CN208347270U - A kind of construction assistance platform of rivers pile foundation - Google Patents

A kind of construction assistance platform of rivers pile foundation Download PDF

Info

Publication number
CN208347270U
CN208347270U CN201820756455.XU CN201820756455U CN208347270U CN 208347270 U CN208347270 U CN 208347270U CN 201820756455 U CN201820756455 U CN 201820756455U CN 208347270 U CN208347270 U CN 208347270U
Authority
CN
China
Prior art keywords
platform
ladder
pile foundation
workbench
construction assistance
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820756455.XU
Other languages
Chinese (zh)
Inventor
张亚洲
何纯桥
郑云生
石雄军
王敏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yichang Changjiang River Waterway Engineering Office
Original Assignee
Yichang Changjiang River Waterway Engineering Office
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yichang Changjiang River Waterway Engineering Office filed Critical Yichang Changjiang River Waterway Engineering Office
Priority to CN201820756455.XU priority Critical patent/CN208347270U/en
Application granted granted Critical
Publication of CN208347270U publication Critical patent/CN208347270U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Ladders (AREA)

Abstract

A kind of construction assistance platform of rivers pile foundation, including platform base, platform base top are connect by support column with workbench;Ladder is equipped between the platform base and workbench, ladder is in the interior space between platform base and workbench and the outlet face with workbench upper end;Card slot is provided on the workbench, sliding is equipped with sliding bottom in card slot, and sliding bottom upper end is equipped with screw shell, and screw telescopic bar lower end is threadedly coupled with screw shell, and screw telescopic bar top and platform are clamped.The working efficiency of staff can be improved by the setting of platform and side of the ladder plate in a kind of construction assistance platform of rivers pile foundation provided by the utility model, while can also prevent from injuring accident by a crashing object when ladder.

Description

A kind of construction assistance platform of rivers pile foundation
Technical field
The utility model relates to pile foundation construction technical field of auxiliary equipment, and in particular to a kind of construction auxiliary of rivers pile foundation Platform.
Background technique
Pile foundation construction refers to building foundation construction process.Pile foundation is made of stake and pile framing.The construction method of pile foundation point For prefabricated pile and bored concrete pile two major classes.Pile-driving method it is selected, in addition to according to other than engineering geological condition, it is also contemplated that the class of stake Type, section, length, space enrironment and design requirement, useful stone flat stone with ropes attached at the sides pounds timber construction to ancient Chinese.Thereafter stake is long, stake diameter It increases, stone flat stone with ropes attached at the sides is gradually pulled the substitution of dropping hammer of cast iron.There is steam hammer appearance in beginning eighties the 17th century.To the 1830's It is hammered into shape using guide rod type diesel.With the development of building industry, in order to adapt to the needs of large-scale pile foundation engineering, pile foundation construction technology Hammer weight should be increased and improve lifting, lifting operating procedure, reduce vibration noise and the pollution to environment again.Some prefabricated piles Construction (or bit pressure) combined process is beaten with the brill of pile sinking after boring extracting soil, replace original simple hammering soil compaction or indentation soil compaction etc. Method.Energy is big simultaneously, non-harmful impact body weighs more than 60 tons hydraulic hammer, 125 tons of steam hammers and 15 tons of diesel hammers all It is applied.Filling pile construction is also proceeded to a full set for noiseless, not blowdown, not soil compaction by original mud off, casing pipe hole forming Pipe construction.
The side of the ladder plate of existing pile foundation construction assistance platform is generally positioned at the two sides of workbench, it is easy to high-altitude pendant occurs The staff for injuring by a crashing object and going up ladder is fallen, simultaneously as because the height of staff is different and the height of working face also not phase Together, staff can not easily adapt to the working face of different height, so that the operation difficulty of working face increases, to making for device With bringing certain influence.
Summary of the invention
The technical problem to be solved by the utility model is to provide a kind of construction assistance platforms of rivers pile foundation, on solving The side of the ladder plate for stating the existing pile foundation construction assistance platform proposed in background technique is generally positioned at the two sides of workbench, it is easy to There is falling from high altitude and injure the staff for go up ladder by a crashing object, simultaneously as because of the height difference and working face of staff Height is not also identical, and staff can not easily adapt to the working face of different height, so that the operation difficulty of working face increases The problem of.
In order to solve the above technical problems, the technical scheme adopted by the utility model is:
A kind of construction assistance platform of rivers pile foundation, including platform base, platform base top pass through support column and work Platform connection;Ladder, interior space of the ladder between platform base and workbench are equipped between the platform base and workbench Outlet face interior and with workbench upper end;Card slot is provided on the workbench, sliding is equipped with sliding bottom, sliding in card slot Pedestal upper end is equipped with screw shell, and screw telescopic bar lower end is threadedly coupled with screw shell, screw telescopic bar top and platform card It connects.
The ladder is located at the outlet face of platform base center and upper end and table core
The ladder includes side of the ladder plate, and the inner sidewall of side of the ladder plate is connected with ladder bars.
The outlet side is provided with rain-proof baffle.
Screw telescopic bar upper end is equipped with connecting rod, and connecting rod is equipped with snap ring, and corresponding platform is equipped with cutting ferrule, card Ring is connected and fixed with cutting ferrule.
The connecting rod top, which is equipped with, adjusts head, and it is hinged by bayonet lock and rotational handle to adjust head upper surface two sides.
The quantity of the card slot and platform is four groups, symmetrical all around.
The depth of the threaded hole of the screw shell and the screw thread segment length of screw telescopic bar are adapted.
A kind of construction assistance platform of rivers pile foundation of the utility model, has following technical effect that
1), by the cooperation between side of the ladder plate and workbench, rainproof function when ladder not only may be implemented, while may be used also When preventing from being climbed from workbench surrounding, the phenomenon that falling object from high altitude injures staff by a crashing object generation.
2), by the cooperation between card slot and sliding bottom, moving left and right for sliding bottom may be implemented, to facilitate spirit Mobile working point living.
3), by adjusting the cooperation between head and screw telescopic bar, the height of adjustable platform, to meet staff Required working depth improves the working efficiency of staff.
Detailed description of the invention
The utility model is described in further detail with reference to the accompanying drawings and examples:
Fig. 1 is the structural schematic diagram of the utility model.
Fig. 2 is the schematic diagram of sliding bottom, screw telescopic bar and platform in the utility model.
Fig. 3 is the schematic diagram that head and connecting rod are adjusted in the utility model.
In figure: platform base 1, workbench 2, support column 3, side of the ladder plate 4, ladder bars 5, outlet 6, rain-proof baffle 7, card slot 8 are sliding Dynamic pedestal 9, clamp 10, screw shell 11, screw telescopic bar 12, connecting rod 13 adjust head 14, snap ring 15, platform 16, cutting ferrule 17, rotational handle 18.
Specific embodiment
As shown in Figure 1-3, a kind of construction assistance platform of rivers pile foundation, including platform base 1, the top of platform base 1 It is provided with workbench 2, the lower surface surrounding of workbench 2 is provided with support column 3, and the bottom of workbench 2 passes through support column 3 and platform The upper surface of pedestal 1 is fixedly connected.The upper surface center vertical of platform base 1 is provided with side of the ladder plate 4, the inside of side of the ladder plate 4 Wall is equipped with c-type mouth or round hole, for being clamped ladder bars 5.Outlet 6, platform base are provided centrally in the upper surface of workbench 2 1 upper surface center is fixedly connected by side of the ladder plate 4 with the lower end inner wall of outlet 6, and the side for exporting 6 is provided with rain-proof baffle 7, The lower end of rain-proof baffle 7 is fixedly connected with the upper surface of workbench 2.The upper surface side of workbench 2 is provided with card slot 8 and sliding Pedestal 9, the two sides of sliding bottom 9 are provided with clamp 10, and the two sides of sliding bottom 9 pass through the inner wall of clamp 10 Yu card slot 8 It is flexibly connected, can be slided along 8 back and forth or left and right of card slot.And the upper surface of clamp 10 is provided centrally with screw shell 11, thread bush The inner wall of cylinder 11 is bolted with screw telescopic bar 12, and the top of screw telescopic bar 12 is provided with connecting rod 13 and adjusts head 14, adjusts First 14 bottom centre is fixedly connected by connecting rod 13 with the top of telescopic rod 12, and the side wall of connecting rod 13 is provided with snap ring 15, the top of clamp 10 is provided with platform 16, and the side wall of connecting rod 13 is applied in the upper surface center of platform 16.The bottom of platform 16 Portion center is fixedly connected with cutting ferrule 17, and the bottom side of the wall of connecting rod 13 is flexibly connected with the inner wall of cutting ferrule 17 by snap ring 15, is adjusted The upper surface two sides of section header 14 are connected with rotational handle 18.
In the utility model, the two sides of the rotational handle 18 are provided with bayonet lock, and the two sides of rotational handle 18 pass through Bayonet lock is flexibly connected with the upper surface inner sidewall for adjusting head 14, is opened rotational handle 18 using bayonet lock and is carried out to the height of platform 16 Adjustment, the outer surface of ladder bars 5, platform 16 and rotational handle 18 is provided with anti-skid chequer, can be more convenient utilize anti-skid chequer To device progress reasonable employment, the quantity of card slot 8 and platform 16 is four groups, and opposite two groups of card slots 8 and platform 16 are symmetrically set It sets, staff can carry out construction processing to rivers pile foundation on the platform 16 of 2 surrounding of workbench by standing, close to flexible The inner wall of the screw shell 11 of 12 bottom of bar is provided with threaded hole, the depth of threaded hole and the equal length of telescopic rod 12, can be with It realizes that telescopic rod 12 rotates in threaded hole using head 14 is adjusted, while realizing the lifting of platform 16.
When in use, it is reached at outlet 6 by the ladder bars 5 on the side of the ladder plate 4 of 2 inside of platform base 1 and workbench, in turn It rises on workbench 2, can effectively prevent by rain-proof baffle 7 when the rainy day carrying out operation, rainwater penetrates into 5 table of ladder bars Face causes to have skidded phenomenon when ladder, the phenomenon that slips easily occurs, while side of the ladder plate 4 being arranged in the inside of workbench 2 Between, it can prevent from being disposed at the weight that edge is easy in upper ladder, on workbench 2 and fall, injure by a crashing object and go up terraced work Make personnel, while when working on workbench 2, so that the clamp 10 of 9 two sides of sliding bottom is moved in card slot 8, will stand Platform 16 is moved to below specified working face, can when staff's head is shorter is unable to reach height required for working face To be driven using rotational handle 18 and adjust the rotation of head 14, in 13 upper snap ring 15 of connecting rod and cutting ferrule by pulling out rotational handle 18 Under 17 collective effect, the snap-fit between connecting rod 13 and cutting ferrule 17 may be implemented.Adjusting the same of the rotation of head 14 simultaneously When, screw telescopic bar 12 also can rotate, so that the depth that screw telescopic bar 12 is inserted into screw shell 11 changes, thus real The lifting of existing platform 16, to meet the height of arrival required for staff.
In conclusion when the utility model by cooperation between side of the ladder plate and workbench, not only may be implemented ladder Rainproof function, while when can also prevent from being climbed from workbench surrounding by side of the ladder plate, falling object from high altitude injures staff by a crashing object The phenomenon that occur, by the cooperation between card slot and sliding bottom, moving left and right for sliding bottom may be implemented, pass through adjust head Cooperation between screw telescopic bar, the height of adjustable platform are improved with meeting working depth required for staff The working efficiency of staff.

Claims (8)

1. a kind of construction assistance platform of rivers pile foundation, it is characterised in that: logical above platform base (1) including platform base (1) Support column (3) is crossed to connect with workbench (2);Ladder is equipped between the platform base (1) and workbench (2), ladder is located at flat Outlet (6) face in interior space between platform pedestal (1) and workbench (2) and with workbench (2) upper end;The workbench (2) it is provided on card slot (8), sliding is equipped with sliding bottom (9) in card slot (8), and sliding bottom (9) upper end is equipped with screw shell (11), screw telescopic bar (12) lower end is threadedly coupled with screw shell (11), and screw telescopic bar (12) top and platform (16) are blocked It connects.
2. a kind of construction assistance platform of rivers pile foundation according to claim 1, it is characterised in that: the ladder is located at flat Outlet (6) face of platform base center and upper end and table core.
3. a kind of construction assistance platform of rivers pile foundation according to claim 1, it is characterised in that: the ladder includes ladder Side plate (4), the inner sidewall of side of the ladder plate (4) are connected with ladder bars (5).
4. a kind of construction assistance platform of rivers pile foundation according to claim 1, it is characterised in that: the outlet (6) one Side is provided with rain-proof baffle (7).
5. a kind of construction assistance platform of rivers pile foundation according to claim 1, it is characterised in that: the screw telescopic bar (12) upper end is equipped with connecting rod (13), and connecting rod (13) is equipped with snap ring (15), and corresponding platform (16) is equipped with cutting ferrule (17), Snap ring (15) is connected and fixed with cutting ferrule (17).
6. a kind of construction assistance platform of rivers pile foundation according to claim 5, it is characterised in that: the connecting rod (13) Top, which is equipped with, adjusts head (14), and it is hinged by bayonet lock and rotational handle (18) to adjust head (14) upper surface two sides.
7. a kind of construction assistance platform of rivers pile foundation according to claim 1, it is characterised in that: the card slot (8) with The quantity of platform (16) is four groups, symmetrical all around.
8. a kind of construction assistance platform of rivers pile foundation according to claim 1, it is characterised in that: the screw shell (11) depth of threaded hole and the screw thread segment length of screw telescopic bar (12) are adapted.
CN201820756455.XU 2018-05-21 2018-05-21 A kind of construction assistance platform of rivers pile foundation Active CN208347270U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820756455.XU CN208347270U (en) 2018-05-21 2018-05-21 A kind of construction assistance platform of rivers pile foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820756455.XU CN208347270U (en) 2018-05-21 2018-05-21 A kind of construction assistance platform of rivers pile foundation

Publications (1)

Publication Number Publication Date
CN208347270U true CN208347270U (en) 2019-01-08

Family

ID=64890231

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820756455.XU Active CN208347270U (en) 2018-05-21 2018-05-21 A kind of construction assistance platform of rivers pile foundation

Country Status (1)

Country Link
CN (1) CN208347270U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108442675A (en) * 2018-05-21 2018-08-24 长江宜昌航道工程局 A kind of construction assistance platform of rivers pile foundation

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108442675A (en) * 2018-05-21 2018-08-24 长江宜昌航道工程局 A kind of construction assistance platform of rivers pile foundation

Similar Documents

Publication Publication Date Title
CN105464117B (en) Rotary marine piling saddle and multi-column pier foundation piling technique waterborne
EP2423390A1 (en) Swivelling module for use when producing an underwater foundation of a structure
CN107461150A (en) A kind of piling machine for bridge construction
CN107268604A (en) The construction system and construction method of a kind of hollow preformed pile
CN103266602A (en) Diameter-expanding pile for manual hole digging and construction method thereof
CN208347270U (en) A kind of construction assistance platform of rivers pile foundation
CN206512718U (en) One kind can tuning multifunction vibration plant stake device
CN105332376B (en) Hydraulic mechanical hand-lifting stake clamping device and pile-drawing machine
CN109853564A (en) A kind of construction method and dedicated inner tamping tube hammer of compaction pile
CN102704479A (en) Hydraulic hammering type concrete cast-in-place pile equipment
CN110529041B (en) Self-soil-taking type double-layer full casing pipe for inclined pile hole forming and construction method thereof
CN108442675A (en) A kind of construction assistance platform of rivers pile foundation
CN207047834U (en) A kind of construction system of hollow preformed pile
CN103334433B (en) A kind of construction method of pile pulling
CN210975799U (en) Double-spraying double-shaft oblique cement-soil stirring and profile steel inserting integrated equipment
RU83780U1 (en) ITS DRIVING AND DEVICE FOR ITS DIVING
CN211849431U (en) Pile clearing device for shield construction
CN209178986U (en) It is a kind of to exempt from broken apart concrete filling pile head
CN106567386A (en) Pouring type pile driver and pile driving method therefor
CN2262568Y (en) Detachable multi-section combined pile head
WO2021189840A1 (en) Construction method and construction apparatus for static-pressure tube-sinking pile
CN105178315A (en) Pouring type pile driver and pile driving method using pile driver
CN207376622U (en) A kind of spiral carrier stake machine and spiral carrier stake
CN201981535U (en) Construction device of ramming compaction pile ramming expanded pile
CN111021942A (en) Small-size hole equipment that draws suitable for finite space

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant