CN208347276U
CN208347276U CN201721466909.1U CN201721466909U CN208347276U CN 208347276 U CN208347276 U CN 208347276U CN 201721466909 U CN201721466909 U CN 201721466909U CN 208347276 U CN208347276 U CN 208347276U
Authority
CN
China
Prior art keywords
support
bar
fixedly connected
support rod
loop bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721466909.1U
Other languages
Chinese (zh)
Inventor
刘洋
崔海超
王辉
商孟全
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong University of Science and Technology
Original Assignee
Shandong University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong University of Science and Technology filed Critical Shandong University of Science and Technology
Priority to CN201721466909.1U priority Critical patent/CN208347276U/en
Application granted granted Critical
Publication of CN208347276U publication Critical patent/CN208347276U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The utility model discloses a kind of construction brackets, including two first support bars, the 4th support rod is fixedly connected at the top of two first support bars, two the 4th support rods are successively arranged with the first loop bar, the second loop bar and the 4th loop bar from the bottom to top, the top of 4th support rod is fixedly connected with second support bar, and the top of second support bar is arranged with third loop bar.The hook that the utility model is equipped with, protective net can be hooked, the safety of construction personnel is protected, hook can hang some posters simultaneously, the pin being equipped with, inserted link and level meter, first support bar can be steadily inserted in soil, the position of first support bar can be adjusted according to horizon bar, so that the level meter fixed plate and working plate that are fixed on the 4th support rod can be with horizontal stables, construction personnel is facilitated to construct on working plate, the third loop bar being equipped with, iron chains and working plate, the stability of working plate can be increased, to further ensure the safety of construction personnel.

Description

A kind of construction bracket
Technical field
The utility model relates to technical field of building construction, specially a kind of construction bracket.
Background technique
With the acceleration of urbanization process, construction is seen everywhere, and bracket is often used in construction, still Traditional bracket is not sufficiently stable, and when construction personnel constructs with bracket, safety is lower, therefore we make this and change Into proposing a kind of construction bracket.
Summary of the invention
Inadequate for solution construction support stability of the existing technology, the lower defect of safety, this is practical It is novel that a kind of construction bracket is provided.
In order to solve the above-mentioned technical problem, the utility model provides the following technical solution:
A kind of construction bracket of the utility model, including two first support bars, two first support bars Top is fixedly connected to the 4th support rod, and two the 4th support rods are successively arranged with the first loop bar, second from the bottom to top Loop bar and the 4th loop bar, the top of the 4th support rod are fixedly connected with second support bar, the top of the second support bar It is arranged with third loop bar, level meter fixed plate, level meter fixed plate top are fixedly connected between two first loop bars The groove in portion is embedded to be connected to level meter, and the two sides of two second loop bars are fixed with hook, two the 4th loop bars Be fixedly connected respectively with the connecting rod that is equipped with of work board ends, two third loop bars by four iron chains respectively with working plate Both ends be fixedly connected, the top of the second support bar is fixedly connected with third support rod, the top of the third support rod It is arranged with serum cap, is fixedly connected at the top of the bottom of the first support bar and substrate, pin is arranged surely at the bottom of the substrate With taper inserted link.
Further, the surface of the 4th support rod and third support rod side is respectively equipped with the first shrinkage pool and second recessed Hole, the 4th support rod pass through the first shrinkage pool by screw rod and are fixedly connected with the first loop bar, and the third support rod passes through spiral shell Bar passes through the second shrinkage pool and is fixedly connected with third loop bar.
Further, the surface of the working plate is equipped with several apertures to assume diamond in shape.
Further, the taper inserted link and pin are fixedly connected by screw rod with the bottom of first support bar.
Compared with prior art, the utility model has the following beneficial effects: this kind of construction bracket, the extension being equipped with Hook can hook protective net, protect to the safety of construction personnel, while hook can hang some posters, the pin that is equipped with, First support bar can be steadily inserted in soil by inserted link and level meter, can adjust first support bar according to horizon bar Position, so that the level meter fixed plate and working plate that are fixed on the 4th support rod can facilitate construction personnel to exist with horizontal stable It constructs on working plate, third loop bar, iron chains and the working plate being equipped with can increase the stability of working plate, to further protect The safety of construction personnel is demonstrate,proved.
Detailed description of the invention
Fig. 1 is a kind of structural schematic diagram of construction bracket of the utility model;
Fig. 2 is a kind of first support bar structural schematic diagram of construction bracket of the utility model;
Fig. 3 is a kind of second support bar structural schematic diagram of construction bracket of the utility model;
Fig. 4 is a kind of second support bar side structural schematic diagram of construction bracket of the utility model;
Fig. 5 is a kind of working plate structural schematic diagram of construction bracket of the utility model.
In figure: 1, first support bar;2, pin;3, substrate;4, the first loop bar;5, level meter;6, it links up with;7, second set Bar;8, level meter fixed plate;9, iron chains;10, working plate;11, third loop bar;12, second support bar;13, third support rod; 14, serum cap;15, the second shrinkage pool;16, connecting rod;17, inserted link;18, the first shrinkage pool;19, the 4th support rod;20, the 4th set Bar.
Specific embodiment
To be easy to understand the technical means, creative features, achievement of purpose, and effectiveness of the utility model, below In conjunction with specific embodiment, the utility model is further described.
As shown in Figs. 1-5, a kind of construction bracket, the top including two first support bars, 1 two first support bars 1 Portion is fixedly connected to the 4th support rod 19, and two the 4th support rods 19 are successively arranged with 4, second sets of the first loop bar from the bottom to top Bar 7 and the 4th loop bar 20, the top of the 4th support rod 19 are fixedly connected with second support bar 12, the top set of second support bar 12 Equipped with third loop bar 11, level meter fixed plate 8 is fixedly connected between two the first loop bars 4, it is recessed at the top of level meter fixed plate 8 Slot is embedded to be connected to level meter 5, and the two sides of two the second loop bars 7 are fixed with hook 6, two the 4th loop bars 20 respectively with work The connecting rod 16 that 10 both ends of plate are equipped with is fixedly connected, and two third loop bars 11 pass through two of four iron chains 9 respectively with working plate 10 End is fixedly connected, and the top of second support bar 12 is fixedly connected with third support rod 13, and the top of third support rod 13 is arranged with The bottom of serum cap 14, first support bar 1 is fixedly connected with the top of substrate 3, and the bottom of substrate 3 has pin 2 and taper to insert surely Bar 17.
Wherein, the surface of 13 side of the 4th support rod 19 and third support rod is respectively equipped with the first shrinkage pool 18 and the second shrinkage pool 15, the 4th support rod 19 passes through the first shrinkage pool 18 by screw rod and is fixedly connected with the first loop bar 4, and third support rod 13 passes through screw rod It is fixedly connected across the second shrinkage pool 15 with third loop bar 11, makes to be fixedly connected more more stable and stronger by screw rod.
Wherein, the surface of working plate 10 is equipped with several apertures to assume diamond in shape, mitigates the weight of working plate 10, diamond shaped openings Can be anti-skidding and avoid 10 ponding of working plate.
Wherein, taper inserted link 17 and pin 2 are fixedly connected by screw rod with the bottom of first support bar 1, when taper inserted link 17 and pin 2 wear when, be convenient for changing.
It should be noted that the utility model is a kind of construction bracket, when specific, user is by pin 2 and inserts Bar 17 is inserted into ground, so that the stabilization of first support bar 1 is not shaken, by 4 sets of the first loop bar at the 4th of 1 top of first support bar On strut 19, the level meter 5 in level meter fixed plate 8 is watched, the height of first support bar 1 is adjusted according to level meter 5, makes two Level meter fixed plate 8 in root first support bar is horizontal positioned, then the first shrinkage pool of 19 side of the 4th support rod is passed through with screw 18, level meter fixed plate 8 is fixed on the 4th support rod 19, then on the 4th support rod 19 and use spiral shell for 7 sets of the second loop bar Nail is fixed, and then the 4th loop bar 20 and second support bar 12 is sequentially sleeved on the 4th support rod 19 again, by 11 He of third loop bar On 12 sets of two support rod of the ground third support rods 13 at the top of second support bar 7, at this moment connecting rod 16 is connected to the 4th loop bar 20 With working plate 10, while third loop bar 11 also pulls working plate 10 by iron chains 9, at 12 top of second support bar at top The top of third support rod 13 puts on rubber sleeve, prevents rainwater from entering in the cavity of third support rod 13, to third support rod 13 Corroded, while being also prevented from third support rod 13 and stabbing other people.
The basic principles and main features of the present invention and the advantages of the present invention have been shown and described above.Current row The technical staff of industry is described in above embodiments and description it should be appreciated that the present utility model is not limited to the above embodiments Only illustrate the principles of the present invention, on the premise of not departing from the spirit and scope of the utility model, the utility model is also It will have various changes and improvements, these various changes and improvements fall within the scope of the claimed invention.The utility model Claimed range is defined by the appending claims and its equivalent thereof.

Claims (4)

1. a kind of construction bracket, including two first support bars (1), which is characterized in that two first support bars (1) the 4th support rod (19) is fixedly connected at the top of, two the 4th support rods (19) are successively arranged with from the bottom to top First loop bar (4), the second loop bar (7) and the 4th loop bar (20), the top of the 4th support rod (19) are fixedly connected with second The top of support rod (12), the second support bar (12) is arranged with third loop bar (11), between two first loop bars (4) It being fixedly connected with level meter fixed plate (8), the groove at the top of the level meter fixed plate (8) is embedded to be connected to level meter (5), and two The two sides of second loop bar (7) are fixed with hook (6), two the 4th loop bars (20) respectively with working plate (10) two Hold the connecting rod (16) that is equipped with to be fixedly connected, two third loop bars (11) by four iron chains (9) respectively with working plate (10) both ends are fixedly connected, and the top of the second support bar (12) is fixedly connected with third support rod (13), the third The top of support rod (13) is arranged with serum cap (14), the fixed company in the bottom of the first support bar (1) and the top of substrate (3) It connects, pin (2) and taper inserted link (17) are arranged surely at the bottom of the substrate (3).
2. a kind of construction bracket according to claim 1, which is characterized in that the 4th support rod (19) and third branch The surface of strut (13) side is respectively equipped with the first shrinkage pool (18) and the second shrinkage pool (15), and the 4th support rod (19) passes through spiral shell Bar passes through the first shrinkage pool (18) and is fixedly connected with the first loop bar (4), and the third support rod (13) is recessed across second by screw rod Hole (15) is fixedly connected with third loop bar (11).
3. a kind of construction bracket according to claim 1, which is characterized in that the surface of the working plate (10) is set There is the aperture that several assume diamond in shape.
4. a kind of construction bracket according to claim 1, which is characterized in that the taper inserted link (17) and pin (2) it is fixedly connected by screw rod with the bottom of first support bar (1).
CN201721466909.1U 2017-11-07 2017-11-07 A kind of construction bracket Expired - Fee Related CN208347276U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721466909.1U CN208347276U (en) 2017-11-07 2017-11-07 A kind of construction bracket

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721466909.1U CN208347276U (en) 2017-11-07 2017-11-07 A kind of construction bracket

Publications (1)

Publication Number Publication Date
CN208347276U true CN208347276U (en) 2019-01-08

Family

ID=64874572

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721466909.1U Expired - Fee Related CN208347276U (en) 2017-11-07 2017-11-07 A kind of construction bracket

Country Status (1)

Country Link
CN (1) CN208347276U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112900820A (en) * 2021-01-16 2021-06-04 中铁一局集团有限公司 Scaffold for building construction

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112900820A (en) * 2021-01-16 2021-06-04 中铁一局集团有限公司 Scaffold for building construction
CN112900820B (en) * 2021-01-16 2022-04-01 中铁一局集团有限公司 Scaffold for building construction

Similar Documents

Publication Publication Date Title
CN208347276U (en) A kind of construction bracket
CN202426187U (en) Structurally modified lengthened clothes hanger stable in hanging
CN206051281U (en) A kind of special hanger of shield crane hanging component hopper
CN202248843U (en) Connector for transverse rod of scaffold
CN205947595U (en) Many clothes pegs clothes hanger that dries in air
CN205777503U (en) A kind of cast-in-situ box girder inner side template support system
CN205659378U (en) Basket is accomodate to basketball
CN205314526U (en) Ledger board that scaffold was used
CN204071594U (en) A kind of movable wind-and skid-proof clothes hanger
CN209013649U (en) Fire hose airing device
CN208471359U (en) A kind of more specification concrete blocks lifting appliance for hoisting
CN206346491U (en) A kind of bar frame colligation servicing unit
CN204970728U (en) Prevent clothes clothes hanger that drops
CN205222438U (en) Prefabricated component gallows and truss superimposed sheet system of lifting by crane
CN202426192U (en) Novel structure for prolonged clothes hanger
CN205368806U (en) Take clothes hanger anti falling clothes -horse of magnetic ring cover
CN208577873U (en) A kind of foldable clothes hanger
CN203486750U (en) Lifting hook capable of being placed flatly for lifting coiled materials
CN205000157U (en) Adjustable clothes hanger
CN202426197U (en) Improved structure for stably hung prolonged type clothes rack
CN202426200U (en) Novel structure of lengthened clothes rack
CN205597685U (en) Standable props clothing fork
CN209701386U (en) For storing the rigging bracket of Large-scale Hoisting rigging
CN210961372U (en) Trousers rack
CN204626079U (en) A kind of clothes hanger

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190108

Termination date: 20191107

CF01 Termination of patent right due to non-payment of annual fee