CN208329502U - A kind of garbage retrieving system suitable for high-building construction environment - Google Patents
A kind of garbage retrieving system suitable for high-building construction environment Download PDFInfo
- Publication number
- CN208329502U CN208329502U CN201820624122.1U CN201820624122U CN208329502U CN 208329502 U CN208329502 U CN 208329502U CN 201820624122 U CN201820624122 U CN 201820624122U CN 208329502 U CN208329502 U CN 208329502U
- Authority
- CN
- China
- Prior art keywords
- storage tank
- microprocessor
- construction environment
- building construction
- system suitable
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Abstract
The utility model proposes a kind of garbage retrieving system suitable for high-building construction environment, including integrated lifting device, control cabinet and monitoring center, integrated lifting device includes control button, steel plate, hoist engine and storage tank;Storage tank includes pulley, pressure sensor, displacement sensor and chamber door;Control cabinet includes power module, current converter, microprocessor, 4G communication module;Hoist engine drives storage tank to rise or fall;Pressure sensor and displacement sensor are respectively used to pressure change and storage tank height change in detection storage tank;When pressure change reaches P, microprocessor controls storage tank decline;Each equipment operation information is passed through 4G communication module real-time Transmission to monitoring center by microprocessor;The utility model facilitates high-building construction personnel to handle building waste, recycles the timber discarded in construction environment, steel pipe, reduces the waste of resource, while reducing construction environment and falling object from high altitude occur.
Description
Technical field
The utility model relates to technical field of building construction, especially a kind of rubbish suitable for high-building construction environment
Recovery system.
Background technique
During existing high-building construction, largely discarded timber, steel pipe are arbitrarily abandoned, and occupy construction space, are influenced
Whole construction speed, while timber, steel pipe are easy to fall in Construction of High-rise environment, jeopardize the life peace of ground construction personnel
Entirely, and largely discarded timber, steel pipe cannot be recycled well, and resource is caused greatly to waste.
Summary of the invention
The utility model proposes a kind of garbage retrieving systems suitable for high-building construction environment, solve skyscraper
The accumulation of construction environment building waste, a large amount of waste woods, steel pipe arbitrarily abandon, and occupy construction space, and reusable resource is tight
The problems such as wasting again.
The technical solution of the utility model is achieved in that
A kind of garbage retrieving system suitable for high-building construction environment, including integrated lifting device, control cabinet and
Monitoring center, the integration lifting device includes control button, steel plate, hoist engine and storage tank;The storage tank includes sliding
Wheel, pressure sensor, displacement sensor and chamber door;The control cabinet includes power module, current converter, microprocessor and 4G
Communication module;The steel plate two sides pass through reserved keyhole by expansion bolt and are fixed on each layer spandrel girder of building body;It is described
Hoist engine is mounted on top steel plate extreme higher position in conjunction with practice of construction floor;The microprocessor passes through control elevator electromechanical source
Power supply mode carries out the operating condition of control hoist engine;The hoist engine drives storage tank to rise or fall;The pressure sensing
Device and displacement sensor are respectively used to pressure change and storage tank height change in detection storage tank;The detectable signal passes in real time
Transport to microprocessor;When the pressure change reaches P, microprocessor controls storage tank decline;The control button is used for micro-
Processor sends storage tank rising signals;The microprocessor reaches specified according to received height change signal control storage tank
Position;Each equipment operation information is passed through 4G communication module real-time Transmission to monitoring center by the microprocessor.
Further, the hoist engine drives spool turns folding and unfolding wirerope;The storage tank leads under wirerope drive
Pulley is crossed to slide on the slide rail;The pulley is mounted on storage tank pedestal and is slidably installed on the slide rail by bearing.
Further, when the pressure sensor detectable signal value P >=1KN, microprocessor controls storage tank decline.
Further, the top opening of the storage tank, side are provided with chamber door;The storage tank bottom is provided with folder
Layer, the pressure sensor are mounted in interlayer;Institute's displacement sensors are arranged in storage tank bottom.
Further, combined aural and visual alarm is provided in the control cabinet and on storage tank;The microprocessor control storage
When object case declines, to combined aural and visual alarm sending action signal;Sound-light alarm in combined aural and visual alarm and control cabinet on the storage tank
After device receives signal, simultaneously operation.
Further, the steel plate includes two groups of sliding rails, detachable metal card slot, screw and mating nut;The steel
Plate and two groups of sliding rail bottoms are welded to connect completely;The steel plate is made of several segments;Distinguish one end of adjacent two sections of steel plates
It is placed into detachable metal card slot, and reserved wire hole is passed through by screw in steel plate and detachable metal card slot contact position
It is connect with mating nut.
Further, the mating nut is that two regular hexagon nuts are welded by band steel;Described two regular hexagons
Nut is welded as regular hexagon nut spatial vertical another regular hexagon nut.
Further, the band steel is bent 30 °;The band steel length is 4 times of regular hexagon nut side lengths.
It is largely built in existing building work progress construction environment on the middle and senior level the utility model has the beneficial effects that solving
Rubbish is arbitrarily accumulated, is abandoned, and the rubbish in Construction of High-rise architectural environment is reduced, and improves construction personnel's working efficiency, accelerates construction
Progress, while safety accident caused by building waste arbitrarily abandons is avoided, to the waste wood of centralized collection, steel pipe is unified back
Receipts processing, reduces resource waste, and equipment is easy for installation in this system, easily disassembled, and position can be adjusted according to actual progress, and
And system has remote signal transfer function, supervisor of construction understands garbage disposal situation, pole in skyscraper environment in real time
Big improves the case where skyscraper rubbish arbitrarily abandons, and improves the environmentally friendly degree in entire construction process.
Detailed description of the invention
In order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, to embodiment or will show below
There is attached drawing needed in technical description to be briefly described, it should be apparent that, the accompanying drawings in the following description is only this
Some embodiments of invention for those of ordinary skill in the art without creative efforts, can be with
It obtains other drawings based on these drawings.
Fig. 1 is that a kind of garbage retrieving system suitable for high-building construction environment of the utility model specifically installs signal
Figure.
Fig. 2 is integrated lifting device structural schematic diagram in Fig. 1.
Fig. 3 is the specific schematic diagram of Fig. 2 superstructure.
Fig. 4 is the specific schematic diagram of Fig. 1 storage tank.
Fig. 5 is Fig. 1 steel plate and detachable metal card slot connection schematic diagram.
Fig. 6 is that the mating nut signal of Fig. 5 is intended to.
Fig. 7 is Fig. 1 control cabinet structural schematic diagram.
Fig. 8 is that Fig. 1 system overall signal transmits schematic diagram.
Numbering in the drawing are as follows: 1 is integrated lifting device, and 2 be the first control button, and 3 be the second control button, and 4 be the
Three control buttons, 5 be storage tank, and 6 be control cabinet, and 7 be hoist engine, and 8 be sliding rail, and 9 be expansion bolt, and 10 be pulley, and 11 be position
Displacement sensor, 12 be chamber door, and 13 be pressure sensor, and 14 be reel, and 15 be power module, and 16 be current converter, and 18 be sound
Light crossing-signal, 19 be microprocessor, and 20 be 4G communication module, and 21 be detachable metal card slot, and 22 be steel plate, and 23 be mating spiral shell
Cap, 24 be screw, and 25 be wirerope, and 26 be bearing, and 27 be closure becket, and 28 be monitoring center.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model
Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole
Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are under that premise of not paying creative labor
Every other embodiment obtained, fall within the protection scope of the utility model.
A kind of garbage retrieving system suitable for high-building construction environment, as shown in figures 1-8, including integration promotes dress
Set 1, control cabinet 6 and monitoring center 28, integrated lifting device 1 include control button, steel plate 22, expansion bolt 9, hoist engine 7,
Two groups of sliding rails 8, reel 14, wirerope 25 and storage tank 5, storage tank 5 include pulley 10, pressure sensor 13, displacement sensor
11 and chamber door 12, control cabinet 6 includes power module 15, current converter 16, microprocessor 19,4G communication module 20, control cabinet 6
It is provided with combined aural and visual alarm 18 on interior and storage tank 5, the first button 2, the second button 3 and third button 4 are respectively used to control
Storage tank 5, which is promoted, arrives corresponding height, for controlling the decline of storage tank 5, pressure sensing when 13 detectable signal of pressure sensor reaches P
When 13 detectable signal value P >=1KN of device, microprocessor 19 controls storage tank 5 and declines;Displacement sensor 11 is for monitoring storage tank 5
Height change, after combined aural and visual alarm 18 receives signal in combined aural and visual alarm 18 and control cabinet 6 on storage tank 5, simultaneously operation;4G is logical
News module 20 is used to 5 dropping signal of storage tank being transferred to monitoring center 28, after staff goes and finds out what's going in monitoring center 28,
Associated construction personnel are sent in time and handle building waste, and to be fixed on building body each by expansion bolt 9 for integrated lifting device 1
On layer spandrel girder, storage tank 5 is upper hollow, and side is provided with chamber door 12, and chamber door 12 is when storage tank 5 is down to ground, manually
It opens, storage tank 5 is connect by being closed becket 27 with wirerope 25, and pulley 10 is slidably connected by bearing 26 with sliding rail 8, steel
Plate 22 and two groups of 8 bottoms of sliding rail are welded to connect completely, and the steel plate 22 of different sections passes through detachable metal card slot 21 and screw 24, matches
It covers nut 23 to connect, mating nut 23 is two regular hexagon nut welding, and two regular hexagon nuts are welded as one vertically
Another horizontal positioned regular hexagon nut of regular hexagon nut spatial vertical is placed, two regular hexagon nuts are welded by band steel
It connects, is bent 30 ° using band steel, band steel length is 4 times of regular hexagon nut side lengths.
During high-building construction, construction personnel needs according to the actual situation, presses corresponding control button, transfers
Storage tank 5 rises to corresponding height, and 5 intrinsic displacement sensor of storage tank, 11 real-time monitoring storage tank, 5 height change guarantees storage tank
5 can reach designated position, and construction personnel is facilitated to launch building waste, when building waste reaches 100KG in storage tank 5, storing
Case 5 declines automatically, and combined aural and visual alarm 18 issues alarm signal on storage tank 5, and associated construction personnel is warned to stop throwing in time
It puts and far from storage tank 5, control cabinet 6 is real-time transmitted in monitoring center 28 equipment operation information each in system, monitoring center
Staff understands relevant device operating condition in time in 28, facilitate staff send corresponding construction personnel carry out processing build
Building refuse improves staff's working efficiency.
Claims (8)
1. a kind of garbage retrieving system suitable for high-building construction environment, including integrated lifting device (1), control cabinet
(6) and monitoring center (28), which is characterized in that the integration lifting device (1) includes control button, steel plate (22), elevator
Machine (7) and storage tank (5);The storage tank (5) includes pulley (10), pressure sensor (13), displacement sensor (11) and case
Door (12);The control cabinet (6) includes power module (15), current converter (16), microprocessor (19), 4G communication module
(20);Steel plate (22) two sides pass through reserved keyhole by expansion bolt (9) and are fixed on each layer spandrel girder of building body;Institute
It states hoist engine (7) and is mounted on top steel plate (22) extreme higher position in conjunction with practice of construction floor;The microprocessor (19) passes through
Control hoist engine (7) power supply power supply mode carries out the operating condition of control hoist engine (7);The hoist engine (7) drives storage tank
(5) it rises or falls;The pressure sensor (13) and displacement sensor (11) are respectively used to the interior pressure of detection storage tank (5) and become
Change and storage tank (5) height change;The detectable signal real-time Transmission of the pressure sensor (13) and displacement sensor (11) is extremely
Microprocessor (19), microprocessor (19) control storage tank (5) decline;The control button is used to send to microprocessor (19)
Storage tank (5) rising signals;The microprocessor (19) reaches specified according to received height change signal control storage tank (5)
Position;Each equipment operation information is passed through 4G communication module (20) real-time Transmission to monitoring center by the microprocessor (19)
(28).
2. a kind of garbage retrieving system suitable for high-building construction environment according to claim 1, which is characterized in that institute
State hoist engine (7) band movable reel (14) rotation folding and unfolding wirerope (25);The storage tank (5) passes through in the case where wirerope (25) drive
Pulley (10) slides on sliding rail (8);The pulley (10) is mounted on storage tank (5) pedestal and by bearing (26) sliding peace
On sliding rail (8).
3. a kind of garbage retrieving system suitable for high-building construction environment according to claim 1, which is characterized in that institute
When stating pressure sensor (13) detectable signal value P >=1KN, microprocessor (19) controls storage tank (5) decline.
4. a kind of garbage retrieving system suitable for high-building construction environment according to claim 1, which is characterized in that institute
The top opening of storage tank (5) is stated, side is provided with chamber door (12);Storage tank (5) bottom is provided with interlayer, the pressure
Sensor (13) is mounted in interlayer;Institute's displacement sensors (11) are arranged in storage tank (5) bottom.
5. a kind of garbage retrieving system suitable for high-building construction environment according to claim 1, which is characterized in that institute
It states in control cabinet (6) and is provided with combined aural and visual alarm (18) on storage tank (5);The microprocessor (19) controls storage tank
(5) when declining, to combined aural and visual alarm (18) sending action signal;Combined aural and visual alarm (18) and control cabinet on the storage tank (5)
(6) after interior combined aural and visual alarm (18) receives signal, simultaneously operation.
6. a kind of garbage retrieving system suitable for high-building construction environment according to claim 1, which is characterized in that institute
Stating steel plate (22) includes two groups of sliding rails (8), detachable metal card slot (21), screw (24) and mating nut (23);The steel
Plate (22) and two groups of sliding rail (8) bottoms are welded to connect completely;The steel plate (22) is made of several segments;Adjacent two sections of steel plates
(22) one end is placed individually into detachable metal card slot (21), and in steel plate (22) and detachable metal card slot (21)
Contact position passes through reserved wire hole by screw (24) and connect with mating nut (23).
7. a kind of garbage retrieving system suitable for high-building construction environment according to claim 6, which is characterized in that institute
Stating mating nut (23) is that two regular hexagon nuts are welded by band steel;Described two regular hexagon nuts are being welded as one just
Another regular hexagon nut of hex nut spatial vertical.
8. a kind of garbage retrieving system suitable for high-building construction environment according to claim 7, which is characterized in that institute
It states band steel and is bent 30 °;The band steel length is 4 times of regular hexagon nut side lengths.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820624122.1U CN208329502U (en) | 2018-04-28 | 2018-04-28 | A kind of garbage retrieving system suitable for high-building construction environment |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820624122.1U CN208329502U (en) | 2018-04-28 | 2018-04-28 | A kind of garbage retrieving system suitable for high-building construction environment |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208329502U true CN208329502U (en) | 2019-01-04 |
Family
ID=64778984
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820624122.1U Active CN208329502U (en) | 2018-04-28 | 2018-04-28 | A kind of garbage retrieving system suitable for high-building construction environment |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208329502U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109969678A (en) * | 2019-05-10 | 2019-07-05 | 李良杰 | Duct type rubbish conveyer system |
-
2018
- 2018-04-28 CN CN201820624122.1U patent/CN208329502U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109969678A (en) * | 2019-05-10 | 2019-07-05 | 李良杰 | Duct type rubbish conveyer system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105113552B (en) | A kind of cable Manhole cover assembly | |
CN209873674U (en) | Assembled garbage collection device for building | |
CN103738856A (en) | Automatic garbage feeding system and control method thereof | |
CN106843040A (en) | A kind of dustbin supervisory systems | |
CN208329502U (en) | A kind of garbage retrieving system suitable for high-building construction environment | |
CN106976769A (en) | A kind of building hoist automatic leveling method | |
CN203638996U (en) | Automatic garbage feeding system | |
CN206209383U (en) | A kind of skip position detection and skip unloading linkage | |
CN201605855U (en) | Steel structure carrier vehicle conveying platform frame of three-dimensional parking device | |
CN204297461U (en) | Scrap discharge gathering-device | |
CN109113131B (en) | Automatic coupling intelligent integrated cable-stayed pump station | |
CN215045846U (en) | Optimized dispatching control system for garbage station | |
CN202954500U (en) | Automatic lifting guard railing device for train top operation | |
CN104597792A (en) | High-rise rescue escaping device intelligent commanding method and system | |
CN211767977U (en) | Buried energy-saving automatic lifting garbage storage equipment | |
CN213268983U (en) | Self-climbing discharging platform | |
CN206307881U (en) | It is a kind of for vertical shaft for mine cage to tank arrangement | |
CN210333639U (en) | High-efficient silo device of decontaminating | |
CN110255020A (en) | A kind of rubbish warehouse exit system and its export method | |
CN205419349U (en) | Construction elevator's control circuit | |
CN107842862B (en) | Maintenance method for garbage crane | |
CN107128755B (en) | Elevator operation control device | |
CN212893641U (en) | Intelligent protection device for preventing top drive from being hung and collided with double-layer platform | |
CN201631936U (en) | High-rise building fire-fighting rescue device | |
CN214358055U (en) | Garbage collection and classification device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |