditioning system
CN113701247A (en) Solution humidifying fresh air handling unit based on water-ring heat pump heat source
CN206488406U (en) A kind of air-conditioner set of pair of evaporating temperature
CN108443960A (en) A kind of VRF Air Conditioning System with fresh air function
CN208567194U (en) A kind of air-conditioning system of complete straight swollen type independent temperature-humidity control
CN208936579U (en) A kind of fresh air conditioner system of independent temperature-humidity control
CN103292398A (en) Composite air conditioning system integrating air-blowing air conditioner with radiation tail end
CN206683104U (en) Multifunctional composite central air-conditioning VMC
CN215951605U (en) Residential five-constant system with exhaust heat recovery function
CN108679869A (en) A kind of complete straight swollen warm and humid sub-control air-conditioning system of type of list refrigerant circuit
CN202303701U (en) Central air conditioning system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190115